Robinson Landing: Pre-Demo Meeting July 6, 2016

Similar documents
Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Robinson Landing Condominium Pre- Construction Meeting

Exhibit G. Construction Mitigation Plan

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

GENERAL NOTES REQUIRED NOTES ON ALL PLANS

SOIL MANAGEMENT PLAN

Orange County Central Utility Facility Upgrade IP

CITY OF LA QUINTA GENERAL NOTES GENERAL NOTES

COMMON WORK RESULTS FOR EXISTING CONDITIONS SCHEDULES FOR EXISTING CONDITIONS

TRAFFIC MANAGEMENT PLAN REQUIREMENTS FOR COMMERCIAL/LARGE DEVELOPMENT SITES

Constructability Guidelines

Final Mitigated Negative Declaration. Mixed Use Office District 65-X Height and Bulk District Fax:

Section XXV Preconstruction Assessments and Damage Mitigation Procedures

1993 Specifications CSJ SPECIAL SPECIFICATION ITEM 4417 DEWATERING IN CONTAMINATED GROUNDWATER

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE

It is the CONTRACTORS RESPONSIBILITY to use OSHA approved shoring

CONTAMINATED MEDIA MANAGEMENT PLAN MIDLAND MARKET RAIL YARD KLAMATH FALLS, OREGON DEQ ECSI SITE #1732 MAY 4, 2009 FOR BNSF RAILWAY COMPANY

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014

Public Open House. Proposed Liberty Village Natural Gas Pipeline Project. Please sign-in at the registration table upon arrival

Town of Friday Harbor PO Box 219 / Friday Harbor / WA / (360) / fax (360) /

BARRY S CORNER. Draft Construction Management Plan

EXECUTIVE SUMMARY. The following is our conclusions of the environmental issues at the Site based on our investigations:

811 Emerson St. - Demolition & Site Prep

PLAN CHECK GUIDELINES MULTI-FAMILY/COMMERCIAL

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

3.7 GROUNDWATER AND SOILS Introduction Environmental Setting Applicable Regulations Impacts and Mitigation Measures

Attachment 1 Findings and Conditions

OVERVIEW SCOPE OF WORK (SOW)

Review of Plans and Specs from a Constructability Perspective

STREET ADDRESS OF EVENT: Description of Event:

Current Hunters Point Projects and Dust Mitigation Practices. Hunters Point Shipyard Community Meeting April 14, 2009

DIVISION 02 SELECTIVE DEMOLITION

Guidance for Filling Out An Application for an Earth Moving Permit / Dust Control Plan. Section 1 Applicant Information

8.0 MITIGATION MONITORING AND REPORTING PROGRAM

ARCHITECTUS FEBRUARY 2010

Guidance for Filling Out An Application for an Earth Moving Permit / Dust Control Plan. Section 1 Applicant Information

Delaware Street

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

AGENDA REPORT. To: Attachments: 1. Site Location and Outreach Map 2. Recommended Permit Conditions 3. Fencing Location

APPLICATION FOR RIGHT OF WAY PERMIT

Q. CONSTRUCTION IMPACTS

SPECIAL PROVISION Control of Materials

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

Columbia, Missouri, Manufactured Gas Plant Project Fact Sheet: August 2013

El Dorado Avenue

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

KABA DEMOLITION INFORMATION PACKET

Jobsite Specifications The A standard provides jobsite specifications for each of the following hazards:

FACTS ABOUT: Former GE Power Systems Apparatus Service Center (Voluntary Cleanup Program) Site Location

SECTION TEMPORARY ENVIRONMENTAL CONTROLS

B. DESCRIPTION OF CONSTRUCTION ACTIVITIES

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Property and Public Protection Plan

CITY OF SOUTH LAKE TAHOE APPLICATION FOR ENCROACHMENT, EXCAVATION and GRADING WITHIN THE CITY RIGHT OF WAY

REQUEST FOR TENDER - SERVICES RFT HOUSE DEMOLITION 7958 BEAVERDAMS RD., NIAGARA FALLS, ON.

