AEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION

Similar documents
Curlex II EROSION CONTROL BLANKET SPECIFICATION

Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION

Curlex Enforcer EROSION CONTROL BLANKET SPECIFICATION

Recyclex TRM TURF REINFORCEMENT MAT SPECIFICATION

TriNet Coconut EROSION CONTROL BLANKET SPECIFICATION

TriNet Coconut EROSION CONTROL BLANKET SPECIFICATION

Specifications for the Selection and Application of Erosion Control Blanket on Slopes or Channels

Curlex Bloc An American Made Alternative to Coir Logs SPECIFICATION

Flexamat Erosion Control Mat

Flexamat Tied Concrete Block Mats

Bindex BFM HYDRAULICALLY APPLIED EROSION CONTROL PRODUCT SPECIFICATION

ROLLED EROSION CONTROL PRODUCTS (RECP)

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 836 SEEDING AND EROSION CONTROL WITH TURF REINFORCING MAT January 18, 2013

SECTION EROSION CONTROL MATTINGS AND COMPONENTS

SECTION 806 WATER COURSE AND SLOPE EROSION PROTECTION

EC-04 ROLLED EROSION CONTROL PRODUCTS (RECP)

Channel FlexTM P-BD Series

REGIONAL CONSTRUCTION STANDARDS

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION CONTROLS

Drop-In Specification Standard Flexamat Erosion Control System (English Units)

IN T R A / M IN T R A M

ARMORMAX ENGINEERED EARTH ARMORING SOLUTIONS

Erosion Control Blankets

MATERIAL SPECIFICATION Manufactured Ditch Checks

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

SECTION EROSION CONTROL DEVICES

INLET STRUCTURE FILTERS

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL

DIVISION 4100 SITEWORK

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

SECTION 903 EROSION CONTROL

ADDENDUM NO. 1 TO THE INVITATION TO BID - ITB # RAMP & SIDEWALK REPAIR PROJECT CITY OF ANN ARBOR, MICHIGAN

SC-07 STORM DRAIN INLET PROTECTION

SECTION UNCLASSIFIED EXCAVATION AND GRADING

EC-7 GEOTEXTILES AND MATS. Objectives. Potential Alternatives

REGIONAL CONSTRUCTION STANDARDS Proposed Revision Form

SECTION 70 SEEDING. This work consists of preparing a seedbed and furnishing and planting seed on disturbed areas within limits of the work.

Section Soil Erosion Protection Tender No. [ ] Page 1

Reinforced Soil Slopes (RSS)

SECTION TRENCHING

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

The Manitoba Water Services Board SECTION Standard Construction Specifications CONSTRUCTION OF WATERWAYS September 2013 Page 1 of 9

BMP 6.4.4: Infiltration Trench

BENTOMAT CL GEOSYNTHETIC CLAY LINER SPECIFICATION GUIDELINES

INLET STRUCTURE FILTERS

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

Quality Control, Quality Assurance and Performance Testing of ECPs. Erosion. Erosion Control

Base Course Design and Construction

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

SECTION EMBANKMENT

ITEM 706 PIPE SLOPE DRAIN

Section (1997 Section 02795) PERMEABLE, FLEXIBLE and PLANTABLE CONCRETE EROSION CONTROL SYSTEM

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

SECTION 603 SEEDING I. GENERAL 1.1 DESCRIPTION OF WORK

REQUEST FOR BIDS CULVERT REPLACEMENT PROJECT FREEPORT, MAINE

SECTION GENERAL EXCAVATION

Geosynthetic Materials for Separation and Stabilization

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 863 REINFORCED SOIL SLOPES. October 19, 2012

ITEM 432 RIPRAP. Dry Riprap is defined as Stone Riprap of the required type with voids filled only with spalls or small stones.

