Long Point Water Treatment Plant Process Evaluation and Design Upgrades for Performance Enhancement; Dover, DE

Similar documents
AD26 Systems for Iron, Manganese, Sulfide and Arsenic Removal

CITY OF SUMNER: CENTRAL WELL DEVELOPMENT

Iron/Manganese Package Plant Pre-Engineered Ground Water Treatment. Village of Bolivar, NY

MWUA 92 nd Annual February Meeting & Trade Show

Innovative Improvements to a 53-Year Old Water Plant for HABs, Crypto, and Whatever Else the Maumee River Brings

Zero Liquid Discharge Project Extends Potable Water Supplies

Integrating Ozone and Ion Exchange into a 40 Year Old Lime Softening Plant

PIONEERING PELLET SOFTENING TREATMENT IN PENNSYLVANIA

PERMIT TO OPERATE SILVER CLOUD CT., MONTEREY, CA TELEPHONE (831) FAX (831)

Pittsburgh Water Treatment Plant Projects. by Jay R. Lucas, P.E. Senior Project Manager

Expanding Capacity and Treatment. Treatment Plant

WEFTEC.06. Lake Okeechobee, Actiflo, peroxone, surface water, Cyanobacteria

ENVIRONMENTAL ENGINEERING LECTURE 3: WATER TREATMENT MISS NOR AIDA YUSOFF

PNW AWWA Conference 2009 Todd Reynolds, PE, BCEE

Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation. J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc.

Side by Side Piloting of Process Alternatives Yields Direct Performance Comparison

biologically active filtration

SECTION 6.0 DESIGN CRITERIA, LAYOUTS, & HYDRAULICS

Amherst, MA, Drinking Water System

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

City of Enderby Water Treatment Plant

Seasonal Source Water Quality and Treatment Challenges Town of Newburgh s Chadwick Lake Filtration Plant

Water Treatment Plant Phase 1 Upgrades CMAR Selection Pre-Submittal Meeting

Submerged Membranes to Replace Media Filters to Increase Capacity 4X for a Small Community. Richard Stratton, PE HDR Engineering, Inc.

City of Davis Introduction of Surface Water. Community Meeting May 5, 2016

Meeting Manganese Removal Goals: A Pilot Study

Utility Partner Data Report

REAL WORLD APPLICATIONS OF USING DYNAMIC SIMULATION SOFTWARE TO OPTIMIZE WATER TREATMENT PLANT PROCESS OPERATIONS

Ohio Section AWWA NW District Fall Meeting April 20, City of Delaware Water Plant Improvements

Tiffin Water Treatment Plant. Comprehensive Facility Plan (Audit)

Providing Infrastructure Redundancy at the Rocky River WWTP. Timothy McCann AECOM Keith Bovard Rocky River WWTP

Trident. Package Water Treatment System

Process Treatment Selection and. Jeff Macomber, P.E. One Water Conference August 28, 2014

UNIT WELL 15 VOLATILE ORGANIC COMPOUND (VOC) MITIGATION

SMCSD Headworks, Primary and Secondary Treatment Pre-Design

WATER TECH 2009 BANFF, ALBERTA, CANADA

TABLE OF CONTENTS SCHEDULE 18 (TECHNICAL REQUIREMENTS) DBFO AGREEMENT SECTION 2 - WATER AND WASTEWATER SYSTEMS EXECUTION VERSION

Disinfection By-Products Reduction and SCADA Evaluation and WTP Sludge Removal System and Dewatering Facility

EVALUATING NANOFILTRATION, REVERSE OSMOSIS, AND ION EXCHANGE TO MEET CONSUMPTIVE USE CONSTRAINTS AND FINISHED WATER QUALITY GOALS FOR BROWARD COUNTY

Innovative Approach to Expanding the Olentangy WTP

Approved Capacity. March 2010

Reducing THM via Aeration: A Case Study August 28, 2014

WATER TREATMENT PLANT NO. 5 PRELIMINARY DESIGN REPORT FOR

Water Treatment and Conveyance System Salem Gammoh, Jordan Ministry of Water and Irrigation

