The prediction of some hull manufacturing parameters during early stages of ship design

Similar documents
Our Motto aims to be "NEW ZESCO" New Value Creater. Endless Innovation. Work with Passion for Stakeholders

NSWLC Shipyard Modernization Project. Bob Hillstrom, SMP Project Manager October 16, 2014

SMG. Smart Maritime Group. Ship Repair & Conversion

Lecture 3-1: Hull production - Product hierarchy and block division

Fatigue crack propagation analysis of ship hull welded components

EQUIPMENT DESIGN LECTURE TANKS, VESSELS & DRUMS - MECHANICAL DESIGN

STRUCTURAL AND ECONOMICAL OPTIMIZATION OF WELDED STEEL STORAGE TANKS

MODELLING AND OPTIMISATION OF PRODUCTION PROCESSES IN OVERHAUL ACTIVITIES

Contents EN 14015:2004 (E) page

Gantt chart analysis to improve shipbuilding panel line assembly

ISO Ships and marine technology Protective coatings and inspection method Part 3: Cargo oil tanks of crude oil tankers

COST ASSESSMENT AT CONCEPT STAGE DESIGN USING PARAMETRICALLY GENERATED PRODUCTION PRODUCT MODELS

Lecture 6-1: Outfitting

MANDATORY APPENDIX 2 RULES FOR BOLTED FLANGE CONNECTIONS WITH RING TYPE GASKETS

Preliminary Consequence Assessment on Harmonized CSR from Chinese Shipbuilding Industry

Hull Survey for New Construction

Introduction. Structures may be classified on the basis of materials used for construction, as follows: Steel structures. Aluminium structures

Fatigue tests of steel sandwich panel

Design Development of Corrugated Bulkheads

Parametric Cost Assessment of Concept Stage Designs

ClassNK Business Planning Department ACADEMY ClassNK Academy Center, South Asia and Oceania

Report Documentation Page

FATIGUE FAILURES IN INDUSTRY CASE STUDIES

EXPERIMENTAL INVESTIGATIONS ON FRICTION WELDING PROCESS FOR DISSIMILAR MATERIALS USING DESIGN OF EXPERIMENTS

Ship Design and Construction Training Module

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

WHITE PAPER. Integrated Design and Production Planning for Ship Block Assembly and Construction

This document is a preview generated by EVS

A SEMI-RIGOROUS APPROACH FOR INTERACTION BETWEEN LOCAL AND GLOBAL BUCKLING IN STEEL STRUCTURES

9/28/ :22 PM. Chapter 9. Welding and the Design of Permanent Joints. Dr. Mohammad Suliman Abuhaiba, PE

Figure 1 Example of HSS column splice

Load capacity rating of an existing curved steel box girder bridge through field test

Lecture 3-2: Hull production Steel processing methods

Hull Survey for New Construction

A Case Study of Shipbuilding Cost Accounting

HIERARCHICAL VALIDATION OF FEM MODELS

Further impact on Bulker design by the current draft of CSR-H

Consequence Assessment of Harmonized CSR

Chapter 2 The Structural Hot-Spot Stress Approach to Fatigue Analysis

Section A A: Slab & Beam Elevation

Smooth Material Flow by strengthening Production Engineering

A New Plate Buckling Design Formula (2nd Report)

ABS TECHNICAL PAPERS 2005 NON-LINEAR TIME DEPENDENT CORROSION WASTAGE OF DECK PLATES OF BALLAST AND CARGO TANKS OF TANKERS

THE COMMON STRUCTURAL RULES INITIAL DESIGNS AND FUTURE DEVELOPMENTS

09-05 Mean Stress Assessment in Fatigue Analysis and Design

Technological potential within the scope of prefabrication of steel structures for offshore wind energy

Shipyard Experience with Advanced Construction Approaches for Naval Nuclear Ships

IACS Common Structural Rules for Double Hull Oil Tankers, January Background Document

DIN EN : (E)

Ore Carriers Part 4, Chapter 11

CONTENTS. Foreword... xiii Statements of Policy... xv Personnel... xvii Organization of Section III... xxvii Summary of Changes...

