The construction of deep excavation ditch in weak soil in St. Petersburg

Similar documents
Research on the Effects of Foundation Excavation by the Environment

EFFECT OF DEEP EXCAVATION SUPPORTED BY CONCRETE SOLIDER PILE WITH STEEL SHEET PILE LAGGING WALL ON ADJACENT EXISTING BUILDINGS

UNDERPINNING A CRANE FOUNDATION

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Contents. Glossary 9. Foreword 10

Case Histories in Geotechnical Engineering

Seven Wonders of the Ancient World

Downloaded from Downloaded from /1

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

Building Construction

Marina Bay Sands Hotel Arch 631 Kayla Brittany Maria Michelle

Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay

Pile foundations Introduction

Reconstruction of Space Steel Constructions

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

Deformation monitoring and analysis of deep foundation pit of Xiaoshan rainbow Boulevard

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

Development of the effective segmental tunnel lining with flexible elements

Risk Management of the Restoration of Shanghai Metro Line 4

The design of soil nailed structures to AS4678

FDA OC/ORA Office Building

fifteen design for lateral loads Lateral Load Resistance Load Direction Lateral Load Resistance

Design of Izmir Bay Crossing Bridge

A Case Study: Foundation Design in Liquefiable Site

fifteen design for lateral loads Lateral Load Resistance Load Direction Lateral Load Resistance

Geotechnical Engineering Software GEO5

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Lateral System Analysis and Confirmation Design

fifteen design for lateral loads Lateral Load Resistance Load Direction Lateral Load Resistance

Sabah Shawkat Cabinet of Structural Engineering 2017

STRESS-RIBBON BRIDGES STIFFENED BY ARCHES OR CABLES

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro

Verification of a multi-anchored wall

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know?

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

The Effect of mixed foundations on the response of some buildings to excavation

h Installation Manual

Level 6 Graduate Diploma in Engineering Structural analysis

Construction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk

Enabling Work Package for Emirates Pearl Tower and Bab Al Qasr Hotel

Council on Tall Buildings. and Urban Habitat BACKGROUND SECTION STEEL REINFORCED CONCRETE SHEAR WALL STEEL PLATE COMPOSITE SHEAR WALL

Construction Technology B (CON4313)

Design of a non-anchored retaining wall

Council on Tall Buildings

Ching Guan Kee ABSTRACT

Lesson 2 Substructure. Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

Full-Ring Experimental Study of the Lining Structure of Shanghai Changjiang Tunnel

DESIGN AND MASONRY BASIC DESIGN GUIDELINES FOR CSEB. General principles for a good design

IGC. 50 th INDIAN GEOTECHNICAL CONFERENCE CONSTRUCTION PRACTICES OF DEEP BASEMENTS ANIL JOSEPH 1, A MURALIKRISHNA 2 ABSTRACT

Misan University - College of Engineering Civil Engineering Department

SECANT PILE. Introduction:

Anti-fatigue Performance Analysis on Steel Crane Beam

The use of ZSoil for complex, large scale 3D simulations of a deep excavation in soft soils

TESTING AND NUMERICAL MODELING - STEEL TRUSS OF THE SPORTS HALL

Earth Retaining Walls CIVL455 CHAPTER I: INTRODUCTION

Design & technology characteristics of main bridge of Chaotianmen Yangtze River Bridge

DFI DEEP FOUNDATIONS. Brazil s Megaproject Shipyard Winner of the 2010 Outstanding Project of the Year

Century Lotus Stadium. Group Member: Hua Tong, Yuan Su, Chao Pan, Jie Sun, Xiaodan Luo

Single Piles and Pile Groups

IOP Conference Series: Materials Science and Engineering. Related content PAPER OPEN ACCESS

Soil Services SCS Ferretti International Soil Services Soil Services Industrial Construction Infrastructures Real Estate Soil Services Soil Services

Prestressed Concrete Tanks. Design & Construction

Zoning Supporting Design of Deep Foundation Pit Based on Controlling Deformation of Surrounding Buildings

DISPLACEMENT OF DIAPHRAGM WALL FOR VERY DEEP BASEMENT EXCAVATION IN SOFT BANGKOK CLAY

"Impact of New IS 1893 & Related Codes on Design of tall Buildings, Including Trend Setting Structures

