Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Similar documents
VIRIDOR WASTE MANAGEMENT LTD

Northacre Renewable Energy

Ardley Waste Management Facility. Non Technical Summary

Northacre Renewable Energy

CONCLUSIONS 14 CONTENTS

Cottonmount Landfill Stable Non Reactive (SNR) Asbestos Cell. Volume 2 NON TECHNICAL SUMMARY. December 2012 SLR Ref:

Northacre Renewable Energy

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary

NON TECHNICAL SUMMARY

Division 15 Earthworks Code (including Lot Filling)

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Works, services and infrastructure code

5. Environmental issues and methodology

Wellington Dock Planning Application, Liverpool. Non-Technical Summary for Environmental Statement

Management Plan: Hazardous Materials Removal & Demolition

Land to the South of Old Mill Road, Sandbach Environmental Impact Assessment Environmental Statement: Non-Technical Summary

NON TECHNICAL SUMMARY

Clifton Marsh Landfill Variation of planning permission 05/09/0376 & 06/09/0395 for the continuation of landfilling until Non Technical Summary

Non-Technical Summary

18 Cumulative Impacts and Interaction of Effects

Excavated Material and Waste Management

Sizewell B Dry Fuel Store. Environmental Statement Non-Technical Summary

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

LOSTOCK SUSTAINABLE ENERGY PLANT VARIATION OF CONSENT UNDER SECTION 36C OF THE ELECTRICITY ACT 1989

NON TECHNICAL SUMMARY OF THE ENVIRONMENTAL STATEMENT

Longbridge Town Centre Planning Application

A1 JUNCTION IMPROVEMENTS DROMORE ROAD, HILLSBOROUGH

DIRECTION UNDER SECTION 90(2ZA) OF THE TOWN AND COUNTRY PLANNING ACT 1990 TO VARY THE CONDITIONS OF THE 2012 DEEMED PLANNING PERMISSION (TRACK CHANGE)

Non-technical summary

Sustainability Statement

CHAPTER 1 INTRODUCTION

Environmental Statement Non Technical Summary. Anthony s Way Frindsbury June creative minds safe hands

Arcow Quarry, North Yorkshire

(1) Site Suitability PURPOSE

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

Non-Technical Summary

Wytch Farm Pipeline Refurbishment Project. Environmental Statement. Non-Technical Summary. November 2007

RURAL LIVING AREAS Rural Living Areas Rural Lifestyle and Rural Residential 8.1 Issues, Objectives and Policies

South Landfill Annual Cover Rate Screening Criteria Checklist

Central Park Mixed Use Development

Thorn Turn Waste. Non-Technical Summary. Central Bedfordshire Council. 10 May Central Bedfordshire Council

Draft Code of Construction Practice

M25 Junctions 27 to 30 Widening

Kitchener Drain Depollution Project: Drain Rehabilitation Solid Waste. Non-Technical Summary

Non-technical summary. Canford. Extension of composting facility. Non-technical summary

NON-TECHNICAL SUMMARY (NTS)

Ellerton. Ellerton. Non Technical Summary

E3: EXCAVATED MATERIAL AND WASTE MANAGEMENT

Environmental Statement Non-Technical Summary Rectory Farm, Hounslow

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI

NON-TECHNICAL SUMMARY

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices

Recycling and Energy Recovery Facility (RERF)

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY

Norfolk Minerals and Waste Local Plan. Sustainability Appraisal Report Non-technical summary

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby.

Ferrybridge Multifuel 2 (FM2) Power Station

Division 8 Intensive Animal Husbandry Code

FORMER BAYER CROPSCIENCE LTD SITE, HAUXTON, CAMBRIDGESHIRE

Viridor s 200 million investment would create around 40 permanent jobs and many more during construction.

