SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

Similar documents
1.01 GENERAL. l.02 PIPELINE TRENCH EXCAVATION PIPELINES AND STRUCTURES REVISION: SECTION 1 PAGE : 1-1

ITEM 706 PIPE SLOPE DRAIN

CW 3170 EARTHWORK AND GRADING TABLE OF CONTENTS

Union County Vocational - Technical Schools Scotch Plains, New Jersey

SECTION MEASUREMENT AND PAYMENT

ADDENDUM No. 2. ITB No WTP LIME RESIDUAL REMOVAL CONTRACT No. 2 DREDGING AND HAULING

SECTION UNCLASSIFIED EXCAVATION AND GRADING

TECHNICAL SPECIFICATION

DIVISION 4100 SITEWORK

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

CITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP

RFB for Wastewater Force Main #3. October 2, Addendum 3: Clarifications and Questions from Pre-Bid Meeting Answered

EXCAVATION, TRENCHING & BACKFILLING..1 The section refers to excavation, trenching, backfilling and all Work pertaining thereto.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

TOWN OF MANCHESTER GENERAL SERVICES DEPARTMENT 494 MAIN STREET P.O. BOX 191 MANCHESTER, CONNECTICUT

EXCAVATION & BACKFILLING GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

SECTION SITE GRADING. Part 1 - General Work Included Related Requirements Reference Standards...

SANBORN COUNTY

SECTION TRENCHING & BACKFILLING

SECTION UNIT PRICES. A. This Section specifies administrative and procedural requirements for the unit prices.

GRADING, EROSION AND SEDIMENTATION CONTROL

SECTION MEASUREMENT AND PAYMENT

SECTION TEMPORARY ENVIRONMENTAL CONTROLS

SPECIAL SPECIFICATION 3504 Septic Tank System

SECTION MEASUREMENT AND PAYMENT

ADDENDUM NO. 1. DATE ISSUED: June 1, 2018

SECTION 14 EMBANKMENT

Special Provision Item P-152 Excavation and Embankment

SECTION A1 EXCAVATION AND BACKFILL GENERAL

a. Unless otherwise specified, all lengths shall be horizontal distances.

Section 5 Specification 5.22 Supply and Install Smooth Wall Steel Pipes TABLE OF CONTENTS

ITEM 430 CONSTRUCTION OF UNDERGROUND UTILITIES

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

Job Order Sewer Repair Services

SECTION PAYMENT PROCEDURES

SECTION EARTHWORK

Construction Specification for General Excavation

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION TRENCHING

SECTION TRENCHING, BACKFILLING, COMPACTION AND GENERAL GRADING

STATE OF NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION DIVISION OF COASTAL ENGINEERING

SECTION 1 GENERAL NOTES

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

DOCUMENT ADDENDA AND MODIFICATIONS

STANDARD CONSTRUCTION SPECIFICATIONS TABLE OF CONTENTS SECTION TRENCHING AND BACKFILL

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

Addendum No. 1 Page 1 of 2

SECTION EMBANKMENT

City of Brandon Division 2 Standard Construction Specifications Section January 2007(Revision 1) Page 1 of 8 ROADWAY EXCAVATION AND GRADING

SECTION 603 SEEDING I. GENERAL 1.1 DESCRIPTION OF WORK

SECTION STORM DRAIN REHABILITATION. 1. Protection of environment; Section O Trench excavation, backfill, and compaction; Section

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

SECTION EARTHWORK. B. Removal of subsoil and excavating all classes of material encountered.

SPECIAL SPECIFICATION 4653 Polypropylene Pipe

CITY OF AUBURN STANDARD SPECIFICATIONS SECTION 13 EXCAVATION AND BACKFILL

Excavate drilled shafts in accordance with Item 416, Drilled Shaft Foundations.

SECTION GENERAL EXCAVATION

STATE OF SOUTH DAKOTA DEPARTMENT OF TRANSPORTATION PLANS FOR PROPOSED

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

ADDENDUM #1 Village of Hawthorn Woods Darlington Drive Culvert Replacement Date: January 29, 2018

Surface Infrastructure Restoration for Utility Cuts DIVISION 14 Shallow Buried Utilities Section _Mar29_2016.pdf Page 1 of 20 INDEX

C. Foundation stabilization for pipe and utility structures.

ADDENDUM 1. Request for Proposals City of Minot, North Dakota Structure Demolition and Site Restoration Project, # Round 3.

