Environmental. Environmental Permits (EP) are required to operate an energy from waste facility within England and Wales. Guide page 32.

Thermal Treatment. For more information, contact us: E :

Viridor (Cardiff Energy Recovery Facility) Substantial Variation

Cory Riverside Energy. Riverside Resource Recovery Facility

Cory Environmental. Riverside Resource Recovery Facility

PROPOSED ENERGY RECOVERY FACILITY Whistleberry Road, Hamilton

Chapter Five Waste Processing, Treatment and Recycling Joe Green Dr Chris Wooldridge Cardiff University

Fuel preparation Phil White, MCIWM

Annual Performance Report 2007

Cory Environmental. Riverside Resource Recovery Facility

a long-term sustainable solution for waste

STUDY TOUR OF SELECTED GERMAN WASTE PROCESSING PLANTS

DERL Overview 3 January DERL Overview. January 2011 DERL - 1 -

Energy from waste. Commercially proven energy recovery

Sheffield s Energy Recovery Facility

HOW PYROLYSIS WASTE TO ENERGY WORKS

MARSS Workshop. Prof. Dr. Ing. Thomas Pretz

Internet Publication Plan. For the proposed public website for Metro Vancouver s Waste-to- Energy Facility

This is a draft revision of the briefing, and any comments are welcome please them to Becky Slater on

1/14/2017. Treatment options: thermal EST 3201 Waste Management. Chapter outline. Main objectives of treatment. Chapter References

Borregaard Case Study. Sarpsborg I & II

Pyrolysis is the thermal degradation of residual municipal waste in the absence of air to produce a solid fraction and syngas.

Introduction: Thermal treatment

Welcome To Our Exhibition

DUDLEY ENERGY FROM WASTE PLANT. PERMIT No AP3435SD WASTE INCINERATION DIRECTIVE ANNUAL REPORT

DUDLEY ENERGY FROM WASTE PLANT. PERMIT No AP3435SD WASTE INCINERATION DIRECTIVE ANNUAL REPORT

Annual WFAS summary data tables are also available to download in Excel format on SEPA's web site.

CEWEP Country Report 2016

WOLVERHAMPTON ENERGY FROM WASTE PLANT. PERMIT No AP3835SM WASTE INCINERATION DIRECTIVE ANNUAL REPORT

WOLVERHAMPTON ENERGY FROM WASTE PLANT. PERMIT No AP3835SM WASTE INCINERATION DIRECTIVE ANNUAL REPORT

EfW Outputs. Guidance on the management of energy outputs and residues including air pollution control residues and incinerator bottom ash

International Experience: MSW Solutions for Urban Centres in India Waste-to-Energy Options

Official Journal of the European Union

Debnath Pal Process Director Peter Brennan Project Director. Advanced Thermal Treatment; Technology Challenges Dr. Ben Herbert R&D Manager

BFB (bubbling fluidized bed) Power Plants (CHP) Fuel: RDF or Biomass CHP

Incineration (energy recovery through complete oxidation) Mass Burn Refuse Derived Fuel Pyrolysis Gasification

Welcome to the H1 Software

GIZ Support to Ministry of Urban Development Training on Preparation of City Sanitation Plan Part III State of Telangana

Chapter 13. Thermal Conversion Technologies. Fundamentals of Thermal Processing

Greatmoor Energy from Waste Facility. Carbon Footprint Assessment

Viridor Energy from Waste Facility. Environmental Statement Non-Technical Summary

WESTINGHOUSE PLASMA GASIFICATION. Hazardous Waste Management

Re-use of waste Recycling of waste Recovery of waste Use of waste as source of energy Incineration without energy recovery

Preparation of City Sanitation Plan Part III. Session 2: Technical Options for CSPs

Government Decree on Waste Incineration (151/2013; amendments up to 1303/2015 included)

RDF: Alternative Fuel tailor-made from Waste

Standard rules SR2012 No13 Treatment of Incinerator Bottom Ash (IBA)

Covanta Durham York Renewable Energy Limited Partnership. Acceptance Test Report. Executive Summary

The following documentation was tabled:

GLASGOW & CLYDE VALLEY AREA WASTE PLAN REVIEW WASTE MANAGEMENT OPTIONS FOR NORTH AND SOUTH LANARKSHIRE COUNCILS

SAMPLE APPROVAL ABC REGULATOR. ENVIRONMENTAL PROTECTION AND ENHANCEMENT ACT R.S.A. 2000, c.e-12, as amended. January 02, 2018.

Waste Combustion or Gasification: Comparing Apples with Apples?

