Task Order Authorization

Similar documents
GRADING, EROSION AND SEDIMENTATION CONTROL

CONSTRUCTION PLAN CHECKLIST

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

Date: June 2, CONTRACT for Engineering Services Kortsen Relief Sewer Design Concept Report. Dear Mr. McKeon,

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

PLANNING AND ZONING COMMISSION APPLICATION FOR IMPROVEMENT PLAT APPROVAL

Storm. Section. B. General Design and Drawing Standards Design

Stormwater Erosion Control & Post-Construction Plans (Stormwater Quality Plans)

PRIVATE STORM DRAINAGE FACILITIES REQUIREMENTS

Items in this checklist identify the base requirements that are to be provided by the design professional.

6 STORMWATER IMPROVEMENTS

6 STORMWATER IMPROVEMENTS

Step 1. Determine if a Small Utility GESC Permit is Applicable and if a Project Specific GESC Plan is Required.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

DOCUMENT ADDENDA AND MODIFICATIONS

TOWN OF MANCHESTER PLANNING AND ZONING COMMISSION Subdivision Application Minimum Submission Requirements

Chapter 3: Permit Procedures and Requirements

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413

CITY OF LAKE FOREST PARK BUILDING CHECKLIST FOR NEW CONSTRUCTION, ADDITION, AND REMODEL BUILDING PERMIT

MODEL Stormwater Local Design Manual. City of Centerville

Project Need and Evaluation

SUBDIVISION CHECKLIST. Subdivision Name. Prior To Review. Preliminary plan approved by Planning Commission / Council as required.

GCG ASSOCIATES, INC. CIVIL ENGINEERING AND LAND SURVEYING 84 Main Street Wilmington, Massachusetts 01887

Middle Tennessee State University (MTSU) Stormwater Plan Review Checklist

SECTION 2 DESIGN CRITERIA

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

APPLICATION FOR RIGHT OF WAY PERMIT

City of Elgin SUBDIVISION FINAL ENGINEERING Engineering Submittal Checklist

Agenda Item B.9 CONSENT CALENDAR Meeting Date: May 19, 2015

Stormwater Local Design Manual For Houston County, Georgia

Warner Robins Stormwater Local Design Manual

General Rules and Regulations

SECTION 12 STANDARDS FOR CONSTRUCTION PLANS AND SPECIFICATIONS

TOWN of LAKESHORE SUBDIVISION DEVELOPMENT PLAN CHECKLIST

Submittal Requirements. Post Construction Verification Document Plan Requirements

FDOT REF. ITEM DESCRIPTION

Appendix J: Storm Conveyance Design Parameters

7.00 INTRODUCTION... 1

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)

Dawson County Public Works 25 Justice Way, Suite 2232, Dawsonville, GA (706) x 42228

The City of North Las Vegas (CNLV) does not allow valley gutters to be constructed across streets with right-of-way widths of 80 feet or greater.

TABLE OF CONTENTS SECTION 700 STORM DRAINAGE STANDARDS...

PART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS

CITY OF MERIDIAN LAND DEVELOPMENT SERVICES SUBDIVISION PLAN REVIEW CHECK LIST

ENGINEERING REVIEW CHECKLIST City of Mount Clemens

Replace BID SCHEDULE with attached revised BID SCHEDULE.

PROJECT SCOPE OF WORK CITY OF TOWN AND COUNTRY STORMWATER PROGRAM

SECTION GENERAL EXCAVATION

SECTION SITE PREPARATION. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

PUBLIC WORKS SKAGIT COUNTY SAMISH ISLAND ROAD SAMISH ISLAND ROAD SLIDE REPAIR

EXHIBIT A FEE SCHEDULE

CITY OF HILSHIRE VILLAGE SWIMMING POOL PLAN SUBMITTAL CHECK LIST ADDRESS: DATE:

City of Redwood City Stormwater Pollution Prevention Program. Drainage Guidelines for Residential Development

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

STORM DRAINAGE DESIGN MANUAL

PUBLIC NOTICE PROFESSIONAL ENGINEERING SERIVCES: DESIGN OF TURF FIELD

CUSTOM HOMES, ADDITIONS TAYLOR BUILDING & COMMERCIAL DESIGNS 63 KENSINGTON ROAD, SAN ANSELMO, CALIFORNIA SPIRIT LIVING GROUP APN

401 Sanitary Sewer System Design Criteria. The following additional design requirements shall also apply:

Good Housekeeping. Phones Weather related emergencies Breaks and facilities. Introductions