Table of Contents for Guide Specifications

STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION CITY OF WEST BEND, WISCONSIN SECTION 800 EROSION AND SEDIMENT CONTROL

2. Insert Pre-Bid Meeting Minutes, and Sign-in Sheet before Technical Specifications.

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

2.1 Backfill - General

SPECIAL SPECIFICATION 6666 Charter Communications System

ITEM 481 MONOLITHIC REINFORCED CONCRETE BOX SEWERS

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

SECTION 10 - TRENCHING AND BACKFILLING

SECTION 18 - EARTHWORK TABLE OF CONTENTS

SPECIAL SPECIFICATION 4425 Thermoplastic Pipe

SECTION 18 - EARTHWORK TABLE OF CONTENTS

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

III. TECHNICAL SPECIFICATIONS DIVISION 56 BORED PIPE

SECTION 32 EXCAVATION, BACKFILL, COMPACTION AND GRADING

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER

CCU Engineering Specifications. Section PIPE REMOVAL, DISPOSAL, ALTERATION, MODIFICATION OR PIPE ABANDONMENT

Bid Item 2 Prevention Control and Abatement of Erosion and Water Pollution Bid Item 3 Soil Tracking Prevention Device

The Regional Municipality of Peel Basis of Payment

2. SECTION MEASUREMENT AND PAYMENT:

TERMS OF REFERENCE PROJECT EDINBURGH ROAD FROM SPEEDVALE AVENUE TO LONDON ROAD

RFB # ADDENDUM NO. 1 ISSUED APRIL 23, 2018 PRE-BID MEETING MINUTES NEW HANOVER COUNTY LANDFILL GAS COLLECTION AND CONTROL SYSTEM CONSTRUCTION

CITY OF FARGO SPECIFICATIONS REMOVALS

CONSTRUCTION SPECIFICATION FOR BORROW

CITY OF FARGO SPECIFICATIONS REMOVALS

B. Borrow: Satisfactory soil imported from off-site for use as fill or backfill.

SECTION EARTHWORK; EXCAVATION, FILLING AND GRADING. A. Excavating soil and other material for surface improvements.

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION TRENCHING, BACKFILL AND COMPACTION

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE

SECTION STORM DRAINAGE SYSTEM Excavating, Backfilling, and Compaction for Utilities Cast-in-place Concrete.

SPECIAL SPECIFICATION. Water and Sewer System and Appurtenances

Erosion & Sedimentation Control Policy

Transcription:

SECTION 334701 - WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING PART 1 - GENERAL 1.1 DESCRIPTION A. Scope: 1. The Contractor shall provide all labor, materials, tools, and equipment required to remove existing residuals from the North Lagoon at the Williams Road Water Treatment Plant site, provide on-site dewatering to a minimum of 20% solids content if required, transport residuals, and dispose of all residuals in an approved, New York State Department of Environmental Conservation (NYSDEC) permitted, manner. 1.2 QUALITY ASSURANCE A. Requirements of Regulatory Agencies 1. Comply with the applicable requirements of the NYSDEC, Division of Solid Waste and other agencies or authorities having jurisdiction. Apply for, pay for and obtain necessary and/or required permits for hauling and disposing of residuals at a site approved by NYSDEC. 1.3 SUBMITTALS A. Shop Drawings: Submit for approval the following: 1. Detailed description of the proposed Lagoon cleaning procedures including materials and equipment used to remove residuals and clean Lagoon. 2. Detailed description of the residuals dewatering system including procedures for handling excess leachate from the residuals dewatering process. 3. NYSDEC permitted (or NYSDEC approved alternative) residual disposal location to be used. 4. Material to be used for clay cut off trench and clay liner. 1.4 DEFINITIONS A. Contract Documents may refer to water treatment residuals as sludge. These two (2) descriptions shall be used interchangeably. PART 2 - REQUIREMENTS 2.1 GENERAL A. The North Lagoon at the Williams Road Treatment Plant has been taken out of service as of the time of this Contract. The Contractor will be responsible to removed supernatant water, remove the sludge from the Lagoon, and provide on-site dewatering of the sludge to a minimum of 20% solids content if required. All sludge removed shall be taken to an approved disposal site and disposed of WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING 334701-1

