Alternate Formwork System Evaluation

Similar documents
Todd Bookwalter A.E. Senior Thesis Summary Book Spring Table of Contents. Building Design & Systems Summary Local Conditions..

PRO-SHORE. Shoring Systems

PRESENTATION PLAN A MODEL COMPARISON FLOOR CONSTRUCTION

Pro-Shore LLC MODULAR DECK SYSTEM. The

P: F: Resi-Ply FORMING SYSTEM BY DAYTON SUPERIOR

Construction Management Study

Elevated Slab Sequence

Framed formwork Frami Xlife

Table of Contents Big expertise. Real convenience. Concrete commitment.

LOGIK. Forming System

Atlas ACS. Atlas Clamp System ATLAS CLAMP WALLFORM SYSTEM

SIGNAL HILL PROFESSIONAL CENTER Manassas, Virginia Morabito Consultants EXECUTIVE SUMMARY

Miller Collective Safety at Height Solutions EPIC ULTRA Barrier System EPIC Post-N-Barrier System EPIC Basic Barrier System

System Design. The two-component slab form system! DeckFast is as simple and quick as erecting two components to provide a ready-to-pour slab surface!

Aluminum Beam Gang System

PT Slab Deflections. What is acceptable? By Douglas Sarkkinen, PE,SE Senior Structural Engineer Otak, Inc PTI Annual Conference, Kansas City, MO

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

DeckFast DAYTONSUPERIOR.COM FORMING. Shoring System

Titan HV panel decking system from

FrameFast Shoring System

Concrete Framing systems. Design choices. Basic flavors

The Structural Redesign of Boyds Bear Country and its Related Systems. Boyds Bear Country, Pigeon Forge, Tennessee

THE FORENSIC MEDICAL CENTER

VARIOUS TYPES OF SLABS

COURTYARD INFILL STRUCTURE DESIGN

HARVEY MUDD COLLEGE TEACHING AND LEARNING CENTER SECTION Page 1 of 6 VOIDED CONCRETE SLAB

Shoring and Reshoring Fundamentals

Pro-Con Structural Study of Alternate Floor Systems

Interior Hangers. Application

Contents of my presentation

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

THESIS PROPOSAL. christopher m. shipper

Section 1 - Introduction 1.1 Introduction Welcome to Fox Blocks. You have made an excellent decision to use Fox Blocks Insulated Concrete Forms (ICFs)

Rapid Clamp EUROBUYSERVICES EBS

FALSEWORK SOLUTIONS: SLAB SHORING SYSTEM - ROYALFRAME50 SERIES

Technical Report #2. Matthew R Peyton

These systems are evaluated on the basis of serviceability issues such as:

Components. Jacks 2 Leg Assembly. Jacks. Typical Frame

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #2 October 31,

HANDSET WALL FORM. Handset Wall Form. Quick Assembly - can be built using only a hammer. Reduced weight increases productivity

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

APPLICATION GUIDE PERFORM WITH PRECISION

Structural Tech Report #2 Pro Con Structural Study of Alternate Floor Systems

181 Fremont San Francisco, CA. Tech Report 3 10/17/2014. PSUAE Structural Option Advisor: Dr. Thomas Boothby

MID-RISE DESIGN & CONSTRUCTION

FDA OC/ORA Office Building

CC-4 Aluminium Slab Formwork

Analysis 2 Pre-fabricated Metal Stud Crete Panels-Structural Breadth

MANUFACTURER S SPECIFICATIONS Section LIME CONCRETE. A. This section describes the requirements for floors and slabs on grade.

BY DAYTON SUPERIOR. Max-A-Form FORMING SYSTEM

Thesis Proposal Structural Redesign / Cost, Schedule and Coordination Analysis / Architectural Impact

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION

CC-4 Aluminium Slab Formwork

Superior strength, flexibility, safety and value.

SPECIAL INSPECTION AGREEMENT

Steel Forming System BROCHURE. A durable, all-steel forming system that is ideal for pier caps and self-spanning applications.