SECTION 14 EMBANKMENT

Table 1: Minimum Perimeter Control Performance Requirements. Physical Property* Test Method Required Value

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

INSTALLATION OF LANDLOK ON SLOPES

Common Construction-Site BMPs Quick Reference Guide

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SECTION 18 - EARTHWORK TABLE OF CONTENTS

P R E M I E R M A N U F A C T U R E R O F E R O S I O N C O N T R O L P R O D U C T S

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

STANDARD SPECIFICATIONS FOR CONSTRUCTING UTILITY FACILITIES DIVISION III - CONSTRUCTION SPECIFICATIONS SECTION 11

STANDARD SPECIFICATIONS FOR CONSTRUCTING UTILITY FACILITIES DIVISION III - CONSTRUCTION SPECIFICATIONS

GEOSYNTHETICS USED IN SUBGRADE STABILIZATION

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 300 EARTHWORK, GRADING, AND GRAVELING

SECTION 18 - EARTHWORK TABLE OF CONTENTS

Stanford University Facilities Design Guidelines SECTION STONE FINES PAVING. American Society for Testing and Materials.

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

BENTOMAT SS100 GEOSYNTHETIC CLAY LINER SPECIFICATION GUIDELINES

SECTION B. Prevention of sedimentation of waterways, open drainage ways, and storm and sanitary sewers due to construction activities.

2-16 EROSION, SEDIMENT & STORM WATER CONTROL REGULATIONS APPENDIX B1

This silt fence system is composed of geotextile filter fabric and steel posts.

This silt fence system is composed of geotextile filter fabric and steel posts.

Section Specification for Geogrid Base Reinforcement of Flexible Pavement Structures

SECTION SHEET PILES. A. This section covers the contract item Sheet Piles. This work includes:

INS T A LLA T I O N G U I D E

SECTION STORM DRAIN

SECTION REVISIONS, CLARIFICATIONS AND MODIFICATIONS ADDENDA. Date Issued No /26/ No.

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

Construction Specification for General Excavation

SECTION EARTHWORK

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

New Market Township. Driveway/Approach Permit

SECTION MECHANICALLY STABILIZED EARTH 1.01 SUMMARY

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

Construction Inspection Checklists

SPECIFICATIONS FOR DRAINTUBE DRAINAGE GEOCOMPOSITES

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

MANDATORY SUPPLEMENTAL SPECIFICATIONS FOR CONTRACTOR QUALITY CONTROL Contractor Quality Control - is replaced with the following:

Transcription:

AEC Premier Straw Double Net Quick Mow EROSION CONTROL BLANKET SPECIFICATION PART I - GENERAL 1.01 Summary A. The erosion control blanket contains agricultural straw fibers for the purpose of erosion control and revegetation as described herein. B. This work shall consist of furnishing and installing the erosion control blanket; including fine grading, blanketing, stapling, and miscellaneous related work, in accordance with these standard specifications and at the locations identified on drawings or designated by the owner s representative. This work shall include all necessary materials, labor, supervision, and equipment for installation of a complete system. C. All work of this section shall be performed in accordance with the conditions and requirements of the contract documents. D. The erosion control blanket shall be used to prevent surface erosion and enhance revegetation. Based on a project-by-project engineering analysis, the blanket shall be suitable for the following applications: 1. Slope protection 2. Channel and ditch linings 3. Reservoir embankments and spillways 4. Culvert inlets and outfalls 5. Dikes, levees, and riverbanks 1.02 Performance Requirements A. Erosion control blanket shall provide a temporary, biodegradable cover material to reduce slope and/or channel erosion and enhance revegetation. Erosion control blanket performance capabilities shall be determined by ASTM D 6459, Determination of Erosion Control Blanket (ECB) Performance in Protecting Hillslopes from Rainfall-Induced Erosion, and ASTM D 6460, Determination of Erosion Control Blanket (ECB) Performance in Protecting Earthen Channels from Stormwater-Induced Erosion. 1