COMPANIES PREQUALIFICATION APPLICATION

GUIDELINES FOR THE INFORMATION TO BE INCLUDED IN A SHIP CONSTRUCTION FILE

Statistical Techniques Useful for the Foundry Industry

Fatigue strength of knuckle joints - a key parameter in ship design D. Beghin Marine Division, Bureau Veritas, Paris, France

Civil Engineering Construction I (CBE5031)

Influence of corrosion-related degradation of mechanical properties of shipbuilding steel on collapse strength of plates and stiffened panels

Design of Catamaran Ship Main Deck and Bulkhead to Withstand the Crane Load

FIGURE 5-1 Types of joints. Cengage Learning Welding Joint Design & Welding Symbols Chapter #5

Class NK s Course of Action to Protective Coating Guidelines for Performance Standard for Protective Coating Contained in IMO Resolution MSC.

1.15 Chemical Tanker Longitudinal corrugated bulkhead (vertical type).

ASTM B363-06a Standard Specification for Seamless and Welded Unalloyed

Influence of Variation in Material Strength on Ultimate Strength of Stainless Steel Plates under In-Plane Bending and Compression

SPAR Scuttlebutt. models now provide automated estimates for nonrecurring

Effects of MIG process parameters on the geometry and dilution of the bead in the automatic surfacing

SAPP Simulation aided production planning at Flensburger

RULES FOR THE CLASSIFICATION OF SHIPS

Requirements for Use of Extremely Thick Steel Plates in Container Ships

Fatigue Testing and Life Estimates of Welded Flat Head Pressure Vessel Joints. Chris Hinnant Paulin Research Group Houston, TX

PO Box: 5881, Ajman United Arab Emirates. Website:

FACILITIES and INDUSTRIAL ENGINEERING EXECUTIVE SUMMARY

CNC PROFILING PLATE ROLLING SUBMERGED ARC WELDING

Copyright 2015 American Institute of Steel Construction. All rights reserved.

Transactions on Engineering Sciences vol 2, 1993 WIT Press, ISSN

DIVISION 34 TRANSPORTATION SECTION SPECIAL TRACKWORK ADDENDUM NO. 1

A Proposed S-N Curve for Welded Ship Structures

WORLDSKILLS STANDARD SPECIFICATION

Company Profile. Chemical & Cement Industry. Petroleum, Oil & Gas. Environmental Technologies. Power & Energy

Main Roads Standard Specification

SECTION METAL STAIRS

Leelachai M, Benson S, Dow RS. Progressive Collapse of Intact and Damaged Stiffened Panels.

ITEM 686 TRAFFIC SIGNAL POLE ASSEMBLIES (STEEL)

Analysis of Non Composite and Composite Space Frame for Varying Support Condition

Distortion Control in Thin Low Carbon Steel Plates Using Sequential Welding and Restraints

W-17 Clad Steel Plate

RULES. PUBLICATION No. 74/P PRINCIPLES FOR WELDING PROCEDURE QUALIFICATION TESTS March

Evaluation of Necessity and Usefulness of IMO PSPC - Performance Standard of Protective Coating

RULES FOR CLASSIFICATION Ships. Part 3 Hull Chapter 8 Buckling. Edition October 2015 DNV GL AS

Development of HighCRest Software for Ship Structure Verifications under CSR-H Requirements

Metal Fabricators. Phone DAKA (3252) Fax Serving the Construction Industry and Manufacturers Since 1977

CNC PROFILING PLATE ROLLING SUBMERGED ARC WELDING

SECTION METAL STAIRS

COASTAL BEND COLLEGE WELDING SYLLABUS (Revised 8/10)

HAT STIFFENED PLATES FOR SHIP BUILDING

71T1 - Gas Shielded Flux Cored Welding Wire Provides excellent performance in all position welding. Weld Metal - Chemistry

Abstract. 1 Introduction

Part 7: 1992 Specification for materials and workmanship Cold-formed

DIVISION 5 METALS SECTION STRUCTURAL STEEL

BMT FLEET TECHNOLOGY LIMITED 5383C.FR ABSTRACT This Ship Structure Committee project was developed to demonstrate the fracture susceptibility of a shi

Guidelines for the Construction of Pressure Vessel Type Tanks Intended for the Transportation of Anhydrous Ammonia at Ambient Temperatures

Transcription:

The prediction of some hull manufacturing parameters during early stages of ship design W.Ch^dzynski Szczecin Shipyard Design Office 71-637 Szczecin, Firlika20, Poland chadzynski. wojciech@sssa. com.pl Abstract Proposed paper is a short description of the activities taken to create the tools for the prediction of the hull manufacturing parameters at the early stage of ship designing. It includes the stages of steel preparation assembly and erection of the hull. The key characteristics of hull manufacturing process will be defined to allow the planning of the building. The relationships will be presented linking the basic ship parameters as known in early stages of design (type of the vessel, main dimensions, block coefficient) with those characteristics. The final remarks indicating the further topics development will conclude the paper. 1 Introduction The designing and engineering in modern shipbuilding is running under strong time pressure raised up by hard competition between particular shipyards with the purpose to obtain the order. The shipyards apprehend the designing as not only the spatial and functional ship identification, not only raw material and equipment specification, but also a complete package of bidding information including such topics as planned delivery date and production costs split into material, man-hours and others. To create such package of information under very general knowledge about the ship designed some specific tools are necessary. Those should allow to define the building strategy as well as some production planning parameters to estimate labour consumption, production capabilities utilisation, required areas under the roof and open air etc. Proposed paper is a short description of the activities taken to create such tools.

46 Marine Technology 2 The hull building cost estimation The hull building cost is the sum of material and personal costs. For this paper purposes the hull is understood as the steel structure of ship envelope. This steel was delivered to the yard, then cut, welded and mounted in panels and blocks and finally erected on the slipway or at the drydock, where the hull is built. The installation of hull equipment, fittings, opening closings, painting etc. is not considered as the part of the hull manufacturing, but only cutting, welding and erection of steel hull. The cost of material depends of the actual price of the steel and of the following factors: -cost of ordered steel (and indirectly of the steel hull weight), -assortment (plates, profiles, pipes, forgings, castings), -type of material (mild steel, high tensile steel, stainless steel, others). The estimation of the hull steel weight is a comprehensive problem of initial and basic ship design and will be not discussed in this paper. Personal costs depends of the hull worker average hour rate and the number of man/hours necessary for the processing of ordered steel into the hull. At the preliminary stage of the design the cost of the hull can be defined as the product of the cost of 1 ton of the steel hull and the hull weight. This cost of one ton of the hull is a function of the some number of variables such as hull form parameters, type of the vessel, and the productivity of hull manufacturing shop. This way of hull cost estimation is named as the Top-Down method and make use of primary design data i.e. steel hull weight, block coefficient, principal dimensions, vessel type. Insufficiency of this method depends on its high level of generalisation and lack of the possibility to estimate the impact of some manufacturing parameters ( for example - the length of welding connections) to the hull cost. The contrary to the Top-Down method is the analytical method called Bottom- Up method. This method decomposes the manufacturing process into the number of elementary activities related to the arbitrarily chosen part of the construction. As an example may serve the number of flat plates and straight frames, type of welding, plates thickness, flame cutting length - all for the predetermined shell plating panel. The work content is calculated separately for every activity and then summed up for the whole panel. The cost of the panel manufacturing is calculated in compliance with man/hour rate differentiation for particular activity. The results obtained with this method are generally more accurate, the method allows to analyse the impact of local hull geometry on the work content, but it needs substantially advanced stage of hull project and that is why this method is not suitable during initial stages of ship designing. In this paper an attempt is made to estimate some hull manufacturing process parameters at the moment, when the knowledge about the ship designed is limited to such data as the type, principal dimensions, block coefficient what usually occur during the acquisition and contractual design preparation. Those

Marine Technology 47 parameters can be used for the early estimation of hull work content and other planning activities. 3 The scope of the investigation The investigated manufacturing parameters are connected with three basic types of hull work planning i.e. -share of particular material assortment, -steel preparation (blasting, rolling, flame cutting, bending), -fabrication and assembling, -hull erection at the berth. Those include among others: material assortment and preparation: - total plates weight, - total profiles weight, - total number of plates including the breakdown into particular thicknesses, - share of curved plates in side and bottom shell, - length of straight line and curvilinear flame cutting, fabrication: - number of flat panels, - total butt welding length including the breakdown into particular groups, - total fillet welding length including the breakdown into particular groups, erection: - units or blocks average quantity, - units or blocks average weight. 4 Output data For 17 vessel types built during 1989-1998 years the manufacturing parameters were collected as recorded in hull workshop documents. Each type was represented by one vessel. It means that output data does not include the deviations which usually occur between particular vessels of given type. Those deviations can be the object of separate study. The set of data consists of 8 container vessels, 4 tankers and 5 bulk carriers. The bigger vessel of the set was 45000 DWT multipurpose bulk carrier, the smaller one - 6000 DWT chemical carrier. All vessels corresponds generally to the same level of manufacturing method, excluding one early built container vessel, which was in some cases omitted because its structural and manufacturing parameters as well as manufacturing method were outlying too strongly from the population. The size of particular type populations was rather unsatisfactory and the decision was made to consider all vessels as one population consisting of 16 (17) vessels of diverse types.