Appendix H Mitigation Monitoring Plan

FINDING OF NO SIGNIFICANT IMPACT

Construction Requirements

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/

Excavation Safety Program

Aztec Substation. Demolition Specifications. May 13, 2016

Delaware Street

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

COUNTY OF SUTTER ENCROACHMENT PERMIT

SECTION UNDERGROUND STORAGE TANK REMOVAL

36 JASPER THPMAS ROAD CRAWFORDVILLE, FL.

Oklahoma Underground Facilities Damage Prevention Act

STAFF REPORT. HEARING DATE: September 29, 2010 Planning Commission Jana Fox, Assistant Planner Beirut Lounge Extended Hours of Operation (CU )

AM-PR-003 Construction Environmental Management Plan (C-EMP)

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

Status Update of the D.C. United Soccer Stadium Construction Thursday, September 8, 2016

Guidance for Filling Out An Application for an Earth Moving Permit / Dust Control Plan. Section 1 Applicant Information

CORNERSTONE RIVER VALLEY VILLAGE FILING NO. 1 STORMWATER MANAGEMENT PLAN

Greene County Demolition and Clean-Up Plan for FEMA Flood Buy Out Properties NYCDEP Properties

LAND DISTURBANCE PERMIT

SECTION 503 TEMPORARY PAVEMENT RESTORATION

Updated/Draft Analysis of Brownfields Cleanup Alternatives Former Birdseye

SECTION TRAFFIC REGULATIONS

The Corporation of The City of London

EROSION CONTROL AND GRADING PERMIT APPLICATION

3.0 Crane Heavy Lift Service General Requirements

V. MITIGATION MONITORING PLAN

A D M I N I S T R A T I V E U S E P E R M I T

PERMITTED USES: Within the MX Mixed Use District the following uses are permitted:

Remediation Approach. W-3839 July 6, 2009

PERMIT COVER PAGE. Site Address. Other. Other. Other

Introduction to Brownfields: Site Assessment and Cleanup

Environmental Guidelines for Construction Sites

SP Old Florida Investment Resources, LLC SMR Aggregates SR 64 Borrow Pit (DTS # )

Charter Township of Garfield Grand Traverse County

STATE OF NEW JERSEY DEPARTMENT OF ENVIRONMENTAL PROTECTION DIVISION OF COASTAL ENGINEERING

4.0 CONSTRUCTION METHODS AND ACTIVITIES

Demolition Information Packet

ROAD CUT PERMIT APPLICATION & INSTRUCTIONS

Jonathan Lange, Planner Community Development Department

CHAPTER MANUFACTURED HOME PARKS

Introduction to Brownfields: Site Assessment and Cleanup

Transcription:

Robinson Landing: Pre-Demo Meeting July 6, 2016

Table of Contents 1. Team Introductions 2. Project Overview 3. Phase I Activities Schedule Buildings for Demolition 226 Strand Demolition Cut & Cap of Utilities Mass Grading By Barge Utility Relocation Archeology Raising Duke Street and Strand Street 4. Environmental Findings Health & Safety Plan 5. Project Operations On Site Parking Haul Routes Pedestrian Circulation Traffic Control Work Hours Building Surveys 6. Closing Remarks Robinson Landing: Pre-Demo Meeting 2

Team Introduction

Team Introduction Adam Hayes, Sr. Director of Engineering, EYA LLC ahayes@eya.com 301-634-8653 Rex Muller, Project Manager, EYA LLC rmuller@eya.com 571-220-7678 Rob Wilson, Project Manager, Aceco rwilson@acecoworld.com 301-440-0718 Mike Johnson, ECS Inc., Sr. Environmental Project Manager mjohnson@ecslimited.com 703-471-8400 Robinson Landing: Pre-Demo Meeting 4

Communication Plan Project Website robinsonlanding.com Construction Updates webpage June 15 Certified Letter to Adjacent Property Owners and June 24 Meeting Notice Email blasts 1 st Notification sent last week Register to receive email updates on Construction Updates webpage Presentation slides Posted on City Website and Project Website City Ad Hoc Monitoring Group on Waterfront Construction Monthly meetings Project Contacts Adam Hayes ahayes@eya.com 301-634-8653 Rex Muller rmuller@eya.com 571-220-7678 2 nd Community Meeting Prior to Construction Activities Robinson Landing: Pre-Demo Meeting 5

Project Overview

Site Plan Robinson Landing: Pre-Demo Meeting 7

Aerial View Robinson Landing: Pre-Demo Meeting 8

Summary Schedule July 2016: Begin demolition Fall 2016: Import fill by barge Winter/Spring 2016/2017: Archeological work Spring/Summer 2017: Excavation/export by barge Summer 2017 Fall 2019: Construction phase Summer 2019: Robinson Landing opens to the public Robinson Landing: Pre-Demo Meeting 9