Pro-Con Structural Study for Alternative Floor Systems October 27, 2004

Nail Laminated Timber

Flexible Building Design

Garage Beam System DAYTONSUPERIOR.COM FORMING. For Post-Tensioned Beam and Slab Parking Structures

Structural Breadth Study

151 First Side. Technical Assignment 2 November 16 th, William J. Buchko. AE 481w Senior Thesis The Pennsylvania State University

This report investigates alternative floor systems for the building. A brief summary of each system is as follows:

Division 03 - Concrete Section New Westminister Multi-Use Civic Facility & Office Building Project No Page 1

NEVI Light modular formwork

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

THE STUDY ON PRuDuLIluN AN L) S1KtNU1H OF ARCH PAN AS PERMANENT FORMWORK FOR FLOOR SLABS ZAID FIKRI BIN ZAINAL RASHID

Rapid Ply versatile, modular formwork

Structural Technical Report #2 Pro/Con Study of Alternate Floor Systems

Temporary Structures. Form Materials and Accessories ATCE--II. Advanced Topics in Civil Engineering Form Materials and Accessories ATCE-II

Jonathan R. Torch Technical Report 2 Columbia University. Technical Report 2. Pro-Con Structural Study of Alternate Floor Systems

THE CUPOLEX SOLUTION EXPANSIVE SOILS. www. cupolex.ca

BOX TYPE RCC BUILDINGS USING ALUMINIUM WALL FORMS UPCOMING TREND FOR HIGH RISE BUILDINGS

CHAPTER 7 STRUCTURAL SYSTEMS

Alisply Circular Headquarters - Spain Alsina USA - Chicago Alsina USA - Miami

Mansfield University Dormitories Mansfield, Pennsylvania

Statement of Special Inspections

Below-grade pours (such as foundations) can be done out of the chute of the concrete truck or conveyer, however using a pump is best.

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

A.H. Harris & Sons, Inc. Formwork and Shoring Solutions

PLANNING DEPARTMENT 701 OCEAN STREET, 4 TH FLOOR, SANTA CRUZ, CA (831) FAX: (831)

EDGEPRO FORMWORK SYSTEM. Twice the strength of traditional material & 100% reusable Reduce project costs with this sustainable building solution.

Trump Taj Mahal Hotel

TECHNICAL REPORT II STRUCTURAL STUDY OF ALTERNATE FLOOR SYSTEMS

BROCHURE. Steel Forming System. A durable, all-steel forming system that is ideal for pier caps and self-spanning applications. DAYTONSUPERIOR.

Caitlin Ferrell Structural Option Dr. Boothby, AE Faculty Consultant. Erie Convention Center and Sheraton Hotel

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

Concrete Framing Systems - Walls and Columns

This section applies to the design and installation of cast-in-place concrete, shotcrete, precast concrete, and post-tensioned concrete.

British Columbia Carpenter Apprenticeship Program

Hershey Research Park Building One. Technical Report 2. Jonathan Krepps Structural Option Advisor: Dr. Hanagan 10/12/12

Eric Alwine Structural Option George Read Hall The University of Delaware Dr. Boothby Technical Assignment #2 October 31, 2005 EXECUTIVE SUMMARY:

North Shore at Canton Baltimore, MD Beau Menard Technical Report 1

MK SYSTEM. // Pieces that can be easily assembled with minimal tools. Numerous configurations with standard components

Aluma EasySet Continuing Innovation from Aluma S ystems

DORMITORY BUILDINGS C & D

SECTION CONCRETE FORMWORK

STEEL STRUCTURAL SYSTEMS

STRUCTURAL TECHNICAL REPORT 2

Transcription:

Alternate Formwork System Evaluation Executive Summary The current handset aluminum formwork system used in the Navy League Building s parking garage is a labor and material (plywood) intensive process. To determine a possible alternate, a variety of pre-manufactured systems were analyzed. The overall goal of this research was to determine if an alternate system could have a positive impact on the budget and sustainability aspects of the concrete formwork. Criteria such as engineering of the system, material costs, labor, local building codes, and reusability were used to determine an alternate. After selecting the Titan HV system, a budget was compiled to judge both systems. With the handset aluminum system providing cost savings and equal environmental impact as the Titan HV, it was concluded to be the most appropriate system for the Navy League Building s parking garage. Although the analysis did not find pre-manufactured formwork to be more beneficial, it reinforced that the standard handset aluminum system is the best choice for Navy League. 16