Energy from Waste Facility Environmental Statement Volume 1: Non-Technical Summary. July 2016

WINGMOOR FARM. Integrated Waste Management Facility. May2009

Vital Earth Composting Facility Environmental Statement: Non Technical Summary

Report by the Executive Director of Community and Environmental Services

EF10 Site Environmental Audit - 1 / 8

CHAPTER 11 LIGHTING NORTHAMPTON GATEWAY

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards

Standard rules SR2012 No13 Treatment of Incinerator Bottom Ash (IBA)

Ponds Farm, Environmental Statement Non-Technical Summary

Waste Management of Canada Corporation (WM) is pleased to welcome you to Public Open House #2 for the. Twin Creeks Landfill Environmental Screening

INSPECTORS REPORT DRAFT PD REGISTER NUMBER

Town & Country Planning Act Notice of Planning Permission for Variation/Non-Compliance with a condition imposed on an earlier permission

GUIDE TO THE PREPARATION OF A WORKING PLAN SCRAPYARD / ELV FACILITY

Manningham Works Code of Practice

Marlow Flood Alleviation Scheme Environmental Statement Non-Technical Summary. Final. WNGLDC Environment Agency Title

Draft Air Quality & Odour Net Effects Analysis & Comparative Evaluation Report

6 Risk assessment methodology

Annex F Scoping Checklist

AM-PR-003 Construction Environmental Management Plan (C-EMP)

BARRASFORD QUARRY PERIODIC REVIEW. Environmental Statement - Non Technical Summary. October 2014

Rural Living Environment

Outline Construction and Environmental Management Plan

Planning, Taxi Licensing and Rights of Way Committee Report. Application No: P/2018/0067 Grid Ref:

ERECTION OF WASTE RECEPTION HALL AND AMENDED HOURS OF OPERATION

A684 Bedale, Aiskew and Leeming Bar Bypass Environmental Statement. Non Technical Summary. Business and Environmental Services

Filey FAS. Presentation to Planners. Stewart Rowe

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

H28. Special Purpose Quarry Zone

About this Exhibition

CHAPTER 7 WATER RESOURCES AND DRAINAGE NORTHAMPTON GATEWAY

Newhurst Energy Recovery Facility, Shepshed, Leicestershire. Proposed modifications to the approved design. Volume 3 NON TECHNICAL SUMMARY

Welcome to this exhibition by DS Smith Paper Ltd regarding the Kemsley Paper Mill (K4) CHP Plant project.

Granville Energy from Waste Centre. Non Technical Summary of Environmental Statement

VIRIDOR WASTE MANAGEMENT LIMITED. Glasgow Recycling and Renewable Energy Centre. Non Technical Summary

Proposed Residential Development at Land to the South of Pepper Lane. Environmental Statement: Non-Technical Summary

Chapter 17 Cumulative Impacts

8 Geology, Hydrology & Hydrogeology

5. Predicting the effects of the Silica Sand Review including alternatives (Task B3)

Comparative Evaluation Option #1 & Option #2

Transcription:

Viridor Waste Management Proposed Development of an In-Vessel Composting Facility Land at Exide Batteries, Salford Road, Bolton Non-Technical Summary January 2009

Introduction Viridor Waste Management (Viridor) are submitting a planning application for the development of an In-Vessel Composting Facility at land (referred to as Exide Batteries) adjacent to CMP Batteries Ltd, Salford Road, Bolton. Background Viridor Waste Management (Viridor) and John Laing Infrastructure Ltd (JLI) joined together as the Viridor Laing (VL) consortium to bid for the Greater Manchester Waste Disposal Authority (GMWDA) waste management PFI Contract. VL was announced as Preferred Bidder on 26 January 2007. The facility is one of a number of key waste management facilities to be constructed by VL around Greater Manchester as part of a strategic initiative to increase recycling and composting, divert waste from landfill, minimise waste transport and allow the recovery of energy. What are the Proposals? Viridor propose to construct an In-Vessel Composting (IVC) Facility at Exide Batteries to treat kerbside collected garden and kitchen waste to produce agricultural and horticultural compost. This development is designed to hold a 50,000 tonnes per annum capacity to process composting waste from Bury, Bolton and Salford Waste Collection Authorities. The site is located approximately 4.8km south west of Bolton town centre. It is located within a mixed rural and industrial setting close to Junction 4 of the M61 motorway and the A6 (Salford Road). The site lies wholly within the Metropolitan Borough of Bolton, and is located as shown on Drawing LE10126/EIA 3.1. The site occupies an area of approximately 3.8ha. The waste will be delivered to an enclosed building where it will be unloaded and placed into silo cages. Within these silo cages, the material will go through a natural composting process, with natural aeration, for a minimum of 2 weeks before being transferred to the maturation hall. Within the maturation hall, the material will be left to mature naturally before being transferred to end markets for agricultural and horticultural products. Odours will be extracted via a forced air ventilation system and treated within an odour treatment system, comprising an acid scrubber and three carbon filters.

