Passive House in Canada: Case Studies on a Near EnerPHit Retrofit and Post-Occupancy Research

Similar documents
ENERGY EFFICIENT RETROFIT OF A HIGH-RISE MULTIFAMILY BUILDING

Deep Energy Retrofit of a HighRise MURB

EVALUATING THE ENERGY SAVINGS OF HIGH PERFORMANCE BUILDING ENCLOSRE RETROFITS Brittany Hanam, MASc, P.Eng. Graham Finch, MASc, P.Eng.

airflow in to, out of, and within buildings. These airflows are resisted by the airtightness of building elements including the exterior enclosure and

COMPARISON OF ENERGY USE INDICATORS OF A NON-RESIDENTIAL PASSIVE HOUSE WITH ASHRAE 90.1 BUDGET BUILDING

Homesol Passive House Design Process

THE IMPORTANCE OF BALCONY AND SLAB EDGE THERMAL BRIDGES IN CONCRETE CONSTRUCTION

The Importance of Slab Edge & Balcony Thermal Bridges

Hamilton Way - Case Study of a High Performance Community in a Cold Climate

Passive Design Solutions. Passive House The Road to Net-Zero

Corridor Pressurization System Performance in Multi-Unit Residential Buildings

NYSERDA High Performance Development Challenge Energy Monitoring Report Hudson Passive Project

Mark Lawton, P.Eng., FEC. Airtightness in Buildings A Canadian History June 2017

2017 SeaBEC Symposium. Advancing Building Enclosures Beyond Code Conformance. Medgar Marceau, PE Principal, Senior Building Science Engineer

Net Zero Building Enclosure Retrofits for Houses: An Analysis of Retrofit Strategies

Future tree planting on the two acre lot will offset remaining lifetime carbon emissions.

Balancing the Control of Heat, Air, Moisture, and Competing Interests

A New Paradigm for the Design of Sustainable Buildings

The Importance of Slab Edge & Balcony Thermal Bridges

1.1 BUILDING DESCRIPTION:

Passiv Haus Institut. Certification as "Quality Approved Passive House" Criteria for Non-Residential Passive House Buildings

PART 9 ENERGY EFFICIENCY AND VENTILATION REQUIREMENTS (For Single and Two Family Dwellings)

Project name Gentoo Retrofit Bid 1 Project summary Refurbishment of 2no. Semi Detached houses using Passivhaus principles

Performance-Risk Methodology for the Design of High-Performance Affordable Homes

Rainscreen Walls: Field Monitoring and Performance in British Columbia

Project Description. Projected build start date 01 Mar 2010 Projected date of occupation 01 Aug Energy target.

2014 British Columbia Building Code Changes

Dienstleistung. Certification as "Quality Approved Passive House" Criteria for Residential-Use Passive Houses

Nearly Zero Energy Building in Lecco Modern technological building compared to an ancient Villa

71 kwh/(m²a) Project Documentation. 1 Abstract. Single family house in Bellbrae, Victoria, Australia. 1.1 Data of building. Year of construction

BUILDING ENCLOSURE DESIGN GUIDE WOOD FRAME MULTI-UNIT RESIDENTIAL BUILDINGS. Summary. 1. Introduction

ENERGY STAR Qualified Homes National Program Requirements, Version 3.0

Three-Story Victorian Partial Retrofit. Overview. Case Study

Built examples and project certification. Zeno Bastian, Passive House Institute

Work Package 2: Performance of naturally ventilated buildings

Great Ocean Rd Ice Creamery

Case Study #9 Phoenix Rising

No ASHRAE Standard By Susan Hayes, P.Eng., LEED AP BD+C & Graham Finch, Dipl.T, MASc, P.Eng. October 2012 rdh.com 1

Energy Efficiency Requirements 9.36

Project Description. Projected build start date Projected date of occupation. Existing external wall construction.