Presentation Outline

FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY

techcommentary Issues for Ozone for Drinking Water Treatment Introduction Ozone in Drinking Water Treatment

Reverse-osmosis membranes were

MAKING THE SWITCH FROM LIME TO MEMBRANE SOFTENING: WHEN IS IT THE RIGHT TIME? Introduction

Chemical treatment of acid mine drainage. Anna Gulkova, Water and Environmental Engineering, Aalto University

Hybrid RO & Softening Birjand Water Treatment Plant

DRAFT July 26, Engineer s Report Water Softening Alternatives for Boyack Road Water Treatment Plant. Town of Clifton Park, New York

Water and Energy in Arizona

Ali Leeds, MWH Austin Peters, MWH

DRINKING WATER CONSTRUCTION PERMIT APPLICATON

Jungzhina Water Treatment Plant Thimpu, Bhutan

WATER AND WASTEWATER FACILITY CLASSIFICATION APPLICATION FORM

Semi-Passive Bioreactors and RCTS Lime Treatment of Acid Mine Drainage

HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE

CRITICAL CRITERIA FOR EVALUATING MEMBRANES FOR WATER SOFTENING

Sulfate Reducing Bioreactor for Sulfate, Metals and TDS Removal

Innovative Activated Iron Solids Treatment and Iron Oxide Recovery from Various High Flow AMD

Appendix D JWPCP Background and NDN

NELSONVILLE WATER TREATMENT PLANT IMPROVEMENTS

Renovation of the Filters at the Soldier Canyon Filter Plant in Fort Collins, Colorado

Water Treatment Plant Design at the Idaho Cobalt Project

SYSTEMATIC APPROACH TO WATER TREATMENT PLANT PROCESS OPTIMIZATION

DW Module 23: Organic Removal Answer Key

There is no sludge treatment process at NWTP. Sludge generated from sedimentation and backwashing is drained directly to the Khan River.

OXIDATIVE PRECIPITATION OF Fe AND Mn BY AIR/SO 2

THE BOSSIER CITY WATER TREATMENT PLANT (Background and Current Process Layout )

Physical and Chemical Processes for Advanced Wastewater Treatment

Eco-efficient Solids Separation Using Salsnes Filter Technology. Jonathan Leech Trojan Technologies Nov 2013

If there are uncertainties about the question, do not hesitate to ask the supervisor.

Government Center Water Treatment Plant Kamphaeng Phet Province, Thailand

Balancing Microbial Control and Stage 2 DBP Rule Compliance (at Ocean City, Maryland)

Matt Leach, P.E. CH2M. Mark Eppich, P.E. City of Columbus Division of Water. S. Dean Ramsey, P.E. CH2M

HARTFORD METROPOLITAN DISTRICT (MDC) WET WEATHER EXPANSION PROJECT PHASE 1 NEW 200 HEADWORKS FACILITIES

Evaluation of Powdered Activated Carbon Feed System For Taste and Odor Removal at City of Camden WTP. Jane Gan

Membrane Technology: From Manufacture to. May Production

Biological Treatment for Hexavalent Chromium at the City of Davis

MUNICIPALITY OF ROBLIN

Georgia Power Plant Bowen NPDES Permit No. GA Ash Pond Dewatering Plan. Revised December 2017

Ready, Set, and Go: Deer Valley WTP East Basins Performance Testing, Start-Up, and Commissioning Toby Teegerstrom Brian Watson

Comparing the Leopold Clari-DAF System to Upflow Contact Clarification

POST TREATMENT OPTIMIZATION FOR DESALINATION AND GROUNDWATER RECHAGE. Executive Summary

Drinking Water Supply and

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

WATER SUPPLY MASTER PLAN UPDATE TECHNICAL MEMORANDUM 2 WATER SYSTEM ASSETS TABLE OF CONTENTS

Introducing Desalinated Seawater into Existing Distribution Systems

CEE 371 Water and Wastewater Systems

At the Mercy of the Process Impacts of Nitrogen Removal Performance on WWTP Disinfection

