DIVISION 02 SELECTIVE DEMOLITION

Similar documents
B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner.

A. Section includes: removal of paving, pipes and utilities, and other site items as required by the project drawings.

1. Before selective demolition, Owner will remove the following items:

HOTEL SANDFORD. C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.

SAN DIEGO STATE UNIVERSITY PACIFIC CORNERSTONE ARCHITECTS TENOCHCA HALL PROJECT NO FAN COIL UNITS, RESTROOM AND FINISH RENOVATION

DIVISION 2- EXISTING CONDITIONS

Union County Vocational - Technical Schools Scotch Plains, New Jersey

SECTION SELECTIVE DEMOLITION

Richmond Hill Primary Renovation SECTION SELECTIVE DEMOLITION

BuildingName The Description of the Project P DOCUMENTS

C. Type of Selective Demolition Work: Demolition requires the selective removal and subsequent off-site disposal of:

A. The extent of Selective Demolition Work is that Work necessary, and required to facilitate the new construction indicated.

INTRODUCTION. A. Overview. A. Scope of Work. B. Additional Requirements

FILED: NEW YORK COUNTY CLERK 05/04/ :16 PM

SECTION A. Examination, preparation, and general installation procedures.

I hereby certify that Drawing Sheets F-100, F-101, M-001, M-100, M-101, M-200, M-400, M-

EXECUTION REQUIREMENTS

SECTION ALTERATION PROJECT PROCEDURES

B. Sections and all references contained therein form a part of this Section of the Specifications.

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

Ft. Clinch State Park 09/09

STATE COLLEGE OF FLORIDA Building 7 Finance Interior Upgrades BRADENTON CAMPUS SCF Project Number :

A. Section includes general administrative and procedural requirements governing execution of the Work including, but not limited to, the following:

Lantz-Boggio Architects, P.C LBA Project No

MEB AV TRAINING CENTER PROJECT MANUAL

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5

SECTION TEMPORARY FACILITIES AND CONTROLS

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 07 Thermal and Moisture Protection 8400 Firestopping

APPENDIX 1 PROJECT REQUIREMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION 23 DEMOLITION

ARTICLE 4: ASBESTOS CONTROL STANDARDS

MASTERSPEC TECHNICAL SPECIFICATIONS DIVISION 01 GENERAL REQUIREMENTS SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

INVITATION TO BID. Prospective bidders are encouraged to conduct a pre-bid site visit to aid in their bidding assessments.

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

WORK INSTRUCTIONS COLORADO SPRINGS NNO FACILITY EQUIPMENT SALVAGE PLAN VERIZON WIRELESS PROJECT MANAGER PATRICK SKILLEN PREPARED FOR:

Addendum #2 B14/9830. East Campus Student Life/Business Services/DSR Renovation

DSC BUILDING 1200 ALTERATIONS OCTOBER 2011 SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

ZAIDA RODRIGUEZ E.E.S. EXTERIOR SECURITY FENCES & GATES SFUSD PROJECT NO SAN FRANCISCO UNIFIED SCHOOL DISTRICT SECTION

Demolition Safety!!!!

Lot C Walkway and Bridge Repair Project #23829

St. Monica Food Pantry Construction Waste Management and Disposal SBA-13105

1. Division 01 Section General Requirements Temporary Facilities and Controls.

Form 9: Infection Control Preventive Measures Level 4

EM385 Construction Safety and Health Certification Course Section 23 Demolition

SECTION CUTTING AND PATCHING

DOCUMENT CONSTRUCTION WASTE MANAGEMENT

PRIVATE PLAN ROOM. Document Information Sheet

SAFEGUARDS DURING CONSTRUCTION

Bucknell University. Lewisburg, Pennsylvania HUNT HALL IMPROVEMENTS 2017 PROJECT LOCATION MAP CS-1 DRAWING TITLE: PROJECT:

SECTION CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL. A. This Section includes administrative and procedural requirements for the following:

MECHANICAL M-1 LEGEND AND DETAILS M-2 FLOOR PLAN - DUCTWORK M-3 FLOOR PLAN - PIPING

EPA s Lead Program Rule At-A-Glance

SPECIFICATIONS - DETAILED PROVISIONS Section Temporary Sewage Lift Station Demolition C O N T E N T S

Developed and Presented by: Wisconsin Healthcare Engineering Association

Window Replacement/Restoration. McCracken County Courthouse 300 South Seventh Street Paducah, Kentucky Architect s File No. 1603

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018

de-construction of Old City Hall

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

Schendt Engineering Corporation 2912 Beacon Street (719)

TRIAD ENGINEERING CONSULTANTS, INC.