Energy Consumption in Mid- and High-rise Residential Buildings

2012 Ontario Building Code Requirements for New Construction. Bradford West Gwillimbury Building Division March 5, 2012

PNWER Roadmap to Net Zero Construction and Deep Retrofits by 2030

St Loyes Extra Care Facility PHPP Pre-Assessment Report

Project Description. Projected build start date 12 Apr 2010 Projected date of occupation 28 Feb

Project name SOLAR HOUSE 80/50 Project summary

2 x BPE studies of Passivhaus domestic projects

A Field Study of Airflow in Mid to High-Rise Multi-Unit Residential Buildings

Project Description. Projected build start date 02 Aug 2010 Projected date of occupation 03 Dec Existing external wall construction

Could a European Super Energy Efficient Standard Be Suitable for the U.S.? John Broniek, IBACOS BEST1 CONFERENCE June 12, 2008

Energy-Efficient Passive House using thermal mass to achieve high thermal comfort

ACHIEVING HIGH-PERFORMANCE MULTI-UNIT RESIDENTIAL BUILDINGS: THE OPPORTUNITIES

SectIon Energy Effldency

6 th Annual North American Passive House Conference. Evaluation of Potential for Moisture in High R- value Walls in Cold Climates

A FIELD STUDY OF AIRFLOW IN MID TO HIGH-RISE MULTI-UNIT RESIDENTIAL BUILDINGS

Can you Believe Energy Savings Forecasts

Preservation of cultural heritage: the design of low-energy archival storage

ECO-RETROFITTING VERY OLD DWELLINGS: CURRENT AND FUTURE ENERGY AND CARBON PERFORMANCE FOR TWO UK CITIES

RESEARCH HIGHLIGHT. Design Development of Low-Energy and Affordable Multi-Unit Residential Buildings

Passivhaus Project Documentation Wrexham Passivhaus

Sustainable Building Façade and Advanced Fenestration Systems

Energy Star Qualified - New Homes

Project name Old Dover Road Project summary Whole house retrofit and formation of new habitable roof structure

2010 National Building Code Adoption and Associated Process Changes

14.8 kwh/(m²a) Project Documentation. 1 Abstract. R-951 Residence: Three Family Passive House Building. 1.1 Data of building. Year of construction

4.2.3 MINERGIE ORIGIN AND ORGANISATION

Brussels Window. Good Windows. Windows. Objectives. Why Good Windows? Windows. Need to control. Learn. Functions: Same as wall - plus.

Project Description. Projected build start date 02 Aug 2010 Projected date of occupation 03 Dec

Wall Enclosure Monitoring and Performance Assessment for the Orchards at Orenco Passive House

The Role of Control Layers in Building Enclosure Design

Residential New Construction Passive House The Nordeast Nest Case Study Tim Eian, Dipl.-Ing., Certified Passive House Planner & Consultant

Analysis 2: Alternative Thermal Window Design

Supplementary Standard SB-12. Energy Efficiency For Housing

Assignment 3 Integrated Energy Design

Tage Møller Architect office building

Building Enclosure Detailing for Walls and Low-Sloped Roofs

Welcome to this continuing education seminar. This is the first of three parts of the Building Enclosure Fundamentals series.

Is Your Envelope Effective? BCBEC Luncheon January 29, 2009

ENERGY EFFICIENT RETROFIT MEASURES GUIDE

Potential of ventilative cooling in German residential buildings

Residential Energy Code Update

Building Performance Evaluation

Project Description. Projected build start date 11 Feb 2013 Projected date of occupation 14 Nov

Project Description. Projected build start date 01 May 2010 Projected date of occupation 01 Nov Belfast, County Antrim, Northern Ireland

Passive House Guidelines for RS-1. Adopted by City Council on November 3, 2015

SURNA Grow Facility: Systems Comparison - IEA

Catalogue of Learning Targets. Certified PHPP Expert

FLORIDA ENERGY EFFICIENCY CODE FOR BUILDING CONSTRUCTION. Florida Department of Business and Professional Regulation - Residential Performance Method

FLORIDA ENERGY EFFICIENCY CODE FOR BUILDING CONSTRUCTION. Florida Department of Business and Professional Regulation - Residential Performance Method

DOE Zero Energy Ready Home National Program Requirements (Rev. 06) April 20, 2017

MID-CONSTRUCTION BLOWER DOOR TESTING February 15, 2017

Adaption of the passive house concept in northern Sweden - a case study of performance

The BIG Energy Upgrade Energy Innovation for Retrofitting Deprived Community Housing in the UK

CENTRA WINDOWS. Manufacturer for Centra Construction Group of Companies

EnerPHit. Criteria for Residential-Use Refurbished Buildings

ENERGY AUDIT. 123 Main Street Mississauga, Ontario. January 1, Report To: Mr. John Smith Smith Printing Company.