Bioreactor Treatment of Ethers and Alcohols such as MTBE & TBA

Robert T. Shoaf, P.E., BCEE Presented by John Krinks, PE

DRINKING WATER WORKS PERMIT

Summary of Flint s Implementation of Veolia s Recommendations

WCW16 Annual Conference & Exhibition October Calgary AB wcw16.wcwwa.ca

A Flight Plan for Success: Practical Aspects of Pilot Testing in Planning, Design and Optimization

Comprehensive Approaches To Maintain Disinfection and THMs Compliance

This is the title of the proposed project. A CIP contract or project number will be assigned to the projects as funding is established.

Transcription:

Long Point Water Treatment Plant Process Evaluation and Design Upgrades for Performance Enhancement; Dover, DE Christopher Walker, PE Christopher Curran, PE Mark Prouty, PE May 12, 2016

Long Point Water Treatment Plant May 12, 2016

Presentation Outline The Story of a WTP Design Upgrade Background Initial Task WTP Capacity improvement - Ozone Original Evaluation and Approach Evaluation Findings Alternatives to Process Train and Recommendations Design Upgrades

Dover Water System - Snapshot Demand: ADD 5.11 MGD, MDD 9.28 MGD Water Supply: 14 deep groundwater wells Long Point WTP by surficial Columbia Aquifer

Future Water Needs Dual Turbine Energy Plant Phase1: 1600 gpm (2.304 MGD) Phase 2: 3200 gpm (4.608 MGD) Long Point WTP

Garrison Oak Technical Park - Energy Plant Construction progressing InfoWater water modeling Minimum Pressures ADD plus Phase 2 (3200 gpm) over 168 hours. Initial HGL 158.0 ft.

Long Point WTP Put into operation in the early 1990 s Six Supply Wells in unconfined Columbia Aquifer Original design rated capacity 5.0 MGD Ozone disinfection, ph adjustment, granular activated carbon, secondary sodium hypochlorite disinfection

Long Point WTP Process Flow Diagram

Long Point WTP Ozone Generators Ozone Contactors

Long Point WTP GAC Units Lime Silo

Long Point WTP GAC Units High Service Pumps

Long Point WTP Storm Water Drainage Lagoon Lime Silo

Long Point WTP Ozone Contactors Intermediate Wet Well Clearwell

Original Evaluation Approach WTP limited in production to less than original capacity Operations Performance Treatment Effectiveness Chemical Requirements Energy Expenditure

Ozone Contactors Pressing Concern: The contactors cannot provide the necessary contact time when more than 5 wells are operational. Excess ozone carried out to ozone destructors. Ozone generation is expensive with considerable ancillary equipment requirements: high pressure air blowers to feed air to the ozone generators, heat exchange equipment with pumps, and ozone destruction equipment to assure that no excess ozone is discharged to the environment. Research into necessity of use. Evaluate existing treatment methods.

Ozone Alterative 1 (of four) Alternative 1 relies on the continued use of the ozonation equipment but with a new injection system that would allow the existing contactors to operate efficiently. The injection system is known as a flash reactor. It takes a sidestream of raw water and pumps it through an injector nozzle (a venturi) where ozone is added. The water rejoins the raw water flow in the pipeline before the contactors. The point at which it rejoins the raw water is known as a pipeline flash reactor.