Research & Analysis Introduction Overview: Determining the best methods of building construction is a challenging aspect on any project. Considering this, the selection of the most appropriate formwork system is necessary for concrete installation. While many different systems may work, a system which is quickly and easily erected can provide benefits to the budget and sustainability aspects of a LEED rated project. In the case of the Navy League building, the viability of a pre-manufactured system for elevated slab placement will be analyzed. Focusing on the sub-grade garage slabs, the alternate system will be compared to the handset aluminum system actually used on site. The current system is a labor and material (plywood) intensive, process. To address these issues, the potential benefits of a pre-manufactured system are compared to benefits of the system as-built. Analysis Outline: The basic steps used to analyze the formwork systems are outlined below: Gathered detailed erection and production data on the current formwork system (from general contractor and concrete subcontractor) Researched pre-manufactured gang form systems Determined viability of possible alternates and selected appropriate system based on erection, material availability, and structural stability requirements Prepared budget for alternate system Compared alternate budget to original and selected system with greater cost / benefit ratio Goal: The overall goal of this research is to determine if an alternate system could have a positive impact on the budget and sustainability aspects of the concrete formwork. As cast in place concrete placement is one of the most expensive activities on the project, an alternate formwork system has the potential to reduce costs. A pre-manufactured system featuring reusable components would also reinforce the sustainable theme of the building. 17

Research & Analysis Introduction (continued) Images of the current handset aluminum formwork system 18

Available Formwork Systems The formwork systems listed below are currently available for rental or purchase through formwork distributors. These systems were examined in terms of their applicability for use in s parking garage. A basic overview, list of advantages, and product images are provided for each different system. Mid-State Filigree Systems (http://www.filigreeinc.com/) The Filigree system uses a combination of factory precast and an on-site cast in place topping to produce elevated slabs. Thin precast panels and trays containing the lower slab reinforcing are set in place on top of standard shoring. After installing further reinforcement and polystyrene foam void blocks, concrete is poured into the precast pieces, thus completing the slab. As listed on the manufacturer s website, advantages of the Filigree system include labor and time savings, as well as the claim that it is environmentally friendly. Although not specifically stated by the manufacturer, it is assumed that the time and labor savings are most easily achieved on a high-rise project using crews trained in the Filigree system s construction. Labor Savings: The prefabrication technology in Filigree reduces the need for field skilled and unskilled trades. Although all trades are represented, fewer are needed for each task with a reduction in payroll needs and enhanced cash flow. Time Savings: Filigree structures go up fast. High production rates of up to 50,000 sq.ft. per 5 day week can be achieved. Environmentally Friendly: Many trees are saved by the elimination of wood and plywood framing. Image of a Filigree beam & slab system 19

Available Formwork Systems (continued) Peri Skydeck Formwork System (http://www.peri.de/ww/en/pub/aktuelles/start.cfm) This modular system from Peri features aluminum-framed panels with integral faced plywood. Props fitted with special dropheads allow the panels to be removed while the props remain in place to act as reshores. According to the manufacturer, advantages of the Skydeck system include: Lightweight o The slab panels featuring the integral aluminum frame and plywood sheathing do not weigh more than 35 lbs. each Early striking o The dropheads on the props allow the slab panels to be removed and reused while the prop remains to support the curing concrete. Low maintenance o The props feature self-draining edges and a powder coated finish Release of panel Drophead 20

Available Formwork Systems (continued) Tabla by Gillespie Practical Technologies, Inc. (http://www.gillespietech.com/22.htm) The Tabla formwork system is comparable to Skydeck in terms of its components and operation. Aluminum-framed panels sheathed with plastic plywood rest on props with an integral drophead. After the slab is poured, the panels can be released and swung down to be removed. The posts remain as reshores. According to the manufacturer, some advantages of the Tabla system include: Fast erection & removal o 250 sq.ft. can be erected per man-hour and 400 sq.ft. can be dismantled per man-hour. Reusable o The deck panels are sheathed with plastic plywood which has a claim of 200 to 250 uses. Custom Details o The system has components which can accommodate many custom slab details such as beams and cantilever sections. Panel sections Drophead 21

Available Formwork Systems (continued) Titan HV Formwork System (http://www.titanformwork.com/titan/home.html) The Titan system is similar to both the Tabla and Skydeck systems in terms of operation and components. The formwork uses main and secondary aluminum beam sections, a reusable drophead, and plywood sheathing. After the slab is poured, the beams sections can be released by hitting a lever. As with the other systems, the posts remain to act as reshores. Some advantages of the Titan HV system include: Safe erection process o The post shores and beam sections can be assembled on the ground, making for a more safe and comfortable work environment. Custom-framed openings o The main beams of the system are designed to allow wood 4x4s in place of the secondary beams. The wood beams can be used to frame unusual slab designs and filler conditions. Quick-release dropheads o The dropheads of the system feature a quick-release mechanism allowing release via a single hammer stroke. Drophead System assembly 22