Phase I Activities

Phase I Schedule 1. DSUP #2014-0006, #2014-0012, #2014-0013, #2014-0014, #2014-0 102 Approved April 2015 2. Approved Special Use Permit #2014-0006 December 2015 3. Demolition and Grading Plan GRD2015-0039 Approved December 2016 4. Permit DEM2016-00001 and DEM2016-00002 Application made January 2016 5. Rodent Abatement Program started January 2016 6. Cut and Cap of existing gas services June 29-July 8 7. Cut and cap of existing water and sanitary services on Strand, Duke and Wolfe July 11-July 29 8. Pre-demolition abatement within the warehouses. July 2-July 18 9. Preconstruction Meeting with City July 15-July 22 10. Above Ground Storage Tanks (AST s) and Underground Storage Tanks (UST s) removed July 1-July 31 11. Installation of sediment controls July 22-July 29 12. Demolition of the existing structures July 29-August 26 13. Mass import by barge for FEMA Grading September-October 2016 14. Archeological Evaluations November-May 2017 15. Remapping of floodplain by FEMA October 2016-April 2017 16. Overhead to underground utility relocation September-December 2016 17. Water and Sanitary Sewer installation October 2016- January 2017 18. Raise Duke and Strand Intersection January- March 2017 19. Construct and Open Sales Center January-April 1, 2017 Robinson Landing: Pre-Demo Meeting 11

Buildings for Demolition 7/29-8/26 Demolition of 2 and 3A Duke Street Warehouses and 226 Strand Street (in yellow), excluding 2 Duke Street Historic Office Building (in blue). DEM2016-00001 for 226 Strand and DEM2016-00002 for 2 and 3A Duke Street were applied for in January 2016. Notices to adjacent residents were sent by certified mail on June 16 th after taking ownership of the property. Robinson Landing: Pre-Demo Meeting 12

226 Strand Demolition 7/29-8/26 The demolition of the old marine repair facility located at 226 Strand Street will be conducted under Permit DEM2016-00001. We will comply with the conditions of BAR CASE #2015-0152 approval to demolish. Digital photographs, plans and interior and exterior elevations documenting the current building are being developed and a copy of the drawings and history report will be provided to Special Collections and Planning & Zoning. We will hold a pre-demolition meeting and subsequent meetings with staff and our consultant to identify 19 th century material that are deemed salvageable. All identified materials will be dismantled and delivered to a City designated location for future reuse in the waterfront park or civic building by the City. Robinson Landing: Pre-Demo Meeting 13

Cut & Cap Existing Utilities 6/29-7/29 Cut and Cap Existing Water, Sanitary, Gas, Power, Phone and Cable to the Existing Warehouses at 2 and 3A Duke Street and 226 Strand Street. Historic Office Building will temporarily be used as a field office and utilities will remain active. Robinson Landing: Pre-Demo Meeting 14

Mass Grading by Barge Sept.- Oct. 2016 Approximately 15,000CY of fill material will be brought to the site by barge. It is anticipated that four to five barge deliveries are required to bring the fill material in. Existing pilings will be removed adjacent to the pier and the barge will dock next to the pier using spud piles to anchor to the river bottom. The fill material will be transferred to the site and then distributed and compacted on site with machines and dump trucks. Robinson Landing: Pre-Demo Meeting 15

Mass Grading by Barge Robinson Landing: Pre-Demo Meeting 16

Mass Grading by Barge Mass Import of Fill Material in accordance with DSUP Conditions. Residential area of site will be graded to a 10.3 elevation and stabilized. Final grades will be surveyed, certified and submitted to the City of Alexandria for conformance with the approved Grading Plan and conditions of approval. Robinson Landing: Pre-Demo Meeting 17

Utility Relocation Sept. - Dec. 2016 Existing overhead power and communication lines adjacent to the properties Strand Street and Union Street will be relocated to an underground duct bank in the right of way. There will be temporary lane closures and sidewalk closures during this process. Some of the work will be performed by the utility company and their designated contractor. Robinson Landing: Pre-Demo Meeting 18

Archeology 11/16-5/17 The Scope of Work (SOW) for Archeological Evaluation was approved by the Alexandria Archeologist and includes a combination of monitoring, trenching of soils, striping of soil by backhoe and potentially shovel test holes to determine if significant archeological resources are present. All ground disturbing activities will be monitored by personnel approved by Alexandria Archeology. Evaluations will examine the stratigraphic profile to identify ca. 1749 shoreline, determine presence/absence of 18 th and 19 th century wharves and structures associated with the banking out process and determine presence/absence of foundations associated with 18 th and 19 th century residences and businesses. If resources are identified, additional scopes of work will be created which may include development of a Resource Management Plan. When the field work is completed an Archeological Evaluation Report will completed and submitted to the City. Robinson Landing: Pre-Demo Meeting 19

