DUBAI ELECTRICITY AND WATER AUTHORITY GUIDELINES FOR NEW DEVELOPMENT PROJECTS UPDATE

Similar documents
WATER SUPPLY SERVICES

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

SALEM CITY REQUEST FOR PROPOSAL CULINARY AND SECONDARY WATER MASTER PLAN 5/2/2018

ADVANCED WATER DISTRIBUTION MODELING AND MANAGEMENT

Hydraulic Modeling and System Optimization

Section 5 - Planning Criteria. Section 5

Guidelines for the Submission of Sub-Corridor Plans and Drawings required for Approval QGDL-CE-012

Table of Contents. 3.1 Source Capacity Analysis

This is only a general checklist; please refer to the CVWD Development Design Manual (DDM) for all requirements and regulations.

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

Damages and risks which are attributed to water leaks are summarized as follows:

WATER MAIN EXTENSION DESIGN REQUIREMENTS

Harvesting the Rain An Overview of the Rainwater Collection Systems at McKinney ISD

CITY OF SASKATOON DESIGN AND DEVELOPMENT STANDARDS MANUAL SECTION FOUR WATER DISTRIBUTION SYSTEM

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY GROUND STORAGE. Section GROUND STORAGE TANK (GST) MODIFICATIONS, CLEANING AND DISINFECTION

Storage and pumping capacity analysis using hydraulic modeling

ENGINEERING REPORT WATER SUPPLY

M A N Y A V U

Agua Consulting Inc. Engineered Water Solutions

GANSEVALLEI RETIREMENT ESTATE, PLETTENBERG BAY Engineering Services Report

Section V WATER DISTRIBUTION SYSTEM DESIGN GUIDELINES

Montara Water and Sanitary District 2011 New Customer CIP and Water Capacity Charge. Presentation to Board April 21, 2011

Galway County Council Portumna Draft Local Area Plan Strategic Flood Risk Assessment of Material Alterations

CHAPTER 6 SECTION 6.19 AN ORDINANCE OF THE TOWN OF MAYODAN TO PROTECT THE QUALITY OF THE PUBLIC POTABLE WATER SUPPLY

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:

T a b l e o f C o n t e n t s

Utilities are constantly striving to

SPRINGWOOD COMMUNITY & CULTURAL FACILITIES

SECTION 3.0 SPECIFICATIONS FOR DRINKING WATER DISTRIBUTION SYSTEMS DESIGN

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System

Project Case Study. Al Muneera Al Raha Beach Development. Project: Al Muneera Start Date: Industry: Residential. Value: US $ 141 Million

APPLICATION FOR COMPLYING DEVELOPMENT CERTIFICATE

San Francisco Water Power Sewer Service* of the San Francisco Public Utilities Commission

ScienceDirect. Numerical model of a district water distribution system in Bucharest. A.-M. Georgescu a, *, S. Perju a, S.-C. Georgescu b, A.

CHAPTER 8 WATER SUPPLY SYSTEM

SYSTEM ID: KY 10 NARRATIVE DESCRIPTION

Section 7 Hydraulic Model Development and Evaluation Criteria

SYSTEM ID: KY 3 NARRATIVE DESCRIPTION

Division II Contractors

REPAIR PERMIT FOR A SEPTIC SYSTEM PROCEDURE & CRITERIA

El Margarita Development Analysis

CHAPTER 4 MINIMUM DESIGN CRITERIA

Guidance for. LNG Fuel Ready Ships

Adoption of sewers. Application for the adoption of a sewer under Section 104 of the Water Industry Act Section 1A: Applicant s details

National Water Demand Management Policy

Talwandi Sabo Power Limited Tender document for Design & Engineering, Supply and Erection of Slurry pumping system from Plant to Ash Dyke

SUBURBAN COMMERCIAL ZONE - RULES

Table A Summary Water System Data Data

Bylaw A Bylaw to amend Bylaw 12800, as amended, The Edmonton Zoning Bylaw Amendment No. 2409

