INSTALLATION AND TESTING PROCEDURES FOR ERM LEAK DETECTION

Similar documents
HT-406 Specification Guide

DUO-THERM 505 Specification Guide

APPENDIX A MEASUREMENT AND PAYMENT

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

POWER PINNER BENCH HAND WELDER 7250 OPERATOR S MANUAL

SUB WATER DEPARTMENT STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION POLYETHYLENE PRESSURE PIPE

CONDUITS AND FITTINGS

Section 2: Underground

San Antonio Water System Standard Specifications for Construction ITEM NO SANITARY SEWER LATERAL STUB OUTS OR RECONNECTIONS

SECTION WASTEWATER FORCE MAINS

SECTION GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY

SECTION WASTEWATER FORCE MAINS

CHAPTER 11 CONDUITS AND FITTINGS

UNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:

DUO-THERM 505 HIGH DENSITY POLYETHYLENE JACKETED CLASS A STEEL CONDUIT SYSTEM

40'-0" PIPE SUPPORT (TYP.) (SEE DWG. NO. SK-2 OR DWG. NO. SK-4)

Underground System. Description

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

2013 ANNUAL AIRFIELD PAVEMENT REHABILITATION CONTRACT NO ADDENDUM NUMBER TWO. Scope of this Addendum

Basic Service. This Section provides information regarding a. Introduction

192GasCatalog.

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems.

2003 International Residential Code ELECTRICAL PROVISIONS ONLY October 2005 EDITORIAL CHANGES SEVENTH PRINTING

SECTION MEDIUM-VOLTAGE CABLES PART 1 GENERAL

ELECTRICAL SAFETY INSPECTION REPORT.

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

Huntsville Utilities Underground Residential Service Requirements

Risk Control Bulletin Damage Prevention Guidelines Excavation Procedures for Underground Facilities

City Of Mendota Construction Procedures

H. Underground Transmission System Design

INSTALLATION INSTRUCTIONS MODEL THE CONTRACTOR SUMP BUDDY

Instructions for Connection to Mesa Antero Subdivision Central Water System

Revision 1 RAM ELEVATORS. Elevator Electrical Planning Guide. RAM Manufacturing Ltd

1. Approved Manufacturers: Carlon Electrical Products, Cantex, or approved equal.

TRICON DOUBLE-CON PLUS

GUIDELINES FOR SAFE CONSTRUCTION IN THE PROXIMITY OF THE THERMAL DISTRIBUTION PIPING SYSTEM

SPECIFICATION for ISCO HDPE DUAL CONTAINMENT PIPE

Assessment Schedule - TS.5

SECTION GROUNDING

SECTION GROUNDING AND BONDING

Model AT Modular Linear Anode

SECTION NATURAL GAS DISTRIBUTION

SPECIAL SPECIFICATION 6664 Level (3) Communications System

SPECIAL SPECIFICATION 6658 Time Warner Communications System

Design and Construction Standards SECTION HYDRONIC PIPING

Keep your head out of the gas. When you are welding, air extractor should be used to prevent inhalation of gas.

SECTION HYDRONIC PIPING

SUPPLEMENTARY SECTION: STANDARD SPECIFICATIONS PAGE 1 STORMWATER MAINS & CULVERTS MAY 2018

ELEVATORS THE GOOD, THE BAD, AND THE UGLY

Underground Steam Condensate Distribution Piping

SECTION HYDRONIC PIPING

SECTION GS10300 UNDERGROUND TRENCHING AND EXCAVATION CONSIDERATIONS

Distributed By: iprocessmart.com

Technical Service. INSTALLATION INSTRUCTIONS FOR TARAFLEX SPORT PRODUCTS over Gypsum base Products. This document refers to the following products:

D-10 OUTLINE SPECIFICATION FOR PRE FAB Undergrd Piping System

CON II CONTAINMENT PIPING SYSTEM

MATERIAL SPECIFICATION FOR LUMINAIRE RAISING AND LOWERING EQUIPMENT

CAL/OSHA ELECTRICAL HIGH VOLTAGE

Northeast Gas Operation School Thursday June 5 th

CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS SECTION 00005B TABLE OF CONTENTS ***CITY OF FRIENDSWOOD TECHNICAL SPECIFICATIONS***

SECTION FACILITY LIGHTNING PROTECTION

Mears Group, Inc. Integrity Assessment for Non-Piggable Pipelines By Jim Walton

ELECTRICAL SAFETY INSPECTION REPORT

[Type text] Heber Light & Power. Developers & Excavators. Electrical Service Requirements Manual

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

J60 Lithium Ion UPS 350VA Model User & Installation Manual Xtreme Power Conversion Corporation. All rights reserved.

