Fastest Growing Electric Utility in Asia for 3 rd successive year. An S&P BSE SENSEX Company Q2 FY Press Meet New Delhi November 9, 2016

Similar documents
Q3 FY Analyst Meet Mumbai February 10, 2017

TRANSMISSION OPPORTUNITIES, CHALLENGES & WAY FORWARD. Confederation of Indian Industry NEW DELHI November 2, 2012

Potential Gains from Regional Cooperation and Trade of Electricity in South Asia

Press Meet Mumbai 29 May, 2013

PROJECT TECHNICAL DESCRIPTION

Tamil Nadu Moving towards 24/7 Sustainable Power Supply

India s Grid Transmission Infrastructure Needs Further Modernisation, Urgently

Power Transmission in India

Media Release Adani Transmission Ltd s Consolidated PAT rose to Rs.842 Cr. in Q3 FY18 compared to Rs.67 Cr in Q2FY18. EDITOR S SYNOPSIS Consistent ope

SUPPORT EXISTING FOR AND

RE Tariff Setting Approach

Overview of Indian Power Sector & Opportunities for for promoting Social Inclusion in Indian power sector

IMPLEMENTATION OF USE OF COUNTRY SAFEGUARD SYSTEMS IN POWERGRID (A CASE STUDY) POWER GRID CORPORATION OF INDIA LTD. ENVIRONMENT AND SOCIAL MANAGEMENT

State wise analysis of RPO Regulation for Captive users

Hydro & Small Hydro Outlook in India 2017

Flexibility in Indian Power System

Urja Global Ltd. BSE Scrip Code:

ENGINEERING AND CAPITAL GOODS

May 24, 2018 I Industry Research. Power: Yearly Update and Outlook. Graph 1 Electricity Generation Mix (FY18)

Grid Integration Of RE Challenges, Roadmap And Way Forward

Dr. Jyoti Parikh Executive Director Integrated Research and Action for Development (IRADe)

Section 86(1)(e): Specify Renewable Purchase Obligation. (RPO), grid connectivity. Section 61(h): Tariff regulations to be guided by promotion

SECTOR OVERVIEW. be restructured with commercial banks. In turn, the utilities commit to implement annual tariff increases. 8

Electronics Limited. Inve. Results Presentation Q3 FY16

/ IBE-WATCH FACT SHEET Q1 2017

JICA s Experiences in Renewable Energy and Energy Efficiency

CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS

IEEJ:August 2018 IEEJ2018 JICA- ENERGY POLICY-2018 INDIA Ammi Ruhama Toppo Director Central Electricity Authority DATA TAKEN FROM CENTRAL ELECTRICITY

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

TeamLease Services Limited Investor presentation August Putting India to work

VADILAL INDUSTRIES. Q2 & H1 FY17 Results Presentation

November, 2017 I Industry Research. India s evolving power sector

Chapter-3 ENERGY CONSERVATION AND RENEWABLE ENERGY OPTIONS TO MEET INDIAN ELECTRICITY DEMAND

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR)

MAGADH Sugar & Energy Limited

Q3 & 9M FY15 Results. Leading Diversified Renewable Energy Generation Company

Comparative study on power situation in the Northern and Central states of India

With the support of the PV Market Alliance. APVIA Q Market Report

Fact Track-Power Distribution Sector in India

Confederation of Indian Industry. Opportunities in. Fisheries. Sector in India. Ministry of Food Processing Industries. Government of India

Presentation to the Company s Shareholders

Water-Food-Energy Nexus in the context of groundwater use in India: Experience from three Indian States

Renewable Energy Market Potential and Policy Overview in India

WIND ENERGY FOR POWER GENERATION

Metamorphosis. Feature - T&D Infrastructure

Status - Indian Electrical Industry April to March

RENEWABLE ENERGY INTEGRATION IN TAMILNADU

Grid Connected Rooftop PV Systems

Paper Presented on Renewable Energy Sources Policies of India. Author- Rucha Korhale