City of Sydney Gasification Project

CARLOW COUNTY COUNCIL GUIDANCE NOTE FOR APPLICANT AIR LICENCE

Duty of Care and the Journey towards Zero Waste to Landfill

metrovancouver SERVICES AND SOLUTIONS FOR A LIVABLE REGION

Waste-To-Energy New Technologies

Form PPC1 Part B : Application for a permit. B1 About the installation

New PRTR-data 2015 in thru.de

PERMIT GVA1O6G. Houweling Nurseries Ltd. located at th Street, Delta, BC V4L 2N7

Which Technologies. for SWM Treatment? By Eng. Anis ISMAIL Senior Environment and Solid Waste Specialist

Biomass CO2: * (carbon-neutral CO2) (renewable carbon to total carbon)

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT Air Division INSTRUCTIONS FOR COMPLETION OF DATA SHEET FOR WASTE DISPOSAL

Westinghouse Plasma Gasification is the Next Generation of Energy from Waste Technology. USEA Annual Meeting May 30, 2013 Washington, DC

TAMPERE WASTE-TO-ENERGY PLANT

Ottawa IWMMP Phase 2 Report on System Options for the Longer Term

Technology Fact Sheet Mechanical-biological treatment (MBT) i

Hitachi Zosen Inova. 13 th Symposium on Waste Management- 2014, Zagreb

Annual household waste summary data tables are also available to download in Excel format on SEPA's web site.

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.

Smart CHP from Biomass and Waste

EVALUATION OF AN INTEGRATED BIOMASS GASIFICATION/FUEL CELL POWER PLANT

Official Journal of the European Union L 181/65

STOKE ON TRENT ENERGY FROM WASTE PLANT. PERMIT No QP3234SX WASTE INCINERATION DIRECTIVE ANNUAL REPORT

Waste treatment technologies I

CIRCULAR ECONOMY IN LAHTI REGION

OUTOTEC ENERGY SOLUTIONS BENEFITS

The applicant has estimated a total of vehicle movements per day.

metrovancouver SERVICES AND SOLUTIONS FOR A LIVABLE REGION

ENVIRONMENTAL PROTECTION ACT AIR QUALITY REGULATIONS

Non-Technical Summary

FACILITY PROFILE J. D. IRVING, LIMITED - LAKE UTOPIA PAPER

COMMISSIONING REPORT 2011

POZP 8 EN Incineration. Combustion Flares Combustion units Catalytic VOC oxidation Incineration of Hazard materials Vent gas cleaning Summary

12 WASTE. Introduction. Review of proposed development

VOLUME IV DESIGN AND OPERATIONS REPORT CAPITAL REGION RESOURCE RECOVERY CENTRE

3 DEVELOPMENT PROPOSALS

Guidance on use of Disposal and Recovery Codes (Waste Management Act, 1996 as amended)

WTERT (Greece and U.S.) PARTICIPATION IN ISWA- APESB 2009 WORLD CONGRESS: Turning Waste into Ideas (Oct 12-15, Lisbon, Portugal)

Pyrolysis and Gasification Appendices

The DGA MBT Mechanical Bio-Treatment System

DEVELOPMENT OF A SUSTAINABLE ENERGY PLANT. KEMSLEY PAPER MILL, SITTINGBOURNE, KENT ST REGIS PAPER COMPANY LIMITED & E.ON ENERGY FROM WASTE UK LIMITED

Section VI. Guidance/guidelines by source category: Source categories in Part III of Annex C

MATERIALS RECOVERY & RDF PRODUCTION OVERVIEW

CH-13 Applicability Of State Rules Air Quality Permit Program

GASIFICATION THE WASTE-TO-ENERGY SOLUTION SYNGAS WASTE STEAM CONSUMER PRODUCTS TRANSPORTATION FUELS HYDROGEN FOR OIL REFINING FERTILIZERS CHEMICALS

Transcription:

LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 1

LEVENSEAT GASIFICATION PLANT NON-TECHNICAL SUMMARY Document Production & Approval Record ISSUE NO. 2 NAME SIGNATURE POSITION DATE Prepared by: Iain Topliss Principal Consultant 23 December 2014 Checked by: Stephen Othen Technical Director 23 December 2014 Document Revision Record ISSUE NO. DATE DETAILS OF REVISIONS 1 24 Nov 2014 First issue 2 3 4 5 6 7 2014 Fichtner Consulting Engineers. All rights reserved. This report and its accompanying documents contain information which is confidential and is intended only for the use of Levenseat. If you are not one of the intended recipients any disclosure, copying, distribution or action taken in reliance on the contents of the information is strictly prohibited. Unless expressly agreed, any reproduction of material from this report must be requested and authorised in writing from Fichtner Consulting Engineers. Authorised reproduction of material must include all copyright and proprietary notices in the same form and manner as the original, and must not be modified in any way. Acknowledgement of the source of the material must also be included in all references. S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 2