GENERAL INFORMATION AND REQUIREMENTS

Summary of Preparatory Study

UBC Technical Guidelines Section Edition Sanitary Sewerage Utilities Page 1 of 6

SCHEDULE 2 TO THE COMPREHENSIVE DEVELOPMENT ZONE THE SANDS TORQUAY RESIDENTIAL LAKES AND GOLF COURSE COMPREHENSIVE DEVELOPMENT PLAN

Project Case Study. Motor City DCP. Project: District Cooling Plant, Motor City Start Date: 2007 Completion Date: 2010

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

ScienceDirect. Network analysis of water distribution system in rural areas using EPANET

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

CHAPTER 4 Hydraulic Model Management and Documentation Protocols


THE INTEGRATED TRADE AND INDUSTRIAL HUB OF ABU DHABI

Guidelines for Design of Potable Water Distribution Facilities In New Developments

REQUEST FOR PROPOSAL Town of Lochbuie Water System Master Plan

THE INTEGRATED TRADE, LOGISTICS AND INDUSTRIAL HUB OF ABU DHABI

Examination paper, both A3 plain and A3 tracing, are provided. Use as appropriate.

B-2 COMMUNITY COMMERCIAL BUSINESS DISTRICT. Uses allowed in the B-2 Community Commercial Business District are subject to the following conditions:

APPENDIX 3A: TRAFFIC INTENSITY FACTORS

City of Richland Comprehensive Water System Plan

ARTICLE IV. ZONING DISTRICTS DIVISION 9. M-X MIXED USE DISTRICT. (2) Ensure sensitivity to the surrounding neighborhood;

SCHEDULE 4 TO CLAUSE THE SPECIAL USE ZONE. Shown on the planning scheme map as SUZ4. GOULBURN VALLEY HARNESS AND GREYHOUND RACING PRECINCT

A. Introduction 7 1. Purpose 7 2. Authority 7 3. Contact 8 4. Plan Submittal Process 8 B. Design Standards General 11 a. Future Extensions 11

Description of Water Systems

%&&2^ Harlan L. Kelly, Jr., General Manager

TOWN OF CARY FISCAL YEAR 2014 UTILITY RELATED CAPITAL FEES

DIVISION 2: BACKFLOW PREVENTION PROGRAM

Green Building Guideline of Jordan

TITLE 9. ENVIRONMENT STATE WATER CONTROL BOARD

130 CROSS CONNECTION CONTROL

The Next Generation Of Network Management And Leakage Detection Systems

CHILLED WATER DISTRIBUTION SYSTEM

ZEBRA MUSSEL PROJECT STATUS

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

I P E L I N E : M I D M A R I D M A R D A M T O M I D M A R

CHAPTER COMMERCIAL ZONES

2013 Water and Wastewater Master Plan for the Lake-Based Systems

Utility Investigation Analysis Report

SAWS WATER PROJECTS MODELING CRITERIA GUIDELINES

1. Required Minimum Flow:

All Outline Applications 462 per 0.1 ha for sites up to and including 2.5 ha 11, for each 0.1 in excess of 2.5 ha to a maximum of 125,000

Code of Practice for a Waterworks System Consisting Solely of a Water Distribution System

SECTION 8 WATER SUPPLY SYSTEMS

ALTERATION PERMIT FOR A SEPTIC SYSTEM PROCEDURE & CRITERIA

Before 1990, roughly 116 wastewater

RULES AND REGULATIONS FOR WATER AND WASTEWATER SERVICE APPENDIX G BACKFLOW PREVENTION AND CROSS CONNECTION CONTROL (BPCCC) PROGRAM

HARKERS ISLAND SANITARY DISTRICT AMENDMENT TO WATER SYSTEM MANAGEMENT PLAN

17.0 INFRASTRUCTURE AND ENERGY

1 April 8, 2015 Public Hearing

DESIGN GUIDELINES FOR MULTI FAMILY AND ATTACHED SINGLE FAMILY INFILL HOUSING

FAST TRACK RELIEF TO MIDLAND S EMERGENCY THIRST

Water supply components

DETAILED TERMS OF REFERENCE. 1.0 Terms Of Reference: I.1 The scope of services of a consultant shall include the following categories:

Transcription:

DUBAI ELECTRICITY AND WATER AUTHORITY GUIDELINES FOR NEW DEVELOPMENT PROJECTS UPDATE - 2010 POWER & WATER PLANNING (WATER TRANSMISSION PLANNING)

DUBAI ELECTRICITY AND WATER AUTHORITY WATER TRANSMISSION PLANNING GUIDELINES FOR NEW DEVELOPMENT PROJECTS CONTENTS AMENDMENT RECORD This Document has been issued and amended as follows: Issue Revision Description Date Signed 1 0 23/3/2008 Amany 1 1 Updated as pre DEWA New Organization 02/02/2009 Amany 1 2 Updated for year 2010 13/10/2009 Amany 2 1 Document is separated for guidelines of WTP only and updated for the year 2010. 22/2/2010 Amany

1 INTRODUCTION The purpose of this document is to provide guidelines to developers and consultants while submitting projects information for DEWA s Water transmission Planning Department review and approval. The guidelines are intended to help understanding DEWA requirements and facilitate the preparation of development projects Master Plans and other required documents. For each new development project, the developer or consultant shall submit to DEWA the estimated water demand planned for the project from its inception through to its completion and full occupancy. This information will be incorporated into DEWA s database for projected water demands. This database is used by DEWA engineers to plan the scope and probable timing of augmentations which will be required to the existing system. Depending on the scope, the additional facilities required will range from an extension of part of an existing distribution network, to a complete transmission and distribution network for a new zone, and to the construction of a new desalination plant that will augment available water resources. The following subsections provide brief descriptions of the several components of the DEWA water supply system, the lead times required for the commissioning of major facilities, demand categories and typical demand ranges, etc. The final page provides a list of the documents which should accompany a submission for review and study by the Water Transmission Planning Department This document may be updated or amended as deemed necessary. 2 WATER RESOURCES REQUIREMENTS Major development projects having considerably high water demands that are likely to trigger the requirement of planning for additional water resources (productions plants) should submitted their water demand requirements at least 5 years prior to the anticipated project completion date. (Lead-time for the construction/development of water production facilities is 5 years). 3 STORAGE RESEROIRS: (a) Storage for DEWA system DEWA policy is aiming to maintain water system potable water bulk storage equivalent to two days of system s peak demand; on this ground DEWA Water Planning Guidelines for New Developments Projects 1 of 9

developers of major projects may be requested to provide land for bulk storage within their project s area, as required and depending on project size. (b) Customers storages The local storage for individual premises should be able to cover average demand for at least 24 hours. Provision of adequate on-site water storage facilities should be considered by the developers. 4 PUMPING STATIONS Developers are required to provide existing and proposed site topography information, based on actual survey data, to facilitate hydraulic analysis and establish the need for booster pumping. Higher land within the water transmission system might require the installation of a new system booster pumping stations for which the standard planning and construction lead-time is 2-3 years before commissioning of system. Occasionally, developers and their consultants are requested to consider booster stations while designing for the project s water supply network in order to supply water to higher grounds where presence of relatively low pressures would result in inadequate supply within the development. 5 TRANSMISSION SYSTEM DEWA s water system consists of a transmission network where pipe diameters range vary from 550 mm to 1200 mm, and distribution network where pipe diameters range vary from 100 mm to 450 mm. The approved pipe materials currently used by DEWA for the water transmission network are: Fibre-cement (FC) pipe CLASS 18 /24 ( subject to DEWA s approval) Glass fibre Reinforced Epoxy (GRE) All fittings (including bends, tees, reducers and flanges) used with FC and GRE water pipelines shall be of GRE material complying with DEWA s specifications. Development of water transmission pipelines requires a lead-time of 3-4 years before completion (depending on the line length). Therefore, developers and their DEWA Water Planning Guidelines for New Developments Projects 2 of 9