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

An analysis of structure design of storey - increase of certain building on natural foundation

Issues on Design of Piled Raft Foundation

FULL-RING EXPERIMENTAL STUDY OF THE LINING STRUCTURE OF SHANGHAI CHANGJIANG TUNNEL

COLUMN SHOES HPKM, PPKM, PEC

(laboratory) (fall semester)

ASSIGNMENT 1 ANALYSIS OF PRESTRESS AND BENDING STRESS BFS 40303

WESTPRO PORTUS Use of RD Piles for Marine Construction

Access Road Construction of the Larsi Building Using Reinforced Earth Walls

FOUNDATION & SHORING. Whatever it takes... We build your vision! WORLDWIDE EXPANSION

Ground Modification Applications for Bio-Fuel Plants Raymond J. Franz, P.E. Roselle, IL

Direct Drilled New Micropile TITAN 127/111 for Underpinning Roman Bullring in Barcelona, Spain

The HKIE Structural Examination Written Examination 2017

Earth Retention Systems

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

Foundation or Footing Design: Part 1

WORK BELOW LOWEST FLOOR FINISH 1/7 230, , , FRAME 2/6 96, , ,056.00

DHANALAKSHMI COLLEGE OF ENGINEERING, CHENNAI DEPARTMENT OF CIVIL ENGINEERING 2 MARK QUESTIONS WITH ANSWERS CE FOUNDATION ENGINEERING UNIT 1

Geotechnical Investigation Reports and Foundation Recommendations -Present status in India -Examples

Braced deep excavations in soft ground

Modelling of RC moment resisting frames with precast-prestressed flooring system

Chapter 1. Introduction to Engineering Ground Modification. The Need for Engineered Ground Improvement

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

Comparison of Seismic Behavior of Multi-Storey R/C Buildings With and Without Internal Beams

The HKIE Structural Examination Written Examination

In-plane testing of precast concrete wall panels with grouted sleeve

GEO-SLOPE International Ltd, Calgary, Alberta, Canada Tie-back Wall

TECHNICAL MANUAL. PC Beam Shoe. Hidden Beam Shoe for Corbel System

composite elements, lateral loads, strain analysis, behavior Composite steel concrete elements made by steel and concrete are used in world wide almos

Study on the settlement and the load-bearing capacity of Long An soft ground reinforced by the stone columns

IS 1893 and IS Codal Changes

TBM rescue projects using shafts and ground freezing

Transcription:

Geotechnical Aspects of Underground Construction in Soft Ground Viggiani (ed) 2012 Taylor & Francis Group, London, ISBN 978-0-415-68367-8 The construction of deep excavation ditch in weak soil in St. Petersburg R. Mangushev St. Petersburg State Civil Engineering University, St. Petersburg, Russia E. Lashkova & V. Smolenkov Company Geoizol, St. Petersburg, Russia A. Osokin Company Geostroy, St. Petersburg, Russia ABSTRACT: The information about the engineering- geological conditions in the central part of St. Petersburg which are characterized by deep thickness of weak water saturated soil is given. Three buildings with large underground space constructed in St. Petersburg are considered as examples. The depth of each space exceeds 12 m and required the usage of modern and nonstandard construction and technological methods for protection of the ditch walls. The wall protection was done by sheet piles, by Wall in ground method, and jet grouting. The soil excavation was carried out by traditional method or Top down method. The basic constructive schemes and technological methods of ditch excavation, test results of deformation of the protection walls during excavation of the ditch and the settlements of the neighboring buildings are given. 1 INTRODUCTION The development of the modern City is not possible without the development of underground space. But the construction conditions in St. Petersburg are much more complicated than in any other region of the country. Mainly this is explained by specific geological conditions the central part of the City is located on weak, water saturated thixotropic soil, which change their properties depending on the effect of different forces natural and technogenic. Most of the buildings which were constructed in 18 19 centuries or beginning and middle of 20-th century have cracks and damages of the bearing structures and require the reinforcement of their base and foundations (Mangushev, 2004). Any additional settlement of such buildings during ditch excavation by traditional method (pile sheet wall, soil excavation, lowering of ground waters by open excavation and etc) may cause unpredictable result. The construction in St. Petersburg require high professionalism starting with projecting work when you choose the method of supporting the wall of the ditch and the technology of the future work. The availability of the modern equipment for underground work and qualified personnel is of great importance. The examples of the construction of three modern buildings with large underground space in St. Petersburg are given in the present article. 2 FIVE LEVEL UNDERGROUND PARKING ON KOMENDANTSKAYA SQUARE In 2006 the company GEOIZOL made the project and started construction of the circular 5 level underground parking on Komendantskaya Square. The depth reached 19,5 m and the diameter 78 m. The general cross section is shown in Figure 1. The main problems which appeared during the construction were the absence of the experience in the construction of such types of buildings Figure 1. The general cross section of the building. 653

