ACHIEVE MULTI-BENEFITS USING THE. COMMISSIONING PROCESS FOR RETRO- COMMISSIONING OF BUILDINGS CLIMA 2005 Lausanne, Switzerland Paper Dorga274s

Similar documents
Energy Efficiency in Multi-Tenant Office Buildings

An Introduction to The Retro-Commissioning Process For Existing Buildings

Guideline HVAC&R Technical Requirements for The Commissioning Process

Energy Auditing for Schools. Maryland Energy Administration Eric Oliver, EMO Energy Solutions, LLC May 10, 2007

Retro-Commissioning in Hospitals

Retrocommissioning Investigation Report

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses

Existing Building Commissioning (or Retro-Commissioning)

9/13/2011. Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center. Terry Malloy P.E., Cxa, Project Manager, Teng & Associates

A Holistic Approach to Energy Management in Healthcare. PRESENTED BY: ROBERT GREENWALD, PEng, MBA September 21, 2010

South Carolina Society for Hospital Engineers

Building Retro-Commissioning

RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT. Adam Renzi, PE

Building Operator Certification Level I

George Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING

HVAC SYSTEM SCHEMATIC DESIGN

Reducing Hospital Energy Use and Maintaining Savings. Glen Anderson, PE

Fifteen Year Plan for Energy Efficiency and Conservation Projects

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction

Persistence Tracking in a Retro-commissioning Program

Higher Value Commissioning

Energy Treasure Hunt ESI Members Meeting. Shaunna Tobin, TE Connectivity Kelli Swain, TE Connectivity

FACILITIES MANAGEMENT

Operations and Maintenance Seminar. Mulak

General Information. Building Name: RPUID #: Address: UFC Requirement 4-2 EMPLOY INTEGRATED ASSESSMENT, OPERATION, AND MANAGEMENT PRINCIPLES.

Commissioning & Retro-Commissioning Meet Energy Code

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

ASHRAE/NIBS Guideline

PARK PLACE CASE STUDY VANCOUVER. Heat reclaim system expected to reduce steam consumption 80%, GHG emissions 68%

Building Control Strategies That Work to Improve Your Energy Bottom Line

Project Information. Measure Description

The Building Systems Detective

High Impact Hotel Projects

Commissioning & Retro-Commissioning Helping You Get the Most of Your Facilities

HVAC SYSTEM DESIGN PROCESS

BOC Training Equivalency Crosswalk

Application of Advanced Energy Technologies

the weidt group Implementation Rates of Energy Conservation Measures for Health Care Buildings collaboration analysis research

Mission Critical Commissioning for Healthcare Facilities

CONTINUOUS COMMISSIONING OF SALT LAKE COMMUNITY COLLEGE SOUTH CITY CAMPUS

Reducing Costs with Energy Efficiency

D DAVID PUBLISHING. Optimizing Thermal Energy Storage Systems in the Hospitality Industry. 1. Introduction

BOMA s Energy Efficiency Program BEEP Course 4. No- and Low Cost Operational Adjustments to Improve Energy Performance

ENHANCED BUILDING OPERATIONS PROGRAM

A Building Commissioning Overview. Presented by: Goetting & Associates Commissioning

Retro-Commissioning for Existing Facilities

ILLINOIS ENERGY NOW Energy Efficiency Incentives for State Facilities. December 2016

MBCx: The Next Wave of Energy Savings in Utility Incentive Programs

Arizona Healthcare Pollution Prevention Workshop April 28, 2005 Jim Westberg

US1 IEA. Renovation of Wausau West High School, Wisconsin, United States of America

Duke Energy Corporation

Energy Modeling Applications for Existing Buildings

FACILITIES MANAGEMENT

Building Retro-Commissioning

Building Systems and Performance: an Introduction to Building Operator Certification Lesson 17: Maintaining for Performance and Energy Calculations