Slab Design Factors Determining which formwork systems adequately accommodate the structure s design is an initial step in the selection process. There are a variety of available systems that cater to specific slab designs. Considering this, inappropriate prefabricated systems should not be forced into use because of their cost or potential schedule and labor savings. As seen in the plan below, s garage is a two-way flat slab with average bay sizes between 20 x 30 and 30 x 30. The slab thickness varies from 8 12 and the average floor to floor height is approximately 9. The irregularshaped polygon outline of the building creates a challenge to formwork installation. If a pre-manufactured system is to be used, it must be adaptable to accommodate the angled slab edges. This characteristic, and other factors such as the slab s multiple elevation changes may limit the possible production efficiencies of the systems described in the previous section. First Floor Slab Framing Plan The parallelogram shape and multiple slab elevation changes pose a design challenge to standardized formwork systems 23

Slab Design Factors (Continued) First Floor Slab Detail The detail provided above of the garage s southwest corner show the angled exterior walls and slab elevation changes two elements which can slow formwork construction. Garage Slab Design Characteristics Slab Design Type Two-way flat slab Design Load 50 psf Concrete Strength 5,000 psi Slab Thickness 8 12 Floor to Floor Height 9-4 Average Column Size 2-0 x 2-0 Number of Levels (of elevated slab) 4 Area of Garage Elevated Slab 119,685 Sq. Ft. 24

Formwork System Selection There are many factors which must be considered to determine the most appropriate formwork system for. These factors include, but are not limited to, the design characteristics of the system itself, engineering of the system, material costs, labor, local building codes, and reusability. Design Characteristics To begin, the critical factor in selecting an alternate formwork system for the Navy League Building is its adaptability to the current structure s design. The parking garage is what is known as a cut-up design the basic outline of the structure is an irregular polygon while the slab itself features a variety of beam sizes and drop panels. The concrete subcontractor chose a standard system due to these irregularities. Use of standard metal formwork is also supported by the Interactive Horizontal Formwork Selection System by Hanna and Sanvido. This document confirms that a standard metal system is the most appropriate under the given conditions. However, it must be noted that many of the formwork systems described above were not yet available after the document was published. Considering that a pre-manufactured formwork system must be selected to suit the Navy League s structure, and not vice versa, the Filigree system can be eliminated as it does not correspond to the slab design. The garage was engineered as a cast in place two-way flat slab. The Filigree s combination of precast and cast in place components in addition to the foam void blocks would require a redesign of the slab and corresponding reinforcement. Despite the Filigree system s incompatibility, the remaining three systems, which are very similar in components and operation, can be adapted to the garage. All feature removable aluminum beams and post shores with integral drop heads. The Skydeck and Tabla systems both contain a possible difficulty in their sheathing. The Skydeck system uses faced plywood while Tabla uses plastic plywood both of which can be expensive to repair or replace if modified. Considering the risk of potential damages for these rented formwork systems, the Titan HV system, using standard plywood sheathing, stands out as a potential alternate. Engineering Given that the Titan HV formwork system may be used for the garage, it must be professionally engineered to accommodate the slab s design. Manufacturers, such as Titan, typically have in-house engineering staff to design layouts and provide logistical support. The cost of these support services provided by Titan are included in the rental 25

Formwork System Selection (Continued) cost of the formwork. Additional costs may be incurred to have the formwork design approved and stamped by a professional engineer in the state. As the Navy League s garage is of a complex design, the use of any formwork system would have to be certified by a P.E.. Material Costs While engineering may be one cost of formwork systems, the majority of formwork erection costs are from labor and the system materials. Contractors can elect to rent either of these formwork systems, or make the investment to purchase the system s components. For the Navy League, the concrete subcontractor would most likely opt to rent the Titan system and use it on a trial basis. As listed under Cost & Production Factors, average costs for material rental of the Titan HV system versus a standard system indicate the standard system is less expensive. Despite including labor savings of 25% for the Titan HV system, its material costs of $0.80 / Sq. Ft. / Month are a large source of the $56,224.00 cost difference. However, $56,224.00 is only a small fraction of the building s total cost of $28 million. The cost difference is not substantial enough to eliminate the Titan HV. Labor Before the concrete subcontractor selects a system like Titan HV, labor costs and productivity must be taken into account. The Titan system was designed so that two men could erect 3,000 5,000 sq.ft. per day of a typical slab. With faster erection times, along with the drophead posts eliminating reshores, systems like Titans can produce as much as 30% labor savings. However, labor savings claims may not account for the type of labor. The labor force used on the Navy League is familiar with the standard metal system. Furthermore, seasoned superintendents may be hesitant to use an new type of formwork. Given these conditions, making the switch to a new system would initially cause inefficiencies and reduce potential labor savings. Local Codes Despite all the factors associated with formwork selection, one that overrides the others are the local building codes. Many manufacturers advertise low costs under the assumption that the decking and beam sections can be removed the day after pouring a slab. On the other hand, one must consider that many building codes are designed around the use of standard formwork and construction. Typically, code inspectors require a formal stripping letter (usually three days after a pour) before the formwork system can be removed and reshores added. In the 26