ZONING ORDINANCE FOR THE ZONED UNINCORPORATED AREAS ARTICLE 1500 OF PUTNAM COUNTY, WEST VIRGINIA Page 149 ARTICLE 1500 DRAINAGE AND STORM SEWERS

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

12 DRAINAGE General Administrative Requirements Standards

ENGINEERING DESIGN STANDARDS

Request for Proposal Design Engineering Services City of Glendale 2019 Road Projects August 2018

Appendix B Construction SWPPP Short Form

Building Project Guide

AMENDMENT D TO THE CONTRACT FOR INDEPENDENT CONTRACTOR SERVICES BETWEEN THE CITY OF FERNLEY AND NCE

T a b l e o f C o n t e n t s

PART V - STORM DRAIN DESIGN CRITERIA

PART V - STORM DRAIN DESIGN CRITERIA

B-PERMIT PLAN CHECK MANUAL

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

Highway / Utility Guide

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

A.1 WATER SYSTEM PLAN SUBMITTAL PROCEDURES AND GENERAL REQUIREMENTS

Richland County Department of Public Works Engineering (Land Development) Division

PRELIMINARY ENGINEERING

TxDOT Houston District Permit Requirements (Information contained herein is subject to change)

Index. Composition and Order of Plan Set. Utility Plan... 5

4.8. Subsurface Infiltration

YES, we received Addendum No. 1

LOT GRADING. LOT GRADING REQUIREMENTS The following lot grading requirements came into effect on May 1, 2007:

Stormwater Infrastructure Funding Study Public Education Session May 27, :00 9:00 pm City Hall, Multi-Purpose Room Level 100

Stormwater line will be ABOVE ground corrugated pipe (No need to bury) running down to basin on NW 99 th St. It is simple and approved.

CITY OF WALLED LAKE 1499 E. WEST MAPLE WALLED LAKE, MI 48390

DEVELOPMENT SERVICES BUILDING COMMUNITY RISK REDUCTION ENGINEERING PLANNING PERMIT SERVICES TRANSPORTATION

Ordinance No Lot Surface Drainage

4.4.6 Underground Detention

DIVISION 5 STORM DRAINAGE CRITERIA

CUYAHOGA COUNTY ENGINEER

STATE UNIVERSITY CONSTRUCTION FUND

VILLAGE OF MORTON GROVE DEPARTMENT OF PUBLIC WORKS RIGHT-OF-WAY (ROW) PERMIT APPLICATION REQUIREMENTS

Metropolitan St. Louis Sewer District Statement of Policy for Maintenance of Stormwater Sewer Systems

ADDENDUM NUMBER TWO. A. SECTION ADVERTISEMENT FOR BIDS 1. REVISE Sealed Bid Date/Time/Location paragraph to read as follows:

CITY OF FARMINGTON HILLS DEPARTMENT OF PUBLIC SERVICES ENGINEERING DIVISION. ENGINEERING DESIGN STANDARDS For Site Development and Redevelopment

REQUEST FOR PROPOSALS For Engineering Design Services Street Reconstruction at Various Locations CITY OF SAN MATEO, CALIFORNIA

Building Permit Submittal Requirements

CITY OF MONROE LA. DRAINAGE AND UTILITY IMPACT STATEMENT NAMES AND ADDRESS OF PERSON, FIRM, OR CORPORATION SUBMITTING STATEMENT

CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application

PROPOSAL KITSAP COUNTY DEPARTMENT OF PUBLIC WORKS COUNTY ROAD PROJECT NO NW Golf Club Hill Road Culvert Replacement To the Honorable Board of Co

Transcription:

Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement by and between the ( City ) and ( Service Provider ), dated March 8, 2016. Task Order 6 is generally described as follows: This work shall consist of installing storm sewer Capital Improvement Projects 1, 2, 4, and 8 in addition to storm sewer improvements identified by City staff noted as Sites 5 & 6. See Exhibit A for project scope. The Service Provider shall perform the services on the project described below as provided herein and in the Agreement. This Task Order shall not be binding until it has been fully executed by both parties. Upon execution, this Task Order shall supplement the Agreement as it pertains to the project described above. See attached Exhibit A for project scope. This Task Order is executed this day of,. CITY OF CLYDE HILL By: Dated: Its: SERVICE PROVIDER By: Dated: Page 1