Sustainable Building Operations & Upgrades

Energy Management Journey

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions

Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619

FOUR YEARS OF ON-GOING COMMISSIONIONG IN CTEC-VARENNES BUILDING WITH A BEMS ASSISTED CX TOOL

Variable Frequency Drive Retrofit Opportunities. Michael Kuk CERx Solutions LLC

Guidance for Retro-Commissioning

Georgetown University New Science Center

Building X Retrocommissioning Final Report

Making the Business Case for Commissioning

PARK DISTRICT ENERGY WALK-THROUGH. Andy Robinson, Training and Education, SEDAC

FirstEnergy s Pennsylvania Utilities. Energy Efficiency Programs for Business

Retro-Commissioning for Energy Efficiency

OUR EXPERIENCE WITH RCX SOFTWARE: TRIUMPHS AND CHALLENGES

Energy Savings Audit

The owner is Oral Roberts University, while management and leasing is handled by Trinity Corporate Real Estate Advisors, LLC.

Achieving High Satisfaction in High Performance Buildings

City of Fort Collins Building Automation Systems Enhances Savings and Commissioning Efficiency Works Training

CxA Gap Session. April 25, :00 p.m. 4:30 p.m. Instructors: Derek De Jesús, CxA, LEED AP Darren Draper, PE, CxA, LEED AP

Wakulla Chamber of Commerce July Place your cover photo here. Size and crop it to 4 high x 9.6 wide. Presented by Derick Farfan

Energy Reduction Strategy Through 2020

Ron Wilkinson October 12, 2016

CHAPTER/REGIONAL TECHNOLOGY AWARD - SHORT FORM

is consciousness and action

NEBBinar: Retro-Commissioning for Comfort and Energy Efficiency. August 21, 2013

Practical M&V for Recommissioning Projects

Xavier Energy Initiative

Introduction. Agenda. New and Existing Facilities. Cx Programs & Terminology. Building Commissioning. Commissioning. D.

Abstract Submission. Key Points: Financial incentives, energy efficiency, best practices

Pepco & Delmarva Power. Commercial & Industrial Energy Savings Program Hotels and Restaurants October 18, 2012

Improving the efficiency, occupant comfort, and financial well-being of campus buildings

Back to Basics Energy Reduction Activity & Employee Engagement. Mark Anderson Maintenance Manager Engineering Division Ricoh UK Products Ltd.

Continuous Commissioning Leading Energy Project Process - An Industry Approach

LIBRARY ENERGY WALK- THROUGH. Andy Robinson, Training and Education, SEDAC

LEEDv4: What s New? February 18, 2016

SLO GB Alliance. Title 24 Non Res Certification Process. Wed, Oct 1, Rick Miller, PE, LC, LEED AP, CLCATT President, RNM Engineering, Inc.

Steve Harrell, LEED AP, CEM, CxA SSRCx Dr. David Claridge, P.E. Energy Systems Lab, Texas A&M University

University of Southern California Main Campus Plant Energy use reduction of 49% compared to previous plants and control strategies.

Commissioning: The Most Important Component of LEED. Rick Miller, PE, LEED AP. RNM Engineering, Inc. San Luis Obispo, CA

Best Practices in Commissioning Existing Buildings Building Commissioning Association

Existing Building Upgrades

Technical Report Three

Bridging the Gap. Between Design and Operating Performance. Jesse Sycuro, PE, CEM May 2014

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc.

Commissioning at NYP. Joseph Lorino, PE, LEED Corporate Director April 1, 2014

Transcription:

1 ACHIEVE MULTI-BENEFITS USING THE COMMISSIONING PROCESS FOR RETRO- COMMISSIONING OF BUILDINGS CLIMA 2005 Lausanne, Switzerland Paper Dorga274s

Authors Chad B. Dorgan, PE, PhD, CxAP, CCP Director, Facilities Science & Technology Farnsworth Group, Inc. Corona, California Charles E. Dorgan, PE, PhD, CxAP University of Wisconsin Madison 2 2