TABLE OF CONTENTS TABLE OF CONTENTS... 3 1 Introduction... 4 1.1 The Applicant... 4 1.2 The Application... 4 1.3 The Site... 4 2 Details of the Amendments to the Levenseat Facility... 5 2.1 The New Facilities... 6 2.1.1 MRF... 6 2.1.2 Gasification Facility... 6 2.2 Emissions... 6 2.2.1 Emissions to Air... 6 2.2.2 Emissions to Water... 7 2.3 Monitoring... 7 2.4 Management... 7 S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 3

1 INTRODUCTION 1.1 The Applicant Levenseat Ltd (Levenseat) is a waste management company which has been engaged in the waste management industry since 1986. Levenseat operate both landfill and recycling operations. Levenseat currently handle approximately 200,000 tonnes per year of wastes including household, commercial, industrial, inert and organic wastes. The company currently operates from 3 sites: Muldron Landfill (Restoration Phase), Torphin Quarry Restoration (a landfill for inert material only plus treatment of contaminated soils) and the Levenseat Waste Management Site. The Levenseat Waste Management Site comprises a fully engineered 2 million cubic meter landfill (non-hazardous wastes) and a five hectare materials recycling facility. Levenseat are committed to on-going enhancement of their facilities and improvement of the service they provide to both private sector customers and local authorities. Levenseat pride themselves on their innovative and environmentally sympathetic approach to waste management. 1.2 The Application The Levenseat Site is currently regulated under an existing pollution prevention and control (PPC) permit (Reference: PPC/E/20001 granted on 31 Jul 2009). Levenseat is proposing to make a number of changes to the Levenseat Site. To be able to operate the proposed plant, a variation to the PPC permit will be required from SEPA. This document is a Non-Technical Summary of the information submitted in support of the PPC application. 1.3 The Site Levenseat is located on the west side of the A706, 2km north of Forth and 2km south of the junction with the A71 at Breich. The site entrance is just within West Lothian on the border with South Lanarkshire. The site is located approximately 3km south of Fauldhouse. The existing landfill site extends to some 10 hectares and is located in a former sandstone quarry and accessed from the A706 along a tarmac roadway to the south-east corner of the site. The site is perched at the top of the north facing hillside of Leven Seat Hill. Elevations on the site range from 350m AOD to 320m AOD and are highly variable due to the current use of the site, particularly within the landfill area. In general however, the site falls towards the north. The access road off the A706 is located on the opposite side of the hill and therefore falls away from the site in a south-easterly direction to an approximate elevation of 328m AOD. The Levenseat site is a well-established fully integrated waste management facility that offers a broad spectrum of waste handling, sorting and recycling facilities. S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 4

2 DETAILS OF THE AMENDMENTS TO THE LEVENSEAT FACILITY Levenseat is proposing to make a number of changes to the Levenseat Site. The New Activities and Directly Associated Activities covered by this application include: (1) a Gasification plant of one gasification line combusting RDF from the fuel storage area; (2) electricity generation and export to the National Grid; (3) production of inert bottom ash material that will be transferred off-site for recovery/disposal; (4) generation of an air pollution control residue that will be transferred to a suitably licensed hazardous waste facility for disposal; and (5) an increase in the overall tonnage of wastes to be received at the site from 150,000 tonnes per annum, as stated in the existing PPC permit, to 400,000 tonnes per annum, as per the planning permission. The following table lists the regulated and directly associated activities. Table 2.1: Scheduled and Directly Associated Activities Type of Activity Schedule Activity Description of Activity Installation 5.4 Part A b) ii) Operation of a materials recycling facility to process the incoming waste to recover recyclates from the incoming waste and to produce an RDF which is suitable to be processed in a close coupled gasification plant. Installation 5.1 Part A b) Directly Associated Activities Directly Associated Activities Directly Associated Activities The waste incineration of RDF in a gasification plant with an aggregated nominal design capacity of 12.9 tonnes per hour. The export of electricity to the national grid. Standby electrical generation to provide electrical power to the plant in the event of an interruption in the supply. Levenseat understands that, due to the extent of the proposed changes, these are considered to be a change in operation, as defined in RGN8. A Substantial Change as stated within Part 1 General, Regulation (2) paragraph (1) of the Pollution Prevention Regulations (2012) is defined as follows: a change in operation which SEPA considers may have a significant negative effect on human health or the environment, or which in itself constitutes the carrying out of an activity described in Part 1 of Schedules 1 or 2 that exceeds any threshold capacity specified in those Schedules. The Pollution Prevention Regulations (2012) Part 2, Schedule 1, Chapter 5, Section 5.1 Part A (b) defines the threshold of installation activities for the incineration of non-hazardous waste as: Incineration of non-hazardous waste with the exception of waste which is biomass or animal carcasses in an incineration or co-incineration plant. S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 5

