LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

Similar documents
TECHNICAL MEMORANDUM

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Conceptual Design Report

2.0 Purpose. 3.0 Work Plan. Page 1 of 7

North Carolina Railroad Company Engineering Department. Design and Construction Guidelines

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

Harlem Avenue Interchange Design Discussion. August 24, 2015

Railway Alignment Design and Geometry

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

FINAL. Sound Transit Long-Range Plan Update Issue Paper S.6: Potential Tacoma Link Extension - East. Prepared for: Sound Transit

2.0 ALTERNATIVES. 2.1 Introduction. 2.2 No Build Alternative

Interchange Workshop Report (August 2004)

Optimal Scheduling of Railroad Track Inspection Activities and Production Teams

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

2010 Indiana Logistics Summit

Frequently Asked Questions Connecting Palo Alto

5/11/2016 SR 15 SECTION 088 CSVT SOUTHERN SECTION SR 15 SECTION 088 CSVT SOUTHERN SECTION AGENDA

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Becoming part historian to identify unknown and abandoned utility infrastructure from the bygone eras of railroading within the same footprint.

5.0 PRELIMINARY ENVIRONMENTAL REVIEW

Bonnie Doon Grade Separation

US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison

Upgrading Rail Lines for Higher Speeds

CHAPTER 3 SCOPE SUMMARY

Rte. 66/29 Interchange Reconstruction Project: ,C505 Grade Separation of Two Crossings Norfolk Southern Railway Right of Way and Track

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

Section IMPLEMENTATION PLAN. 7. Implementation Plan

SPECIAL PROVISION Description of Project, Scope of Contract, and Sequence of Work

Preliminary Engineering Report. For the. Foxglove Trail. Prepared for: The City of Moore. Prepared By:

Chapter 2. Alternatives

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

Commercial Ties. Cost Effective Solutions for Mainline Track Applications

CHAPTER 18 TEMPORARY ROADS AND BRIDGES

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

Uinta-Wasatch-Cache National Forest Service. 857 W South Jordan Parkway MEMO

Passenger/Freight Railroad Projects in Michigan

WELCOME HDR, all rights reserved.

COAST LINE CONNECTOR. Facilities Redevelopment Port Commerce Department

INCREASING CAPACITY ON THE SAN JOAQUIN CORRIDOR A PUBLIC-PRIVATE PARTNERSHIP

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

LONG BRIDGE - PRESENT & FUTURE: A MULTIMODAL ANALYSIS

LOCATION AND DESIGN DIVISION

Appendix B. Design. Page i. Design

49-2A Clear-Zone Width for New Construction or Reconstruction B Clear-Zone Adjustment Factor, K cz, for Horizontal Curve...

Rail Division 2012 Annual Summary

ESTIMATING MAINTENANCE COSTS FOR MIXED HIGHER SPEED PASSENGER AND FREIGHT RAIL CORRIDORS

Baltimore & Potomac Tunnel Project.

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017

Appendix E Cost Estimating Methodology for High-Speed Rail on Shared Rightof-Way

South Sounder Capital Improvements Program

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

Village of Glendale Quiet Zone Evaluation. Final Report Presented by: Railroad Controls, LP March, 2007

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting.

I-65/I-70 North Split Interchange Reconstruction Project Frequently Asked Questions

Benefit Cost Analysis Narrative

Operations Analysis using Simulation Modeling to Evaluate Capacity Requirements. for Direct Intermodal Rail Facilities at the Port of Long Beach

RESOLUTION NO

Long Bridge - Present & Future: A Multimodal Analysis

CLA /10.54, PID Project Description:

500 Interchange Design

Project Purpose and Need Statements

Going/Greeley Interchange Enhancements for Truck Operations

HAMPTON ROADS HIGH-SPEED AND INTERCITY PASSENGER RAIL PRELIMINARY VISION PLAN

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis

WOO-SR Feasibility Study (PID 90541) Feasibility Study Report April 22, 2011

TCWR Route Alternatives Study St. Louis Park Presentation November 29, Mark Amfahr Amfahr Consulting

I 244 Arkansas River LRT Track & Bridge Design Criteria Report

MEMORANDUM. Date: July 14, 2006 Project #: To: US 97 & US 20 Refinement Plan Steering Committee

NOISE TECHNICAL MEMORANDUM. Inland Rail Trail Project Cities of San Marcos and Vista, San Diego County DISTRICT 11 SD CML 5381(003)