in St. Petersburg and complicated geological conditions (thixotropic soil in the upper part of the geological section, high level of ground waters and presence of big boulders). Since the parking with such spacious underground room was constructed in newly developing region it was possible to dispose it at the distance of 100 m from the nearest buildings. This allowed to ignore the effect of the parking on neighboring buildings. The technical solution of the erection of the underground part of the building suggested: 1. Initial trench made by wall in ground method 24 m deep and 0,8 m wide which was filled cement-clay solution (Fig. 2a) The ground was excavated by portions 3,3 m long each. 2. Immersion of the metal semicircular sheet pile into the trench and its subsequent concreting (Fig. 2b). Sheet pile served as a reinforcing element and additional seal. 3. Erection of monolith concrete beams which served as stiffening ribs and excavation of the ditch by portions while making monolith walls and parts of beam ceiling (Fig. 3). 4. The erection of 290 anchor borrow concrete piles 12 m long section 250 mm and concreting the reinforced concrete plate on the level 18 m (Fig. 4). There were no influx of the water from outside of the wall since the wall in the ground reached the dense undisturbed Cambrian clay. In order to avoid the floating up of the bottom of the structure under the pressure of hydrostatic force, the reinforcement of anchor borrow concrete piles was connected with the reinforcement of the lower plate. This allowed to make united anchor system. The horizontal movement of the circular walls during the ditch excavation was checked with the help of inclinometers. Inclinometers were immersed into the earlier installed plastic tubes along the whole height of the Wall in ground. Figure 3. The beams, parts of ceiling and excavation of the ditch level by level. Figure 2. Initial trench made by Wall in ground method (a) and sheet pile immersion (b). Figure 4. Anchor piles and monolith reinforced concrete bottom plate. 654

Figure 5. The horizontal movement of walls of underground structure within certain period of time. corner of Nevskii Prospect. and Vosstania str. The building has 3 4 level underground space 15 meters deep in the form of trapezium (the base is 60 m the height of one of the sides 130 m) (Fig. 7). On 2 sides of the construction site there were neighboring buildings. As a protective structure of the underground part the initial project suggested the metal sheet pile Larcen V 25 m long which was immersed by vibro immerser of high frequency. The experience received in St. Petersburg showed that this method of immersing the sheet pile into unstable soil could result in the settlement of the neighboring buildings and exceed the allowed value. That is why foundations of the buildings along Nevskii Prospect were reinforced by piles Titan prior the excavation of the ditch. The piles were tested against 70 ton vertical loading. Since the Client failed to agree with the owner of the building along Vosstania str. upon the foundation reinforcement of his building, it was necessary to make the protection wall along one of the sides of the ditch as wall in ground instead of pile sheet. Figure 8 (Smolenkov, 2009). Figure 6. General view of the building with 4 level parking. Figure 7. Center. Scheme of the underground part of the Trade The horizontal movement of walls of underground structure during excavation within certain period of time is shown in diagram (Fig. 5). The maximal measured movement of the wall into the ditch was 250 mm and happened at the depth of 15 meters. A t the end of 2008 the building was put into operation (Fig. 6). 3 THE UNDERGROUND PART IN STOCKMANN TRADE CENTER In 2007 the construction of the new Stockmann Trade Center was started in the center of the city on the Figure 8. Wall in ground along one of the sides of the ditch. 655