48 Marine Technology 5 The review of some obtained relationships. 1. steel material assortment 1.1 The weight of ordered steel [t] MS=32+1.116PK (1) 1.2 The weight of steel plates [t] MB =1.027 MS-015L(B+2H) (2) 1.3 The weight of profiles [t] MP = -0.16MS -20IB -0.446LBHCb+13.03BH+0.818LB (3) 1.4 The number of plates [pcs] IBL = 880 +.253 MS (4) 2. Preparation 2.1 Length of straightlinear flame cutting [m] DPP- 101480-1404L -1561? -615 B^ - 35.6L(B+2H)+ +1191BH+138/7LB (5) 2.2 Length of curvilinear flame cutting [m] DPK = -1643L+10855B+12,86PK+59,86-400B (6) 3.Fabrication 3.1 Number offlatpanels IPP = 0.074PK + 0,00962 LBHCb ~ 0,0145LBH + 1,92 H* (7) 3.2 Total length of butt welding [m] SC = 2,55PK + 317,9B - 2,085LH (8) 3.3 Total length of fillet welding [m] SP = -1156L+29,26PK - 115,6 LBHCb +501,4BH+ 8,25 \} (9)

Marine Technology 49 4. Erection 4.1 Number of blocks at berth mounted ISB = 0,00536 LBHCb - 0,0158PK - 0,003L* +13,08H- -1,41H* + 0,0731LH (10) 6 The investigation procedure description The analysis was conducted using statistics methods. Preliminary estimations show that simple regression methods will not act in this case because of extremely great scatter of results. It was clearly seen that the parameters explored are the function of many variables including nonlinear combinations of principal dimensions of the vessel. An assumption was made that demanded manufacturing parameter is a random variable with normal distribution, unknown average J and unknown variance Q and that pis a linear function J = ao + ai X ji+ 82X12+ + a^xim of certain subset of variables (X ;,, X^ X^ ), being known geometrical or weight hull parameters and/or its nonlinear combinations. The hypothesis was tested that the coefficients a of the equations are equal zero. It was assumed that Fisher-Snedecor statistics will be F= 4 with with significance level value Q = 0.05 as usually adopted. It means that zero hypothesis will be rejected if F>4 and significance value O< 0.05. For every relationship the error characteristics were estimated as follows: 1. mean absolute error (MAE) defined as - 2. average quadratic error (ME) I 1 TC 1 / \"> (12) where Az is a distance between adjusted trend line and measurement point, but n is a number of points. The correlation level is characterised by determination coefficient R?( R-SQ) varying in range 0-1. The characteristics of error and R^ are presented in Table 1.

50 Marine Technology 7 The error characteristics Table 1 Eq. No Symbol Unit SE MAE R-SQ 1 MS t 264-0,987 2 MB t 157 125 0,991 3 MP t 104 66 0,923 4 IBL pcs 150-0,953 5 DPP m 822 468 0,956 6 DPK m 3463 2464 0,997 7 IPP pcs 54 39 0,979 8 SC m 1323 940 0,990 9 SP m 8433 5746 0,994 10 ISB pcs 10 6 0,978 8 Conclusion 1. Presented relationships can be suitable for the prediction of some manufacturing parameters of the ships with size and type as presented in Output Data. 2. The number of ships in the particular groups (types) is still unsatisfactory and the relationships should be continuously updated by the introducing to the data base the information about the parameters of further newbuildings. 9 Acknowledgement This paper cover the presentation of some results obtained during the realisation of the extensive project targeted to the improving of the shipyard facilities utilisation. The author express his gratitude to all those who participated in the collecting and interpretation of hull manufacturing process data as well as to the manager of the project mr. T. Jablonski for his supporting.