Pasquia Area Drainage and Pumping System

Similar documents
A Proposed Regulation under The Water Rights Act

City of Edmonton Drainage Services Summary Notes of Cloverdale Flood Mitigation Meeting Held May 13, 2015 at Cloverdale Hall

Water Security Agency. Plan for saskatchewan.ca

Water Security Agency. Plan for saskatchewan.ca

RED RIVER FLOODWAY OPERATION REPORT SPRING Manitoba Infrastructure

GENERAL SPECIFICATION FOR TEMPORARY FLOW CONTROL FOR CONSTRUCTION IN WATERBODIES

SURREY COASTAL FLOOD ADAPTATION STRATEGY (CFAS) South Nicomekl Irrigation Meeting November 2 nd, 2016

Respecting Our Rivers Alberta s Approach to Flood Mitigation

City of Edmonton Drainage Services Summary Notes of Riverdale Flood Mitigation Meeting Held May 14, 2015 at Riverdale School

ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT

Forecast Informed Reservoir Operations for Groundwater Recharge Prado Dam

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)

SHARING THE EXPERIENCES IN MODERNIZATION OF IRRIGATION SYSTEMS IN KOREA POPULATION IN THE WORLD

Background and History of Water Management of Okanagan Lake and River

Flood risk management and land use planning in changing climate conditions Mikko Huokuna Finnish Environment Institute, SYKE

LAW OF THE REPUBLIC OF INDONESIA NUMBER 7 OF 2004 REGARDING WATER RESOURCES

Update on Cuyama Basin Groundwater Modeling

Management of Water Resources in Cyprus

TECHNICAL MEMORANDUM Summerhill Rd Texarkana, Texas fax


CONSTRUCTION SPECIFICATION FOR DEWATERING

Chapter 1 Introduction

CANADA: FLOOD MANAGEMENT IN THE RED RIVER BASIN, MANITOBA

Columbia River Treaty Frequently Asked Questions (FAQs)

APPENDIX E ESTIMATING RUNOFF FROM SMALL WATERSHEDS

Review of Hydrological Potential in Combined Gin and Nilwala River Basins of Sri Lanka

Background to the Saskatchewan River Basin

South Saskatchewan River Sub-Basin Contributions To International and Interprovincial Water-Sharing Agreements

Physical Works Terms of Reference

Independent Expert Engineering Investigation and Review Panel. Report on Mount Polley Tailings Storage Facility Breach. Appendix G: Water Balance

Subject: Notice of Preparation of a Draft Environmental Impact Report

Lake Texoma Water Management Frequently Asked Questions (FAQs)

An Overview of 2009 Spring Flooding in Manitoba

Dry Creek Flood Control Improvement Project

Implementation Plan and FAQs for the Guide to Water Act Authorizations Required for Dugouts, Borrow Pits and other types of Pits/Excavations

Storm Water Management

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT

TERMS OF REFERENCE SOUTHWEST INTERLAKE INTEGRATED WATERSHED MANAGEMENT PLAN

Great Lakes Update. Volume 189: 2013 January through June Summary

APPENDIX E APPENDIX E ESTIMATING RUNOFF FOR SMALL WATERSHEDS

DRAINAGE AND NATURAL AQUIFER GROUNDWATER RECHARGE ELEMENT

Prior Lake Stormwater Management & Flood Mitigation Study

EID POLICY MANUAL. WATER Water Delivery and Operations Policy Revised January [supersedes May ]

WATER 101. Chris Treese. May 26, 2015 Grand County State of the River

2017 Operations Update Meeting. Castlegar Monday, 1 June 19, 2017

DRAINAGE. Actions for Tomorrow. Drainage. Actions Today

RECOMMENDATION PREVIOUS REPORTS PERTINENT TO THIS MATTER STRATEGIC PLAN

Land Evaluation & Area Review (LEAR) Study and Minimum Distance Separation (MDS) Review

TECHNICAL MEMORANDUM

2.0 Existing Conditions

Modelling Environmental Systems

ADDITIONS & DELETIONS TO THE COMPREHENSIVE PLAN

AND WHEREAS the Minister is satisfied that all the requirements of the Act have been met, including those required of Premier Tech;

