Measurement and verification of a municipal water pumping project

Similar documents
Measurement and verification of load shifting interventions for a fridge plant system in South Africa

Reducing the electricity cost of a Three-Pipe Water Pumping System a case study using software

CHAPTER 2: METHODOLOGY

Measurement & Verification of Coal Fired Power Station Maintenance Projects

ENERGY INITIATIVE ENERGY EFFICIENCY PROGRAM Impact Evaluation of Prescriptive and Custom Lighting Installations. National Grid. Prepared by DNV GL

Power Bills and Energy Efficiency for Irrigation. James Curran, Agricultural Resource Management

REVISED TARIFF STRUCTURE STATEMENT. ActewAGL Distribution Electricity Network

National Grid USA Service Company. Impact Evaluation Of 2006 Design2000plus Custom Comprehensive Projects. Final Report

Electric Standard Offer Program

The Ex Ante Calculations match the claimed savings in the project tracking system.

Impact of localised Energy Efficiency (EE) and Renewable Energy (RE) on City of Cape Town s finances over the next 10 years Report.

Impact of localised Energy Efficiency (EE) and Renewable Energy (RE) on Ekurhuleni s finances over the next 10 years Report.

Managing Energy Use and Cost with Integrated Metering

Hydropower from pressurized conduits Energy generation from distribution systems Research project

HOW TO READ YOUR ELECTRICITY BILL

Incentives. After work is complete:

Measuring and Verification Review. (M&V) Savings Report

1. Agricultural Loads 2. Time Differentiated Tariff Structure 3. Cost of Energy

GLOSSARY OF TERMS January 2017

Appendix D Example M&V Plans

Does It Keep The Drinks Cold and Reduce Peak Demand? An Evaluation of a Vending Machine Control Program

Bloemwater Conduit Hydropower Plant launched

Variable Speed Drives: Reducing energy costs in petrochemical manufacturing

J. Classification of Service

Performance optimization of an air source heat pump water heater using mathematical modelling

M&V Fundamentals & the International Performance Measurement and Verification Protocol

Impact Evaluation of National Grid Rhode Island s Custom Refrigeration, Motor and Other Installations

SOLAR ASSISTED HVAC HVAC

1 EXECUTIVE SUMMARY 3 2 PROJECT AIM 4 3 OVERVIEW OF THE KOGARAH TOWN SQUARE SITE 5 4 PROJECT PROCEDURE AND SETUP 9 5 RESULTS 11

TOU Tariff Analysis and Program Development

7 Measurement and Verification for Generic Variable Loads

Energy efficiency through optimisation of water reticulation in deep mines

Preparing for Technical Training: Essential Skills for Water/Wastewater Operators. Practice Tests

Project Information. Measure Description

EMBEDDED GENERATION: THE CITY POWER EXPERIENCE

Angelica Salomon-Dealino & Dilip Limaye International Institute for Energy Conservation. Asian Development Bank, 19 June 2015

Impact Evaluation of 2010 Custom Process and Compressed Air Installations

4. Energy Ef ficiency Options

Bundled Energy Solutions to Lower Operating Costs and Maximize ROI. Harvey Katzen Director of Bundled Energy Services ABM Building and Energy

MEASUREMENT AND VERIFICATION GUIDELINES FOR RETROFIT AND NEW CONSTRUCTION PROJECTS

Residential Heat Pump Rebate Programme

Tariffs January 1, 2017

Fig. 1: Installed capacity of small to medium scale solar PV in different parts of the World [1, 2]

Computer Efficiency Product Changes

Optimal power control of grid tied PV-battery-diesel system powering heat pump water heaters

Energy Conservation & Demand Management Plan

Demand Response Association of Energy Engineers. Presenter: David Wylie, P.E. ASWB Engineering

Pumpset Energy Efficiency: Agriculture Demand Side Management Program

Project Measurement and Verification Procedures

Air quality monitoring and management for the industrialized Highveld region of South Africa

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions

Electric Rate Schedule GS-TOU General Service Commercial, Time-of-Use

The ESP Handbook. Chapter 15 Obtaining Consumer Usage and Metering Information. Version 7.0 February 1, 2017

ELECTRICAL ENERGY AND POWER SAVING POTENTIALS IN THE AREA OF AGRICULTURE

Total Monthly Electricity Cost (R)

Practical Experiences in Applying Savings M&V

Reduction in the electricity costs for irrigated potato production in Limpopo

A mini-integrated resource plan for a commercial entity in Gauteng Province: planning for energy autonomous businesses

An Experimental Study on the PV Systems Contribution on Lowering the Demand Charge