SECTION GENERAL REQUIREMENTS

SCOPE OF WORK AND GENERAL INSTRUCTIONS

Attachment 3 Statement of Work Statement PROJECT NUMBER MA DIRECTORATE OF PUBLIC WORKS FORT BRAGG, NORTH CAROLINA

TYPICAL APARTMENT FLOOR PLAN

FIRESTOPPING & SMOKE SEALS

Read Health Canada s Tools for schools Action Kit s Introduction, Backgrounder and pages 14-3 to

CONTRACT AGREEMENT. This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the

~lamance <tount!' 9'~UUJ ;i)epwdment 124 We6t ElmStltm (j,taluun,.ncjjdli &vwfina 27253!Jefepfwae(336) :Jax(336)

SECTION CONSTRUCTION WASTE MANAGEMENT. 1. Section Sustainable Project Requirements. 2. Section Temporary Facilities and Controls.

WESTERN CONNECTICUT STATE UNIVERSITY ASBESTOS ABATEMENT PROCEDURE E-101

Asbestos Consulting Radon Measurements Lead Assessments Indoor Air Quality Testing Mold Investigations. Project Number: Page 1 of 22

Indoor Air Quality Management Plan for LEED

MITTERSILL WARMING HUT

HELEN C. WHITE COLLEGE LIBRARY RESTROOM RENOVATION UNIVERSITY OF WISCONSIN - MADISON UWSA Project No. A

SPECIFICATION DIVISION 7 NUMBER SECTION DESCRIPTION DIVISION 07 THERMAL AND MOISTURE PROTECTION SECTION THROUGH-PENETRATION FIRESTOP SYSTEMS

END OF SECTION SECTION FINAL CLEANING PART 1 - GENERAL 1.1 REQUIREMENTS INCLUDE

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

SECTION CONSTRUCTION FACILITIES AND TEMPORARY CONTROLS

LOWE S INSTALLER LRRP CHECKLIST FOR RENOVATIONS PERFORMED IN PRE-1978 HOUSING AND CHILD-OCCUPIED FACILITIES

ACADEMIC SUCCESS CENTER THE COLLEGE AT BROCKPORT STATE UNIVERSITY OF NEW YORK PROJECT NO

DIVISION 02 EXISTING CONDITIONS

A. IEMA ten day notification for demolition provisions as necessary. C. IEPA Uncontaminated Soil Certification LPC 663

TILE TILE

SECTION SPECIAL PROCEDURES. A. Section includes: Administrative and procedural requirements for special project procedures.

INFORMAL BID SPECIFICATIONS FOR LDS ISLAND PARK ANNEX FURNACE. Island Park, Idaho. December, 2013

SECTION PROJECT SUMMARY-PROJECT SCHEDULE

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

BID FORMS AND SPECIFICATIONS FOR THE DEMOLITION OF COMMERCIAL STRUCTURES IN THE 1700 BLOCK OF M STREET. CITY OF BELLEVILLE

A. Hazardous Areas: Hazardous areas as defined by the NEC as Class I, Division 1, Group D, or Class I, Division 2, Group D hazardous are as follows:

Certification Number: NAT Lead Renovation, Repair and Painting Program

STATE UNIVERSITY CONSTRUCTION FUND

New Jersey Home Inspection - Standards of Practice

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system.

