BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

Similar documents
(Draft Captive and Renewable Energy Generating Plants) Regulations

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION

Uttar Pradesh Electricity Regulatory Commission. No. UPERC/Secy/Regulation/ Dated: 23 March, 2006

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION, LUCKNOW. Petition no.493/07. IN THE MATTER OF: Tariff for supply of electricity and payment of bills.

Uttar Pradesh Electricity Regulatory Commission

Chhattisgarh State Electricity Regulatory Commission

Jammu and Kashmir State Electricity Regulatory Commission

Bihar Electricity Regulatory Commission Vidyut Bhawan-II, J.L. Nehru Marg, Patna

Petition No of 2017 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW

Case No. 35 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member Smt. Chandra Iyengar, Member

NEW DELHI. Coram: Chairperson Shri S. Date of. Order: read with Regulations 14

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR ***** NOTIFICATION Dated the 30 th September, 2010

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

CASE No. 328 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member

Government of Gujarat Energy and Petrochemicals Department G.R. No.EDA B Sachivalaya, Gandhinagar. Dated the 25 July, 2013.

MADHU SHARMA University of Petroleum and Energy Studies, Dehradun, India

COMMERCIAL CIRCULAR NO.: 194.

Welcome to Presentation on Integration of RES to the WR grid. 02 nd Sept, 2015 Taj Lands End, Mumbai

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR-34 A, CHANDIGARH

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR *********

November Explanatory memorandum for CERC Regulations for implementation of REC mechanism in India

Published byauthority EXTRAORDINARY ISSUE TRIPURA ELECTRICITY REGULATORY COMMISSION NOTIFICATION OF

Comm/CP/NCE/Tariff/28362 Date: COMMERCIAL CIRCULAR No. 228

PROCEDURE FOR GRANT OF DISTRIBUTION OPEN ACCESS PERMISSION AS PER MERC (DISTRIBUTION OPEN ACCESS) REGULATIONS, 2014

APPLICATION FOR GRANT OF LONG-TERM OPEN ACCESS (to be submitted by the customer to STU)

Transmission Policy and Wind Energy

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION

PUBLISHED IN THE KOLKATA GAZETTE, EXTRA ORDINARY, PT.I DATED AUGUST 10, 2010 VIDE NO. WB (Part-I)/2010/SAR-460

No. EZ/Comml/PP&R/726 Jabalpur, Dtd. 02/08/2011

Petition No 730 of 2011 BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Date of Order :

Gujarat Electricity Regulatory Commission

Approach Paper on Methodology for computation of Cross-Subsidy Surcharge for Open Access transactions

State wise analysis of RPO Regulation for Captive users

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION LUCKNOW. Date of Order :

Impact of Renewable Energy Certificate (REC) Mechanism in India

GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No 1 Order Energy Deptt. letter no. F.

COMPENDIUM REGULATIONS & TARIFF ORDERS ISSUED BY REGULATORY COMMISSIONS FOR RENEWABLE ENERGY SOURCES IN INDIA

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR *********

Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Procurement Process) Regulations, 2004, Revision 1, 2006 (RG-19(I) of 2006)

BEFORE THE ORISSA ELECTRICITY REGULATORY COMMISSION BHUBANESWAR

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR *****

TAMIL NADU ELECTRICITY REGULATORY COMMISSION Comprehensive Tariff Order for Bagasse

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

No. CEjPPjNCEj RE Tariff jCommentsj18224 Date:

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO NO , SECTOR 34-A, CHANDIGARH

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

RE Tariff Setting Approach

Case No. 308 of Coram. Anand B. Kulkarni, Chairperson I.M. Bohari, Member Mukesh Khullar, Member

PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO No , SECTOR 34-A, CHANDIGARH

Case No. 81 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member

Case No. 111 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member ORDER

MPERC (Power Purchase and Procurement Regulations), 2004

Discussion Paper. Development of Renewable Energy Framework for Maharashtra For New Control Period (FY to FY )

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR

CENTRAL ELECTRICITY REGULATORY COMMISSION

SMP-36/2013 M.P. Electricity Regulatory Commission Bhopal

CASE No. 39 of Shri P. Subrahmanyam, Chairman Shri Jayant Deo, Member Dr Pramod Deo, Member O R D E R