The Pollution Prevention Regulations (2012) Part 2, Schedule 1, Chapter 5, Section 5.4 Part A (b) ii) defines the threshold of installation activities for the pre-treatment of waste prior to incineration as: Recovery or a mix of recovery and disposal of non-hazardous waste at an installation with a capacity exceeding 75 tonnes per day by one or more of pretreatment of waste for incineration or co-incineration. Therefore, as the both of the additional activities proposed by this PPC permit variation introduce new Schedule 1 activities as stated in Part 2, Schedule 1, Chapter 5 of the Pollution Prevention Regulations (2012), the proposed variation is considered a Substantial Variation. 2.1 The New Facilities 2.1.1 MRF The MRF has been designed to process 42 tonnes per hour (TPH) of commercial and industrial (C&I) waste or municipal solid waste (MSW). The proposed plant will allow Levenseat to produce a high grade SRF fraction (to be baled and wrapped), along with an RDF fraction (to be sent to the gasification plant). The proposed system layout will also allow for the recovery and removal (through a combination of automatic and manual separation methods) of; wood, old corrugated card (OCC), ferrous metals, non-ferrous metals, mixed plastics and mixed paper. 2.1.2 Gasification Facility The gasification facility will comprise a fluidised bed close-coupled gasification plant that will convert Refuse Derived Fuel (RDF) - that will be delivered to the Levenseat Site preprepared - into low carbon electricity and heat. The nominal design capacity of the facility is 100,000 tonnes per annum, based on a mechanical throughput of 12.9 tonnes per hour of RDF with a net calorific value (NCV) of 13 MJ/kg. The gasification facility will consist of a single combustion line. The gasification facility will be designed to be able to accept RDF within a NCV design range of circa 10-17.5 MJ/kg. Fluctuations in the delivered RDF NCV may lead to variations in the waste throughput. The Facility has been designed to operate with maximum fuel flexibility in order to be able to receive as wide a range of WDF within an agreed specification as possible. Only RDF that has been processed on site to meet a pre-determined fuel composition range will be sourced for the Facility. The sources of the RDF will typically comprise Municipal Solid Waste (MSW) and Commercial and Industrial Waste. The gasification facility will generate up to 12.34 MW of gross electrical output and it will also be designed to export up to 12 MWth of heat to the MRF and to potential future heat users offsite. 2.2 Emissions 2.2.1 Emissions to Air Emissions to atmosphere from the gasification facility will be released via a 55 metre high stack. The proposed emissions to air from the gasification facility will comply with the emission limits required by Chapter 4 of the Industrial Emissions Directive (IED) and other relevant Air Quality Guidance. Emissions to atmosphere from the MRF will be released via a 13 metre high exhaust from the MRF dryer scrubbing units. S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 6

A detailed air quality assessment has been completed which is presented in Annex 5 of the full application. 2.2.2 Emissions to Water The arrangements for the discharge of emissions to water from the Levenseat site will not be amended through implementation of this variation. Discharges to water will be dealt with in the following ways: the site s existing connections to the surface water and landfill drainage systems will be utilised; run-off from roof and hardstanding areas will be kept separate from process effluents and discharged into the existing SUDS system for the site; surface water run-off from all hardstanding areas will pass through a compliant Class 1 Bypass Separator prior to being combined with run-off from roofs; and where practicable, process effluent from the Gasification plant will be recycled within the process. Foul drainage from welfare facilities, toilets and mess-rooms from MRF and gasification facilities will be collected in a septic tank prior to discharge into a swale which will be located around the perimeter of the MRF and gasification plant. 2.3 Monitoring The gasification facility will include a Continuous Emissions Monitoring System (CEMS) for the continuous monitoring of oxygen, carbon monoxide, hydrogen chloride, sulphur dioxide, nitrogen oxides, ammonia, volatile organic compounds (VOCs), and particulates in the flue gases in the stack. Other pollutants will be monitored by spot measurements at regular intervals. The data will be recorded and operators will be alerted if emissions to air approach authorised limits. The results of the monitoring will be reported to SEPA. Solid residues generated by the gasification plant will be sampled on a regular basis to assess bottom ash burnout and to monitor the levels of specified pollutants. There will be no emissions monitoring from the MRF. 2.4 Management There is an environmental management system for the Levenseat Site. This will be maintained and adapted to reflect the changes to the operation of the Levenseat Site. S1481-0320-0004IRT Levenseat Waste Management - Non-Technical Summary Page 7