Figure 9. Excavation of the soil under the ceiling. Though the stiff sheet pile was used along three sides and wall in ground along the forth side, the stiffness of the structure was not sufficient due to the weak soil in the construction site. The deformation of the sheet pile below the bottom of the ditch could occur. In order to avoid the damaging effect of the new building on the old neighboring buildings and metro station the engineers suggested to fix the lower part of the sheet pile at the depth 17 20 m by making the soil diaphragm by jet technology (Broid, 2004). Further development of the underground space was done by Top-Down method. Some new technical solutions were applied: borrow piles-columns reinforced by steel tube and special metal profile and also borrow piles of standard diameter and with expansion in the lower part up to 1300 mm which supported the ceiling. The length of the piles was 40,8 m. The ceilings which were put on the ground and under which the soil was later excavated through technological apertures, served as strut elements for protecting the structure. (Fig. 9). After finishing the ceiling on the ground level the construction of the overground elements columns, walls, ceilings of the upper floors was started. All the works on the ground level and further construction of the over ground level did not cause any serious additional settlements of the neighboring buildings, their foundations were earlier reinforced by piles Titan. But the building which was not reinforced in its foundation, received deformation of the bearing structures and required the restoration. 4 THE ERECTION OF THE UNDERGROUND PART IN THE TRADE CENTER IN LIGOVSKII PROSPECT In 2006 the territory which earlier was intended for the construction of the railway station was bought by another Company. The plans were changed and it was decided to construct there a trade Center with underground 3 level parking. The third level must have independent entrance from Ligovskii prospect which was not possible due to several reasons and as a result it was decided to have 2 levels. The ground characteristics in the construction site are typical for the central part of St. Petersburg glacial moren deposits, laid below weak water saturated sea, lake and lake glacialdeposite. are located on the depth 25 m. Since the destination of the building changed, the construction scheme was changed. It became necessary to evaluate the bearing capacity of the existing piles which were erected earlier. For this purpose the ditch was excavated and piles were tested under the loading 3000 kn. 785 piles with diameter 550 mm were added to the existing piles using DDS method and 6 of them were tested under static loading (Mangushev et al., 2010). The test results showed the growth of the bearing capacity of the piles erected earlier the settlement of the pile was less than 30 mm under the loading 3000 kn. When the work started again at the construction site at the end of 2006 there was already sheet pile along the perimeter of the construction site immersed to the depth of 11 m. The preliminary calculations showed that the stability of the pile sheet protection was not provided after the excavation newly projected ditch 8,5 m deep. Different variants were checked and finally semicircular pile sheet 21 m long was chosen. The calculations made by different experts showed that the stability of the pile sheet can be provided on condition of certain sequence of work done while excavation of the ditch. According to the calculations made in the computer programmer Steel Wall, during the last period of ditch excavation the deformation of the sheet pile when 2 levels of struts were made, should be equal to 34 mm and maximal value of the bending moment 303,0 kn, coefficient of the stability 1,94 (Fig. 10). The technology of ditch excavation included the excavation of its central part and making slopes of the pile sheet wall on the projected mark and the erection of the monolith reinforce concrete plate in the center, followed by erection of strut in the form of metal beams between reinforce concrete plate and sheet pile protection. (Fig. 11). It was suggested to make ditch excavation part by part in the area of location of metal beams and after that to make final concreting of monolith plate and walls of the underground part, after that the struts were dissembled. All the work was done 656

very close to the existing rail way and the building of the railway station. The further construction of the underground part of the building was done by open technology under the protection of the sheet pile and walls in the underground part (Fig. 12). At present time the construction of the building is successfully finished. Figure 10. Calculated value of the moment M and movement X at different stages of the ditch excavations. 5 CONCLUSIONS The considered examples of these civil buildings in St. Petersburg with large underground space showed that it was possible to make the deep large ditches in soft soil on the condition of proper selection of the rigidity of the protection structure. The choice of these structures is determined by calculations and organizing the test sites. REFERENCES Figure 11. View of struts in the ditch. Broid I.I. 2004. Jet grouting technology, ASV, M, 448 pp. Mangushev R.A. 2004. The analysis of the constructions of the bases of old buildings in the Centre of St. Petersburg. «Soil mechanic and Foundations», No 5, M, p.13 16. Mangushev R.A., Ershov A.V., Osokin A.I. 2010, Newpile technologies. SPBGASU ASV, Sankt- Peterburg-Moskow, 160 pp. Smolenkov V.Ju. 2009. Company GEOIZOL experience constructions of the underground objects in St. Petersburg. Building construction, No 2, p.43 45. Figure 12. The construction of the underground part of the Trade Center at Ligovskii prospect. 657