How We Obtained LEED Certification pertaining to the Indoor Environmental Quality Category. Ron Fields, CAFS, NCT General Dynamics C4 Systems

Standing Committee on Policy and Strategic Priorities. General Manager, Planning, Urban Design and Sustainability

Project Description. Projected build start date Projected date of occupation 01 Jun Low Energy Buildings

Some Performance Results and Lessons Learned from EQuilibriumTM Housing Monitoring Avalon Discovery 3

Transcription:

Passive House in Canada: Case Studies on a Near EnerPHit Retrofit and Post-Occupancy Research Brittany Coughlin, RDH Building Science Inc. 224 W 8 th Ave, Vancouver, BC Canada Phone: +011 604 873 1181; bcoughlin@rdh.com Christy Love, RDH Building Science Inc. 500-3795 Carey Road, Victoria, BC Canada Phone: +011 250 479 1110; clove@rdh.com Robert Lepage, RDH Building Science Inc. 500-3795 Carey Road, Victoria, BC Canada Phone: +011 250 479 1110; rlepage@rdh.com Case Study 1: Near EnerPHit Retrofit of a High-Rise Residential Building in Vancouver Introduction Multifamily residential buildings account for 62% of the housing stock in the City of Vancouver. Several studies have identified many opportunities to improve energy efficiency in these buildings [RDH 2012]. Deep energy retrofits focused on the building enclosure present one of the largest opportunities for significant energy and greenhouse gas reductions. A pilot project was initiated in Vancouver to perform a deep building enclosure energy retrofit and HVAC upgrade of a 1980 s vintage, 13-storey multifamily. Modelled energy savings were compared to metered post-retrofit energy consumption. Further details on this project are provided in other publications [Hanam et. al. 2014; Pape-Salmon 2016]. Although the project was not designed with EnerPHit in mind, the retrofit project was compared to the EnerPHit standard mid-way through the retrofit to highlight what additional measures would need to have been incorporated to achieve EnerPHit. This paper provides a brief description of the study building and retrofit project that is in progress at the time of writing (enclosure retrofit is complete, ventilation retrofit is underway), with an analysis of the EnerPHit heating demand target as it relates to the planned retrofit. Case Study Building Background Originally constructed in 1986, the case study building is a 13-storey residential building in Vancouver. After weighing various options on how best to maintain and reinvest in their property, the owners decided to proceed with a building enclosure renewal project in 2012. While the primary objectives of the renewal pertained to durability, aesthetics, and comfort, improving the energy efficiency of the building was also a key objective. The renewals included replacing windows, overcladding walls with exterior insulation (and rainscreen), and improving the airtightness of the building. Triple-glazed windows with fiberglass frames were used rather than the more typical double-glazed, aluminum-framed

windows. Exterior insulation was added to the exposed concrete walls, which was then overclad with stucco and metal panels attached with fiberglass clips to minimize thermal bridging. Airtightness improvements were made through detailing at windows, doors and penetrations. Design work is currently underway to upgrade the ventilation system through the installation of in-suite heat recovery ventilation (HRV) equipment. The retrofit has so far achieved an overall 63% measured reduction in electric baseboard heating energy. Following the ventilation retrofit, the project is on track to reduce total building energy consumption by 30%, with an associated 39% reduction in greenhouse gas (GHG) emissions. The following EnerPHit criteria were assessed in this study: Component approach Heating demand approach: 25 kwh/(m 2 a) for cool-temperate climate Airtightness: 1 ACH50 Although EnerPHit also includes a Renewable Primary Energy (PER) requirement, this target was not assessed through the study as building heating and hot water systems were outside the scope of the retrofit project. EnerPHit Component Approach EnerPHit certification can be achieved through one of two paths: the component method, or the energy demand method. First considering the component method, Vancouver falls under the cool-temperate climate zone. Table 1 shows the retrofit assemblies compared to the retrofit performed at the case study building. The wall and window retrofits completed for this project do not meet the EnerPHit requirements, and the project would not have certified following the component approach. Certifying using this methodology would have required additional wall insulation, Passive House suitable windows with high solar heat gain glazing, and additional insulation at the roof and ground floor (above the parkade). Component EnerPHit Criteria Project Comments Max U-value, W/m 2 -K Walls: 0.35 W/m 2 -K Exterior insulation a) : 0.15 Roof & Ground Floor: Interior insulation: 0.35 0.62 W/m 2 -K Opaque Envelope against Ambient Air Windows Overall Windows Glazing Ventilation Max U-value, W/m 2 -K 0.85 Roof and floor insulation was not increased as part of the retrofit. 0.97 W/m 2 -K b) Windows were triple glazing with insulated fibreglass frame optimized for North American energy standards. g-value 0.53 g-value 0.21 Low solar heat gain glazing was selected, typical local practice Minimum heat recovery rate 0.75 82% Proposed; ventilation unit selection is in progress and not yet confirmed 1.0 ACH50 1.35 ACH50 Tested prior to HRV installation Airtightness (includes losses through bathroom exhaust fans) c) Footnotes: a) While the initial building had only interior insulation at opaque walls, the retrofit added exterior insulation to the walls; b) Window U-value assessed using ISO 10077 and EN 673; c) Compartmentalized airtightness testing was performed due to the challenges in completing whole building testing in a large, occupied multifamily residential building. Table 1: EnerPHit component method criteria compared to case study retrofit.

