Exposition Light Rail Transit Project

Similar documents
Exposition Light Rail Transit Project

Exposition Light Rail Transit Project

Expo Light Rail Line. Expo Line Community Meeting Quarterly Phase 2 Construction and Design Update October 2012

Exposition Light Rail Transit Project

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

OPTIONAL STATIONAVIATION/MANCHESTER

Phase 2 Exposition Metro Line Project

Purple Line Extension Section 1 Construction Community Meeting September 26, 2017

Purple Line Extension. Construction Community Meeting March 16, 2017

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

Introductions Project Updates Summary of Proposed Community Improvements Construction Impacts Management Open House

Crenshaw/LAX Transit Project Construction Update Meeting July 28, 2015

Phase 2 Exposition Metro Line Project

Purple Line Extension Section 2 Community Meeting September 28, 2017

Phase 2 Exposition Metro Line Project

Regional Connector Transit Corridor Project Draft Environmental Impact Statement/ Draft Environmental Impact Report

Phase 2 Exposition Metro Line Project

Crenshaw/LAX Transit Project

Engineering & Construction -- Transit Status Report. Significant Issues

Phase 2 Exposition Metro Line Project

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Eastside Transit Corridor Phase 2

Expo Operations & Maintenance Facility. Operations and Maintenance Facility Pre-Construction Meeting July 10, 2013

NEPA and Design Public Hearings

Phase 2 Exposition Metro Line Project

Purple Line Extension. Construction Community Meeting January 19, 2017

Construction Notice: Infrastructure Renewal on York and Talbot Streets

I-405 Sepulveda Pass Widening Project. Community Advisory Committee Meeting June 24, 2010

East Link Extension South Bellevue Completion of Design Open House. November 6, 2014

Metro Purple Line Extension

Westside Subway Extension

RPM Phase One: Lawrence to Bryn Mawr Modernization

AGENDA REGULAR BOARD MEETING

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013

City of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ)

Purple Line Extension Section 2 Construction Community Meeting February 22, 2018

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

Environmental Setting

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address.

Slide 1: CTA Blue Line Forest Park Branch Feasibility/Vision Study

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Conceptual Design Report

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

Robinson Landing: Townhouse Pre-Construction Presentation January 9, 2018

Environmental Analysis, Chapter 4 Consequences, and Mitigation

State Route 710 North Environmental Study Update Online Media Briefing July 12, 2013

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

STAFF REPORT. Attachments: 1. Location Map 2. Project Schedule 3. Sound Wall Graphics Design Concept

Future Build Alternative Traffic Forecasts and Level of Service Analysis

City of Los Angeles 2010 Bicycle Plan First Year of the First Five-Year Implementation Strategy & Figueroa Streetscape Project Draft EIR

CROSSTOWN LRT Construction Liaison Committee November 1, 2017

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

LONG ISLAND RAIL ROAD EXPANSION PROJECT FROM FLORAL PARK TO HICKSVILLE DRAFT ENVIRONMENTAL IMPACT STATEMENT

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

HUDSON TUNNEL PROJECT

Lesner Bridge Replacement

Traffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center

Zoo Interchange Reconstruction

City of Johnston NW 70 th Avenue Improvements Phase 2 CONSTRUCTION PHASE Public Open House. March 27, 2018

Purple Line Extension. Section 1 Construction Community Meeting March 17, 2016

THE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence.

Construction Project Briefing. March 9, 2016

Estimating Work Zone Performance Measures on Signalized Arterial Arterials

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

Operational Analysis of Dulles Toll Road Ramps to Tysons. Board Transportation Committee Meeting September 17, 2013

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Miscellaneous Demolition & Concrete Removal Future Ball Square Station

Metro Blue Line Improvements & Project Update

Public Information Meeting - 14 September 2015 New Champlain Bridge Corridor Project

3.6 GROUND TRANSPORTATION

Exposition Light Rail Transit Project

FACT SHEETS LOS ANGELES COUNTY

Comparison of I-210 and I-710 as Potential ICM Corridors

CITY OF SAFETY HARBOR 750 MAIN STREET, SAFETY HARBOR, FLORIDA PHONE: 727/ FAX: 727/

Appendix H Mitigation Plan

Environmental Analysis, Chapter 4 Consequences, and Mitigation

Purple Line Extension. Construction Community Meeting May 19, 2016

Strategies to keep people and goods moving in and through Seattle

Metro Board Action: Motion 22.1

NAME STREET ADDRESS CITY, STATE & ZIP CODE. GAS ELECTRIC TELEVISION TELECOMMUNICATION OTHER (check one) UNDERGROUND OVERHEAD BOTH (check one)