Ozone Alterative 1 (of four) SUBMERSIBLE WELL PUMPS OZONE CONTACTOR 1 OZONE CONTACTOR 2 OZONE CONTACTOR 3 BLOWER OZONE DESTRUCT OPEN LOOP PUMP FLASH REACTOR HEAT EXCHANGE CLOSED LOOP PUMP EXISTING RESERVOIR INJECTOR AT 1.75% O 3 1 100 HP SIDESTREAM PUMPS 2 NEW VFD NEW VFD CARBON UNIT CARBON UNIT NEW VFD CARBON UNIT CARBON UNIT CARBON UNIT EXISTING COMPRESSOR 1 AND 2 EXISTING OZONE GENERATORS 1 AND 2 NEW VFD EXISTING INTERMEDIATE PUMPS NEW VFD NEW VFD REPAIRED LIME SILO PLANT UTILITY WATER New Equipment Ozone POLYPHOSPHATE SYSTEM SODIUM HYPOCHLORITE TO DISTRIBUTION SYSTEM HIGH DUTY PUMPS DISINFECTANT CONTACT CHAMBER MIXING CHAMBER STATIC MIXER Unfiltered Water Filtered Water Alternative 1 - Existing O3 Generator and Sidestream Injector

Ozone Alterative 4 (of four) Additional O 3 Contactor SUBMERSIBLE WELL PUMPS New OZONE CONTACTOR OZONE CONTACTOR 1 OZONE CONTACTOR 2 OZONE CONTACTOR 3 BLOWER OZONE DESTRUCT OPEN LOOP PUMP CARBON UNIT CARBON UNIT CARBON UNIT CARBON UNIT CARBON UNIT HEAT EXCHANGE CLOSED LOOP PUMP EXISTING RESERVOIR NEW VFD NEW VFD NEW VFD EXISTING COMPRESSOR 1 AND 2 EXISTING OZONE GENERATORS 1 AND 2 NEW VFD EXISTING INTERMEDIATE PUMPS NEW VFD NEW VFD REPAIRED LIME SILO PLANT UTILITY WATER New Equipment Ozone POLYPHOSPHATE SYSTEM SODIUM HYPOCHLORITE TO DISTRIBUTION SYSTEM HIGH DUTY PUMPS DISINFECTANT CONTACT CHAMBER MIXING CHAMBER STATIC MIXER Unfiltered Water Filtered Water Alternative 4 - Existing O3 Generator and One Added Contactor

Water Quality Evaluation Long Point WTP - Dover, DE Dover Data AECOM Water Quality Analysis - January 2015 mg/l mg/l mg/l mg/l mg/l - CaCO 3 mg/l - CaCO 3 mg/l mg/l Source Fe ph Fe Mn Nitrate Alkalinity Hardness TDS Na + Well 1A 5.2 1.92 0.0543 2.4 4.0 87 221 32.6 Well 2 5.2 1.64 0.209 0.47 7.7 43.6 143 23.7 Well 4B 5.3 0.0334 0.0206 9.7 4.1 85.4 165 11.7 Well 5 5.7 0.0334 0.0738 3.8 13.2 65.6 122 10.3 Well 6A 5.5 0.0975 0.178 1.2 3.5 84.0 158 9.43 Well 8A 5.7 1.85 0.041 6.4 8.4 75.4 165 18.0 Wells Wells Average 5.43 0.93 0.0961 4.00 6.82 73.50 162.33 17.62 WTP Raw Water Influent Confluence 0.75 5.7 0.484 0.106 3.7 7.5 71.8 153 17.8 WTP Post Ozone Treatment 0.65 5.3 0.465 0.0986 3.7 5.3 71.9 147 17.3 WTP WTP Effluent 0.25 Long Point WTP - Dover, DE Division of Public Health Sanitary Survey Water Quality Analysis - November 2012 mg/l mg/l mg/l mg/l - CaCO 3 mg/l - CaCO 3 mg/l mg/l mg/l Source ph Fe Mn Nitrate Alkalinity Hardness TDS Na + Cl - Well 1A 5.02 2.34-2.7 8 34.5 198 28.5 51.9 Well 2A 4.86 1.09-1.0 8 15.9 174 26.3 31.9 Well 4B 5.74 0.0334-7.8 4 15.9 142 12.2 22.0 Well 5A 5.23 0.0334-3.9 12 26.4 172 10.3 18.3 Well 6A 5.20 0.11-1.4 6 36.8 154 9.5 16.1 Well 8A 5.12 2.14-6.1 10 25.1 174 17.4 30.7 Wells Wells Average 5.20 0.96-3.82 8.00 25.77 169.00 17.37 28.4