in an approved manner. All liquid obtained in dewatering process shall be removed from the site and disposed of in an approved manner. B. All sludge removed from the Lagoon shall be processed and treated on-site to twenty percent (20%) (min.) solids and no free moisture shall be evident in the sludge. C. All removal, treatment, transportation, and disposal of sludge and liquid obtained from dewatering process shall be in accordance with the New York State Department of Environmental Conservation, Division of Solid Waste, 6 NYCRR Part 360 Solid Waste Management Facilities and the rules and regulations of the Agency. D. The Contractor shall handle, transport, and dispose of sludge using methods consistent with all regulations of the NYSDEC or other agencies having jurisdiction of the work. E. Upon removal of the sludge from the Water Treatment Plant site, the Contractor shall assume and hold ownership of all removed materials. F. The Contractor shall dispose of all sludge obtained hereunder, at a NYSDEC approved disposal site as identified in the Bid Requirements Section. The Contractor shall not be limited to the use of one approved NYSDEC approved disposal site. The Contractor shall be required to remove from the site all sludge from the North Lagoon at the Water Treatment Plant throughout the terms of this Contract regardless of operating status of any disposal site owned or operated by the Contractor or others. G. The Contractor shall clear and grub the existing vegetation and trees growing in the sludge deposits at the bottom of the existing Lagoon prior to removal of the sludge. All vegetation and trees removed shall be disposed of off-site in an approved manner. Vegetation and grass removed from the side slopes of the Lagoon embankment shall be disposed of off-site in an approved manner. All costs associated with clearing and grubbing shall be included in the applicable lump sum item(s). H. All sludge must be properly disposed as outlined in Section 2.1 of this section. Alternative disposal or private disposal of the sludge is strictly prohibited unless NYSDEC permit documentation is provided showing alternative or private disposal is permitted by the NYSDEC. 2.2 OBLIGATION AND RESPONSIBILITY OF CONTRACTOR A. The Contractor shall, at his own cost and expense, provide any and all manner of superintendence, insurance, taxes, permits, permit fees, testing, labor, materials, apparatus, appliances, tools, machinery, power, transportation and whatever else may be required of every description necessary to do and complete the work as shown and as specified. B. The Contractor shall be capable of providing all aspects of work required for the handling, transportation, disposal, procurement of applicable permits and testing required for the treatment and disposal of the Water Treatment Plant sludge removed from the North Lagoon. 2.3 PERMITS AND TESTING A. Full TCLP, ph, and total solids tests were performed on the sludge and are included in this Specification under Appendix "C". The test results are for informational purposes only and are representative of the sludge on the day the tests were taken. Testing required in order to obtain or WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING 334701-2

comply with permits, shall be performed by the Contractor and all costs associated with these tests will be the responsibility of the Contractor and included under the applicable lump sum prices. B. The Contractor shall obtain all permits required for the handling, transportation and disposal of all sludge from the Water Treatment Plant site. C. Permits may include transportation permits, disposal permits, NYSDEC permits, and any other permits required to complete the work as shown and as specified. D. All fees required for the procurement of the above mentioned permits and any tests required shall be paid by the Contractor. E. The Contractor shall obtain approved permits prior to the start of any work requiring permits and shall deliver a copy to the Engineer prior to starting any work under this Contract. F. All testing required for disposal of the sludge shall be obtained by the Contractor. G. Appendix "B" contains safety data sheets for chemicals used in the water treatment process from which the sludge originated. These sheets are supplied for information purposes only. PART 3 - EXECUTION 3.1 REMOVAL OF SLUDGE A. The existing sludge shall be removed by the Contractor. The Contractor is responsible for all methods used for the removal of the sludge from the Lagoon; however, any methods employed shall be approved by the Engineer. The Contractor's selection of equipment and methods used to remove the sludge from the Lagoon shall take into account the construction of the existing Lagoon to be cleaned, the sizes of the available work areas, existing Owner's operations in the area and any other factors which may affect the work under this project. B. The approximate quantity of sludge in the Lagoon is 4,980 CY+/-. This calculated volume is only representative of the volume of sludge on the day the field tests and survey was completed. The Lagoon bottom was surveyed in August 2009 after cleaning. The top of sludge was surveyed in March 2015. Actual volumes may vary. The Contractor is responsible to remove all sludge in the Lagoon from the existing top elevations to the top of the existing Lagoon bottom. If the amount of sludge to be removed to reach the clay layer exceeds 4,980 CY, no additional compensation to the Contractor shall result. C. The Contractor shall confine his operations to the limits of work areas as designated by the Owner. Any damage resulting from work outside the limits of work areas shall be restored by the Contractor and shall be subject to approval by the Engineer. Upon completion of all work required under this Contract, the Contractor shall restore the areas used for his work to the original condition and to a condition acceptable to the Engineer. Restoration shall include but is not limited to grading as required, furnishing and installing topsoils and seeding. D. An approximate cross section of the existing Lagoon have been included in Appendix D. Prior to excavation and sludge removal, the Contractor will be required to make test excavations to determine and verify the elevation of the top of the existing Lagoon bottom. The cost of the test excavations shall be included in the lump sum price bid by the Contractor for completion of this WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING 334701-3