Although the tested airtightness rate was higher than the EnerPHit requirement, this test was performed prior to the installation of HRVs, with bathroom and kitchen exhaust fans that were not sealed during the test. Considering this would have accounted for significant air leakage, it is anticipated that the building should easily meet the 1.0 ACH50 requirement when tested with HRVs installed and HRV ducts sealed. PHPP Modelling and Upgrades to Achieve EnerPHit Compliance with the energy demand method was assessed by modelling the case study building in PHPP. Three initial model iterations were produced: Pre-retrofit: Original building prior to energy interventions in 2012 Phase 1 Enclosure retrofit: Building performance through 2014-2015, with enclosure retrofit (wall, window, and airtightness improvements) Phase 2 Ventilation retrofit: Following planned 2017 HRV retrofit PHPP results for these three phases are summarized in Table 2. The three stages of the building s renewals cycle (pre-, intermediate, and post-retrofit) show the significant improvement achieved. As designed, the post-retrofit heating demand of 42 kwh/(m 2 a) is 68% higher than the EnerPHit requirement of 25 kwh/(m 2 a) for the cool-temperate climate. Space Heating Demand, kwh/(m 2 a) Pre-Retrofit 213 Phase 1 Post-Retrofit 69 Phase 2 Post-Retrofit 42 Table 2: PHPP simulation results for the case study building. Despite being significantly higher than the EnerPHit heating demand target as implemented, several simple strategies could have brought the project within reach of the heating demand target: Reduced air leakage to 1.0 ACH50: likely to be achieved with HRV installation Soffit insulation: the soffits were the only uninsulated enclosure component that remained following the retrofit; adding minimal insulation provides a significant improvement over the uninsulated condition. High solar heat gain glazing: The installed triple glazed units had low solar gain glass; changing to a high solar gain glass yields significant savings. This configuration would still have lower solar gain than the original glazing units, however further analysis would be recommended to assess the risk of overheating in south- and west-facing suites. Reduced thermal bridging: Several details were identified that could be improved to reduce thermal bridging. These measures were assessed in the PHPP model to view the impact on heating demand and to assess whether the project could meet EnerPHit. Together, these measures yield a heating demand of 23 kwh/(m 2 a), as shown in Table 3.

Heating Demand, kwh/(m 2 a) Phase 2 post-retrofit 42 EnerPHit package: Reduce air leakage Reduce thermal bridging 23 Soffit insulation High solar gain glazing Table 3: PHPP results for EnerPHit measures. Economics and Market Readiness The additional cost of the measures required to achieve EnerPHit was assessed, as follows: Reduced air leakage to 1.0 ACH50: This would likely be achieved (or very close) if the building were tested with HRV vents sealed per the Passive House testing standard. If additional air sealing was required to meet this standard, this could have been achieved through targeted investigation (such as smoke testing) performed at the time of the airtightness test and sealing during construction with little added cost to the project. Soffit insulation: Estimated cost of $20,000 to $30,000 for insulation, low-conductivity cladding attachment, and metal panel cover. High solar heat gain glazing: No additional cost for high solar gain glazing. Reduced thermal bridging: Estimate $5,000 to $10,000 to improve ground, parapet, and window installation details. Table 4 shows the incremental costs that would be required to reach 25 kwh/(m 2 a) space heating demand. Additional costs would apply for the building to meet the primary energy target (e.g. high efficiency fireplaces, DHW, make-up air unit, etc.). Airtightness Testing $5,000 to $10,000 Soffit Insulation $20,000 to $30,000 High solar heat gain glazing No cost Reduced thermal bridging $5,000 to $10,000 Total incremental cost for EnerPHit Retrofit $10,000 to $50,000 % above construction budget 0.3% to 1.4% Table 4: Incremental construction costs to achieve EnerPHit heating demand requirement. Added market barriers to an EnerPHit retrofit include the following: Airtightness testing: The Passive House standard test method requires a whole building test, which is very difficult in an occupied multifamily residential building. Compartmentalized, suite by suite testing is much more practical in existing occupied buildings, but may also be cost prohibitive in large buildings and comes with other challenges such as pressurizing adjacent suites. There is concern among many North American window fabricators that high solar gain glazing can result in overheating of residential spaces without air conditioning; as a result, window fabricators tend to recommend low solar gain products locally, as was installed at this project. Further research is required in this area to understand