consultants should submit projects design details including the internal network design well ahead of time for DEWA s review and approval. 6 DISTRIBUTION SYSTEMS The Distribution System is planned and developed in parallel with the project s development only within road right-of-ways for which the final designs are approved and levelled accordingly. Lead-time for water distribution network development is 2-3 years before commissioning depending on the length and complexity of the proposed network). Developers must submit their project s internal network design for DEWA s Projects and Engineering Department study and approval. Please refer PE(W) Developer s Guide Pipe materials currently adopted are either FC or GRE, subject to DEWA s approval. 7 SYSTEM MONITORING Depending on the nature and size of the project s network, developers may install monitoring devices at main connection locations as per DEWA s specifications. 7.1 Bulk Flow Metering Bulk flow meters are essential for measurement and flow monitoring along the transmission and distribution systems. Bulk flow meters shall be proposed at selected locations as per DEWA s specifications. 7.2 Pressure Transmitters Pressure gauges and transmitters may be required as per DEWA s specifications to monitor pressures at locations selected by DEWA. 7.3 Water Quality Controls Analyzer Stations consisting of transmitters and sensor assemblies for measuring ph, residual chlorine, conductivity and temperature shall be installed at specified locations as per DEWA s specifications. DEWA Water Planning Guidelines for New Developments Projects 3 of 9

7.4 Water SCADA requirements DEWA s requirements for integrating newly developed network for major projects into DEWA s SCADA system should be discussed and agreed by DEWA s Projects Dept. & Operation and Maintenance Dept. 8 SERVICE CONNECTIONS As per DEWA s policy, separate house connection pipes for each premise should be metered. In case of buildings, a main meter is installed on the main inlet pipe before the underground storage tank and sub-meters are installed on the roof of the building on the discharge side of the elevated storage tanks. Developers should provide house connections, proposed layouts and pipe materials proposed for DEWA s approval. 9 WATER DEMAND As demand and its phasing represent the most crucial element for the whole water transmission network planning process, developers are requested to keep the following list of information available for DEWA s review ahead of time in order to cater for different lead times needed for each type of development: 1. Reasonably Projected Demand Figures along with yearly phasing up to ultimate build-out, occupancy phasing until 100% is achieved and phasing wise percentage of land used. 2. Reasonable Demand Phasing throughout the project s development period. Each phase should be represented by expected occupancy commissioning dates and occupancy saturation date, rather than construction starting and completion dates. For Mega Projects, information for each phase should include similar information on the relevant individual projects and their demands. 3. There are six major demand categories recognized by DEWA Planning system: RESIDENTIAL COMMERCIAL GOVERNMENT & PUBLIC PREMISES INDUSTRIAL DEWA Water Planning Guidelines for New Developments Projects 4 of 9

LABOUR CAMPS DISTRICT COOLING water not provided by DEWA for new projects Developers should map their project demand types, as applicable, using the DEWA established demand categories. This is required to facilitate incorporating the same into the demand forecast process. 4. Base information and calculations used to determine the water demands, such as population, land use and district cooling demands, etc. 5. DEWA does not supply potable water for: a. Construction purposes (particularly if there is no existing developed network at the project area). b. Water features (lagoons, etc.). c. Irrigation / landscape purposes. d. District cooling water for new projects (in compliance with Executive Order No.27). 10 PEAKING FACTOR A peaking factor in the range of 1.2-1.5 should be used while designing for the network in order to accommodate the daily variation in demand. This factor varies depending on the nature of the development and derived by the demand categories adopted. 11 DEMAND REQUIREMENTS The following Table outlines typical ranges of water consumption rates, which may be used as a reference for calculating different land use demands for development projects. However, the consultant / developer should accurately calculate the demand required with due consideration to the nature of the development project. DEWA Water Planning Guidelines for New Developments Projects 5 of 9