Owners and Others are Evaluating Existing Building Objective is to reduce energy cost, identify maintenance and repair needs, sometimes fire/life safety, or to determine potential for rehab. Why not use the same quality evaluation approach used for new buildings? 3 3

Owners and Others are Evaluating Existing Building The commissioning process: Identifies energy opportunities, use change or upgrade opportunities, maintenance and other needs of the building. Provides information on all economic benefits. Plus it has maximum input from all stakeholders at a low cost. Plus it leaves the same quality documentation in the form of an effective systems manual. 4 4

Using Guideline 0-2005 Broadens the scope and benefits of retrocommissioning Allows formal format for all projects Usually identifies more energy and maintenance opportunities than traditional approaches of (retro-commissioning) Provides engineering, operations, and maintenance information in a usable Systems Manual 5 5

Key Differences Does not assume the original design intent and basis of design was correct for the current usage of the building or facility Uses a Team vs. an Expert Allows the use of many quality tools for identification and optimization 6 6

Table 1 This is the comparison of using the commissioning process steps in Guideline 0-2005 as an approach for improving existing buildings and facilities. This is typically referred to as retrocommissioning in US 7 7

Table 1 However, traditional retro-commissioning was energy cost reduction orientated, without looking at the functional use of the facility A discussion of the comparison of the two retro-commissioning approaches is not included in this paper 8 8

ase The Commissioning Process Retro-Commissioning e-design esign Develop the OPR, CxPlan with CxP team lead by the CxA and develop the programming document. Verifies that the design meets the OPR and assist with developing construction phase requirements in the documents that will allow effective commissioning process activities in the construction phase, turnover, and during occupancy Finalize Design Develop facility needs, potential changes, and energy/iaq/eom opportunities with a team, lead by the CxA. The retro-commissionin plan includes OPR for the facility. Develop data to determine the benefit of changes, including maintenance, repair, tuning, and modifications to the building assem or systems. During this phase many opportunities will be identified can be immediately implemented without budgeting or expending a funds. Develop the retro-commissioning implementation document onstruction Construct the building or facilities Implement the retro-commissioning document requirements (this m be done over a number of years, as some items may require capital budgeting that have a long term payback or low, but effective productivity benefits to the users) rnover ccupancy Commissioning activities to verify that all construction is complete and functional tests are performed with results satisfactory to meet the OPR Develop procedures to continuously maintain and operate at the level of current and future needs. First year specific tasks will be verified by the CxTeam, including lessons learned and what is required for the on-going commissioning of the building s assemblies and systems for the life of the building A verification and acceptance procedures are developed, using statistical sampling for all retro-commissioning items or opportuniti from owner s staff tuning to construction projects. Construction projects may use the commissioning process, with some streamlinin especially where the retro-commissioning is done through a performance contract Implement procedures to assure the benefits of the retrocommissioning process are continuously maintained. Do a lessons learned workshop and report to assist with improving all other retro commissioning projects. Since retro-commissioning implementation may be achieved through several delivery means (owner, service contract, contract, or performance contract) there will be several separate construction and occupancy phase RCxP documents and plans. 9 9

The Commissioning Process It is not startup commissioning It is an owner s quality process for evaluating existing buildings and verify needs are achieved. 1010

The Commissioning Process It is a formal approach to delivering quality buildings at a reduced cost and improved users satisfaction It uses a team and provides benefits to all stakeholders: owner, architects, engineers, contractors, vendors, service, operations. 1111

Case Studies Executive Office AHU Identified Opportunities 3-way to 2-way valve control Disable the duty cycling Benefits Energy Operations and Maintenance Productivity 1212

1313

AHU Typical 40 year old AHU Operations modified by a number of different O&M staff 1414

Benefits of Disabling Duty Energy Duty Cycling: Cycling (1000L/s*870Pa t.p.)/(1.023* 10 6 *0.85 fan eff.)* 0.5 operating ratio = 0.5 kw/1000 L/s (0.236kW/1000 cfm) Continuous Run, at 50% of airflow: 0.5 kw/1000 L/s * 2 (double operating time) * 0.25 average power ratio reduction = 0.25kW/1000 L/s (0.12kW/1000cfm) 1515