EXHIBIT A 2017 Small Drainage Program Scope, Hour and Fee Estimate March, 2017 Engineering Services, Preparation of Bid Documents & On-Call Construction Services PROJECT DESCRIPTION The Consultant shall prepare final Plans, Specifications and Estimates for the 2017 Small Drainage Program. The project will include the following sites: CIP # 1 (Site 1): 1615 85 th Ave NE Remove and replace approximately 80LF of existing 12 concrete pipe in drainage easement with new HDPE storm water pipe. Install in-line catch basin prior to storm water draining to 84 th Ave NE and connect to 84th Ave NE system. As necessary, replace existing asphalt pavement, concrete sidewalk and curb & gutter and restore private property to original conditions. CIP # 2 (Site 2): 2315 85 th Pl. NE Remove and replace approximately 150LF of existing 8 corrugated metal pipe in drainage easement. Easement must be cleared of large trees, and landscaping prior if installation of standard trenching construction methods is used. Install in-line catch basin prior to system draining to 84 th Ave NE system in order to improve maintenance and inspection of upstream pipe located within drainage easement. CIP # 4 (Site 3): 8805 Points Dr. NE Install new bar screen and inlet headwalls (if needed) on 30 CMP inlet located in a drainage easement, removal of sediment and loose debris, stabilization of existing slopes and rockery wall repair (if needed). HPA permit required. CIP # 8 (Site 4): 8420 NE 19 th Pl. Replace existing damaged (root intrusion) 6 pipe along property frontage within ROW with new 8-12 pipe and catch basins at connections/junction points. Private roof drains shall be reconnected to system. Restoration includes installing HMA pavement and driveway apron and landscaping. Coordinate with property developer at 8420 NE 19 th Pl as needed. CCTV (by city) downstream connection across 8408 NE 19 th Pl to verify free flow downstream of issue. Site 5: 2505 85 th Ave NE Remove one existing inlet structure and install new beehive grate intake structure and surrounding quarry spall pad within drainage easement. Site 6: 94 th Ave NE 2017 Small Drainage Program Page 1 of 6 March 22, 2017

Install new storm drainage system on 94 th Ave NE, extending south (upstream) from NE 24 th St. for approximately 650 feet. The storm drainage system will be designed to collect storm drainage discharges (both pumped and gravity) from adjacent private properties. The Consultant shall provide necessary surveying, project design, quantity and cost estimates, and utility coordination required to complete final bid documents. It is anticipated that sites will be bid as a single bid package for the 2017 Small Drainage Program as budget or other considerations allow. The Consultant shall provide surveyed base maps with horizontal utility locations, ortho-photography, and GIS data as necessary for each site. Surveyed base maps will include right-of-way line work based on ROW research. Project horizontal and vertical datum will be assumed on all sites. The Consultant shall provide assistance to the City with preparation of an HPA application required for Site 3. No additional permits are anticipated. It is the Consultants understanding that none of the 2017 Small Drainage Program sites require biological assessments, additional permits beyond those listed, wetland delineations, geotechnical review, detention facilities, or water quality treatment facilities. The budget assumes a straightforward approval process with no special studies or extensive coordination. All work will be completed within City rights of way or easements and no easement acquisition is anticipated. For the 2017 Small Drainage Program, the Consultant shall submit a 30% Review Submittal (plans and estimate only), and a 90% review Submittal that includes plans, specifications and estimate to the City for review prior to bidding. SCOPE OF WORK TASK 1 2017 Small Drainage Program Design 1.1 MANAGEMENT/COORDINATION/ADMINISTRATION The Consultant shall provide continuous project management and administration for the duration of the Project. (Estimate 8 months). The consultant shall meet the City at all project sites for one (1) project kickoff meeting. Hold project coordination meetings with the City to update progress and review submittals. Assume (2) meetings for the 30% and 90% reviews. The Consultant shall provide monthly status reports and billings. The Consultant shall provide independent QA/QC reviews by senior in-house staff of all deliverables prior to submittal to the City. o The City shall perform necessary property owner coordination and the Consultant shall assist on an as-requested basis. 2017 Small Drainage Program Page 2 of 6 March 22, 2017