Modelling Environmental Systems

REPORT UNDER THE OMBUDSMAN ACT. CASES and MANITOBA SUSTAINABLE DEVELOPMENT

SILVER SPRINGS/RIVER POLLUTION REDUCTION PROJECT IMPROVING THE WATER QUALITY OF THE SILVER SPRINGS ECOSYSTEM

Columbia River Drainage

Yoshinaga Ikuo *, Y. W. Feng**, H. Hasebe*** and E. Shiratani****

Staff contact: Mr. Bob Holden, Principal Engineer Phone: (831) Fax: (831)

Welcome to the Farmers Workshop. Tuesday 9 th March 2010 Commercial Hotel, Tarland

John H. Kerr Dam and Reservoir Virginia and North Carolina (Section 216)

AGRICULTURAL DRAINAGE CRITERIA

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

AREA STRUCTURE PLAN SW W4M CAMROSE COUNTY BYLAW ## JULY 2017(REVISED) PREPARED BY: AUSTROM CONSULTING &VICINIA PLANNING & ENGAGEMENT INC.

AENV Water Shortage Procedures for the South Saskatchewan River Basin

Agricultural Land and Water Policies

2015 Restoration Allocation and Default Flow Schedule January 20, 2015

Terms of Reference. for an Approved Water Management Plan to be Developed for the Milk River Basin (Alberta) Phase One.

A Tale of Two Dams and a dry river. November 1, 2011 Planning, Resources and Technology Committee Mojave Water Agency

PAKISTAN BALOCHISTAN SMALL SCALE IRRIGATION PROJECT (SSIP) PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB1661 Project Name

SITE ALTERATION PERMIT INFORMATION PACKAGE FOR LAND OWNERS

Klamath Hydroelectric Project Interim Measure 11 Study Activities for 2018

CRYSTAL LAKE FLOODING STUDY EXECUTIVE SUMMARY

The Water Act in brief The Water Act. in brief. The Netherlands

List of Appendices APPENDIX A: WY 2000 LAKE MICHIGAN DIVERSION ACCOUNTING REPORT APPENDIX B: WY 2001 LAKE MICHIGAN DIVERSION ACCOUNTING REPORT

(#' John Irving, P.Eng. Director, Engineering ( )

Protection of wetlands as an element of water management in rural areas

ANALYSIS OF HYDRAULIC FLOOD CONTROL STRUCTURE AT PUTAT BORO RIVER

Introduction. Manure Management Facts Prioritization and Rotation of Fields for Manure Application. July 2014

FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN. EB3679 February 2011

APPENDIX A. Hydraulic Investigations: Cascade Mall at Burlington

FLOOD IMPACTS ON BUILT INFRASTRUCTURE AN OVERVIEW

Colorado River Challenges Impacts to Southern Arizona

5 SUTTON/JACKSON'S POINT SECONDARY PLAN

Exploring the Possibilities At Prado Dam

SUMMARY OF COMMENTS/RECOMMENDATIONS

Report. Office of the General Manager. Colorado River Management Report. Summary. Detailed Report

Facts and Figures. Greater Victoria Water Supply Area. May 2015

GCI Survey---Lake Winnipeg Watershed

Water Management Under Severe Storm Conditions in Central and South Florida

Environmental Guideline for Saskatchewan Asphalt Plants

Prepared by: UMA Engineering Ltd. March City of Pitt Meadows Proposed Drainage Utility

Water and Climate Change in British Columbia, Canada

Government. Alberta s Irrigation A Strategy for the Future

Public Information Centre No. 1

Canada-Ontario Domestic Action Plan for Lake Erie Phosphorus Reduction. Agriculture Sector Working Group April 19, 2017

THE KBRA S UNWARRANTED AND COSTLY SUBSIDIES

WATER FROM THE CLOUDS

OLD DUNDAS ROAD SEWAGE PUMPING STATION (HC005) EMERGENCY OVERFLOW SCHEDULE C MUNICIPAL CLASS ENVIRONMENTAL ASSESSMENT (EA)

Adapting to climate change: examples from the Netherlands. The Netherlands 31/03/ % below sea level 65% would be flooded in absence of dikes

Transcription:

Pasquia Area Drainage and Pumping System Review of Operating Guidelines Public Open House August 22, 2017