SPECIAL SPECIFICATION 6623 Multi-Duct Conduit System

OPERATION MANUAL. A220 Arc Welding Machine. Serial Number: Where Purchase: Date of purchased:

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

ELECTRICAL SAFETY INSPECTION REPORT

Section 7: Specifications

Earthing in electrical network purpose, methods and measurement

Guidance on Avoiding Danger from Underground Electricity Cables based on HSE Document HS(G)47

CONSTRUCTION SPECIFICATION FOR CEMENT MORTAR LINING OF WATERMAINS

ENMET Corporation PO Box 979 Ann Arbor, MI GS-24-DF. Manual October 2003 MCN-314, 12/05/03

DJ Switch 10F V2 ORDERCODE 50365

A. The work consists of furnishing a Chiller Noise Reduction System as listed in the specifications.

Natural Science and Technology Grade 5 Term 3 Energy and Change and Systems and Control. Topic 10: Stored energy in fuels Unit: 1 Fuels...

Installation Instructions For Overly Acoustical / Bullet Resistant Window

NCCER Progress Blvd, Alachua, Florida Tel: (888)

Grounding Conductor & GFCI Employee Protection Program

SECTION CHEMICAL FEED SYSTEM

Equipment Guide shorten restoration times underground

SECTION 401 WATER PIPE AND FITTINGS 2.2 POLYVINYL CHLORIDE (PVC) PIPE AND FITTINGS

Nassau County Building Department

6. SECONDARY SERVICES (under 600 volts) 6.1 AVAILABILITY For the electrical characteristics of available secondary services see Section 3.4.

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Model: 770 Light Vehicle Scale Size: 8 x30 x5 Size: 10 x30 x5 Capacity: 40K CLC: 20K Capacity: 60K CLC:30K Installation, Set-Up and Operation Manual

All service lines shall conform to the following requirements:

Quality NBR Insulation

SECTION HYDRONIC PIPING

Given a functional welder, instruction and demonstration of use, each employee will be able to:

With CE certificate EN USER MANUAL BORA-CLEAN FILTER 5

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

RIGGING INFORMATION & INSTRUCTIONS SEASONS-4 RES PRODUCTS

CONSTRUCTION SPECIFICATION FOR TRAFFIC ACTUATION EQUIPMENT

GREAT PRODUCTS GREAT PEOPLE GREAT SERVICE

SECTION INSTALLATION OF OWNER-FURNISHED PRODUCTS

SECTION PUBLIC WATER SERVICE CONNECTIONS

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

Transcription:

14.601 Materials & Equipment MATERIALS: 1. Teflon Coated Insulated Wire with Crimps 2. Shop Rags 3. Standard ANALOG Ohmmeter INSTALLATION AND TESTING PROCEDURES FOR ERM 4. Wire Crimping and Stripping Tool 1. Each piece of pipe, as it arrives at the jobsite, must be checked for isolation and continuity. Isolation and Continuity Check: Switch your analog ohmmeter to its high-end resistance scale R x 100k (see images A & B below). Touch one lead to the copper wire and the second lead to the carrier pipe (see figure 1). The bare metal of the carrier pipe shall be exposed at all locations where the probe (or copper wire) will make contact. For good isolation, the reading on your ohmmeter should be close to infinity for any single piece and not less than 1 Million Ohms for an entire run. For example, in image B below with the meter on x100k setting, a blue equates to 20 Million Ohms, or a blue 10 equates to 1 Million Ohms. For a single piece, the needle should not move past the marker, and for the entire run the needle should not move past the 10. If this happens, make sure that moisture is not present at the ends of the pipe and clean any excess mastic from the wire. Use a propane torch with a light billowy flame to get rid of the moisture. If the foam catches on fire, quickly extinguish with a rag. A. B. Ex. 50 x 100K = 5,000,000 Figure-1: Isolation Reading After isolation check, the continuity check must be performed. Short the leak detection wire to the bare pipe at the opposite end of the pipe. It is best if a partner is used that can place the wire into and out of contact with the steel pipe. The instant this occurs, the Ohm reading should drop to zero. This zero reading occurs when the Ohm reader s needle pegs to the right (zero resistance). See Figure- 2.