Residuals Generation Number Parameter Chemistry - Stoichiometry (at Equilibrium) x # of Wells On-Line 2083.3 Well Flowrate (gpm) E (V) 3.000 WTP Influent Flowrate (MGD) O 2 (g) + 4H + + 4e - 2H 2 O -1.06 0.484 Weighted Average Raw Water Iron Concentration (mg/l) 4(Fe 2+ + 3H 2 O Fe(OH) 3 (s) + 3H + + e - ) 1.23 0.106 Weighted Average Raw Water Manganese Concentration (mg/l) 4 Fe 2+ + 10H 2 O + O 2 (g) 4 Fe(OH) 3 (s) + 8H + 0.17 0.926 mg/l Fe(OH) 3 (s) Residual lb/hr Fe(OH) 3 (Atomic Weight) Fe (Atomic Weight) 23.2 Residual Mass Flow (lb/d - Fe(OH) 3 (s) ) 0.97 106,869 mg/mol 55,847 mg/mol 0.280 mg/l MnO 2 (s) Residual lb/hr 6.99 Residual Mass Flow (lb/d - MnO 2 (s) ) 0.29 E (V) lb/d 30.168 Mn 2+ + 2H 2 O MnO 2 (s) + 4H + + 2e - -1.21 1.206 mg/l Precipitates (s) lb/yr 11018.83 - MnO 4 + 4H + + 3e - MnO 2 (s) + 2H 2 O 1.68 lb/mg 10.0560 3Mn 2+ - + 2MnO 4 + 2H 2 O 5MnO 2 (s) + 4H + 0.47 MnO 2 (Atomic Weight) Mn (Atomic Weight) 86,937 mg/mol 54,938 mg/mol

Analysis of Existing Treatment Methods Current process treatment method not appropriate as treatment for iron and manganese removal is required.

Analysis and Alternatives for Overall Process Train Major Treatment Upgrades/Components Oxidation followed by Pressure Filtration Horizontal or Vertical Configuration ph Adjustment -> Upgrade Lime Silo and lime delivery to treatment Centrifuge/Sand Drying Beds/Sanitary Sewer for Residuals disposal Pumping Configuration - Intermediate Booster Pumps or improve well pump capacity and add VFDs

Pressure Filters Horizontal Configuration at Design Water Production Capacity is more cost effective For filter media only oxidant required will be chlorine (NaOCl) ph adjustment will be required pre-filtration.

Horizontal Pressure Filters

Horizontal Pressure Filters Communication and work the with The State of Delaware s Division of Public Health s Office of Engineering (Office of Drinking Water) to have approval for a hydraulic loading rate of greater than 7.0 gpm/ft 2

ph Adjustment Investigation included NaOH, CaO, air stripping and combinations of all. Lime Silo location is immediately adjacent to clearwell. ph adjustment occurs prior to entry into clearwell. This location is on the opposite side of water treatment facility from where the raw water enters into WTP Pneumatic lime delivery system to a day tank adjacent in rapid mix tank.

ph Adjustment Silo System Rehab. Pneumatically convey lime to the headworks of the WTP into a day hopper dispensing into a mix tank,

Residuals Disposal Sand drying beds will work very effectively and will operationally be much cheaper. All process water will be able to be recycled to headworks - Zero Discharge.

Process Flow Diagram for Upgrades Design on-going

Process Flow Diagram for Upgrades Design on-going

Thank You!

Questions? Christopher A. Walker, P.E. AECOM Sabre Building, Suite 300 4051 Ogletown Road Newark, DE 19713 302-781-5965 chris.a.walker@aecom.com