Welcome! Manitoba Infrastructure, the Rural Municipality (RM) and The Pas and District Farmer s Co-op Association are currently conducting a review of the operating guidelines to develop a sustainable plan for future drainage and pumping in the Pasquia Area Land Settlement. You ve been invited to share your views at this open house. Manitoba Infrastructure operates the pumping system in consultation with the Pasquia Pumping Committee and in accordance with the Operating Guidelines for Pumping Runoff, called Operating Guidelines. The Pasquia Pumping Committee includes representatives from The Pas and District Farmer s Co-op Association and the RM of Kelsey. Changes to the operating guidelines for provincial water control works may be approved by the minister under Section 5 of The Water Resources Administration Act. The province would like to solicit comments regarding proposed revisions to the operating guidelines. We value your feedback! Ask us any questions you may have. Share your thoughts on the presented information. Fill out a comment form.

Background The Pas area is bordered by the Pasquia River (south) and the Carrot and Saskatchewan Rivers (north). It is very flat with an average elevation of 850 860 metres (m) above sea level. The need for new lands was identified by the Manitoba government and in 1914 they began to examine rehabilitation of the area. Feasibility studies began in 1921 and in 1951 the Manitoba government initiated the Pasquia Project. Agricultural lands are maintained through a system of dikes, drains and five pumping stations. The area contains four polders (area reclaimed and protected by dikes). 1970 s to early 1980 s Completion of Polders 1 and 2. Demand for additional land for agricultural use re-emerged. Reclamation scheme was implemented to further develop the area. 1986-1991 The upper portion of the Pasquia River was blocked, and diverted to the Carrot River. By diverting the upper portion, the size of the Pasquia River catchment basin was reduced thereby reducing the amount of water naturally reaching the river. Conceptual plans finalized and the overall development scheme was downsized. Proposed the full development of Polder 3 east for agricultural use and Polder 3 west (Big Lake area) for a temporary water storage facility. Construction of the Pasquia Lake Drain and the Victor Jory pump-house as funds became available. Approximately 25% of the total project plan was completed during this period.

Background The project area is serviced by five pumping stations: 1. Town Pump Station: Upgraded in 2001 and located closest to the Town of The Pas. Four pumps each pumping 125 cubic feet/second (cu ft/second) or almost 47,000 gallons/minute. Includes a gravity system that can move another 300 cu ft/second of water. Adjacent to the Town Pump Station is the Knapp Dam which prevents Saskatchewan River waters from flowing up the Pasquia River. 2. Mile 9 Station: Installed in 1977, located nine miles from the Town of The Pas along Provincial Road 283. Each of these two pumps move 105 cu ft/second of water or almost 40,000 gallons/minute/pump. 3. Mile 14 Station: Upgraded and operational in 2016, located fourteen miles from the Town of The Pas. This pump station has the capacity of 210 cu ft/second. 4. Mile 18 Station: Installed in 1976, located eighteen miles from the Town of The Pas. There is one pump at this station that moves 125 cu ft/second of water. 5. Victor Jory Pump Station: Opened in 1989, located on the south side of the valley. This station has two pumps, each moving 105 cu ft/second. There are 100 km of provincial drains in the Pasquia area removing water from farmland into the Carrot, Pasquia and Saskatchewan rivers. 2011 / Recent Upgrades Two additional pumps were installed at the Town Pump Station that were dedicated to pumping the Pasquia River. Two pumps dedicated to Z Drain can be switched to the Pasquia River if they are not required on Z-Drain. Additional pumping capacity on the Pasquia River was to compensate for the inflows added to the river from the Victor Jory Pump Station. The two pumps provided the ability to lower the level of the river below the natural condition as water originating from outside the project area could also be removed during periods when gravity flow at Knapp Dam is precluded.

Existing Operating Guidelines The current operating guidelines were approved in 2008. Operating guidelines are intended to balance interests of agricultural producers. The existing operating guidelines are available online at: http://www.gov.mb.ca/mit/wms/wm/pasquiareview.html OR Copies are available today as a handout.