The Hong Kong Polytechnic University Facilities Management Office

Rowan University Asbestos Management Program

6. ENGINEERING SYSTEMS REQUIREMENTS F20 SELECTIVE BUILDING DEMOLITION

Transcription:

DIVISION 02 SELECTIVE DEMOLITION

SECTION 02 41 19 - SELECTIVE DEMOLITION PART 1 - GENERAL 1.01 SUMMARY A. This Section includes the following: 1. Demolition and removal of selected portions of a building. 2. Demolition and removal of selected building elements. 3. Saw cutting/core drilling 4. Patching and repairs. B. Related Sections: The following also contain requirements that relate to this Section: 1.02 DEFINITIONS 1. Division 0 Specifications and Notes on the Contract Drawings also clarify use of the building and phasing requirements. 2. Division 23 Sections for cutting, patching, or relocating and replacing mechanical items and installing new equipment and installations. 3. Division 26 Sections for cutting, patching, or relocating and replacing electrical items and installing new equipment and installations. A. Remove: Remove and legally dispose of items except those indicated to be reinstalled, salvaged, or to remain the Owner s property. B. Existing to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. 1.03 MATERIALS OWNERSHIP A. Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain the Owner s property, demolished materials shall become the Contractor s property and shall be removed from the site with further disposition at the Contractor s option. 1.04 QUALITY ASSURANCE AND PROTECTION A. Regulatory Requirements: Comply with governing EPA notification regulations before starting selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction. B. Coordinate all hazardous material demolition with the Mississippi Division of Environmental Quality (MDEQ) with their mandatory prior notice requirement (minimum 10 days). OCTOBER 2017 SELECTIVE DEMOLITION 02 41 19 PAGE 1 OF 5

C. The Contractor shall provide for a safe and secure healthy working environment at all times per OSHA, local code and safe practice. Refer to the Hazardous Material Survey Report attached hereto. D. Temporary barrier, railing fencing, etc. shall be provided and a safely installed to limit access to unauthorized personnel to work areas, limit the spread of construction duct/debris to User occupied spaces, and security for construction trailers, equipment and supplies. E. Any Owner furniture, especially cloth materials, shall be substantially protected. Contractor shall cover all furniture and protect blinds, curtains, etc. in demolition and other areas where demolition occurs or where construction routes and/or dust may be interactive. 1.05 PROJECT CONDITIONS A. Owner shall occupy building continually during construction. B. Owner will occupy all buildings and grounds immediately adjacent to this building and some selective demolition areas. Conduct selective demolition so that Owner s operations will not be disrupted. Provide not less than 72 hours prior notice to Owner of activities that will affect Owner s operations, including traffic dust, noise, etc. C. Owner assumes no responsibility for actual condition of buildings or systems to be selectively demolished. D. Asbestos and Lead Based Paint: If any materials suspected of containing asbestos are encountered, do not disturb the materials. Immediately notify the Professional and the Owner. See Hazardous Material Survey Report attached hereto. E. Storage or sale of removed items or materials on-site will not be permitted. F. Removal, relocation of some of the furniture in construction areas shall be by Using Agency. The remainder of furniture, fixtures and built-ins shall be protected by the Contractor during all construction. All areas, furniture and fixtures left in the construction area shall be daily cleaned and thereafter comprehensively cleaned after construction is complete in each space or room, at the Contractor s expense. 1.06 SCHEDULING A. Arrange selective demolition schedule so as not to interfere with Owner s on-site operations. Significant nighttime, after hours, and weekend work should be expected. 1.07 WARRANTY A. Existing Special Warranty: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties and to provide a neat finish to match existing adjacent finishes and material. PART 2 - PRODUCTS 2.01 REPAIR MATERIALS OCTOBER 2017 SELECTIVE DEMOLITION 02 41 19 PAGE 2 OF 5