Raising Duke and Strand 1/17-3/17 The existing grade at the intersection of Duke Street and Strand Street will be raised approximately three feet to approximate elevation 9 at the intersection. The grading design of the roads and sidewalks were coordinated with the adjacent development team of the Indigo Hotel. We will continue to communicate with their team and T&ES to develop an agreeable strategy for scheduling the improvements to avoid unnecessary conflicts. We estimate work to commence after all underground utilities are completed and accepted. A combination of full depth restoration and milling and overlay of asphalt will occur in the location highlighted in the plan below. Robinson Landing: Pre-Demo Meeting 20

Environmental

Environmental Findings Hazardous Materials Friable and non-friable asbestos containing materials were identified in the Robinson Terminal buildings and in the Alexandria Marine building. Lead based paint was identified in the Robinson Terminal buildings and in the Alexandria Marine building. Soil and Groundwater Petroleum hydrocarbons, semi-volatile organic compounds (SVOCs) and metals were identified in the soil across the site from the surface to 10 feet below ground surface (bgs) at concentrations that exceeded their respective screening criteria. Petroleum hydrocarbons and polyaromatic hydrocarbons (PAHs) were detected in the groundwater across the site at concentrations that exceeded their respective screening criteria Robinson Landing: Pre-Demo Meeting 22

Health & Safety Plan A Health and Safety Plan (HASP) and a Soil and Groundwater Management Plan (SGWMP) has been established and approved to address procedures for archeological, construction, demolition or other activities where subsurface soil or groundwater contamination may be encountered during the course of activities at the site. Rex Muller will be our Site Safety Officer (SSO) and will have full responsibility to implement the HASP and to verify compliance with applicable OSHA, EPA and other environmental, health and safety guidance and regulations at the site. The SSO will provide or designate a person to provide Hazardous Awareness Training to all visitors and contractors entering suspected areas of contamination. A safety meeting will occur prior to beginning daily activities to discuss potential chemical, physical and environmental hazards and preventive safety measures. All materials removed from the site will be disposed of in accordance with all required local state and federal regulations. Air monitoring by a licensed industrial hygiene technician will be provided during abatement and demolition of the buildings. Robinson Landing: Pre-Demo Meeting 23

Health & Safety Plan Personnel and equipment decontamination stations will be made available by the general contractor. Workers will be required to remove and dispose of disposable coveralls or outerwear, wash off footwear, properly clean or dispose of gloves and wash face, arms and hands. Equipment that comes into contact with contaminated materials will be washed before leaving the site. If required, all wash water and disposable Personal Protective Equipment (PPE) will be containerized and properly disposed of in accordance with the Virginia Department of Environmental Quality (VDEQ) Waste Management Regulations. Construction workers will not be allowed to eat, drink or smoke in areas of the site where impacted materials are exposed. A worker break area will be established as needed. During all activities at the site where the soil will or may be disturbed, an ECS Environmental Technician will be onsite daily to screen the soils using a photoionization detector (PID) or other visual field-screening kit specific to the contaminants of potential concern (COPCs). Contaminated material produced as a result or the archaeological survey or other construction activities will be disposed of in accordance with the VDEQ Waste Management Regulations. Mass excavated materials will be loaded directly onto barges. If material is stockpiled, it will be covered with plastic or otherwise stabilized to prevent runoff. Robinson Landing: Pre-Demo Meeting 24

Health & Safety Plan For the installation of utility corridors in areas where impacted soils are encountered, the utility trenches will be over excavated unless the Environmental Technician has performed testing to document that the soils are not contaminated as required by the City of Alexandria. Engineering controls, such as sprayers or water trucks, will be used to prevent dust or visual emissions during the development process. Daily exposure monitoring for Volatile Organic Compounds (VOCs) will be performed using a PID by the Environmental Technician during soil excavation activities. If the concentration of VOCs is below the action limit of 25 parts-per-million (ppm), no action will be required. However, if VOCs exceed 25 ppm, Level C PPE will be required. In areas that will not be covered by the building or hardscape, two feet of clean soil will be placed on the surface to encapsulate the contaminated soil to prevent direct exposure to future occupants. If groundwater is encountered during the archaeological survey and/or mass excavation, it will either be pumped out of the trench, containerized and disposed of at an appropriate facility or will be discharged to the sewer system. A VPDES permit from VDEQ will have to be acquired before any water is discharged to the storm sewer. If contaminant concentrations exceed the VPDES permit limit, the water will need to be treated to reduce contaminant concentrations to acceptable levels prior to discharging to the storm sewer. Robinson Landing: Pre-Demo Meeting 25