Annual Hours Issues with the Existing Operating Guidelines Current guidelines are driving operations to be financially unsustainable. Pumping Operations Historical Trend Annual Hours 16000 JORY THE TOWN PUMP STATION MILE 9 MILE 14 MILE 18 BIG LAKE 14000 12000 10000 8000 6000 4000 2000 0 Year Budget Actuals 2009/10 $170,000 $121,500 2010/11 $125,000 $183,500 2011/12 $150,000 $672,500 2012/13 $350,000 $395,000 2013/14 $400,000 $506,500 2014/15 $450,000 $657,200 2015/16 $450,000 $186,500 2016/17 $450,000 $766,500 2017/18 $450,000 $511,600

Proposed Changes to the Operating Guidelines 1. Increasing the threshold water level for pumping the Pasquia River. Current guidelines specify that dedicated pumping of the Pasquia River at the Town Pump Station will commence when the level at Young s Point exceeds 259.0 m. The proposed revision would increase the threshold level for pumping to 260.35 m. In order for Victor Jory to maintain a similar level of service a consequential amendment is required: Current guidelines allow for pumping at the Victor Jory Pump Station when levels of the Pasquia River at Young s Point are below 259.3 m. The proposed revision would allow pumping whenever the Young s Point level is below 260.35 m. Note: the maximum level of the Pasquia River at Young s Point in 2017 was 260.44 m on July 10 th. 2. Changes to the regulation of Big Lake. The existing guidelines state that the operating range of Big Lake is 259.50 m to 260.15 m. The existing guidelines allow water release from Big Lake when the water level at Young s Point is below 259.3 m during post spring runoff. The proposed revisions include: Eliminating the operating range. Water may be released from Big Lake when the level exceeds 259.50 m. Release of water from Big Lake would be allowed subject to guidelines governing operation of the Victor Jory Pump Station. Outflows from Big Lake must be regulated to maintain a level below 258.55 m downstream of the Donfield crossing during the growing season. The Big Lake Control Structure shall be operated at the discretion of the province in consultation with the Pumping Committee. 3. Changes in water levels on Z Drain A change is proposed regarding the level at which Z Drain is to be maintained. Formerly, the water level at the junction of Q Drain and Z Drain was to be maintained below 258.5 m. The proposed revision would lower the target level to 258.1 m. Note: No changes to the operating guidelines are proposed relating to the operation of Mile 9, Mile 14, or Mile 18 Pumping Stations

Rationale for Proposed Changes to the Operating Guidelines: The existing operating guidelines were developed and adopted during a drier period in the hydrologic cycle. There have been increasing demands on the drainage and pumping system from persistent wet conditions and extreme weather events such as the unprecedented rainfall that occurred in October and November 2016. Need to develop sustainable guidelines Current guidelines may not be affordable The Provincial budget for pumping runoff has been exceeded 4 out of the last 5 years. Expenditure trends are not sustainable. By raising the threshold level for pumping on the Pasquia River the proposed changes will allow gravity flow to occur at Knapp Dam more frequently. This will reduce pumping costs in average precipitation years and will significantly reduce costs in wet years. Pumping the Pasquia River presently accounts for about 25% of the total pumping budget in The Pas. Rising fuel prices could significantly increase future pumping expenditures. 140 130 120 110 100 90 80 70 Diesel Fuel Price Trend 60 2009 2010 2011 2012 2013 2014 2015 2016 2017 Annual Average Diesel Price (Ontario) Canadian Dollars per Litre Source: Ontario Ministry of Energy The Manitoba government is in discussions to cost share pumping costs with the stakeholders. In 2016 local stakeholders contributed in excess of $100,000 towards pump operation costs. For the current and future years, the Manitoba government will be requiring local cost sharing of operating costs.

Advantages and Disadvantages: Advantages Reduced pumping costs would contribute to a more sustainable operation. More flexibility to move water out of Polder 3 and Big Lake. Disadvantages Agricultural leases along the Pasquia River total approximately 5,000 acres. During wet years or during periods when gravity flow at Knapp dam is precluded, portions of these lands will be flooded. This situation will cause hardship to producers who rely on those leases for pasture and forage. Several parcels of privately owned land will be affected during high water periods. Loss of use during wet periods may financially impact the property owners.

Questions and Comments Comment forms are available here today or please feel free to share your feedback using the following link: https://manitobasurveys.gov.mb.ca/checkbox/pasquiaareadrainage.as px Reach out to one of the Manitoba Infrastructure, RM of Kelsey or Pasquia Pumping Committee representatives here today! They would be happy to answer any questions or discuss the proposed operating guidelines with you! OR Contact: Dan Laychuk Acting Director Regional Water Operations Phone: 204-648-4217 Email: Dan.Laychuk@gov.mb.ca