Contract. Location and quantity of these test excavations shall be approved by the Engineer. The Contractor shall remove sludge to the elevations and limits as shown on the Contract Drawings or to the top of the existing Lagoon bottom. For the Lagoon bottom, the Contractor shall use care when excavating and removing sludge from the lagoon so as not to over excavate below the proposed elevations as shown. Any over excavation caused by the Contractor's operations may result in removal of sections of the existing Lagoon bottom. These test excavations (to confirm the Lagoon bottom elevation) are not considered test pit excavations and shall not be paid for under the test pit excavation bid item. E. In the event that the Lagoon bottom is disturbed or damaged by the Contractor's operations, the bottom shall be repaired with additional compacted clay material by the Contractor. The Contractor shall not repair the bottom with the disturbed existing material unless directed by the Engineer. Repairs, if required, shall be approved by the Engineer. A shop drawing submittal is required to be submitted by the Contractor outlining materials, equipment and methods used by the Contractor to repair the Lagoon bottom. The Lagoon bottom shall be repaired or replaced to the thickness of the required for the proposed clay liner, as required and approved by the Engineer. Clay material shall have a permeability of 1 x 10-7 centimeters per second or less. Compaction shall meet 95%of maximum density at the approximate optimum moisture content determined by the procedure ASTM D-1557 modified proctor. Compaction shall be obtained by the use of mechanical tamping devices. 3.2 ON-SITE SLUDGE TREATMENT A. The Contractor will be required to ensure that the sludge taken to an approved landfill is a minimum of 20% solids with no free liquid evident in the sludge as per requirements of the NYSDEC Part 360. If the sludge removed meets these criteria, the sludge may be directly taken to an approved landfill. If the sludge does not meet the 20% solids criteria, the Contractor shall provide means to treat the sludge to meet the criteria. As the Contractor's option, the sludge can be mixed with sludge consisting of higher percent solids in order to obtain a uniform mixture of solids meeting the Specification requirements. As solids content requires, the Contractor shall provide a trailer mounted on-site dewatering unit to provide on-site sludge dewatering to meet the 20% solids criteria. The dewatering unit shall be trailer mounted and outfitted with all necessary equipment to make it a complete dewatering facility. Equipment shall include sludge pumps, sludge conditioning equipment, chemicals, and all other equipment necessary to treat and dewater the sludge. The Contractor will not be allowed to add water to the sludge to aid in the removal of the sludge from the Lagoon. B. Liquids produced from the dewatering operation shall be collected and sent to a tank or other approved collection system. No liquids will be allowed to escape from the process. The Contractor shall provide all means necessary to ensure complete collection of liquids resulting from dewatering operations. The liquids obtained from dewatering operations shall NOT be returned to any point of the Water Treatment Plant site. C. The Contractor shall provide all required tanks, trucks, or other methods necessary to contain the water and liquids produced from the sludge removal operations and shall dispose of the liquids offsite in an approved manner. The Contractor is responsible to make all arrangements and obtain all permits required in order to dispose of the liquids produced by his operations. WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING 334701-4

D. The Contractor will be responsible to perform and pay the associated costs for all testing required by the permits in order to ensure the sludge meets all the criteria including percentage of solids, as well as any additional tests ordered by the Engineer, to ensure conformance with the permits and the Contract Documents. 3.3 SLUDGE HAULING AND DISPOSAL A. Methods employed by the Contractor to haul and dispose of sludge shall meet all permit requirements and local ordinances in effect at the time of this Contract. The Contractor shall use bed liners, covers, and all other equipment necessary to prevent sludge spillage or seepage during transportation. The Contractor shall be responsible for all costs for cleanup of all spilled sludge between the project and disposal sites. B. The Contractor shall coordinate his sludge hauling operations with the Owner's operations and with other Contractors performing work at the site. Any hauling operations by the Contractor shall be scheduled in order to avoid conflicts with Owner's operations and other work and shall be acceptable to the Owner. The Owner will designate routes or roadways at the Water Treatment Plant site for the Contractor's uses. The hauling operation shall be limited to these designated routes or roadways. 3.4 SITE MAINTENANCE A. The Contractor shall be responsible for daily clean-up of the site including the grass area, stone haul road, and asphalt pavement area. B. While cleaning the pavement area, at no time is the Contractor allowed to discharge water into the existing storm sewer system located on the site (within the pavement area). C. The Contractor shall be responsible for all necessary soil and erosion control measures to prevent the discharge of soil or contaminated water into the storm sewer system. D. The Contractor shall be responsible for final cleaning of the site at the completion of the project. This will include stone haul road restoration, site grading, topsoiling, and seeding, and pavement restoration (if necessary). END OF SECTION 334701 WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING 334701-5