Project Operations

Parking We will provide on site parking during first phase of construction activities. Workers will park behind the existing warehouses and at 226 Strand after demolition occurs. To the extent off-street parking is necessary, construction workers will all park off site without charge to the workers and with locational preference given to those who carpool. Construction workers shall not be permitted to park on the public streets. For the construction workers who use Metro, DASH, or another form of mass transit to the site, we will subsidize a minimum of 80% of the fees for mass transit. Robinson Landing: Pre-Demo Meeting 27

Haul Routes A Haul Permit will be obtained for removal of all materials related to the demolition of the buildings. Inbound traffic will use Franklin Street to Union Street and Outbound traffic will use Union St. to Gibbon Street. The Haul Route provided below is Draft and subject to change at the discretion of the City of Alexandria Department of Transportation and Environmental Services at Permit issuance. Robinson Landing: Pre-Demo Meeting 28

Pedestrian Circulation There will be temporary sidewalk closures along Duke, Union and Wolfe during certain times of the utility cut and cap process, overhead to underground utility improvements, and demolition. Prior to temporary closures we will obtain required permits and install traffic control devices to direct pedestrians to alternate sidewalks at intersections to the North and South of the property at locations to be discussed and approved by T&ES. Construction Fence currently located at the back of sidewalk will be moved to the curb line during the sidewalk closure period and returned to the back of sidewalk when the work is complete. Robinson Landing: Pre-Demo Meeting 29

Traffic Control We anticipate temporary lane closures during the Utility Cut and Caps and during the Overhead to Underground Utility Relocation scopes of work. A combination of traffic signs, flagging stations, barriers, arrow panels and other devices will be used to manage the vehicular maintenance of traffic. The Vehicular Traffic Management will be coordinated with the Pedestrian Traffic Management when sidewalk closures are also required. Travel lanes, parking and sidewalk closures on Duke and Strand will be coordinated with the development team at Carr Properties and with T&ES. Lane closures will be required during the raising of Duke St. and Strand St. and access through this area will be very limited. Robinson Landing: Pre-Demo Meeting 30

Traffic Control Robinson Landing: Pre-Demo Meeting 31

Work Hours All Construction Activities will comply with the Alexandria Noise Control Code Title 11, Chapter 5, which permits construction activities to occur Monday through Friday 7AM to 6PM and Saturdays from 9AM to 6PM. No construction activity will be permitted on Sundays. Pile driving is further restricted however it is not part of the anticipated Construction Activities. Robinson Landing: Pre-Demo Meeting 32

Pre-Construction Exterior & Interior Surveys The Building Monitoring Plan is a requirement described in Condition 76 of the DSUP. Implementation of the plan is not required until the garage and vertical construction. We are electing to offer and conduct Exterior and Interior Surveys of immediately adjacent properties during the Phase 1 Activities. Exterior- Conduct site observations and document the existing accessible exteriors of the buildings and ancillary structures. The exterior survey will be performed from ground level. The use of a telephoto lens will aid in the survey and documentation of higher portions of the buildings, as necessary. The survey of the buildings will be limited to the readily accessible areas only. Interior Building Surveys-Conduct site observations and document the existing accessible interior of the buildings. Interior and exterior crawl spaces and other areas which are obscured for reasons including but not limited to vehicles, equipment, stored materials, wall hangings, furniture, or other similar conditions which affect visibility are not considered accessible. All reports will be provided to the property owners at no charge. Robinson Landing: Pre-Demo Meeting 33

Crack Gauge Monitoring and Vibration Monitoring Crack Gauge Monitoring- For any cracks identified during the preconstruction surveys, install crack monitoring gauges on cracks. These gauges will be read with a caliper monthly. Vibration Monitoring- a written Structures Monitoring Plan (SMP) will be developed to further define the monitoring program and the potential impacts of vibrations transmitted to nearby receptors from construction activities. This plan will include the installation of seismographs which will obtain vibration measurements at the surrounding structures to determine whether the vibrations are below established safe thresholds. During construction, the seismographs will measure construction vibrations transmitted to representative structures adjacent to the site. The seismographs will be programmed to record in every minute of the day. Any vibrations that reach or exceed the vibration control threshold will trigger the unit and a two-second waveform event will be recorded for further analysis. Each seismic station will be equipped with a cellular modem for communication. If vibrations reach or exceed established project thresholds, then a text message or email will be sent to alert designated project personnel. Robinson Landing: Pre-Demo Meeting 34