Energy Savings Do to existing turndown of thermostats, it is estimated the net savings are: 0.6kW/3840L/s (0.6kW/8200cfm) Operating Hours per Year: 3000 Net Saving:0.6kW*3000*0.12 ~ $200 1616

Productivity Savings Operations and Maintenance Reduced service calls (comfort complaints) 60 or more per year 60 calls/year * 65/call = $3,900/year 1717

Productivity Benefits Based upon informal feedback, it appears that the temperature discomfort was a daily occurrence and lead to daily stop work discussions or even leaving the office for extra breaks There is also some direct lost related to distraction at the work station or desk There may have been some lost of customers, as this was an executive office for the organization 1818

Productivity Benefit A conservative estimate is that 5% productivity loss was related to the selected Duty Cycling control strategy At least everyone is more satisfied, and few complaint calls, and usually related to other issues 40 Associates*$1,600/year = $64,000/year 1919

Summary Energy Benefit = Operations Benefit = Office Productivity = $ 200/year $ 3,900/year $64,000/year Even if Productivity is only 1%, it is still the major benefit, and it is often 10-15%, large dollars. 2020

Conclusion Using the team and proven methods of the commissioning process for doing retrocommissioning provides more benefits to the owner, and provides the documentation to make evaluations beyond just energy dollar savings. 2121

Questions Finished 2222

2323

Total Facility Energy Reduction Large Resort Hotel in California Estimated energy opportunities by traditional expert lead approach, was about 10%, based on experience at other similar hotels The retro-commissioning approach identified 27% energy reduction opportunities 2424

Total Facility Energy Reduction Large Resort Hotel in California Plus, it identified operation and maintenance opportunities In addition, it lead to well trained staff that could perform a large majority of the energy conservation (cost saving) opportunities (ECOs) 2525

Total Facility Energy Reduction Large Resort Hotel in California It concentrated on documentation that required revision and organization Discovered that one BAS was no longer supported by the manufacturer and would not be able to be reprogrammed to meet some energy opportunities, until it was upgraded or replaced 2626

Lighting Watts Reduction Dimming Reduced Time On Daylighting (really watts reduction) Reduced maintenance and cost of lamps 2727

m Description Deman d kw Usage kwh Maintenance Annual Energy Cost Reducti on Cost to implement SPB andescent ghts 126 incandescent lamps installed, of which 366 are nondimming and should be replaced with compact fluorescent fixtures, saving 48 watts per lamp 36kW 52,980 Reduced annual reduction, related to long life of lamps, not included in initial cost benefits. Can be as much as energy cost savings, especially with group replacement $5,828 $3,276 0.56 2828

Vacuum Cleaning Improved IAQ Use best HEPA filter vacuum Vacuum most areas weekly, high traffic daily Vacuum walls once a month (tricky) Save energy, labor, and improve IAQ 2929

Savings from Vacuum Program Approximately 50% of current Janitorial cost, which results in $0.23/sf/year or $23,000 per 100,000 sf 3030

Why Should New Buildings (1-3 yrs) Be Recommissioned? 3131

Other Opportunities 3232

Develop Project Intent/Project Requirements First step is to determine the facility needs BR (building requirements) OFR (owner s facility requirements) This leads to developing the retrocommissioning project intent or project requirements. 3333

Develop Retro-Cx Project Intent This has not usually been documented for the existing building, however there may be a programming document that is of some use Our goal is to details current requirements of building systems and maybe some building assemblies (example windows and roofs) Need to make sure the PI Workshop or Process does not focus on existing problems Must focus on building or facility needs 3434

Project Intent Workshop Questions What are functional needs of this building List conditions important to your comfort in an ideal building. What activities generate pollutants in this building (school and community)? What functions must the heating and air conditioning system perform? What problems with heating and air conditioning systems have you experienced in other school buildings that you would like to avoid? 3535