B. Blanket performance requirements: C factor:.05 Shear Stress: 1.75 lb/ft 2 (84 Pa) Velocity: 7.0 ft/sec (2.1 m/sec) Functional Longevity 1 : 3 months (Netting) 1 Functional Longevity varies from region to region because of differences in climatic conditions. 1.03 Submittals A. Submittals shall include complete design data, Product Data Sheets, Product Netting information, SDS, Staple Pattern Guides, Installation Guidelines, Manufacturing Material Specifications, Manufacturing Certifications, CAD details, and a Manufacturing Quality Control Program. In addition, the Manufacturer shall provide a test report providing data showing the performance capabilities of the erosion control blanket, along with reference installations similar in size and scope to that specified for the project. 1.04 Delivery, Storage, and Handling A. Erosion control blanket shall be furnished in rolls and wrapped with suitable material to protect against moisture intrusion and extended ultraviolet exposure prior to placement. B. Erosion control blanket shall be of consistent thickness with fibers distributed evenly over the entire area of the blanket. C. Erosion control blanket shall be free of defects and voids that would interfere with proper installation or impair performance. D. Erosion control blanket shall be stored by the Contractor in a manner that protects them from damage by construction activities. PART II - PRODUCTS 2.01 Erosion Control Blanket A. Erosion control blanket shall be AEC Premier Straw Double Net Quick Mow, as manufactured by American Excelsior Company, Arlington, TX (1-866-9FIBERS). B. AEC Premier Straw Double Net Quick Mow erosion control blanket (ECB) consists of the finest available agricultural straw with 75% four-inch fibers or greater fiber length, and is certified weed seed free. The straw fibers are evenly distributed throughout the entire area of the blanket. The top and bottom of each blanket is covered with polypropylene netting containing an UV degrader additive. AEC Premier Straw Double Net Quick Mow shall be manufactured in the U.S.A. 2

C. Erosion control blanket shall have the following material characteristics: Width 8.0 ft (2.4 m) 16.0 ft (4.9 m) Length 112.5 ft (34.3 m) 112.5 ft (34.3 m) Area 100.0 yd 2 (83.6 m 2 ) 200.0 yd 2 (167.2 m 2 ) Weight 2 50.0 lb (22.7 kg) 100.0 lb (45.4 kg) Mass per Unit Area (± 10%) 0.50 lb/yd 2 (0.27 kg/m 2 ) 0.50 lb/yd 2 (0.27 kg/m 2 ) Net Openings Quick Mow 0.50 in x 0.50 in (12.7 mm x 12.7 mm) 0.50 in x 0.50 in (12.7 mm x 12.7 mm) TYPICAL INDEX VALUES Index Property Test Method Value Thickness ASTM D 6525 0.31 in (7.9 mm) Light Penetration ASTM D 6567 26.4% Resiliency ASTM D 6524 61% Mass per Unit Area ASTM D 6475 0.43 lb/yd 2 (233 g/m 2 ) MD-Tensile Strength Max. ASTM D 6818 196.8 lb/ft (2.87 kn/m) TD-Tensile Strength Max. ASTM D 6818 92.4 lb/ft (1.35 kn/m) MD-Elongation ASTM D 6818 32.7% TD-Elongation ASTM D 6818 26.4% Swell ECTC Procedure 22% Water Absorption ASTM D 1117/ECTC 460% Bench-Scale Rain Splash ASTM D 7101 SLR = 9.58 @ 2 in/hr 2,3 Bench-Scale Rain Splash ASTM D 7101 SLR = 7.53 @ 4 in/hr 2,3 Bench-Scale Rain Splash ASTM D 7101 SLR = 5.92 @ 6 in/hr 2,3 Bench-Scale Shear ASTM D 7207 1.95 lb/ft 2 @ 0.5 in soil loss 3 Germination Improvement ASTM D 7322 530% 2 Weight is based on a dry fiber weight basis at time of manufacture. Baseline moisture content of AEC Premier Straw fibers is 15%. 3 SLR is the Soil Loss Ratio, as reported by NTPEP/AASHTO. 4 Bench-scale index values should not be used for design purposes. 2.02 Staples A. Staples shall be a minimum 4 in biodegradable E-Staple, as provided by American Excelsior Company, or 6 in wire for cohesive soils and 6 in biodegradable E-Staple, as provided by American Excelsior Company, or 8 in wire for non-cohesive soils. All staples shall have a U- shaped top. PART III - EXECUTION 3.01 Blanket Supplier Representation A. Contractor shall coordinate with the blanket supplier for a qualified representative to be present at the job site at the start of installation to provide technical assistance as needed. Contractor shall remain solely responsible for the quality of installation. 3