India s Cities of Opportunities

Q3 & 9M FY18 Earnings Presentation. 19th January, 2018

HYDRO POWER IN INDIA 2017

Sarda Energy & Minerals Ltd Management Meet Note 13th January 2010

ANALYTICAL HIGHLIGHTS

SECTOR ASSESSMENT (SUMMARY): ENERGY

Objects of the Issue

Power Distribution Outlook in India 2018

FUTURE SCADA SYSTEM WITH SMARTER GRID A SMART VISION FOR INDIA

Address for Correspondence

International Journal of Advance ISSN and Applied Research (IJAAR) Impact Factor 0.899

Soil Health Management in India

Irrigation Market in India

Presentation on Investment Opportunities in Indian Power Sector

Q2 & H1 FY15 Results. Leading Diversified Renewable Energy Generation Company

WELLSPUN RENEWABLES Metamorphosis competition Metamorphosis Vista The Metamorphosis challenge: Metamorphosis Disclaimer: Metamorphosis


Agricultural Equipment India

Public Private Partnership in Wind Power in India

VADILAL INDUSTRIES. Q1 FY17 Results Presentation

ECONOMIC AND FINANCIAL ANALYSES I. ECONOMIC ANALYSIS

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

MOL CEZ Joint Venture. Budapest, 20 Dec 2007

Power For India Efficient, Cost effective and Clean

Forest Cover and Forest Area

Renewable Energy. These Slides Accompany the YouTube Video Tutorial:

Confederation of Indian Industry. Opportunities in. Ministry of Food Processing Industries. Government of India

Confederation of Indian Industry. Opportunities in ORGANIC. Food in India. Ministry of Food Processing Industries. Government of India

Safe Water Network is recognized as a National Key Resource Center by the Ministry of Drinking Water and Sanitation KNOWLEDGE PARTNER GRANT PARTNER

Q1 FY 18. Industry Update & Key Performance Highlights. 8 th August, 2017

COMPENDIUM REGULATIONS & TARIFF ORDERS ISSUED BY REGULATORY COMMISSIONS FOR RENEWABLE ENERGY SOURCES IN INDIA

Strong Fundamentals Sustainable Value

EMERGING AND PERSISTENT ISSUES

Transmission Policy and Wind Energy

International Journal of Engineering, Business and Enterprise Applications (IJEBEA)

National Aluminium Company Limited. Integrated operations : Bauxite Alumina Aluminium Power. Investor Presentation

India Solar Market Update Q Executive Summary.

Power Scenario in India 2018 State Wise Track

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Status of Poverty in India A State wise Analysis

AUSTRALIAN CLEAN ENERGY SUMMIT

HAMBURGER HAFEN UND LOGISTIK AG COMPANY PRESENTATION

South Asia Energy Security : Challenges And Opportunities

Hindalco Industries Limited. Media s Analyst Meet 04 July 2018

Flexibility Options in India

Solar Power in India 2011

CROSS BORDER ELECTRICITY TRADE

Comparative Study of Marginal Farms in India vis-a-vis West Bengal; Evidences from Last Decade

UK Generation. BAML lunch - 29 th March Alison Kay Commercial Director Transmission

Overview of the Legal Framework. New Policy Initiatives. Renewable Energy Certificate Mechanism

Indian Copper Industry February 2018

Transcription:

Q2 FY 2016-17 Press Meet New Delhi November 9, 2016 Fastest Growing Electric Utility in Asia for 3 rd successive year An S&P BSE SENSEX Company