Advance Metering Infrastructure (AMI) in South Africa Eskom s Challenges and Lesson s Learnt

The ESP Handbook. Chapter 9 Billing under CCA. Version 2.0 May 1, 2015

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Case Studies on Using Load Models in Network Calculation

Measurement and verification of industrial DSM projects

Schedule TOU-PA-2-SOP Sheet 1 TIME-OF-USE - AGRICULTURAL AND PUMPING SUPER OFF-PEAK - SMALL TO MEDIUM

Demand Reduction and Energy Savings Potential of Integrated Dimming Ballast Controls in Mid-Size Retail Facilities: PetSmart Stores

4 PROJECT ALTERNATIVES

Energy Project Measurement and Verification Procedures

ENERGY MANAGEMENT PLANNING. Mary Tiger

Total Monthly Electricity Cost (R)

Energy Storage Buildings-to- Grid Applications

The targeting of industrial energy audits for DSM planning

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

OREGON SCHEDULE 125 COMMERCIAL AND INDUSTRIAL ENERGY SERVICES NO NEW SERVICE Page 1

Dynamic Pricing Programs Focus on Peak-Time Rebate Programs

SSC-JE STUDY MATERIAL ENVIRONMENTAL ENGINEERING [PA ENVIRONMENTAL ENGINEERINGG PART-A

Final Report for National Grid USA Service Company. Evaluation of 2003 Custom HVAC Installations Part II. September 27, 2005.

DEMAND SIDE PARTICIPATION INFORMATION GUIDELINES

I P E L I N E : M I D M A R I D M A R D A M T O M I D M A R

Load-shifting opportunities for typical cement plants

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany

Energy savings reporting and uncertainty in Measurement & Verification

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

Using Low Voltage Smart System (LVSS) Data for Intelligent Operations and Customer Support

Dynamic Stray Current Interference Testing And Mitigation Design For A 90-Inch Water Main

NYSERDA CHP Assessment Report A S S E S S I N G T H E C H P P L A N T A T C L A R K S O N U N I V E R S I T Y

The Negative Effects of Electricity Cost Increases on Sugar Cane Production in the Bundaberg Mill area. CASE STUDY

Behind the Meter Energy Storage Applications & Solutions Design

The South African Grid Code

SCHEDULE COGEN/SPP (Cogeneration and/or Small Power Production)

Principles of cost recovery: electricity tariff design

Farm Energy Efficiency June Collin Macpherson - JCM Solutions

Report. Preliminary study, Power for running pumps in Taveta city, Kenya. Author(s) Anders Austegard

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Effective Energy Modeling WGBA Leadership Conference October 19, 2005

APES Math Instructional Guide

Energy Audit Tool Manual. Client Name

Electricity Supply to Africa and Developing Economies. Challenges and opportunities. Planning for the future in uncertain times

Energy efficiency through variable speed drive control on a cascading mine cooling system D van Greunen

Geothermal Heat Pumps at Ft. Polk: Early Results

Transcription:

Measurement and verification of a municipal water pumping project I E Bosman North-West University, Potchefstroom L J Grobler North-West University, Potchefstroom Abstract The processes that were followed to develop the baseline to Measure and Verify (M&V) a Municipal Demand Side Management (DSM) water pumping project that is being implemented is described in this paper. This paper is a follow-up on a previous paper presented at the ICUE 2004 (Measurement and Verification of a Municipal Water Pumping Project). The previous paper described the M&V process and the methodology that would be used to develop the baseline for the project. The project is currently in the implementation phase. To develop the baseline, energy data was recorded for all the pumps as well as the total flow from the pump station. The baseline was developed by determining an average 30 minute weekday, Saturday and Sunday profile. The baseline also includes a relation between daily water pumped and electricity consumption. Therefore, the baseline can be adjusted if the total amount of water pumped daily is lower or higher than the average values used. This will ensure that the baseline takes possible load growth or possible load reduction into consideration. The baseline will be used to determine the impact of the project after implementation. Keywords: measurement and verification, water pumping, load management, baseline development 1 Overview This paper describes the development of a baseline for the Witbank municipal water pumping project. The baseline was developed for the pump station and for the pumps at the reservoir. The baseline will be used during the post-implementation phase to determine the actual savings of the project. The effect of load growth on the baseline is also discussed in this paper. The DSM project aims to reduce the average demand between 18:00 and 20:00 during weekdays by 3.138 MW. 1.1 Site description The pump station is situated after the sluices of the Witbank Dam, which is located east of Witbank, in the Mpumalanga Province. This is the main site where the DSM activities will occur. A basic layout is shown in Figure 1. Point B is situated in the town of Witbank, and is the reservoir collection point for the pumped water before it goes to the purification works. This point is situated at Klipfontein, adjacent to the N4 highway, at the western end of Witbank. The systems that will be affected by the DSM-project activity consist of four pumps (1045 kw) at the pump station and three pumps (145 kw) at the reservoir (point B). 1.2 Audit of systems Raw water is pumped directly from the Witbank Dam via three pipelines to two concrete reservoirs at point B. This is done with four 1045 kw pumps. From here, the water gravitates at a constant rate underneath the N4 highway through a culvert to the Witbank Water Purification Works (WWPW) in town. Raw water also gravitates to the Highveld Steel industry situated to the west of Witbank. On days when the WWPW demands a lower volume of water, excess water flows from the concrete reservoirs to an open quarry situated at point B. On days of higher demand, water is pumped back from the quarry to the concrete reservoirs in order to supplement the demand for water gravitating to the WWPW and Highveld Steel. Since the level of the quarry is too low for water to gravitate to the WWPW and Highveld Steel, water has to be pumped from here to the two reservoirs. This is 42 Journal of Energy in Southern Africa Vol 17 No 1 February 2006