3.02 Site Preparation A. Before placing erosion control blanket, the Contractor shall certify that the subgrade has been properly compacted, has been graded smooth, has no depressions, voids, soft or uncompacted areas, is free from obstructions such as tree roots, protruding stones or other foreign matter, and is seeded and fertilized according to project specifications. The Contractor shall not proceed until all unsatisfactory conditions have been remedied. By beginning construction, the Contractor signifies that the preceding work is in conformance with this specification. B. Contractor shall fine grade the subgrade by hand dressing where necessary to remove local deviations. C. No vehicular traffic shall be permitted directly on the erosion control blanket. NOTE: Topsoiling, seeding, and fertilizing is not included in this specification. 3.03 Slope Installation A. Erosion control blanket shall be installed as directed by the owner s representative in accordance to manufacturer's Installation Guidelines, Staple Pattern Guides, and CAD details. The extent of erosion control blanket shall be as shown on the project drawings. B. Erosion control blanket shall be oriented in vertical strips and anchored with staples, as identified in the Staple Pattern Guide. Adjacent strips shall be abutted or overlapped to allow for installation of a common row of staples that anchor through the nettings of both blankets. Horizontal joints between erosion control blankets shall be sufficiently overlapped with the uphill end on top for a common row of staples so that the staples anchor through the nettings of both blankets. C. Where exposed to overland sheet flow, a trench shall be located at the uphill termination. Erosion control blanket shall be stapled to the bottom of the trench. The trench shall be backfilled and compacted. Where feasible, the uphill end of the blanket shall be extended three feet over the crest of the slope. D. When terminating into a channel, slope erosion control blanket shall be overlapped by the channel erosion control blanket sufficiently for a common row of staples to anchor through the nettings of both blankets. 3.04 Channel Installation A. Erosion control blanket shall be installed as directed by the owner s representative in accordance with manufacturer's Installation Guidelines, Staple Pattern Guides, and CAD details. The extent of erosion control blanket shall be as shown on the project drawings. B. Erosion control blanket shall be installed parallel to the flow of water. The first roll shall be centered longitudinally in mid-channel and anchored with staples as identified in the Staple Pattern Guide. Subsequent rolls shall follow from channel center outward and be overlapped to allow installation of a common row of staples so that the staples anchor through the nettings of both blankets. 4

C. Successive lengths of erosion control blanket shall be overlapped sufficiently for a common row of staples with the upstream end on top. Staple the overlap across the end of each of the overlapping lengths so that staples anchor through the nettings of both blankets. D. A termination trench shall be located at the upstream termination. Erosion control blanket shall be stapled to the bottom of the trench. The trench shall be backfilled and compacted. 3.05 Quality Assurance A. Erosion control blanket shall not be defective or damaged. Damaged or defective materials shall be replaced at no additional cost to the owner. B. Product shall be manufactured in accordance to a documented Quality Control Program. At a minimum, the following procedures and documentation shall be provided upon request: 1. Manufacturing Quality Control Program Manual 2. First piece inspection of products produced to assure component materials and finished product tolerances are within manufacturer specifications. 3. Additional inspections for product conformance shall be conducted during the run after the first piece inspection. 4. Every roll shall be visually inspected. 5. Moisture content of fibers measured upon receipt. 6. At a minimum, every third roll shall be weighed to insure conformance of manufacturers specifications. 7. Each individual erosion control blanket shall be inspected and weighed prior to packaging for conformance to manufacturing specifications. 3.06 Clean-up A. At the completion of this scope of work, Contractor shall remove from the job site and properly dispose of all remaining debris, waste materials, excess materials, and equipment required of or created by Contractor. Disposal of waste materials shall be solely the responsibility of Contractor and shall be done in accordance with applicable waste disposal regulations. 3.07 Method of Measurement A. The erosion control blanket shall be measured by the square yard of surface area covered. No measurement for payment shall be made for overlaps, fine grading, trenching, staples, or other miscellaneous materials necessary for placement of the erosion control blanket. 5

3.08 Basis of Payment A. The accepted quantities of erosion control blanket shall be paid for at the contract unit price per square yard, complete in place. Payment shall be made under: Pay Item Erosion Control Blanket Pay Unit Square Yards Disclaimer: AEC Premier Straw is a system for erosion control and revegetation on slopes and channels. American Excelsior Company (AEC) believes that the information contained herein to be reliable and accurate for use in erosion control and revegetation applications. However, since physical conditions vary from job site to job site and even within a given job site, AEC makes no performance guarantees and assumes no obligation or liability for the reliability or accuracy of information contained herein for the results, safety, or suitability of using AEC Premier Straw, or for damages occurring in connection with the installation of any erosion control product whether or not made by AEC or its affiliates, except as separately and specifically made in writing. These specifications are subject to change without notice. 6