Disclaimer By attending the meeting where this presentation is made, or by reading the presentation slides, you agree to be bound by the following limitations: This document has been prepared for information purposes only and is not an offer or invitation or recommendation to buy or sell any securities of Power Grid Corporation of India Limited (the Company ), nor shall part, or all, of this document form the basis of, or be relied on in connection with, any contract or investment decision in relation to any securities of the Company. The information in this document is being provided by the Company and is subject to change without notice. The Company relies on information obtained from sources believed to be reliable but does not guarantee its accuracy or completeness. This document contains statements about future events and expectations that are forward-looking statements. These statements typically contain words such as "expects" and "anticipates" and words of similar import. Any statement in this document that is not a statement of historical fact is a forward-looking statement that involves known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. None of the future projections, expectations, estimates or prospects in this document should be taken as forecasts or promises nor should they be taken as implying any indication, assurance or guarantee that the assumptions on which such future projections, expectations, estimates or prospects have been prepared are correct or exhaustive or, in the case of the assumptions, fully stated in the document. The Company assumes no obligations to update the forward-looking statements contained herein to reflect actual results, changes in assumptions or changes in factors affecting these statements. You acknowledge that you will be solely responsible for your own assessment of the market and the market position of the Company and that you will conduct your own analysis and be solely responsible for forming your own view of the potential future performance of the business of the Company. Neither the delivery of this document nor any further discussions of the Company with any of the recipients shall, under any circumstances, create any implication that there has been no change in the affairs of the Company since that date. Annual Accounts for FY2015-16 have been approved by the shareholders.

Recent Highlights Indian Power Sector Overview & Outlook POWERGRID Today Performance (Q2FY17) Performance (Q2FY17) Transmission Consultancy Telecom XII Plan Performance Investment Outlook 3

4

Recent Highlights ±800kV NER-Agra HVDC Pole-II commissioned TBCB Projects POWERGRID Vizag Trans. Ltd. - completed 765kV D/C Srikakulam Vemagiri Pooling Station TL (~345 ckm) 400kV D/C Khammam Nagarjunasagar TL (~ 146 ckm) POWERGRID Unchahar Trans. Ltd. - completed 400kV D/C Unchahar-Fatehpur TL (~106ckm) POWERGRID NM Transmission Ltd. 765kV D/C Nagapattinam Salem TL (~212ckm) completed 765kV S/C Salem Madhugiri TL (~ 234ckm)- under constn. POWERGRID & Railways Beginning of a New Journey Railway Electrification works of 761 route km assigned on Consultancy basis 5

6

Indian Power Sector - Overview Peak Demand : 157 GW Installed Capacity : 306 GW Thermal :69% Renewables :15% Hydro :14% Nuclear : 2% Renewables : 46 GW Growth rate : 7-8 % per annum Map not to scale 7

National Grid Need Transmission growth driven by Uneven distribution of energy resources vis-à-vis uneven demand growth Need of Long Distance Transmission System Continuous momentum in Transmission expansion Sustained GDP growth : 7-8% (Projected > 10%+) Govt. of India focus on Increasing Electricity Access to Rural Area Adequate Margin To Cater Power Market, Reliability 8

Generation Potential in India Energy resources (coal, water etc.) unevenly distributed Hydro In North Eastern & Northern Himalayan region Coal In Central India Chhattisgarh, Orissa, Jharkhand, Madhya Pradesh Coastal based Andhra Pradesh, Tamil Nadu, Gujarat Renewable Energy- Solar & Wind Across the country Major Potential Areas: Tamil Nadu, Andhra Pradesh, Karnataka, Rajasthan, Maharashtra, Gujarat 9

National Grid Present 765kV/400kV lines: ~ 1,80,376 ckm POWERGRID: 1,10,602 ckm 220kV lines: ~ 1,60,804 ckm POWERGRID: 8,894 ckm HVDC Bipole(±500kV/±800kV): 12,939 ckm. 6 nos. POWERGRID: 9,454 ckm 4 nos. HVDC Back-to-Back: 7 nos. (3,000MW) POWERGRID: 7 nos. (3,000MW) Series Capacitor : 22 nos.; Thyristor Controlled Series Capacitor (TCSC): 6 nos. POWERGRID: 22 nos. (Series Capacitor); 6 nos. (TCSC) Inter-Regional Capacity: 62,650MW National Grid Strengthening A Continuing Process POWERGRID: 56,450 MW Source: CEA, POWERGRID Data as on 30.9.2016 10

One Nation One Grid One Price 31 Oct 16 at 6.30 pm Power Market Bringing Efficiency Into the Sector Snapshot 11