Figure 1: Schematic layout of the project done with three pumps, each driven by a 145 kw motor. The total storage capacity of 263 Mega litres (ML) has been shown to be sufficient for a 48-hour storage backup for the expected summer peak consumption until 2005. 1.3 Current operation Currently, the pumps at the Witbank Dam pumping station are running 24 hours per day. The quarry is used during the week to help the pump station match the water demand. Three pumps operate during the week at the pump station. During the weekends, the fourth pump of the pumping station provides the extra delivering capacity to math the water demand and that required to fill the quarry. Because of this, there are no backup pumps available. 1.4 Demand-side management activities 1.4.1 Description The project consists of the following: A new pump station was build at the Witbank Dam on a higher flood line, and will be able to accommodate extensions as well as improved drainage facilities. Two additional 1045kW pumps will be installed in the new pump station. The four existing pumps will be moved to the new pump station providing six pumps. Five pumps will be operating outside the peak demand periods of Eskom, with the sixth pump on standby only. Figures 2 and 3 show the current and proposed operating strategies during a weekday and a day on the weekend. It can be seen that the maximum Figure 2: Current and proposed operation during the week Figure 3: Current and proposed operation during the weekends Journal of Energy in Southern Africa Vol 17 No 1 February 2006 43

demand will increase with the proposed pump system, but during peak periods, there will be a demand of only 145kW. During the weekends, the proposed operation is five pumps operating in order to fill the quarry for days of higher water demand as described in paragraphs 1.2 and 1.3. 1.4.2 Assumptions The following assumptions have been made by the Energy Service Company (ESCO) during their calculations: A standard growth in water demand of 1.5% per year. The planned development of 10 000 housing stands in the next 5 years are also included in the water demand. Eskom 2003 MegaFlex tariffs are used in calculations. 2 Baseline characterization process 2.1 Baseline strategy In order to determine the baseline for the electrical consumption of the pumps, the following variables need to be taken into consideration: Amount of water pumped, Liquid flow rate, Size of the pipeline, Length of the pipeline, Geometry of the pipeline, Static Head, Amount of pumps operating, Efficiency of the pumps, Size of the pumps, and Medium that is pumped. Therefore, the equation is as follows: IP kw = f (X 1, X 2, X 3, X 4, X 5, X 6, X 7, X 8, X 9) (1) Where: IP kw = electric power X 1 = liquid flow rate X 2 = size of the pipeline X 3 = length of the pipeline X 4 = geometry of the pipeline X 5 = static head X 6 = amount of pumps operating X 7 = efficiency of the pumps X 8 = size of the pumps = medium that is pumped X 9 To develop the baseline, how the system would have been without any DSM intervention, only the variables that change before and after implementation need to be examined. The following variables will stay the same before an after implementation: Size of the pipeline, Length of the pipeline, Geometry of the pipeline, Static Head, Efficiency of the pumps, Size of the pumps, and Medium that is pumped. Therefore, the equation is simplified to: IP kw = f (X 1, X 2,) (2) Where: IP kw = electrical power X 1 = amount of pumps operating = liquid flow rate X 2 This equation is used to determine the average demand profile (kw) for a typical day and can be seen in Figures 4, 6 and 8. In order to determine the daily energy consumption (kwh), Equation 2 needs to be integrated over time. (3) Now the question arises: how sensitive is the energy consumption to the number of pumps operating? An analysis was done and the resulting graphs can be seen in Figures 5, 7 and 9. The procedure of the analysis is described in paragraph 2.2 to paragraph 3.7. Figures 5, 7 and 9 show the relation between the daily energy consumption (kwh) and the daily amount of water pumped. From these figures, it can be determined that the influence of the number of pumps operating is minimal. The energy consumption equation can be simplified to a function of only the water flow rate. Therefore Equation 3 is simplified to: E kwh = ƒ(x 1) (4) Where: X 1 = Water flow rate. 2.2 Determining the baseline The energy data of the 4 pumps at the pump station and the 3 pumps at the reservoir pumps (Point B) has been recorded since October 2003, and is still being recorded at present. The flow from the pump station was recorded since February 2004. This means that the following data is available: Averaged 30-minute amp meter readings of each pump affected. Daily water pumped at the pump station. The above values have been used to do the following: Determine the kw in 30-minute periods with some assumptions. Determine from the metered data an average Weekday profile, consisting of 48 actual metered values. Determine from the metered data an average Saturday profile, consisting of 48 actual metered 44 Journal of Energy in Southern Africa Vol 17 No 1 February 2006