1.2 TOPOGRAPHIC SURVEY/UTILITY LOCATES/ROW PREPARATION The Consultant shall prepare base maps for each 2017 Small Drainage Program site. Topographic survey will be performed for all sites including horizontal utility locations within the right of way and easements. The consultant will utilize a private utility locating service to determine the location of utilities in the project corridor, including watermains, gas, and other underground utilities, and if possible, existing storm drain force main locations. The consultant shall conduct right of way calculations and establish right of way from assessor/gis/plat maps The consultant shall identify existing easements from existing city filed data and include in base maps. o Title reports will not be ordered. o Existing topography survey performed for the City of Bellevue s 2011 AC Water Main Replacement, Phase 1 project will be utilized to the extent possible in creating the basemap. Deliverables o CAD file and PDF of basemap 1.3 ALTERNATIVE ANALYSIS The consultant shall review all available site data including CCTV, drainage easements, site conditions and perform an alternative analysis for: o CIP # 1 (Site 1): 1615 85 th Ave NE Alternative 1: Trenchless pipe method Alternative 2: Complete pipe replacement via standard trenching methods. o CIP # 2 (Site 2): 2315 85 th Pl NE Alternative 1: Trenchless pipe method Alternative 2: In-Line catch basin installation only. o The City shall order any CCTV inspections needed for site review. 1.4 PREPARE 30% PLANS & ESTIMATE The Consultant shall prepare final Plans for the proposed improvements including the following: o Plans shall be prepared with such provisions in such detail as to permit field layout and construction within a degree of accuracy acceptable to the City and per industry standards. 2017 Small Drainage Program Page 3 of 6 March 22, 2017

o o o o o It is assumed there will be eighteen (18) plan sheets at 1 =20 scale full size (22 X 34 ), 1 =40 at reduced scale (11 X 17 ). Details will be prepared for items not available as standard details from the City, State, or WSDOT standard drawings. The plans shall illustrate complete details of construction of the proposed improvements including limits of construction and removals, proposed invert elevations, rim elevations and required construction materials. Plans shall also illustrate site restoration as necessary including roadway and private property restoration to generally meet the conditions that existed prior to construction. Drainage designs will be determined through alternative analysis (where identified) consultation with City staff and from previous experience rather than detailed basin modeling. Calculate quantities and prepare Engineers Estimate of Probable Construction Cost. o For 94 th Ave NE The proposed storm drain is not intended to collect street runoff; therefore the pipe alignment and catch basin locations will be designed to connect private drainage systems while minimizing impacts to other utilities. The proposed storm drain will be 12 diameter and will not require conveyance capacity calculations to be performed. o The plan set will include the following sheets: Cover sheet (1) Index/Abbreviation plan sheet (1) Site preparation/tesc plan sheet (4) Storm drainage plan/profile sheets/site restoration (8) Detail sheet(s) (4) 1.5 UTILITY COORDINATION The consultant shall prepare a potholing plan and the city shall order potholes if needed. The Consultant shall distribute the 60% plans to franchise utility owners to identify potential conflicts within the Project limits. o It will be determined if potholing is necessary after the 30% design submittal is complete. o No utility upgrades are planned for in the project design. 1.6 2017 SMALL DRAINAGE PROGRAM FINAL DESIGN The Consultant shall conduct QA/QC and constructability reviews in the field for each site and consult with City staff during the field reviews. The Consultant shall calculate quantities and prepare Engineers Estimate of Probable Construction Cost for the 90% submittal and Bid Documents. 2017 Small Drainage Program Page 4 of 6 March 22, 2017

The Consultant shall prepare the Contract Specification per 2016 WSDOT Standard Specifications for the 90% submittal and Bid Documents. The Consultant shall assist the City with Project Advertisement and Award. o No federal funding is anticipated for the Project engineering or construction. o Drainage & Water Quality Reports will not be required. o Geotechnical Engineering services will not be required. o Environmental Documentation will not be required with exception of SEPA Checklist. SEPA Checklist shall be prepared by the city to support the HPA permit. Deliverables o 30% review submittal with Plans and Estimate o 90% review submittal with Plans, Specifications, and Estimate. o Bid Documents and Engineer s Estimate o 3 sets of Plans (11 X 17 ) and specifications provided for each review submittal. o 5 sets of Plans (11 X 17 ) and specifications for the Bid Documents. o 1 sets of Plans (22 X 34 ) for the Bid Documents. o Coordinate upload of Plans and Specifications to Builders Exchange and posting of advertisement to a local newspaper. TASK 2 2017 Small Drainage Program Permitting 2.1 The Consultant shall meet in the field with a representative from Washington Department of Fish & Wildlife and prepare a JARPA for HPA approval on Site 3. o No wetland or stream delineations will be required. o No special studies (biological assessments, etc.) will be required. o The $150 processing fee for the JARPA application will be paid by the Consultant and reimbursed by the City through the invoice process. Deliverables o JARPA Application TASK 3 Construction Services 3.1 Construction management, inspection and materials testing will be provided by the City. An allowance is included in the budget for on-call construction support provided by the Consultant as requested by the City. These services may include preconstruction conference, construction inspection and engineering, submittal reviews, and/or record drawings within the budget allowances included in Exhibit B. 2017 Small Drainage Program Page 5 of 6 March 22, 2017