Power Sector - Outlook 24x7 Affordable Power for All by 2019 Renewable Integration : 175 GW by 2022 Per Capita Consumption : about 4000 units by 2030; CAGR:10% Seamless SAARC Power Grid 12

Major Schemes Creation of Energy Highways based on envisaged load growth 11 high capacity corridors - each capacity of about 4000 MW 3 high capacity HVDC system (6000 MW each) Green Energy Corridors for Renewable Integration Intermittency, Variability, Balancing, matching trans. development Wide Area Measurement System (WAMS)- Making Smart Grid Dynamic Compensation- STATCOM, SVC etc. Renewable Energy Management Centers equipped with RE forecasting 13

National Grid Development 11 nos. High Capacity Transmission Corridors Green Energy Corridors for Renewables 14

SAARC Interconnections Geographically widely spread Indian Grid can facilitate interconnections with Neighboring countries India can provide a good demand market to harness energy resources of other countries Optimal utilization of energy resources 15

16

POWERGRID Today A NAVRATNA ENTERPRISE CENTRAL TRANSMISSION UTILITY LISTED COMPANY since 2007 GOVT. SHAREHOLDING 57.90% PAYING DIVIDEND SINCE 1993-94 >90% ISTS Transmission Network owned by POWERGRID Market Capitalization 92,599 crore 1 POWERGRID s Transmission Assets: Trans. Lines: 132,138 ckm Sub-stations: 213 Nos. - 273,862 MVA 400kV & above: >90% Availability: 99.78% (Apr16-Sep16) State-of-the-art technologies like HVDC, SVC, FACTS etc. >45% power generated in India transmitted through POWERGRID AAA Stable CRISIL ICRA AAA Stable AAA CARE CREDIT RATINGS Domestic International BBB (-) Stable Outlook S&P Fitch BBB (-) Stable Outlook Physical parameters as on 31 st October, 2016 1- Based on BSE Closing Price of 177.00 per share on 08.11.2016 17

Recognition & Awards POWERGRID completes a Hat-Trick Fastest Growing Electric Utility in Asia # for 3 rd successive year (2014, 2015 & 2016) Also, 3 rd Fastest Growing Electric Utility, Globally # #- Based on Platts Top50 Fastest Growing Energy Companies List 2016 & Platts Top250 Energy Companies Rankings 2014, 2015 & 2016 Awarded as the Winner in Power Transmission Category at D&B India s Leading Infrastructure Companies & Infra Awards 2016 @ @ - by D&B: Dun & Bradstreet 18

19

Performance- Financial (Q2 & H1FY17) Description Revenue Year ended Quarter ended Six Months ended 31.03.201 6 as per IGAAP 30.09.2015 As per Ind AS 30.09.2016 As per Ind AS % change 30.09.2015 As per Ind AS 30.09.2016 As per Ind AS ( in crore) % change - Transmission Charges 19,945 4,670 5,971 28% 9,182 11,860 29% - Consultancy Income: Services 465 99 154 56% 188 274 46% - Telecom 392 97 130 34% 185 241 30% - Other Income 479 124 225 227 364 Total Income 21,281 4,990 6,480 30% 9,782 12,739 30% -Operating Expenses 2,456 558 656 18% 1,113 1,356 22% EBITDA-Gross Margin 18,825 4,432 5,824 31% 8,669 11,383 31% Depreciation 6,183 1,448 1,877 2,826 3,634 Interest 5,023 1,185 1,587 2,327 3,105 Tax 1,592 381 488 742 970 Profit after Tax 6,027 1,418 1,872 32% 2,774 3,674 32% Other Comprehensive Income/ (Exp) net of Tax (9) (1) (22) 16 Total Comprehensive Income 6,027 1,409 1,871 33% 2,752 3,690 34% 20