values. Determine from the metered data an average Sunday profile, consisting of 48 actual metered values. Determine the maximum operating capacity (kw) during the metered period for Weekdays, Saturdays and Sundays. Determine the pre-dsm utilisation factors for Weekdays, Saturdays and Sundays in the time of use (TOU) periods. This is a factor indicating the average utilisation of equipment in the TOU periods with the respect to the total installed capacity of affected equipment. Determine the daily kwh electricity consumption for the metered period for Weekdays, Saturdays and Sundays. Determine a relation between the daily water pumped and the daily electricity consumption for Weekdays, Saturdays and Sundays. Determine the reference value (daily water pumped and electricity consumption) for which the baseline was developed. 2.3 Baseline data gathering, assumptions and calculations 2.3.1 Boundaries of the baseline Energy was metered at all the affected pumps in the pump stations. The energy loggers were synchronised before installation. All the data was then added so that a total energy reading for all the affected motors was obtained. Data were logged at 5-minute intervals, averaged to 30-minute intervals. 2.3.2 Assumptions Only the current of one phase of all the motors was metered. To convert the current to kw, a number of assumptions were made. The assumptions are: All the phases of the motors are balanced. The voltage of the pumps at the pump station is 2 200 Volts. The voltage of the pumps at the reservoir group is 380 Volts. All the motors of the pump station have a preimplementation power factor of 0.9. All the motors of the reservoir group have a preimplementation power factor of 0.9. 2.3.3 Calculations needed for the baseline kw Calculations Using the assumptions stated in the previous paragraph, the kw for the pumps was calculated using the following equation: (5) To verify both the accuracy of the assumptions and the actual calculation, the calculated values were compared to actual meter readings. There was only a small (less than 2%) variation between the two values. Pre-DSM utilisation factors For the pre-dsm utilisation factors, the following information and data was needed: Total installed capacity of the affected motors (4615 kw). The average kw demand in the TOU periods for a Weekday (2679 kw), Saturday (2712 kw) and Sunday (2537 kw). To determine the pre-dsm utilisation factor, the following equation was used: (6) 2.3.4 Days used Data recording started in October 2003. Not all data recorded was used. The primary reasons are the following: One or more of the loggers had a battery failure. This means that the energy consumption of not all the motors was recorded. Days where data was incomplete and not used. Days when the pumps were not running at typical operation. In total, 43 days were used of which 28 were weekdays, 8 were Saturdays and 7 were Sundays. 2.3.5 Data integrity and validation The logged data was put through a data integrity test module in order to eliminate invalid data such as the following: Motors operating at an extremely small load. Typically, a motor of 1045kW operating at only 5kW. Motors operating at far more than the rated capacity. No events were filtered due to this. 2.3.6 Baseline determination After the data has been selected, the actual baseline can be determined. The baseline was developed by determining an average 30 minute Weekday profile, an average 30 minute Saturday profile and an average 30 minute Sunday profile. The baseline is presented later. 3 Baseline for Witbank Dam water pumping 3.1 Components of the baseline The M&V baseline for the Witbank Water Pumping Project consists of the following components: Average Weekday, Saturday and Sunday demand profiles. Weekday, Saturday, and Sunday daily electricity consumption and daily water pumped scatter plots. Journal of Energy in Southern Africa Vol 17 No 1 February 2006 45