A. Use repair materials identical to existing materials. PART 3 - EXECUTION 3.01 EXAMINATION 1. Where identical materials are unavailable or cannot be used for exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible as approved by Professional A. Verify that utilities have been disconnected and capped, as appropriate, to safety protect occupants and the facilities. B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required. Minimally demolish to match the extent to adequately access for repair or replacement work necessary. C. When unanticipated mechanical, electrical, or structural elements that conflict with the intended function or design are encountered, investigate and measure the nature and extent of the conflict. Promptly submit a written report to the Professional and provide suggested remedial action and cost estimate(s). D. Survey the condition of the building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of the structure or adjacent structures during selective demolition. Contact the Professional immediately if an unsafe condition is noted. Protect people first and foremost. 3.02 UTILITY SERVICES A. Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations. 3.03 PREPARATION 1. Do not interrupt existing utilities serving occupied or operating facilities, except when authorized in writing by Owner and authorities having jurisdiction. Provide temporary services during interruptions to existing utilities, as acceptable to Owner and to governing authorities. a. Provide not less than seven (7) days written prior notice to Owner if shutdown of service is required during any changeover, replacement, repair, etc. b. Utility Requirements: Refer to Division 20, 22, 23 and 26 Sections for shutting off, disconnecting, removing, and sealing or capping utility services. Do not start selective demolition work until utility disconnecting and sealing have been completed and verified in writing. A. Conduct demolition operations to prevent injury to people and damage to adjacent buildings and facilities to remain. Ensure safe passage of unauthorized non construction personnel around selective demolition area(s). OCTOBER 2017 SELECTIVE DEMOLITION 02 41 19 PAGE 3 OF 5

1. Erect temporary protection, such as walks, fences railings, canopies, temporary construction barriers, and covered passageways, where required by authorities having jurisdiction. 2. Provide temporary weather protection, during interval between demolition and removal of existing construction, on exterior surfaces and new construction to ensure that no water leakage or damage occurs to structure or interior areas. 3.04 SELECTIVE DEMOLITION A. Demolish and remove existing construction only to the extent required by new construction and as indicated for renovation, etc. Use methods required to complete work within limitations of governing regulations, high quality of Standard of Care, and as follows: 1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition work above each floor or tier before disturbing supporting members on lower levels. 2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. To minimize disturbance of adjacent surfaces, use hand or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain. 3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces. 4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable firesuppression devices during flame-cutting operations. 5. Maintain adequate ventilation when using cutting torches, welding, brazing, soldering, etc. 6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site. 7. Remove structural framing members and lower to ground by methods suitable to avoid free fall and to prevent ground impact or dust generation. 8. Locate selective demolition equipment throughout the structure and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing. 9. Dispose of demolished items and materials promptly. On-site storage or sale of removed items is prohibited. 10. Return elements of construction and surfaces to remain to condition existing before start of selective demolition operations. OCTOBER 2017 SELECTIVE DEMOLITION 02 41 19 PAGE 4 OF 5

B. Demolish concrete and masonry in small sections. Cut concrete at junctures with construction to remain, using power-driven masonry saw or hand tools; do not use power-driven impact tools during Owner s normal building use periods. C. Break up and remove concrete slabs on grade, as shown. D. Remove resilient floor coverings and adhesive according to recommendations of the Resilient Floor Covering Institute s (RFCI) Recommended Work Practices for the Removal of Resilient Floor Coverings and Addendum. 1. Remove residual adhesive and prepare substrate for new floor coverings by one of the methods recommended by RFCI. E. Remove no more existing walls or roofing than can be promptly covered and interior areas protected. F. Remove air-conditioning equipment without releasing refrigerants. Recover all refrigerants and oils per governing codes. G. Provide temporary walls and seal air tight between construction areas and Owner occupied spaces. Construction barriers shall be provided where shown and as required, per Professional directive. 3.05 PATCHING AND REPAIRS A. Patching is specified in Division 1 and on Drawings 3.06 DISPOSAL OF DEMOLISHED MATERIALS A. General: Promptly dispose of demolished materials to an appropriate disposal site per local code requirements. Do not allow demolished materials to accumulate on-site or in building renovation areas. B. Burning: Do not burn demolished materials on-site. C. Promptly haul off debris and demolition and unused construction material and equipment. 3.07 CLEANING A. Sweep the building, equipment room and outdoor concrete spaces, broom clean and provide for a thorough comprehensive vacuuming and dust removal on completion of selective demolition operation, at minimum daily intervals and prior to next day Owner occupancy of premises. B. All areas affected by construction dust shall be thoroughly cleaned. All furniture, plumbing and light fixtures, wall, ceiling, and floor surfaces shall be cleaned. --END OF SECTION-- OCTOBER 2017 SELECTIVE DEMOLITION 02 41 19 PAGE 5 OF 5