Additional Services The may require other services of the consultant. These services could include additional design, right of way, utility potholing, environmental documentation, property owner coordination. Additional construction services or other work tasks not included in the scope of work. At the time these services are required, the Consultant will provide the City with a detailed scope of work and an hour and fee estimate. The Consultant will not proceed with the work until the City has authorized the work and issued a Notice to Proceed. 2017 Small Drainage Program Page 6 of 6 March 22, 2017

HOUR AND FEE ESTIMATE EXHIBIT B Project: On Call Task Order 6 2017 Small Drainage Program March 22, 2017 Labor Hour Estimate Total Fee Principal Project Project Design CAD Const Survey Senior Office Task Description Engineer Manager Engineer Engineer Technician Inspector Crew Admin Admin $ 180.00 $ 160.00 $ 125.00 $ 100.00 $ 90.00 $ 100.00 $ 150.00 $ 100.00 $ 75.00 Fee Task 1-2017 Small Drainage Program Design 1.1 Management, administration & QA/QC Reviews 2 4 16 2 12 $ 4,100.00 1.2 Topographic Survey/Basemapping/ROW Establishment Topographic Survey - CIP # 1,2,4,8, Site 5 & Site 6 4 56 $ 8,900.00 Base Map Creation - CIP # 1,2,4,8, Site 5 & Site 6 56 $ 5,040.00 ROW Establishing 16 16 $ 3,840.00 1.3 Alternative Analysis CIP #1 (Site 1) 1615 85th Ave NE 1 2 12 $ 1,610.00 CIP #2 (Site 2) 2315 85th Pl. NE 1 2 12 $ 1,610.00 1.4 Prepare Plans CIP #1 (Site 1) 1615 85th Ave NE 1 1 8 12 8 $ 3,260.00 CIP #2 (Site 2) 2315 85th Pl. NE 1 8 12 8 $ 3,080.00 CIP #4 (Site 3) 8805 Points Dr. NE 1 1 16 12 8 $ 4,260.00 CIP #8 (Site 4) 8420 NE 19th Pl. 1 8 16 8 $ 3,480.00 (Site 5) 2505 85th Ave NE 1 4 4 8 $ 1,780.00 (Site 6) 94th Ave NE 1 12 16 12 $ 4,340.00 1.5 Utility Coordination $ - CIP # 1,2,4,8, Site 5 & Site 6 1 8 8 $ 1,960.00 1.6 Final Design Field Reviews - CIP # 1,2,4,8, Site 5 & Site 6 2 6 6 $ 1,670.00 Quantity and Cost Estimating - CIP # 1,2,4,8, Site 5 & Site 6 1 24 40 $ 7,180.00 Prepare Specifications - CIP # 1,2,4,8, Site 5 & Site 6 1 24 40 $ 7,180.00 Finalize Bid Documents - CIP # 1,2,4,8, Site 5 & Site 6 2 8 16 4 $ 3,220.00 Reimbursable expenses - see breakdown for details $ 4,800.00 Task Totals 6 17 150 206 124 0 72 2 16 $ 71,310.00 Task 2-2017 Small Drainage Permitting 2.1 HPA Permitting - Site 3 1 4 8 $ 1,460.00 Reimbursable expenses - see breakdown for details $ 200.00 Task Totals 0 1 4 8 0 0 0 0 0 $ 1,660.00 Task 3 - Construction Services 3.1 Construction Services CIP # 1,2,4,8, Site 5 & Site 6 1 2 24 32 $ 6,700.00 Reimbursable expenses - see breakdown for details $ 125.00 Task Totals 1 2 24 32 0 0 0 0 0 $ 6,825.00 Total hours by Classification 6 18 154 214 124 0 72 2 16 Project Total: $ 79,795.00 4/5/2017

HOUR AND FEE ESTIMATE EXHIBIT B Project: On Call Task Order 6 2017 Small Drainage Program March 22, 2017 Reimbursable Breakdown Cost Task 1-2017 Small Drainage Program Design Mileage - CIP #1,2,4,8, Site 5 & Site 6 $ 250.00 Utility Locates - CIP #1,2,4,8, Site 5 & Site 6 $ 4,300.00 Reproduction $ 250.00 Task 1 - Total $ 4,800.00 Task 2-2017 Small Drainage Permitting Mileage $ 25.00 JARPA Application $ 150.00 Reproduction $ 25.00 Task 2 - Total $ 200.00 Task 3 - Construction Services Mileage $ 75.00 Reproduction $ 50.00 Task 3 - Total $ 125.00 Total Reimbursable Costs: $ 5,125.00 4/5/2017