overheating risks in high-rise multifamily buildings with various window to wall ratios, and how these risks could be alleviated through exterior shading. Combustibility of window frames may be a concern in other multifamily buildings. At the case study building, an alternative solution to the Vancouver Building Bylaw was approved to allow combustible window frames (i.e. fiberglass or PVC) in a noncombustible building. High-rise buildings with higher window to wall ratios or combustible cladding materials (e.g. exterior foam insulation or certain claddings) may be challenged to find an acceptable solution. The case study building s balconies were previously enclosed, allowing the building to be wrapped in insulation with minimal thermal bridging. However, many Vancouver multifamily buildings have non-thermally broken balconies that pose a retrofit challenge. A variety of retrofit options may be possible (e.g. insulating or removing balconies); further research would be beneficial to assess the economics of alternatives. The pressurized corridor ventilation system, common in North American multifamily buildings [RDH 2012], may present a challenge to EnerPHit retrofits. At the study building, the airflow rate required to provide minimum corridor ventilation was low enough that central heat recovery was not necessary to meet the heating demand standard. If heat recovery was necessary, this would add significant work to the project, either ducting return air to a rooftop HRV or adding floor by floor corridor HRVs with ducting through a suite. Summary and Conclusions As designed and implemented, the deep energy retrofit of the case study building will be close to the EnerPHit standard after the planned HRV installation is complete. Heating demand calculated using PHPP is 42 kwh/(m 2 a), compared to the EnerPHit standard of 25 kwh/(m 2 a). This work showed that only minor improvements were needed to reach the EnerPHit standard. Key changes that led to a compliant building included high solar gain windows, insulation of thermal bridges (specifically at the soffit, roof parapet, and window installation), and whole building airtightness testing with HRVs installed and ducts sealed. The incremental costs associated with these measures are minor; additional insulation of thermal bridges would add $10,000 to $50,000 to the project (0.3% to 1.4% of the project budget). High solar gain glass typically has no added cost (though shading may have been required to prevent overheating), and airtightness testing was already completed as part of the project (though a different test method would have been necessary). This work could have easily been completed within the project scope and budget. The primary energy requirement for EnerPHit was not evaluated with the scope of this project, but it is noted that additional upgrades would be required to achieve this target. This would likely include the removal or replacement of fireplaces and a high efficiency DHW system. While the EnerPHit standard proved to be well within reach for the case study building, several additional barriers may be present for other multifamily residential building retrofit projects. Buildings with exterior balconies would be challenged by thermal bridging. Higher window to wall ratios may limit the use of windows with low conductivity frames.