Proposed Site Opening Hours Waste Reception Composting Within IVC Building Monday - Friday Saturday Sunday Monday Sunday 07:00-18:00 07:00-1300 - 24 hours a day Environmental Statement An Environmental Statement (of which this is a summary) has been prepared in accordance with the requirements of the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999 (amended 2008). The Environmental Statement sets out the possible impacts of the proposals, considers their significance and identifies measures for reducing the effects. Principal Environmental Impacts The principal environmental impacts addressed in the Environmental Statement are summarised below. Landscape and Visual Impact Assessment The impacts to the landscape character have been assessed and will be moderate adverse due to the loss of open land. The removal of the invasive species Himalayan Balsam will have a beneficial impact on the character. The initial impacts will reduce to slight adverse as the proposed planting and habitats mature. The introduction of a management and maintenance programme will also benefit the wider area as the spread of Himalayan Balsam is reduced. The visual impact will be slight adverse during the construction phase, but these impacts will only be temporary. On completion, visual impacts for viewpoints with longer views of the site will be slight adverse to imperceptible due to the ventilation stack; however, the landscape character and visual will benefit from proposed planting and the improved management and maintenance of the site. All built developments generate landscape and visual effects, but these are addressed as part of the design process, to ensure that the resulting development will fit appropriately into the site and the surroundings. The site is currently open land, adjacent to an existing industrial complex with established and mature screening. The facility will be developed in a well screened position adjacent to a larger industrial development. The location and scale of the IVC Facility are therefore considered to be appropriate to the site and the surrounding land uses.

Ecology and Nature Conservation Surveys and consultation of ecology and nature conservation have been undertaken from the early stages of the proposed development. One impact on ecology would derive from the removal and clearance of vegetation (as part of development and restoration processes). If this was to occur within the bird breeding season, it could potentially cause harm to bird species. However, by undertaking clearance works outside of the breeding bird session and providing additional foraging and nesting habitat, it is anticipated that the impact will be not significant. Development of the site has the potential to have a significant adverse impact on great crested newts. A licence will be applied for and a mitigation strategy will be agreed with Natural England, prior to works commencing. This will result in an impact that is not significant. Lighting during vegetation clearance, development and restoration activities may constitute a significant adverse impact. Adoption of mitigation measures will reduce these impacts to the degree that they are considered to be not significant. The potential increase in vehicle movements and pollution during site clearance, construction, restoration and operational activities may constitute a significant adverse impact. Appropriate mitigation and best practice reduces this impact to not significant. Geology, Mining, Ground Conditions and Land Quality The geology, geotechnical, mining and contaminated land issues, associated with the proposed development, were assessed as part of the Environmental Impact Assessment. The property is within an area formerly used for mining. Made ground was identified within the site, thus ground improvement may be necessary. During the construction of infrastructure and drainage systems, consideration will be made to the potential unstable nature of the made ground. Although further investigation will be needed to finalise the design details for the proposals, there are no identified risks or constraints which will prevent construction. Hydrology and Hydrogeology The site is not considered to be especially sensitive in terms of hydrology and hydrogeology; however potential impacts have still been assessed.