CE/Comm/CP/NCE/Tariff/6699 Date: COMMERCIAL CIRCULAR No. 260

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Order No.4 of 2015 dated

ABC of ABT - AVAILABILITY TARIFF

NEW POLICY FOR POWER GENERATION FROM NON-CONVENTIONAL SOURCES OF ENERGY -2008

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

Case No. 61/2015. WESCO Utility Petitioner. - Vrs. DoE, GoO & others Respondents AND Case No. 62/2015

Haryana Solar Power Policy, 2016

Comprehensive Tariff Order on WIND ENERGY

Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

BEFORE THE NATIONAL GREEN TRIBUNAL CENTRAL ZONAL BENCH BHOPAL

CENTRAL ELECTRICITY REGULATORY COMMISSION. New Delhi In exercise of powers conferred under Section 178 of the Electricity Act,

BEFORE THE ORISSA ELECTRICITY REGULATORY COMMISSION BHUBANESWAR

TANGEDCO (ACCOUNTS BRANCH)

BEFORE THE GUJARAT ELECTRICITY REGULATORY COMMISSION GANDHINAGAR

Case No. 52 of Shri. V.P. Raja, Chairman Shri. Vijay L. Sonavane, Member CLARIFICATORY ORDER

Delhi Electricity Regulatory Commission Viniyamak Bhawan, C Block, Shivalik, Malviya Nagar, New Delhi 17.

CASE No. 120 of And. Miscellaneous Application No. 16 of 2016

ORDER WEST BENGAL ELECTRICITY REGULATORY COMMISSION IN THE MATTER OF

Case No. 89 of Shri V.P. Raja, Chairman Shri Vijay L. Sonavane, Member

ASSAM ELECTRICITY REGULATORY COMMISSION

The Energy Solutions Company OPEN ACCESS

CASE Nos. 8/9/10/15/17/18/19/20/21 of In the matter of Purchase of power from Bagasse based Co-generation Projects, etc.

RENEWABLE ENERGIES REGULATION & INCENTIVES THE CASE OF MEXICO

UP Electricity Regulatory Commission Kisan Mandi Bhawan, 2 nd Floor, Gomti Nagar, Lucknow

CASE No. 110 of In the matter of

Section 86(1)(e): Specify Renewable Purchase Obligation. (RPO), grid connectivity. Section 61(h): Tariff regulations to be guided by promotion

Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

Staff Paper Determination/Fixation of generic levellised generation tariff for various Renewable Energy Technologies / Projects for the year

UTTARAKHAND STATE GOVT. POLICY FOR HARNESSING RENEWABLE ENERGY SOURCES

Frequency Stability Voltage Stability Transmission congestion Angular Stability

Solar Power Policy Uttar Pradesh 2013

GOVERNMENT OF ANDHRA PRADESH ABSTRACT

SPP at a Glance. Located in Little Rock. Approximately 600 employees

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

EXPLANATORY NOTES FOR DRAFT GUIDELINES FOR OPERATION OF MERIT ORDER DESPATCH

ORDER. (Date of Hearing: 1 st October, 2013) (Date of Order : 8 th October, 2013) M.P. Power Transmission Co. Ltd., Jabalpur - Petitioner.

PRAYAS Initiatives in Health, Energy, Learning and Parenthood

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Comprehensive Tariff Order for Biomass based Power Plants

National Power Summit Hyderabad. 9 th February 2018

GOVERNMENT OF INDIA CENTRAL ELECTRICITY AUTHORITY (MINISTRY OF POWER)

Relevant changes will be made to corresponding sections of OA and RAA.

Transcription:

BEFORE THE UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Quorum Shri Desh Deepak Verma, Chairman Smt. Meenakshi Singh, Member Shri I. B. Pandey, Member In the matter of: Petition no. 1013/2015 u/s 33 (4) read with section 86 (1) (e), 61 (1) (a), (h) & (i) of the Electricity Act, 2003 and Rule 156 and 160 of UPERC Conduct of Business Regulations, 2004, provisions of power purchase agreement and other enabling provision of the Act and Regulations. Petitioner Secretary, Uttar Pradesh Sugar Mills Cogen Association, 4 th Floor, Room No. 403, Chintels House Trade Center, 16, Station Road, Lucknow-226001. Respondents Versus 1. Chief Engineer (PSO) State Load Despatch Centre, U.P. Power Transmission Corporation Ltd., Shakti Bhawan, 14, Ashok Marg, Lucknow 2. Managing Director, U. P. Power Corporation Ltd. Shakti Bhawan, 14 Ashok Marg, Lucknow-226001 Order (Hearing held on 4.6.2015) The Uttar Pradesh Sugar Mills Cogen Association filed the present petition on 23.3.2015 against the SLDC order / notice dated 18.3.2015. SLDC by order / notice dated 18.3.2015 informed the petitioner that there is crash in load on account of weather conditions and several generating units have already been shut down. Further on instructions of buyer (UPPCL/DISCOM), SLDC has directed that the co-generators of generating capacity 10 MW and above should minimize their generation by limiting it to their own process use only upto 15.4.2015. In the said order SLDC has further elaborated that due to crash in load several generating units have already been shut down to match the load generation balance

and to ensure safe and secure grid operation. The above order dated 18.3.2015 addressed to the Cogen Plants has not been actually served to the Cogen Plants and the concerned Executive Engineer has been directed to communicate the said order to all Cogen Plants as per the list attached thereof. The concerned Executive Engineer so far has not conveyed the above order dated 18.3.2015 to the Cogen Plants. During the hearing on 30.3.2015, the petitioner submitted the following: 1. It is the gross violation of the provision of the Electricity Act 2003. 2. It is against the PPA as the para 17 of the PPA. 3. Electricity Act, 2003 has accorded special preferences to co-generation plants on renewable fuel under section 86 (1) (e), 61 (1) (a), (h) & (i) of the Electricity Act, 2003. 4. Gujrat ERC in its order no. 4 of 2010 did not put such Bagasse Based Cogenerating unit under merit order dispatch but suggested that SLDC is Supreme Authority for secure operation of the State Power System. During the hearing on 10.4.2015, Shri Rahul Srivastava, Advocate appearing on behalf of SLDC, submitted that the order revoking earlier order dated 18.3.2015 has been issued vide letter no. 615 dated 24.3.2015 and further submitted that during the intervening period between 18.3.2015 to 24.3.2015 the petitioner member has continued to supply electricity to respondent no. 2. SLDC sought some time to file reasons for issuing and withdrawing of order. The Commission in its order dated 2.6.2015 had directed SLDC to file its response within ten days with a copy to the petitioner and petitioner to file rejoinder within next seven days. During the hearing on 4.6.2015 Smt. Sangeeta Saxena, Executive Engineer, appearing on behalf of SLDC submitted that letter dated 18.3.2015 was issued on grounds of weather condition and sudden crash of demand and instructions from buyers and on improving the weather conditions the order dated 18.3.2015 was revoked vide letter dated 24.3.2015.

The Commission enquired that why the letter was written to Co-generating plants only and weather it was solely on grounds of weather conditions or from the instructions from the buyers. The respondent replied that it was on the weather conditions as well as instructions from buyers. The respondent further clarified that the directions were issued to all State Generating Units, Central Generating Units, IPP and Members of the Petitioner Organizations. The respondent further submitted that as per Section 32 (2) (e) of the Electricity Act 2003. 32 (2) (e) be responsible for carrying out real time operations for grid control and dispatch of electricity within the State through secure and economic operation of the State grid in accordance with the Grid Standards and the State Grid Code. Section 33. (Compliance of directions): --- (1) The State Load Despatch Centre in a State may give such directions and exercise such supervision and control as may be required for ensuring the integrated grid operations and for achieving the maximum economy and efficiency in the operation of power system in that State. (2) Every licensee, generating company, generating station, sub-station and any other person connected with the operation of the power system shall comply with the directions issued by the State Load Depatch Centre under sub-section (1). (3) The State Load Despatch Centre shall comply with the directions of the Regional Load Despatch Centre. (4) If any dispute arises with reference to the quality of electricity or safe, secure and integrated operation of the State grid or in relation to any direction given under subsection (1), it shall be referred to the State Commission for decision: Provided that pending the decision of the State Commission, the directions of the State Load Despatch Centre shall be complied with by the licensee or generating company. (5) If any licensee, generating company or any other person fails to comply with the directions issued under sub-section(1), he shall be liable to a penalty not exceeding rupees five lacs. He further submitted from the perusal of the above Sections it is clear that for the safety and security of the grid SLDC may give any direction to any State entity and such entity is bound to follow the said direction. It is also pertinent to mention that State and Central Generating Units were issued such direction in the shape of day ahead schedule but as