Overall, this work showed that going the extra step to meet the EnerPHit heating demand target requires careful attention to detail, but could have been achieved with little added cost beyond the deep energy retrofit that was performed. This project demonstrates how EnerPHit could be implemented cost-effectively for existing mid- and high-rise multifamily retrofits in North America. Acknowledgements The authors are grateful for the support of the City of Vancouver, BC Hydro, and the City of New Westminster in assessing EnerPHit as part of the pilot project. Numerous organizations supported the retrofit and research completed at the pilot project: BC Hydro, the Homeowner Protection Office of BC Housing, FortisBC, NRCan, City of Vancouver, City of New Westminster, City of North Vancouver, City of Richmond, City of Surrey, and the Owners. References [RDH 2012] [Hanam et. al. 2014] [Pape-Salmon 2016] [Pape-Salmon 2016] RDH: Energy Consumption and Conservation in Mid- and High- Rise Residential Buildings in British Columbia. Available online: https://www.bchousing.org/publications/murb-energystudy- Report.pdf Hanam, B.; Finch, G.; Ricketts, D.: Deep Energy Retrofits of High- Rise Multi-Unit Residential Buildings. Proceedings of the 2014 ACEEE Summer Study on Energy Efficiency in Buildings. ACEEE, Pacific Grove, 2014. Pape-Salmon, A.: Confirming: A Benchmarking Update Verifies Deep Energy Savings after a Tall Building Retrofit. APEGBC Innovation Magazine, Nov-Dec 2016, 34-37. Pape-Salmon, A.: Deep Energy Retrofit of The Belmont. Available online: http://rdh.com/wp-content/uploads/2015/08/deep-energy- Retrofit-Vancouver-Andrew-Pape-Salmon.pdf Case Study 2: Post-Occupancy Research at the North Park Passive House, Victoria, Canada Introduction The North Park Passive House, a 6-unit condominium building located in Victoria BC, was occupied in September 2015. It is the first market strata-title certified Passive House development in Canada. While well-established elsewhere, the potential benefits of Passive House and other low energy design approaches are not as well documented in Canada, and there are limited data on the actual performance of these buildings in the Canadian west coast climate. To address this gap, RDH, in partnership with the Canadian Mortgage and Housing Corporation, the Homeowner Protection Office of BC Housing, and FP Innovations, has undertaken detailed quantitative and qualitative performance measurement of the North Park

Passive House. The intent of this research is to develop a comprehensive case study for a Passive House project in the Pacific Northwest climate. The building s performance was considered in two separate, but interrelated, components: occupant experience and building performance. Occupant experience relates to the interaction of the occupants with the building. This includes indoor air quality (IAQ), interior comfort, and energy consumption. Building performance relates to the building enclosure s effectiveness at managing heat, air, and moisture phenomenon. Two suites within the 6-plex were selected for the study: both with the same exposures (south, north, and west) and similar floor layouts, but on different floors. The following data were collected over a full year post-occupancy: 1) Thermal comfort and Indoor Air Quality (IAQ) conditions: a. Air temperature b. Interior surface temperatures c. Relative Humidity (RH) d. Carbon Dioxide (CO2) concentration e. Two occupant surveys to compare measured data with perceived comfort in two different seasons 2) Building Enclosure performance: a. Moisture content, relative humidity, and temperature sensors at critical wall and roof sheathing interfaces b. Whole building air leakage 3) Energy Consumption: a. Overall annual building energy consumption and energy usage intensity b. Overall annual and monthly energy use of test suites c. Suite level end use energy consumption This paper will present the study results for quantitative thermal comfort monitoring and building enclosure performance monitoring, demonstrating the viability of Passive House and the chosen building enclosure strategy in this climate. Energy data and interview results were still being processed at the time of this writing and are excluded from this paper. Thermal Comfort and IAQ Results Temperature, RH, and CO2 sensors were installed at two locations in each of the two test suites: at ceiling level in the main living space (which includes the open kitchen), and one just below ceiling level in the bedroom. The RH readings in all cases did not exceed 61%, which is within acceptable thresholds for humidity and comfort and so will not be discussed in detail. Figure 1 below shows the temperature boxplots for three in-suite locations.

Figure 1: Monthly Temperature Boxplots for Suite B Living Room and Bedroom and Suite A Bedroom Both suites maintain temperature very close to or above 20 C throughout the heating season. Suite A had a slightly higher indoor temperature due to occupant stated comfort preferences. The indoor temperature of all suites rises in the summer months, with the 75% percentile data straddling 25 C from June to August. Table 1 below shows the frequency of overheating, for data collected from December 20, 2015 through November 22, 2016. Suite A is located above Suite B; is on the top floor of the building, and has a larger building enclosure area and increased solar exposure than the lower suites. Both suites have operable exterior shading devices on the west facing windows. Suite A Living Suite A Bed Suite B Living Suite B Bed Hours > 25 C - 1174 355 482 Total Hours logged - 8055 8054 8055 % of hours > 25 C - 14.6% 4.4% 6.0% Table 1: Hours and % of hours over 25 C. The temperature threshold for Suite A s bedroom is identified as Poor comfort performance for summer conditions according to the Passive House Planning Package (PHPP). As data is updated to include the full year s monitoring period, the percentage of hours greater than 25 C will be reduced, although it will likely remain above the 10% threshold for Suite A. These data point to a potential to revisit operating conditions with the suite occupants, but also to potential challenges in assigning an overall building thermal comfort value in a compartmented multifamily building. The probability of CO2 readings exceeding a given value for the full measurement period is shown in Figure 2 below, and a weekly snapshot is provided to demonstrate daily fluctuations. Both suites show ranges of CO2 values that generally conform to a satisfactory level of CO2, per ANSI/ASHRAE Standard 62.1-2016, Appendix D. According to this reference, maintaining a space CO2 concentration of no greater than 700 ppm above outdoor air levels will satisfy the majority of occupants. Ambient levels are approximately 400 ppm, meaning that total CO2 levels less than 1100 ppm would be considered acceptable. Note that the Living Room CO2 sensors are located between the open kitchen and living space and