Performance Financial (Q2 & H1FY17) ( in crore) As on 31.03.2016 As Per IGAAP As on 30.06.2015 As per Ind AS As on 30.06.2016 As per Ind AS As on 30.09.2015 As per Ind AS As on 30.09.2016 As per Ind AS Gross Fixed Assets 1,50,052 1,22,578 1,52,249 1,27,642 1,58,937 Capital Work-in-Progress 46,830 56,878 48,831 58,094 46,335 Debt 1,06,321 99,412 1,09,789 1,04,164 1,12,284 Net Worth 42,598 40,408 45,470 40,987 46,391 Earning Per Share ( ) 11.52 2.59# 3.44# 5.30# 7.02# Book Value per Share ( ) 81.43 77.24 86.91 78.35 88.67 Key Financial Ratios Debt : Equity 71:29 71:29 71:29 72:28 71:29 Return on Net Worth 14.15% 3.36%# 3.96%# 6.76%# 7.92%# # Not Annualized 21

Project Execution- Q2FY17 Capex ( in crore) 4850 5111 5291 4703 Capitalization ( in crore) 5049 6688 Q2FY15 Q2FY16 Q2FY17 Q2FY15 Q2FY16 Q2FY17 Cumulative Commissioning during FY17 till date: about 11,000 crore 22

Performance Summary in H1FY17 (Apr16-Sep16) H1FY16 H1FY17 Capex 11,523 10,876 Investment Approvals 9,490 26,948 Contracts Awarded 10,632 18,094 ( in crore) 23

Consultancy (Domestic) Q2FY17 Increase in Income 56% w.r.t Q2FY16 Assignments in Hand: 105 Nos. (~ 17,000 cr.) Major Assignments NER PSIP; T&D System Strengthening in Sikkim- Arunachal; TS to Leh-Kargil; Lalitpur TPP Evacuation; IPDS at Old Kashi; RE works in Odisha; TS strengthening works for DTL; Assignment from DFCC Recent Addl. Work: Railway Electrification of 761 route km by Ministry of Railways Further Orders under Development Assignments from Railways, Jammu & Kashmir, Tamil Nadu, Bihar 24

Consultancy (International) Q2FY17 Footprints in 18 countries 14 nos. 5 nos. 8 nos. EPC Ongoing Assignments (as on Sep-16) New Orders recd. - Nepal (2); Kenya (1); Bhutan (1) & Bangladesh (1) EoIs/ Techno-commercial proposals submitted - Kenya, Bangladesh, Nepal, Uganda, Liberia, Indonesia 1 Bid under evaluation (Bangladesh) 25

Telecom Q2FY17 Increase in Income 34% w.r.t Q2FY16 Infrastructure: Fiber Optic Network : ~ 36,500km Points of Presence : 595 Backbone Availability : 99.96% Major Projects: National Knowledge Network (NKN): Project completed & Under Operation National Optic Fiber Backbone (NOFN): Work in progress Scope of work enhanced to connect 9,372 Gram Panchayats - 5,082 Gram Panchayats connected 26

27

XII Plan Performance Planned Capital Outlay 110,000 crore FY12-13: 20,037 cr. (Achieved) FY13-14: 23,158 cr. (Achieved) Annual Capex Plan FY14-15: 22,456 cr. (Achieved) FY15-16: 22,584 cr. (Achieved) FY16-17: 22,550 cr. [Achieved 10,876 cr.] ~ 99,111 crore achieved in XII Plan (Apr12 till Sep16) Physical Parameters (Apr12-Oct16) 38,635 ckm Tr. Line addn. (42% over Mar 12) 63 S/S addn. (42% over Mar 12) 148,337 MVA X-formation Capacity addn. (120% over Mar 12) XII Plan Target: 40,000 ckm XII Plan Target: 60 Nos. XII Plan Target: 100,000 MVA 28

29

POWERGRID Outlook (as on Sep 16) Ongoing Projects approx. 1,16,000 crore New Projects approx. 14,000 crore TBCB Projects Total Works in Hand approx. 16,000 crore (as per Empowered Committee Estimate) approx. 1,46,000 crore Expenditure done (CWIP) approx. 46,000 crore Balance Capex approx. 1,00,000 crore 30