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

Environmental Scoping Information Report

VII. FREIGHT MANAGEMENT

WELCOME TO THE LONG BRIDGE PROJECT

9.0 I-26 & I-526 Interchange Improvements

NATIONAL WESTERN CENTER

Willmar Wye Public Open House #4 and Public Hearing

Summary. 1. Introduction

Options for Sustained Freight Rail Growth

Appendix C Presentation Slides with Script

EXECUTIVE SUMMARY. Part 1 Introduction

Project Prioritization for Urban and Rural Projects TEAM CONFERENCE March 7, 2018

T a b l e o f C o n t e n t s

Section IMPLEMENTATION PLAN. 7. Implementation Plan

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project

Oversight Team Meeting

TABLE SUMMARY OF POTENTIAL CONFLICTS WITH MAJOR UTILITIES DUS ACCESS TO 162 ND AVENUE AREA

Route Selection and Design of a Coal Shuttle Railroad: Experiences of a Recent Railroad Engineering Graduate

DRAFT AIR QUALITY TECHNICAL MEMORANDUM

Railroad Surveys, Profiles and Topographic Surveys

Guidelines for New Development in Proximity to Railway Operations

<33 February OMF South Alternatives Evaluation Technical Memorandum

Public Meeting. US Highways 18 & 281 and SD Highway 50 From Douglas County Line to SD46 Charles Mix County

Rail Freight and Passenger

Preparation of an Environmental Impact Statement for High Capacity Transit

Chapter URBAN & RURAL FREEWAY DESIGN

LA 23 NOGC Railway Relocation PE/NEPA Project. Public Meeting

GREENE TOWNSHIP Pike County, Pennsylvania SPEED LIMIT STUDY T-370, T-372 & T-378

Town of Whitchurch-Stouffville Bethesda Side Road Reconstruction

Automated Condition Assessment as an Aid to Complying With the FTA State of Good Repair Regulations

Sieve Size 2" 1" 3/8" No. 10 No. 40 No. 200 % Passing Size

Transcription:

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR July 12, 2002 A Paper Submitted for the AREMA Annual Conference by: Paul B. Satterly, P.E. HNTB CORPORATION 111 Monument Circle, Suite 1200 Indianapolis, Indiana 46204 317-636-4682 Fax 317-917-5210

Abstract Lafayette Railroad Relocation, Norfolk Southern Corridor Paul B. Satterly, P.E. The Norfolk Southern Corridor project is the phase of the Lafayette, Indiana Railroad Relocation project that moved the Norfolk Southern Railway (NSR) from their existing corridor through the City to the new corridor adjacent to the Wabash River. The main focus of the railroad relocation project has been safety. When the Environmental Impact Statement (EIS) was put together in 1979, there were approximately 20 trains per day traveling on the NSR mainline. Since the split of Conrail, there is now an average of 50 to 60 trains per day and peaks of 80 trains per day have occurred. The Norfolk Southern Corridor project eliminated 20 busy grade crossings that have had a history of accidents resulting in many injuries and several fatalities. Components of the new 4.5-mile corridor have been under design and construction since 1986. The final construction to complete the NSR corridor started in 1999 and the NSR mainline tracks were cut-over on January 22, 2001. The alignment is designed for 50 mph and has two mainline tracks throughout. The corridor is grade separated and is shared with CSX. The corridor features four sets of railroad bridges over roadways and two highway overpasses. Because of innovative financing and the compression of the design schedule, the project schedule was reduced by four years, which allowed the project to provide earlier relief to the City from potential accidents in the existing corridor. Key Words: railroad relocation, railroad corridor

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR Background and Project History Relocation of the railroads in Lafayette, Indiana has been discussed since the predecessor to the CSX railroad was first constructed up the middle of 5 th Street in the 1850 s. Serious consideration was given to railroad relocation in the 1920 s but it was not until the 1970 s that work began on studies for the railroad relocation project. The Environmental Impact Statement for the project was completed in 1979. Design of the project started soon thereafter and the first phase of construction began in 1986. HNTB was hired for construction engineering and inspection for the first phase and continued as the lead designer and construction engineers for the remaining phases of the project. The project was broken down into phases, each designed to be a stand-alone project in case Federal Railroad Relocation Demonstration Project funding was constrained. The project goal was to eliminate 41 railroad-highway grade crossings through the downtown area by relocating the Norfolk Southern and CSX railroads to a corridor that parallels the east bank of the Wabash River. The CSX Railroad was relocated from the middle of 5 th Street to the new corridor in July 1994 and trains of the Norfolk Southern Railway were relocated to the new corridor in January 2001. Reference Figure 1 for the overall project map. The project consisted of independently usable segments and construction began on the first phase in 1986. This required a significant planning effort with the railroads and a track design that was completed ahead of the major design components. The segments for this project and their completion dates are as follows:

Wabash Avenue Grade Separation 1987 SR 26 Grade Separation and Wabash River Bridge 1992 9 th Street Grade Separation 1993 CSX Relocation, Harrison Bridge Grade Separation 1994 Wabash Avenue and 9 th Street Bridges 1996 US 52 Grade Separation and Embankment 1998 SR 25 Grade Separation 1999 Norfolk Southern Corridor 2001 The Norfolk Southern Corridor project was the final railroad related phase, with all other phases preparing the way for both the CSX and Norfolk Southern railroad relocations. The Norfolk Southern Corridor construction project represents approximately a third of the $180 million cost of the overall project. The Norfolk Southern Railway alignment through the City consisted of a double track mainline with 20 highway/railroad grade crossings. Train speeds were limited to 25 mph because of the numerous grade crossings. The City had enacted a whistle ban through the City because of the noise associated with the frequent trains. Many grade crossings did not have gates and car/train collisions were caused in part by trains passing each other on this section of track. The main focus of the railroad relocation project has been safety. When the Environmental Impact Statement (EIS) was put together, there were approximately 20 trains per day traveling

on the Norfolk Southern mainline and there was not much anticipated growth. Since the split of Conrail in 1999, there has been a considerable increase in train traffic. There now is an average of 50 to 60 trains per day and peaks of 80 trains per day though the City. The two track Norfolk Southern mainline crossed through Lafayette diagonally creating angled grade crossings at almost every street. In the three years prior to the writing of the EIS, there were 50 accidents along the Norfolk Southern of which 16 involved personal injuries. In recent years there were fatalities at the NSR crossings and collisions of vehicles running around lowered gates then hit by trains. The Norfolk Southern relocation eliminates 20 busy grade crossings that had the greatest potential for accidents, injuries and fatalities. The Norfolk Southern mainline now has no grade crossings within the central city. The new corridor is fenced throughout to prevent pedestrian trespassing. The city aggressively pursued an advanced construction schedule in 1998 by proposing an innovative financing plan. Norfolk Southern and the Indiana Department of Transportation together advanced funds totaling $16.4 million to accelerate the project, to be paid back in later years as federal funds became available. The advance of these funds and the acceleration of the project schedule became more important because of the increase of train traffic on the Norfolk Southern corridor due to the Conrail split. The City was concerned that with the increased train traffic, additional accidents might occur at

the grade crossings before Norfolk Southern tracks were relocated. Design was completed in October 1998 and construction began in early 1999. The alignment along the new corridor is approximately one-half mile longer than the old alignment but speeds have been increased significantly. General freight can travel up to 50 mph and the road-railers can travel up to 60 mph. These speeds match the speeds allowed on the mainline north and south of the City. Trains can also stop at the East Yard and not block grade crossings. Updated track signaling allows train traffic in both directions on both tracks. Additional crossovers allow greater flexibility in train movements and also increase capacity on the line. Design and Design Criteria Close to 4.5 miles of two track mainline were built in this final railroad construction project. The Norfolk Southern mainline is single track north and south of the project. Two tracks were constructed in the corridor to replace the two tracks that traversed through the City. Along with the mainline track, a three track interchange yard was constructed between Harrison Bridge and 9 th Street, a two wye track yard connection was constructed at the south end of the East Yard along with the construction of a pull-back track using an existing NS mainline track south of Underwood Street. Portions of the railroad grade and all railroad bridges had been constructed during previous construction projects. The railroad grade had been constructed between Wabash Avenue and 9 th Street and between US 52 and SR 25.