the members of the petitioner are not subjected to scheduling and dispatch and real time of the generation of many co-generators is still not available in SLDC in spite of several requests by SLDC. So these directions were issued to the Members of the petitioner. SLDC further submitted that the Commission has never accorded the status of Must run plant to the Baggase Base Generation Plant. However generation from these plants is normally not rescheduled to abide by the policy of encouraging generation from Renewable/Non-Conventional energy sources. It is also pertinent to mention here that from perusal of the Dispatch principles for electricity generated from renewable energy sources it is clear that biomass power plants unit with installed capacity of 10 MW and above like petitioner and non-fossil fuel based cogeneration plants are not in the MUST RUN status. The Members of the petitioner are not only free from the merit order dispatch but also free to generate as per their convenience and not subjected for the scheduling and also exempted from Deviation Settlement Mechanism. Due to crash in load on account of the weather condition, there was a situation of under drawl and frequency of the grid was also very high, therefore for the grid safety and security, SLDC had issued direction to all State and Central generating units including members of the petitioner to minimize their generation. That it is also pertinent to mention here that CERC has not exempted Co-gen plants from Deviation Settlement Mechanism and only exempted solar generation units. In view of the above the petitioner submitted that UPERC while deciding review petition no. 282 of 2005 by order dated 15.9.2005 in paragraph 6.7 has categorically held that the Commission has already created a must run condition for bagasse based cogeneration. The paragraph 6.7 of the order dated 15.9.2005 in petition no. 282 of 2005 is reproduced below: ABT and Merit Order Despatch: The Petitioners have stated in the Petitions that ABT and Merit Order Dispatch should not be applied in their case as it would hamper their operations and shall be detrimental to promotion of generation from such nonconventional sources of energy. It is stated that the Commission has made exception to solar and wind projects only on the ground that such plants would not be able to comply with the requirement of scheduling and dispatch due to inherent characteristics. Sri. Prasad, on behalf of the Association submitted that the Petitioner be provided must run status to these plants. It is clarified that having specify a percentage of mandatory percentage of power from non-conventional and renewable energy source based plants, the 24 Commission has already created a must run condition for such generating plants and the merit order dispatch would not apply in such cases. The Commission in Para 8.3 and 8.4 of the approach paper have already dealt with this issue that 8.4 The plants generating from bagasse based generation and biomass shall be exempted from

UI mechanism but not from day ahead scheduling under ABT, with the exception that on operation actual generation shall be deemed as the actual schedule, in case of supply of full capacity to a distribution licensee of the area the the plant is located. However, in other cases, the provisions of ABT shall apply. For generation from industrial waste, municipal waste, biogas, solar energy, wind and hydro (micro/mini and canal fall hydro generating schemes upto total capacity below 25 MW) shall be exempt from UI mechanism but not from day ahead scheduling under ABT, with the exception that on operation actual generation shall be deemed as the actual schedule. 8.4 All these generating stations, except those which do not have connectivity, shall be subject to scheduling and unscheduled interchange, as the case may be, as per the availability based tariff order of the Central Electricity Regulatory Commission as made applicable in the State by an order of UPERC. The meter at such generating stations shall be special energy meter to be installed by State Transmission Utility for the purpose of accounting by State Load Despatch Centre, as the case may be, under ABT. Therefore, it is decided that such plants shall be subject to day ahead scheduling under intra-state ABT as and when implemented in the state but shall not be subject to payment of Unscheduled Interchange charges. The Commission clarifies that it has not provided must run status to the bagasse based co-generating plants, but has only provided a conducive environment for such generating plants for providing mandatory specified percentage of power from Non Conventional Renewable Energy Source Based Plants i.e. Renewable Purchase Obligation (RPO). The Commission while doing so has also exempted the renewable energy generator from the obligation of UI /deviation settlement mechanism. The Commission finds that as SLDC vide letter dated 24.3.2015 has already withdrawn its directions issued vide letter dated 18.3.2015 the present petition becomes infructuous. The petition is disposed off. (I. B. Pandey) (Meenakshi Singh) (Desh Deepak Verma) Member Member Chairman Dated: 6.7.2015