During construction, potential impacts could include an increase in surface water runoff as a result of soil compaction by construction vehicles, increased erosion and increased sedimentation of water courses. Best working practices will be implemented to ensure that impacts are minimal. During the operation, potential impacts could include an increase in surface water runoff from soil compaction, rapid transfer of rainwater to watercourses via drains and a decrease in water quality from releases or gradual seepage of leachate (includes pollutants) into the nearby watercourse. These impacts can be mitigated through good site management measures based on best practice guidance, such as impervious bunding of oil and fuel storage tanks, to control potential impacts on the water environment. Flood Risk and Drainage A Flood Risk Assessment has been carried out in relation to the proposed development at Exide Batteries. The development lies within an area classified as less vulnerable by the relevant planning legislation. The assessment found that there are no local site specific risks that would adversely affect this categorisation. There are considered to be no significant increased offsite flooding risks as a result of the development. The site is therefore considered suitable for the type of development proposed. Archaeology and Cultural Heritage It has been established that there are no Scheduled Ancient Monuments or Listed Buildings within the boundary of the site or within 500m of the site boundary. The site is not within a Conservation Area, a Historic Park or Garden or a Historic Battlefield. As part of a map regression exercise, a farmhouse has been identified within the south western corner of the site (dating from at least 1722). It has therefore been established with the County Archaeologist that trial trenching should take place within the southern part of the site. This will assess the potential for remains in the southern part of the site. Noise The construction phase will cause an increase in noise levels but these will only be temporary. To minimise the noise impact, mitigation measures will be put in place including the implementation of best working practice and restriction of working hours.

The potential noise impacts of the operation of the proposed IVC facility and on-site vehicle movements have been assessed. The noise survey indicates that the current ambient noise levels at the receptors in the vicinity of the site are predominantly influenced by the road traffic on the local road network. The noise assessment concludes that with appropriate mitigation, the noise levels generated by the operation of the proposed development will be below background noise levels at sensitive receptors. Air Quality and Public Health This assessment considers the impact of the emissions from the construction and operational phases of the development. Construction Phase The appropriate implementation of mitigation measures, such as the regular damping down on public roads/footpaths and the use of a wheel wash to control dust generated from general traffic at the site during earthworks and construction works, will be incorporated as part of a best working practice scheme and construction Environmental Management Plan; this should ensure that the residual dust impacts are negligible. The overall impact during the construction phase would in turn be negligible at sensitive locations near to the site. Operational Phase The development has the potential to generate dust, odour and bioaerosols. However, mitigation measures have been incorporated into the design of the IVC Facility, which includes air collection and treatment systems, to ensure impacts on air quality and public health, are insignificant. The impacts from potential changes in road traffic emissions, as a result of traffic generation associated with the proposed IVC Facility have been assessed as being non-significant. Traffic Traffic generation associated with the development is minimal and unlikely to have an effect on the highway network, especially as the vast majority of vehicles will access the site during offpeak periods. The site is conveniently located for access to the regional and national highway network; this ensures that vehicle movements are restricted to principal routes, away from residential areas. A traffic impact analysis was carried out using a worst case scenario. This showed that the future impact of the development is negligible on the local highway network.

Amenity Site construction works and the operation of the proposed facilities have the potential to generate amenity impacts associated with odour, dust, pests, litter, mud and lighting. A detailed and comprehensive set of design, management and mitigation procedures will be implemented to limit and negate the potential adverse effects. Efficient site management will minimise possible litter generation. Materials transported to the site will be securely contained or fully covered. Unloading of waste products will take place within the enclosed building. The risk of nuisance caused by pests is considered to be negligible. The site will be inspected regularly for signs of pest infestation. Lighting will be downward and into the site, and limited to the operational period. Low level security lighting and CCTV systems will be used outside the main operating period. Conclusion Viridor is submitting a planning application for the development of an In-Vessel Composting Facility at Exide Batteries, Bolton. The facility is one of a number of key waste management facilities to be constructed around Greater Manchester as part of a strategic initiative to increase recycling and composting, divert waste from landfill, minimise waste transport and allow the recovery of energy. The proposals comply with relevant national, regional and local planning policy. A full Environmental Impact Assessment has been carried out, and the findings summarised above are detailed in the Environmental Statement submitted as part of this application. The Environmental Impact Assessment has driven the site design proposed in the planning application to ensure the potential for impact is minimised or removed completely. A number of benefits will result from the proposals including the increase in recycling and composting, diversion of waste from landfill and the minimisation of waste transport.