therefore vary widely as cooking and other activities occur throughout the day. Differences between the living spaces in the two suites likely result from variation in occupant behaviour and the number of pets living in the space. The CO2 levels in the bedrooms are much lower and more stable, as expected. Percent Time Exceeding 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 400 600 800 1000 1200 1400 1600 1800 CO2 Concentration (ppm) Suite A Living Room Suite A Bedroom Suite B Living Room Figure 2: Cumulative Density Function for Percent Time Exceed CO 2 Levels for Suite A, Living Room and Bedroom, and Suite B Living Room Figure 3: Hourly CO 2 Measurements for the Week of November 6 th, 2017. Enclosure Performance The wall assembly for the North Park Passive House is a deep-stud cavity wall with additional service wall. The details of the assembly are shown in Figure 4.

Figure 4: Wall Assembly The enclosure performance aspect of the research ascertained the hygrothermal performance of a deep-stud wall assembly in the Pacific Northwest Climate. The moisture durability of the sheathing was of principle interest, followed by other parameters such as the impact of solar heating and inward driven moisture. The factors that were characterised as part of this project were as follows: Moisture durability of the exterior and interior sheathing Hygric buffering capacity of the densepack cellulose Impacts of solar radiation on temperature profiles through the assembly Impacts of solar radiation on the hygric profiles through the assembly The performance metrics of the wall assemblies were measured with relative humidity sensors, moisture content sensors, and temperature sensors, which were hard wired to a laboratory grade data acquisition system. The sensor packages for each wall assembly were designed to provide the maximum amount of information while minimizing complexity and cost. It was determined that at a minimum, two moisture content sensors were required to monitor the moisture content of the sheathing. The temperature sensors were included to provide the surface temperatures that form part of the boundary condition. The relative humidity sensors were used to assess the impact of the hygric performance of the dense-pack cellulose, and to provide an indication of the influence of exterior cavity humidity conditions on the insulation. Sensor locations in the exterior wall assemblies are shown in Figure 4 above. Analogous sensors were also installed in north and south facing roof assemblies. Figure 5 shows moisture content profiles at the exterior sheathing of the four wall monitoring locations. The north wall was expected to be colder and wetter than the south wall, and the data validates this expectation. At the third floor ( Suite A ) north wall sensor location, the moisture content was close to 20% at the start of the monitoring period, which also coincided with the rainy season. However, the data is suggesting a drying trend over the measurement period, which may indicate drying of construction related moisture.

25 Moisture Content (%) 20 15 10 5 0 Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Suite A South Suite A North Suite B South Suite B North Figure 5: Moisture Content for Suite A and B, North and South Walls Conclusions The interior IAQ sensor packages were able to demonstrate that the interior CO2 levels and relative humidity fall within standard norms of comfort. On some occasions, the interior temperature of the uppermost suite exceeded the recommended comfort levels from PHPP. However, as the PHPP model only considers the entire building, localized areas of overheating cannot be readily captured. For future multifamily Passive House projects, consideration may be given to the likely concentration of overheating hours in only a few suites and to provide a simplified method of modelling and managing overheating in these suites. The hygrothermal assessment of the enclosure indicates that for interior conditions not exceeding 60%RH in the winter time, this wall assembly performs well in the Pacific Northwest climate. The moisture content of the sheathing is demonstrating drying from initial construction moisture, and first-winter data suggest the sheathing is staying below the recommended 19% moisture content limit for durability. Additional research would be required to ascertain the effects of elevated interior RH or the risk of air leakage induced condensation. Due to the strict air leakage requirements of Passive House, though, the risk of air leakage induced condensation is minimized.