DEWA s Reference for Demand Categories CATEGORY RESIDENTIAL BUILDINGS 250-400 COMMERCIAL BUILDINGS 60-100 VILLAS 250-400 LABOUR ACCOMMODATION / WORKERS 80-150 RESTAURANT (per meal) MOSQUES 10-60 HOTELS( per room including workers, visitors) 300-500 WORKSHOPS/ MACHINERY 60 SHOPS 60-80 OFFICES 60-80 SCHOOLS 60-80 PUBLIC AMENITIES 10-60 RETAIL 60-80 VISITORS 14-45 MIXED USED Commercial 60-80 MIXED USED Residential 250-400 ENTERTAINMENT & LEISURE S 60 THEATER 10-60 TOWN CENTER 60-80 MEDICAL (per bed) 60-80 HEADQUARTERS 60-80 UNIVERSITY 60-80 LABORATORY 60-80 MANUFACTURING 60-80 BASED METAL CHEMICAL ZONE 100 LOGISTIC, ACADEMIC & BUSINESS ZONE 60-80 MINERALS 80 NURSERY 60-80 LOCAL PLAZA 60-82 OTHER 60-82 EVENTS 10-60 GUARDHOUSE 60-80 CLUBHOUSE/SWIMMING POOL 100 Demand Range (L/Cap. Day) 10-15 l/d per meal Source: Standard Practises & Submitted Master Plans for Major Developments. DEWA Water Planning Guidelines for New Developments Projects 6 of 9

12 NETWORK DESIGN CRITERIA AND HYDRAULIC MODELING For every developer network, models should be the basis for network design, including pipe sizing, layout, and connectivity. DEWA s Water Network design criteria are based on previous experience and on recommendations by network material manufacturers. The following criteria should be considered by developers during their network design: Maximum applied Pipeline Velocity is 1.0 m/s for Distribution lines & 1.5 m/s for Transmission lines. [Design velocity for distribution and transmission main should also be specified] Minimum expected Pressure is @ 1.0 Bar at highest point within the developer (distribution) network. Maximum Pressure is @ 4 Bar at lowest point within the Transmission network. A minimum number of connections should be adopted for better network management. Pressures assumed at connection points should satisfy the design criteria above for the adopted network layout. However, these pressures will be reviewed by DEWA and changes if necessary will be recommended as appropriate, including additional pumping or pressure reduction requirements. Zoning and network pressure control as applicable should be considered in the design. Hydraulic Model demands should correspond to the Demand figures submitted in the demand calculation sheets. The developer or their consultant should submit peak hour Network Models for each main phase of the development as applicable. Models should be created using DEWA s adopted software or any EPANET compatible software. Network Models should be geo-referenced to the actual physical Geographic location s coordinates using the standard DM coordinate system known as DLTM. If the development expands through major phases, it is required to submit separate models representing each phase. As well as one overall network model as appropriate. DEWA will review the models in contrast with its requirements and planning information, and as required, recommendations for changes will be made accordingly. The network design layout should consider looping the system wherever possible, for better water circulation and system reliability. DEWA Water Planning Guidelines for New Developments Projects 7 of 9

13 REQUIRED DOCUMENTS: Developers, or their consultants, should submit the following documents for the review and study of Planning Water Transmission Department. Addressed to: Mr. Yousef Jebril. Executive Vice President Power & Water Planning P.O. Box 564 Dubai, U.A.E. Fax 04-3249206 1 Coloured Hard copy of the Location map and layout of the project as well as soft copy in CAD or GIS system shapefile format in DLTM coordinate system. 2 The complete Master Plan study for the project. 3 Project s water demand calculation sheets, year wise phased total demand, plot / zone or phase wise demands all calculations should be provided in MS Excel (1997-2003) spreadsheet format including all formulas used along with supporting data files. 4 Land use wise demand calculations including percentage of land use types and year wise percentage of occupancy envisaged by the developer. 5 Factors used to calculate Average as well as Peak Demands along with justification of the same. 6 Availability Statements for plots / corridors required by the development as per DEWA requirements. 7 Digital as well as hard copies of internal network design indicating proposed take off points and expected pressure at each of them. 8 All Hydraulic modelling file(s) developed for the network study geo-referenced to the actual coordinate system (DLTM) 9 Updated submittals for the above-mentioned documents are required in case of any changes in the demand requirements or network design. Upon receipt of Water Transmission Planning Approval for submitted water demands and main connections, developers or their consultants should submit application for network design approval to DEWA s Water Projects Department please refer to PE (W) Guidelines. DEWA Water Planning Guidelines for New Developments Projects 8 of 9