Formwork System Selection (Continued) case of the Navy League Building, Arlington county relies on the engineer of record to approve alternate stripping and reshoring procedures for the formwork system. If approved by the structural engineer, the Titan HV system can be used as advertised, and thus reduce material costs. Reusability To reinforce the sustainability theme of the building, formwork reusability should be addressed. Both the Titan HV and the handset aluminum system are designed to use plywood sheathing. The system as-built used ¾ thick, 4 x8 sheets of FSC Certified plywood. On average, the contractor was able to reuse each sheet (or smaller pieces) up to three to four times before it became unusable. If selected for the project, the Titan HV would use the same type of plywood. Considering the sheathing material, the environmental impact due to wood consumption is assumed to be equal for both types of formwork. Cost & Production Factors Formwork Cost & Production Factors Please see Estimating Notes * Standard System Titan HV System Average Framing Material Unit Cost $0.50 / Sq. Ft. / Month $0.80 / Sq. Ft. / Month (not including sheathing) 1 Sheathing Unit Cost 2 $1.19 / Sq. Ft. $1.19 / Sq. Ft. Average Labor Savings 3 --- Up to 30% Formwork Construction Labor Unit Cost 4 $2.80 / Sq. Ft. $2.10 / Sq. Ft. Stripping & Reshoring Labor Unit Cost 4 $0.72 / Sq. Ft. $0.54 / Sq. Ft. Average Framing Total (not including sheathing) 5 $269,244 $430,791 Sheathing Total $54,598 $54,598 Formwork Construction Labor Total 4 $335,118 $251,339 27

Formwork Cost & Production Factors Cost & Production Factors (Continued) Please see Estimating Notes * Standard System Titan HV System Stripping & Reshoring Labor Total 4 $86,174.00 $64,630.00 Overall Material & Labor Total 6 $745,134.00 $801,358.00 Overall Cost Difference $56,224.00 in favor of the Standard System Estimating Notes: 1) Framing material cost data for the Standard System was obtained from a Washington D.C. area concrete contractor. Framing material rental cost data of the Titan HV System was obtained from the supplier. 2) Amount of sheathing required: [ 119,685 Sq. Ft. (total area) / 3 reuses] X 1.15 (waste factor) = 45,880 Sq. Ft. 3) Possible labor savings of up to 30% as advertised by manufacturer. Labor savings of 25% were used as conservative estimate in calculations. 4) Formwork construction and stripping & reshoring labor cost data for Standard System was obtained from a Washington D.C. area concrete contractor. Labor cost data for the Titan HV System was obtained from the Standard System s labor costs minus 25% in labor savings. 5) Material totals based off of 89,748 Sq. Ft. (approximately two entire levels) of framing needed during a 6 month construction period. 6) Overall material and labor totals based off of total elevated slab area; 119,685 Sq. Ft. Conclusion Considering the various factors used when selecting a formwork system, the pros and cons of the Titan HV system and handset aluminum system appear to balance. With the handset aluminum system providing a possible savings of over $56,000, it was concluded to be the most appropriate and most reliable system for the Navy League Building s parking garage. 28

Conclusion (Continued) While the Titan system may indeed produce labor savings, the lack of crews experienced with its installation indicate that a standard system is a conservative choice. Other than labor issues, another major factor is the garage s unusual design. The Titan HV may require modifications and custom-framed sections to conform to the irregular polygon shape of the building. The standard handset aluminum formwork system is more adaptable to the building and more compatible with the available labor force. In addition to labor issues, the environmental impact of each system was considered. Given that both systems accommodate plywood sheathing, both would require equal amounts of wood. Thus, the environmental impact of the standard system is equal to that of Titan HV. Although the analysis did not find pre-manufactured formwork to be more beneficial, it reinforced that the standard handset aluminum system is the best choice for Navy League. 29