14.602 Figure-2: Continuity Check 2. After several pieces of pipe have been welded in the trench and the section has passed the hydrostatic field test, we are ready to insulate the joints. a. b. c. d. Make sure that the entire joint area is completely dry. Any moisture in the joint will adversely affect the initialization and operation of the leak detection system. Perform and record on the attached form isolation and continuity checks on the two pieces you are about to seal with a joint closure to ensure that each piece reads close to infinity, and when all pieces are connected that the system reads 1 Million Ohms. Use a propane torch with a light billowy flame to remove any residual moisture and dry the area out. Even if the area already appears dry, the torch should still be used to make certain all residual moisture has been removed. Additionally, the foam immediately surrounding the wire should be dug out approximately 1 around the wire and 1 deep to remove foam that may have surface moisture trapped inside. Next (HT-406 Only), sectional insulation is to be placed over the joint and secured with duct tape. If the foam does not initially fit, measure the distance between the factory end and cut to fit. Make sure the insulation fits without any gaps and the embedded copper wire is visible. Trim the bare copper wire so that it extends just beyond the face of the insulation. Crimp the bare wire with the Teflon coated wire at each end (see fig. 3). Insure there is some slack in the Teflon coated wire. Figure-3: Crimping Teflon Coated Wire e. Make sure that the crimp is attached securely by tugging firmly on either side of Teflon coated wire. Additionally, make sure that the crimp and bare copper wire cannot touch the steel carrier pipe. Perform an isolation and continuity test on the joint as described in Section 1 of these instructions. After the tests are passed install your joint kit per the projects joint kit installation instructions (Remember fusion joints require factory f. g. training, which is already included in the product sales price. You must remember to schedule this visit!). After the joint is insulated and sealed, perform an isolation and continuity check on the entire run of installed pipe. One person will be at the last piece of pipe currently installed in the ditch. This person will attach the ohmmeter and perform the tests as described in Section 1. A second person will be at the opposite end of the run in order to short the run when instructed. * Repeat steps a - d to insulate each remaining joint. Isolation should meet or exceed 1 Million Ohms for up to 0 ft.

14.603 * For long runs, the use of a second person to short the opposite end may not always be practical. For a shortcut, see figure 4 where the supply and return pipes are grounded together via a tack welded metal bar, and the ERM wire is connected between the supply and return. Now you can short the system right next to the joint you are reading. TEMPORARY CONNECTION SHORT THIS END METAL BAR Additional Notes: 1. 2. 3. 4. 5. 6. 7. Figure-4 Performing isolation and continuity checks on the pipe as it arrives at the job site is imperative. This ensures that if any pipe was damaged during shipping, repair or replacement of the piece can be performed prior to installing the pipe in the trench. Thermacor will not be responsible for any cost associated with removing the pipe from the trench, and then reinstalling a piece that had to be repaired. Performing isolation and continuity checks after each individual joint kit is installed is imperative. This is because if a joint is connected improperly, you will know immediately and be able to identify and repair the bad joint immediately. If the checks are performed after a string of joints are installed, you will not be able to identify the individual bad joint without opening and checking each joint or paying for a Thermacor factory technician to travel to the job site with a TDR machine to locate the bad joint. Performing isolation and continuity checks on the entire run of installed pipe prior to backfill is imperative. This will prevent costs associated with re-excavation should the system not be connected properly. Ambient moisture, especially in high humidity regions, will deteriorate resistance readings. As more and more joints are connected, these joints will act as a circuit in parallel and further diminish the resistance reading. To prevent this, closely follow the steps detailed in Section 2.a of these instructions. This will prevent residual moisture from giving you poor readings. Connections through manholes are possible. The crimp and testing of this wire is the same as a regular joint. Access to the leak detection wire and carrier pipe should be made possible through the field applied vault insulation as shown in our vault detail. Contact Thermacor if you require a copy of this detail. Resistance readings for the entire system should not drop below 1 Million Ohms. If this happens during installation, you are not drying the pipe enough to remove the residual moisture. A dry system is important because every additional joint that is connected in the system will cause the reading to drop. This system includes a continuous monitoring panel. The panel should be mounted inside the building at the location the pipe enters that building. One lead of the panel needs to be attached to the copper wire and the other lead to the steel carrier pipe. The panel should then be plugged into a standard power outlet. THE IMPORTANCE OF EARLY DETECTION OF A BAD CRIMP, BROKEN WIRE, OR SHORTED WIRE CANNOT BE STRESSED ENOUGH. THIS IS BECAUSE REPAIRS AND CORRECTIONS CAN EASILY BE MADE TO A PIECE PRIOR TO A PIECE BEING WELDED IN THE TRENCH AND ESPECIALLY PRIOR TO BACKFILL. THERMACOR TESTS EACH PIECE AS IT LEAVES THE FACTORY, BUT NEVERTHELESS, DURING SHIPPING AND HANDLING, PIECES CAN BE DAM- AGED. IT IS THE CONTRACTOR S RESPONSIBILITY TO ENSURE THAT THE SYSTEM IS COR- RECTLY CONNECTED PRIOR TO BACKFILLING THE TRENCH. FOR ANY QUESTIONS PLEASE FEEL FREE TO CONTACT THERMACOR DIRECTLY AT (817)-847-7300.