The Norfolk Southern corridor was designed for 50 mph freight operations with a maximum 4º00 horizontal curvature, although road-railer trains are able to travel at 60 mph through the corridor. Refinements in design at the north end of the project introduced two 5º00 curves and a compound curve of 4º30 /4º00 reducing the design speed to 40 mph. These refinements consisted of extending the wye track lead up to the US 52 bridge where the 4º00 curve was changed to two 5º00 curves with enough tangent track in between to install a No. 15 turnout. The compound curve alignment allowed the mainline track to be tied into existing track at an earlier point than what was originally designed allowing the reuse of additional existing trackage and yard leads. This change provided additional clearance between the mainline tracks and the yard lead. Conventional track construction was used in this project. Wood ties, cut spikes and 136 lb. rail were used. No. 10, 15 and 20 turnouts were used and a double crossover is located approximately half way through the new corridor. The maximum grade is 0.75% and is used on either end of the corridor as the line drops down next to the Wabash River. Areas of Concern and Design Focus To make the project successful, many years of planning and redesign were required to satisfy the operating needs of the two railroads that were to share the corridor. The EIS in 1979 was concerned about the basic placement of the railroad corridor. It was not until later in the project that design issues concerning track and train operation details had to be addressed. Many track alignment details were worked out in this final railroad construction contract. This section addresses the

refinements in the final design for the Norfolk Southern Corridor made as a result of numerous meetings and discussions with Norfolk Southern, the City of Lafayette and HNTB personnel. Lafayette Junction Lafayette Junction is located at the south end of the project. This is where the Norfolk Southern Muncie line crosses the CSX and also where the two railroads diverge from each other. The original design did not address the railroad s current operating needs such as trackage rights for NSR on CSX as a result of the Conrail split. The original alignment concept had NSR as a single track though the junction and then splitting into two tracks at the north end. To resolve the single track bottleneck and to allow NSR to CSX movements, the eastern most NSR track was extended to make a direct connection with the NSR Muncie line and an additional No. 10 crossover was added. The junction now consists of one No. 15 crossover between the No. 1 and No. 2 NSR mains, a No. 20 crossover between the No. 1 and No. 2 mains, and two No. 10 crossovers between NSR No. 2 main and CSX. Signal mounds were added for signal bungalows and signal bridges. The original and final junction designs are shown in Figure 2. Interchange Yard The interchange yard consists of a double ended three track arrangement that can be switched by both railroads at both ends. Each track is approximately 2,200 ft. in length. The yard is located between the mainlines at the south end of the CSX yard.

The track alignment at the south end of the interchange yard was modified from the original design. The double track lead into the yard was reduced to one track to simplify operations, improve safety and to allow the installation of split point derails. The railroads were concerned about the possibility of cars rolling out the south end of the yard due to the 0.30% grade. To prevent cars from rolling on to the NSR and CSX mainline, split point derails were installed on both mainline leads to the yard. The previous yard design had its entire 2,200 foot length at 0.30%. Modifications to the north end of the yard, interchange lead and interchange bridge, allowed the north half of the yard to be constructed at a 0.00% grade. The original and final interchange yard lead designs are shown in Figure 3. East Yard The original design of the Railroad Relocation project was approved in 1983 by the Indiana Department of Transportation and other agencies. The original design included a single wye track connecting the south end of the East yard to the realigned mainline tracks and a pullback track to switch the East yard that ended at Underwood Street. The goal of the relocation project was to remove tracks from all grade crossings within the City including Underwood Street. Upon further discussions with Norfolk Southern, it was determined that modifications were needed to the wye track arrangement and that terminating the pull-back track at Underwood Street was unacceptable in terms of yard operations. The pull-back track was not of sufficient length to efficiently switch the yard; another 2,200 feet of track was needed. Norfolk Southern requested that the pull-back track be extended up to Greenbush Street, requested the addition of another wye track and requested that the wye track lead be extended up to the US 52 bridge.

The City was determined to keep tracks from crossing Underwood Street. Therefore, a study was performed to investigate alternatives to the extended pull-back track. Four alternatives, discussed below, were studied that included: a beltway pull-back track, a north end pull-back track, the originally designed pull-back track and the extended pull-back track. See Figure 4 for the location of these alternatives. Norfolk Southern needed wye track lengths of at least 2,200 feet to handle cuts of cars from the yard and the pull-back track had to be a sufficient length (at least 2,400 feet from the end of the wye tracks) to allow for the switch moves. Beltway Pull-Back Track - The beltway track was connected to only two of the main yard tracks and could not be connected to any other yard tracks or the proposed wye tracks without major reconstruction of the yard. Reconfiguration of the yard, to make the other tracks accessible, would have cut the yard capacity in half. Industrial activity in the Lafayette area required the use of the yard with its existing capacity. The sharp curvature of the beltway track made it unsuitable for pulling and pushing long cuts of cars due to the undesirable train handling characteristics of this type of movement on a sharp curve and the lack of visibility. For these reasons, the beltway pull-back track alternative was determined to be unacceptable. North End Pull-Back Track - This alternative required the construction of a bridge across the Wildcat Creek to allow pull-back operations to be conducted from the north end of the yard. It also required the reconstruction of the ladder track on the north end of the yard and the construction of four tracks parallel to the proposed NSR mainlines between the north end of