The average pre-dsm utilisation factors in the time of use (TOU) periods for Weekdays, Saturdays and Sundays. 3.2 Baseline reference values Essentially the baseline was developed assuming an average daily water flow rate. The values are indicated in Table 1 as well as on the graphs that follow (Figures 4, 6 and 8). Table 1: Daily average water and electricity values of baseline determination period Daily average for the metered period Weekday Saturday Sunday Megalitre water 102.55 105.90 97.97 KWh consumption 63 895 66 834 60 900 3.3 Baseline and load changes experienced by Witbank water pumping Variations in the daily average values indicated in will result in the baseline being adjusted using a tobe determined adding factor. If the water pumped (load) drops significantly, the baseline needs to be lowered. If the water pumped increases, the baseline needs to be lifted. The method is as follows: 1. The total water pumped in mega litres (ML) daily will be known at the end of the month. 2. Using the equation from the electricity consumption vs. total water flow scatter plot, calculate what the baseline electricity consumption (kwh) would have been. 3. The baseline is then adjusted either upwards or downwards so that the total electricity consumption predicted by the baseline (area under the demand profile) is equal to the electricity consumption read off in step 2. The adjustment will not be made by using a scalar (multiply all values with a factor). Instead, a constant value will be added or subtracted from all 48 points. In other words, the whole baseline will be shifted upwards or downwards. The baseline will thus differ from day to day, related to the total quantity of water pumped. 3.4 Information on the baseline demand profiles Each of the baseline demand profiles contain the following information: The installed capacity using a solid line. The maximum operating capacity during the data recording phase of the specific day type using a dashed line. The baseline with 48 dots to indicate the values. 3.5 Weekday baseline The baseline for weekdays is shown in this paragraph (Figures 4 and 5 and Table 2). 3.6 Saturday baseline The baseline for Saturdays is shown in this paragraph (Figures 6 and 7 and Table 3). 3.7 Sunday baseline The baseline for Sundays is shown in this paragraph (Figures 8 and 9 and Table 4). Table 3: Saturday pre-dsm utilization factors Installed capacity (kw)4 615 4 615 Standard Off peak Contractual value (kw) 3 138 3 138 Average (kw) 2736 2702 Utilisation factor (installed capacity) 59.3% 58.5% Utilisation factor (contractual value) 87.2% 86.1% Table 4: Sunday pre-dsm utilization factors Off peak Installed capacity (kw) 4 615 Contractual value (kw) 3 138 Average (kw) 2537 Utilisation factor (installed capacity) 55.0% Utilisation factor (contractual value) 80.9% 4 Conclusion A relationship has been found between the energy consumption and the water flow rate. This was used to develop the baseline consisting of average Weekday, Saturday, and Sunday profiles. The baseline can be adjusted if the daily water pumped is lower or higher than the average values used. This will ensure that the baseline takes possible load growth or possible load reduction into consideration. Table 2: Weekday pre-dsm utilization factors Morning peak Standard Evening peak Off peak Installed capacity (kw) 4 615 4 615 4 615 4 615 Contractual value (kw) 3 138 3 138 3 138 3 138 Average (kw) 2 683 2 652 2727 2701 Utilisation factor (installed capacity) 57.1% 57.5% 59.1% 58.5% Utilisation factor (contractual value) 85.5% 84.5% 86.9% 86.1% 46 Journal of Energy in Southern Africa Vol 17 No 1 February 2006

Figure 4: Average weekday demand profile: Weekday baseline Figure 5: Daily water pumped and electricity consumption scatter plot Figure 6: Average Saturday demand profile: Saturday baseline Journal of Energy in Southern Africa Vol 17 No 1 February 2006 47

Figure 7: Daily water pumped and electricity consumption scatter plot Figure 8: Average Sunday demand profile: Sunday baseline Figure 9: Daily water pumped and electricity consumption plot 48 Journal of Energy in Southern Africa Vol 17 No 1 February 2006

If all the pumps are switched of during Eskom s evening peak hours, then an average of 2.8 MW will be dropped. Therefore, 90% of the ESCO s intended target will be realised. This is still within Eskom s requirements and the project can be classified as successful. References Grobler, LJ and Van Rooyen IE, 2003. Measurement and Verification Plan: Witbank Dam Water Pumping, 2003. Grobler, LJ and Verwey, WH, 2003. Measurement and Verification Scoping Study: Witbank Dam Water Pumping, 2003. Grobler, LJ and Van Rooyen IE, 2004. Baseline Report: Witbank Dam Water Pumping, 2004. Received 20 July 2004; revised 1 April 2005 Journal of Energy in Southern Africa Vol 17 No 1 February 2006 49