Project Intent Workshop Questions If you become uncomfortable in the building, what do you do to solve the problem? List your top five concerns/criteria from the entire discussion today. What is required for a maintainable system? What efficiency/quality benchmarks must the system meet? What must your manuals provide/accomplish? 3636

Project Intent Workshop Questions If energy conservation is a key or primary reason for the retro-cx What are operation and maintenance level energy opportunities What are low cost energy opportunities (simple payback in 2 yrs) What are capital level opportunities How does this building waste energy? 3737

Case Studies Thermal energy storage (TES) system Medical facility 3838

Why Commissioning Initiated TES was installed with the last addition to the studio However, energy cost were much higher than projected 3939

TES System Layout 4040

Verification Test 4141

TES System - Opportunities Identified TES differential temperature increase Install VSD on secondary pumps and control valves on air handling units $20,400/year savings at a cost of $17,500 Control system adjustments Adjust set points and control outdoor air $2,400/yr. savings with in-house labor 4242

TES System - Opportunities Identified TES tank piping insulation/repair Insulate branch piping to tank Install larger band clamps on branch piping $800/year savings at a cost of $500 Overall system improvements Modify operating sequence Add discriminator control (minimize reheat) $10,050/year savings at a cost of $14,600 4343

TES System - Results of Recommissioning Increased storage capacity by approximately 40% Reduction in energy use by approximately 20% (reheat) Verified operation of system through field test Developed useful Systems Manual 4444

Other Benefits Staff re-trained and given systems manual to operate all systems Implement control sequence to quickly cool large studio, plus increased cooling capacity with 47 F supply air to this studio Eliminated an additional chiller that was part of a new studio addition under construction Satisfied a demanding producer, who did bring in a large revenue source to the studio. 4545

Medical Center - Background New medical center with out-patient surgery and offices Construction completion was two years after design was finished All new people hired to operate facility 60% occupied after two years Building was recommissioned at two year point 4646

Initial Purpose that lead to Cx High steam usage was the problem identified by the hospital However, we convinced them to use the retro-commissioning process 4747

Medical Center - Layout AD&T = Ambulatory Diagnostic and Treatment MOB = Medical Office Building 4848

Medical Center - Opportunities Identified Modify steam system to match usage (5.7 year payback) Modify AHU control (1.4 year payback) Install active pressure control on surgery suites Install easy to read temperature in surgery Modify lobby airflow pattern Implement commissioning procedures on tenant fit-out 4949

Medical Center - Opportunities Identified Install computer interface with existing Trane Tracer system Modify hot water freeze protection procedures Implement smoking area policy/system 5050

Medical Center - Results of Recommissioning Most opportunities improved the space conditions and were not energy related Provided system documentation which was previously unavailable 5151

Results If only energy issues addressed, then many facility issues would not be achieved and we would not be developing the systems manual for effective operations and maintenance of the facility For the TES case we would have only fixed the TES, which did not need fixing For the Hospital we would have only concluded that the steam use required a new smaller steam boiler 5252

Energy Retro-Cx Examples mall building: 100,000 s.f. office or school, 270kW demand Cost for Retro-Commissioning (which includes verifying energy opportunities are being operated and maintained as required and provide continuous assistance to the operational staff or service contractor during the first year after implementation): $ 4.1K Expected Savings for O&M and less than 3-year Simple Payback: $ 119K Annual Electrical Energy Cost Reduction: $ 52K Annual Gas Energy Cost Reduction: $ 10K Demand Reduction: 38 kw 5353

Energy Retro-Cx Examples Medium Size Hotel: 300,000 s.f., 760 kw Demand Cost for Retro-Commissioning (which includes verifying and assistance to the operational staff or service contractor during the first year after implementation): $ 28.7 K Estimated cost to implement Savings for O&M and less than 5-year Simple Payback: $ 399 K Annual Electrical Energy Cost Reduction: $ 142 K Demand Reduction: 228 kw 5454