Atlantic Street Bridge Project CTDOT Project Nos (Phase 1) & (Phase 2)

Williston Road Network Transportation Plan South Burlington Planning Commission Meeting

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX


SPECIAL SPECIFICATION Description of Project, Scope of Contract, and Sequence of Work

Review of Plans and Specs from a Constructability Perspective

I-395 Reconstruction MDX SR Improvements I-95 Concrete Pavement Reconstruction

Final Recommendations Identification of Improvements, Strategies, and Solutions

BENNING ROAD & BRIDGES

APPROVAL TO SUBMIT COMMENTS ON I-45 AND MORE DRAFT ENVIRONMENTAL IMPACT STATEMENT

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014

Lesner Bridge Replacement

Executive Summary Introduction and Background

Welcome. Public Meeting. August 2, :00 to 7:00 p.m. Presentation 6:00 to 6:30 p.m.

CMNAA. Central Manatee Network Alternatives Analysis Alternatives Public Meeting CMNAA STUDY PROCESS. STUDY AREA 17th St. W

ARCHITECTUS FEBRUARY 2010

West Santa Ana Branch Transit Corridor. Draft EIS/EIR Scoping Meeting June 2017

Transcription:

Exposition Light Rail Transit Project Downtown & Mid-Corridor Project Status Update Meeting Holman United Methodist Church Thursday, July 23, 2009

Phase 1 Project Description 8.6 mile corridor from Downtown Los Angeles to Culver City 1.3 miles shared with existing Metro Blue Line 11 stations, 2 shared with Blue Line 1,500 spaces at 3 park and ride lots 27,000 Daily Riders in 2020 30 min travel time from Downtown Los Angeles to Culver City Project Completion 2010 Estimated Cost $862 million

Expo Line Alignment Map

Planning and Design Principles Project Planning and Design Principles Establish a multi-modal transit corridor that accommodates light rail transit, a regional bikeway, sidewalks, parkway landscaping and automobiles Develop a Transit Parkway that encourages links, buffers, and paths into communities Provide design continuity along the alignment through Art, Architecture, and Landscaping

Landscaping Palette and Vertical Elements Golden Medallion Pink Trumpet Guinea Gold Vine Bougainvillea

Station Renderings

Phase 1 Project Status Design Baseline Design is approximately 97% complete Venice/Robertson design is 97% complete Construction Construction is approximately 43% complete Current construction activities along the corridor Street improvements on the east side of Flower St Reconstruction of bridges, southbound on-ramp, intersection and walls at I-110 Freeway and Adams Blvd along Flower St Construction of trench walls on Flower St and Exposition Blvd from south of Jefferson Blvd to west of Figueroa St Pouring of trench wall

Phase 1 Project Status Utility improvements, sewer realignments and street upgrades continue along Segment B Ballast walls, soundwalls, track drains, sub-ballast and station within K- rail along Segment B Conduit installation near 7 th Ave and Exposition Blvd Pouring of ballast wall

Phase 1 Project Status Construction of aerial stations at La Brea and La Cienega continue with the pouring of the concrete columns and the installation of false work for the bridges Drilling of CIDH pilings at the La Brea aerial station Pouring of cement at the National Blvd Bridge

Segment A Expo Park/USC Station

Segment A Construction Overview Construction on the Expo Line commenced in October 2006. Construction activities in Segment A have included utility relocations and upgrades and various street improvements such as new curbs, gutters, street lights and traffic signals. Upon the completion of the trench in October 2009, street restoration will commence and include activities such as installation of permanent street lights and sidewalks. Utility relocation and installation work in Segment A is scheduled for completion by September 2009 Trench construction will be completed by October 2009 Exposition Boulevard street reconstruction from Flower Street to Vermont Avenue will continue until October 2009 Temporary traffic signals and street lights will remain through October 2009 Sidewalk and street reconstruction along the east side of Flower Street will be completed by January 2010 Forming of the trench wall near the Expo Park/USC Station