the yard and the SR 25 bridge. The topography of the north end of the yard was not conducive to switching operations since the north end of the yard slopes toward Wildcat Creek. This grade would have made it difficult to shove cars south into the yard and to couple to cars within the yard. This grade would have caused additional difficulties by allowing cars to roll out of the yard and onto the switch leads. This alternative cost was estimated at $10 million, but the cost issue was not the deciding factor since the north end pull-back alternative was found to be operationally unacceptable to Norfolk Southern due to the grades and the need to cross the creek. Pull-Back Track Ending Before Underwood Street - Ending the pull-back track at Underwood Street would have required shortening the two wye tracks from a length of 2,200 feet to a length of 1,200 feet each. Each track would have had a capacity of 15 to 20 cars and the total capacity of these two tracks (30 to 40 cars) would be approximately half of what would be available with an extended pull-back track. It was not possible to add two additional tracks to the wye track group to increase the track capacity because of restrictions in geometry at the east end of the SR 25 bridge and because of restrictions created by the track curvature. Norfolk Southern needed a total car capacity of 60-70 cars in the wye track group to adequately service their westbound trains. Therefore, the pull-back track ending before Underwood Street was found to be an unacceptable alternative to Norfolk Southern. Pull-Back Track Ending Before Greenbush Street - In order to accommodate a pull-back track in the preferred location, the track needed to extend to a point 300 feet north of Greenbush Street. This design provided enough room for a switch locomotive with cars to

move back and forth into the yard assembling a cut of cars that may be up to 2,200 feet long (30 to 35 cars) and then putting these cars in one of the two 2,200 foot wye tracks. The two wye tracks start just east of the SR 25 bridge, extend to just north of the Underwood Street grade crossing and have a total car capacity of 60 to 70 cars. There would be approximately 2,400 feet of track between the south switch of the wye tracks and the end of the pull-back track at Greenbush Street allowing 200 feet of track for margin of safety. This alternative would reuse a mainline track and would extend across Underwood Street. This alternative was preferred by Norfolk Southern and was accepted by the City of Lafayette. Once it was determined that tracks would not be removed from Underwood Street, the City took the issue to the public to determine the citizen s preference for keeping the crossing open with grade crossing protection, or closing the crossing to vehicles. Earlier studies determined that a grade separation at this location would not be feasible from a cost and neighborhood impact standpoint. After collecting input at the public meeting, the City decided to keep the grade crossing open to provide the mobility in the neighborhood that was desired. The crossing would have a single track and would have infrequent slow moving trains crossing at this location. Fencing was constructed on both sides of the pull-back track to prevent trespassing and landscaping was added along the pull-back track to mitigate the visual impact of the fence and track. Quad gates were installed at the crossing and motion detectors were used to activate the gates. Erie Street was constructed parallel to the pull-back track to connect Underwood

Street and Greenbush Street to provide an alternative route for neighborhood traffic in the event of a crossing blockage. Maintenance of Train Traffic Maintenance of train traffic was an important factor in the development of the design plans. The sequence of construction was driven by the need to maintain train movements. This was an added factor in the final design of the corridor. The construction of the mainline at the south end of the project required the NSR Muncie line to be taken out of service. This track was used by CSX for their trackage rights to the south side of Lafayette. Mainline track was constructed along the new corridor from Lafayette Junction to the wye tracks where a temporary connection was made to the NSR mainline. This trackage was used to transfer CSX traffic to the south end of the City, cars were routed north up the new mainline to the East Yard and back south though the City to get the south end once again. This arrangement eliminated the need for a costly temporary track and helped to speed construction south of the junction. Once the NSR mainline was cut-over, the old mainline was taken out of service to allow the construction of the Muncie line. The mainline tie-in at the north end of the project was modified to facilitate the maintenance of train traffic. The alignment was changed to tie into the existing mainline at a point where track shifts were more manageable and to eliminate the need for temporary track. This allowed more existing mainline track to be reused.