14.604 SYSTEM DIAGNOSIS, POST- INSTALLATION REVIEW THE FOLLOWING IF YOU RECEIVE BAD READINGS WITH YOUR SYSTEM AFTER INSTALLATION. The following steps should be taken if a leak is suspected in your underground pre-insulated piping. 1. If the Alarm Panel goes into alarm, perform the following. 1. Turn off the power to the Panel 2. Disconnect Lead Wires at the Terminal Strip 3. Use a Hand Held Ohmmeter to take a resistance reading between the copper wire and the steel pipe. Make sure you are connecting to bare metal on the steel pipe. You will need to provide the resistance reading to either a Thermacor Sales Representative or a Thermacor Field Representative. 2. Perform the following steps based on the resistance reading: 1. Resistance 5000 (5 K ) Contact a Thermacor Field Service Representative to setup a site visit to isolate the problem*. The Representative will use a TDR to isolate the failure location. If you have a TDR at your facility, you can isolate the failure yourself**. Be sure to forward the TDR readings to Thermacor to validate the failure. 2. Resistance 100,000 (100 K ) and >5000 (5 K ) Take additional readings between the lead wire and the pipe. Remove any jumper wire and take a reading as close to where the wire exits the pipe as possible. Take readings on both terminal ends of the piping (where it enters the manhole or building.) If multiple runs are connected, disconnect additional runs and test each run independently. All readings should be very similar (within 10% of the original reading.) o If all readings are similar, inspect to make sure the valve pit is dry and no moisture is present on the end plate/end cap. o If the readings keep dropping, try to isolate the section with the lowest reading. Re-evaluate the resistance value and follow the appropriate steps. Provide your Thermacor Sales Representative with the resistance reading. Monitor the resistance every other day for 2 weeks and provide the readings to your Thermacor Sales Representative. o If the readings stay the same or improve, the original reading might have been caused by residual moisture which has dried due to system operation. Continue to take a reading once a month for 12 months to ensure the resistance does not drop. o If the reading deteriorates (by greater than 10%) over the 2 week period, contact a Thermacor Field Service Representative to schedule a site visit*. The Representative will analyze the routing using a TDR machine. If you have a TDR machine at your facility, you can try to isolate the system yourself**. 3. Resistance > 100,000 (100 K ) Your Panel has been damaged. Contact your local Thermacor Sales Representative to replace the ERM Panel. 3. A leak or short in the system will be signaled by an event on the TDR, represented as a sharp dip in the wave form. It is critical that you take several readings from different locations (i.e. different buildings and/or valve pits) because this will allow you to most accurately pinpoint leaks**.

14.605 11.04.09 *Water flashing to steam on a hot pipe, as occurs during a leak, will deteriorate the foam insulation. However, this deterioration is gradual, not immediate. Therefore, from the time of a leak, an owner still has time, potentially weeks, to arrange to have the leak located, excavated, and repaired before significant damage occurs to the system. **It is important to note that due to the manufacturing processes, there is more linear feet of wire in a system than linear feet of pipe. Therefore, taking TDR readings at several terminations is critical to get an accurate location of the leak. This minimal extra effort up front, to accurately locate the leak, will minimize potential excavation work.