Segment A Traffic Advisories CONSTRUCTION WORK HOURS Days: 7:00 a.m. 3:00 p.m. Nights: 9:00 p.m. 6:00 a.m. EXPOSITION BOULEVARD (westbound - Flower Street to Vermont Avenue): Intermittent nighttime lane closure, Monday night through Saturday morning. One westbound lane on Exposition Boulevard between Flower Street to Vermont Avenue is available for through traffic while both eastbound lanes on Exposition Boulevard will continue to be open. FIGUEROA STREET (northbound and southbound - Jefferson Boulevard to MLK Boulevard): Intermittent nighttime lane closures, Monday night through Saturday morning, for both the northbound and southbound lanes. 37th STREET (eastbound - Figueroa Street to Flower Street): Intermittent nighttime lane closure

Segment B Station Renderings

Mid-Corridor / Segment B Construction Overview Work behind the K-Rail through October 2009 Track drain and cable ductbank installation Overhead Catenary System (OCS) foundation, pole and cable installation Sound wall construction Station construction Installation of track foundation Track (concrete ties and rail) installation Curb and gutter installation Traffic Impacts No long-term vehicular traffic impacts Concrete pour for approach slabs at Harvard pedestrian crossing tunnel Occasional interruptions to traffic as trucks enter/exit the ROW

Mid-Corridor / Segment B ROW Timetable and Hours Work behind the K-Rail (within the ROW) When: June 2008 October 2009 Work Hours: Intermittent Saturdays: Where: Monday through Friday 7:00 a.m. - 3:00 p.m. 9:00 p.m. 6:00 a.m. 7:00 a.m. - 3:00 p.m. Vermont Ave to La Brea Ave Pictures to the right show construction work at Arlington Ave and Exposition Blvd

La Brea Station Construction The following work is being done in preparation for the construction of the La Brea aerial station: Completion of the concrete columns Installation of false work for the bridge Grading of the area Falsework at La Brea aerial station Drilling of CIDH pilings on the west side of the La Brea station

Mid-Corridor / Segment B Construction Overview Upcoming utility and street improvement work at the intersections Halldale Ave/Exposition Blvd Relocation of sanitary sewer line Temporary street closure and detour Day and night work Vermont Ave/Exposition Blvd Intermittent night-time closures Relocation and upgrading of existing water and sewer lines Western Ave/Exposition Blvd Intermittent lane closures as necessary Crenshaw Blvd/Exposition Blvd Installation of track crossing Intermittent lane closures as necessary Day and night work Examples of traffic control signs The community will continue to be notified of work activity, timeline and traffic advisories by way of construction notices

Construction Activities Impact Mitigation Types of Mitigation Measures Thru traffic lanes are maintained during peak traffic hours Watering trucks are used regularly throughout the alignment Noise produced by construction activity is monitored to ensure compliance Advanced notification of traffic detours and delays will be provided Street sweepers are used regularly to clear debris from paved streets in the construction zone Street sweeper at Farmdale Watering truck near Virginia/Exposition

Construction Safety Education EXPO CONSTRUCTION SAFETY EDUCATION PROGRAM The purpose is to increase public awareness and promote safe practices around light rail construction sites. The program reaches out to students, parents and staff at schools along the alignment. Program includes the following: School-Based Presentations Participation at Community Events Distribution of Safety-Oriented Collateral Materials Construction crew (Flagger) at Exposition and Buckingham

Community Outreach A 24-hour hotline phone number has been set up for all construction inquiries and emergencies: (213) 922-EXPO (3976) Team will respond to all construction inquiries as soon as possible and no later than 48 hours. All emergencies will be addressed immediately. Community art mural project at the Expo construction field office Construction notices are distributed throughout adjacent communities prior to the start of new construction activities. Regular project status meetings, elected briefings and stakeholder updates will continue to be held throughout construction and startup of the line.

Contact Information For more information regarding this project, please contact: Gabriela G. Collins Expo Community Relations Manager 213-243-5535 or gcollins@exporail.net Adrienne Sasser-Gardner FFP Community Relations Manager 323-601-1941or adrienne.gardner@parsons.com