Other Design Details There are several other design details that were refined and developed after NSR s review of the concept drawings and during design. Details such as signal mounds, access roads, fencing and drainage were addressed during final design. The subgrade was widened at crossover locations to allow for the installation of signal bungalows and signal structures. This often necessitated piping the adjacent ditch and in some cases, using gabion retaining walls to allow encroachment into the earth sound attenuation berms. See Figure 5 for a typical section showing the use of gabion walls. Access roads were non-existent in the original design. Access roads were added by widening the subgrade and embankment where feasible throughout the corridor. The corridor through the downtown area has only 17 feet clearance to the retaining walls, therefore roads could not be installed in these areas. These roads provide access to all signal equipment, power operated turnouts and crossovers. To prevent pedestrian trespassing, 6 foot black vinyl chain link fencing was installed on both sides of the corridor. Gates were installed to provide access to the corridor. The fencing is also used to guard drop-offs at the tops of retaining walls and sound attenuation berms. Since the rail corridor is narrow in several areas, paved side ditches were designed to drain these areas. Where the clearance from centerline of track is 17 feet, a 5 foot paved side ditch

was used. A three foot paved side ditch was used in areas with 15 foot clearance. See Figure 6 for a paved side ditch typical section. Summary It is important to get input from all departments of the railroad during planning and final design. Many design factors can develop that may be unknown by the various departments without coordination. Train operations affect the sequence of construction and signaling needs affect the width of embankments and the design of the track. Because of the oversight by the City of Lafayette on this project, design changes and changes in the scope of the project had to be approved by the City. It was important to have the City participate in design discussions, especially because many of the proposed changes increased the cost of the project and affected the City and its neighborhoods. Anytime the project varied from the concepts outlined in the EIS, the proposed changes were presented at a public meeting. These public meetings were important to obtain consensus from the public. In most all instances, the changes presented at these public meetings were endorsed by the majority of the people in attendance. The Underwood Street crossing issue was the most difficult due to the City s desire to keep this crossing closed to trains. Through meetings with the railroad and meetings with the public, the need for a pull-back track through this crossing was understood and cleared for design.

Because of the size of this project, it was important to develop independently usable design segments due to uncertainty in federal funding. All project segments were packaged so they would be no more than $15 million, to match the funding stream. It is ironic that the lowest density line was relocated first followed by the next highest in terms of density (CSX). The big payoff in terms of removing the majority of trains from the center of the City was not realized until the final design segment with Norfolk Southern. The final relocation of Norfolk Southern was key in mitigating the increased train traffic experienced by Norfolk Southern due to the split of Conrail. The acceleration of the project scheduled helped to reduce the amount of time these grade crossings were exposed to the increase in train traffic. The City of Lafayette had the vision to relocate the railroads and devoted a staff to look after the project and assure its completion. This project has had widespread community support from the beginning of the planning process in the 1970 s all the way through the final relocation of the Norfolk Southern railroad. The project has been a success. The CSX and Norfolk Southern railroads can move through a conflict free corridor and have significantly increased their speeds and flexibility in operations. The biggest measure of success, of course, has been the elimination of 41 busy highway/railroad grade crossings within the City.

List of Figures Figures Figure 1 Figure 2 Figure 3 Figure 4 Figure 5 Figure 6 Overall Project Map Lafayette Junction Interchange Yard East Yard Pull Back Track Alternatives Typical Cross Section, Gabion Walls Typical Cross Section, Paved Side Ditch

FIGURE 1 Overall Project Map Lafayette Junction SR 26 Bridge Harrison Bridge New Corridor 9 th Street Bridge US 52 Bridge Wabash Ave. Bridge Wye Tracks SR 25 Bridge Old Corridor Pull Back Track East Yard

FIGURE 2 Lafayette Junction CSX Mainline KBSR Track NSR Muncie NSR Mainline Original Design Concept NSR Mainline CSX Mainline No. 10 Crossover No. 10 Crossover KBSR Track NSR Muncie No. 15 Crossover NSR Mainline No. 20 Crossover NSR Mainline Revised Design Concept

FIGURE 3 Interchange Yard CSX Mainline Interchange Tracks NSR Mainlines Original Design Concept CSX Mainline Interchange Tracks Split Point Derails Single Track Yard Lead NSR Mainlines Revised Design Concept

FIGURE 4 East Yard Pull Back Track Alternatives End of Wye Tracks 2,200 ft. 1,200 ft.

FIGURE 5 Typical Cross Section, Gabion Walls

FIGURE 6 Typical Cross Section, Paved Side Ditch