MDEP Common Position CP-STC-01

Similar documents
Multinational Design Evaluation Programme MDEP

NRC INSPECTION MANUAL

REGULATORY CONTROL OF SAFETY AT NUCLEAR FACILITIES

REGULATION REGARDING EQUIPMENT PROCUREMENT PROCESS AND APPROVAL OF MANUFACTURERS FOR NUCLEAR FACILITIES

Licensing Process for International Projects

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities

REGULATORY GUIDE (Draft was issued as DG-1080)

Opportunities and limits of enhanced co-operation from MDEP experience. Lennart Carlsson Senior Advisor SSM

Page 1 / 11. Version 0 June 2014

NUCLEAR FUEL AND REACTOR

Licensee Design Authority Capability

Use of PSA to Support the Safety Management of Nuclear Power Plants

WENRA. Recommendation in. in French reactors.

REGULATORS FORUM PILOT PROJECT REPORT

Nuclear I&C Systems Safety. The Principles of Nuclear Safety for Instrumentation and Control Systems

LC 16 SITE PLANS, DESIGNS AND SPECIFICATIONS

Research on software systems dependability at the OECD Halden Reactor Project

Guidance on the Application. of ISO / IEC Accreditation International Association for Certifying Bodies

Ageing Management and Development of a Programme for Long Term Operation of Nuclear Power Plants

NOT PROTECTIVELY MARKED

Javier Reig Head, Nuclear Safety Division

Integration of Human and Organization Factors in Canada Enhancing Nuclear Safety

MDEP STC SELF ASSESSMENT REPORT

CNSC Framework for the Regulation of Licensees Supply Chain

Inspection Qualification and Implementation of ENIQ in Sweden

ERG S.P.A. GUIDELINES OF THE INTERNAL CONTROL AND RISK MANAGEMENT SYSTEM

Occupational Health & Safety Management Systems Requirements

Nuclear power plant outages. 1 General 3. 2 General outage requirements 3

REPORT 2015/100 INTERNAL AUDIT DIVISION. Audit of contract administration at the United Nations Framework Convention on Climate Change

SMR Regulators Forum. Pilot Project Report:

Audit & Risk Committee Charter

ONR GUIDE. Licence Condition 12 - Duly authorised and other suitably qualified and experienced persons. Nuclear Safety Technical Inspection Guide

25 D.L. Martin Drive Mercersburg, PA (717)

Proposed - For Interim Use and Comment

Industry Responses to NRC Request for Additional Information Concerning the Industry s September 15, 2010 Proposal on Changes during Construction

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

TECHNICAL DIRECTIVE PART ONE: STANDARDIZATION AND RELATED ACTIVITIES GENERAL VOCABULARY

JOINT PROGRAMME OFFICE

MDEP TR-VICWG-03. Technical Report. Common QA/QM Criteria for Multinational Vendor Inspection

The Hashemite Kingdom of Jordan Jordan Institution for Standards & Metrology. Jordanian Quality Mark

Safety Classification of Structures, Systems and Components in Nuclear Power Plants

SNC-Lavalin Nuclear Comments on Draft Discussion Paper DIS Small Modular Reactors: Regulatory Strategy, Approaches and Challenges

Final May Corporate Governance Guideline

Regulatory Guide Developing Software Life Cycle Processes for Digital Computer Software Used in Safety Systems of Nuclear Power Plants

1. Membership of the Committee

1 In t r o d u c t i o n 3 2 Sc o p e 3

FUNDAMENTALS OF SAFETY MANAGEMENT SYSTEMS IN NUCLEAR POWER PLANTS

Contents. 4.1 Principles Barrier concept Defence-in-depth concept Main safety functions and safety functions...

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

Design Quality. Indu Lakshman

NUPIC General Membership and Vendor Meetings June Greg Galletti Quality Electrical Vendor Branch Office of New Reactors U.S.

CORPORATE MANUAL OF INTEGRATED MANAGEMENT SYSTEM

HUMAN FACTORS INTEGRATION

REQUIREMENTS FOR AGEING MANAGEMENT AND LONG TERM OPERATION OF UKRAINIAN NPP

Draft Regulatory Guide DG-1080 (Proposed Revision 3 of Regulatory Guide 1.149)

NUCLEARINSTALLATIONSAFETYTRAININGSUPPORTGROUP DISCLAIMER

Views on possible improvements to emissions trading and the project-based mechanisms

POLICY MANUAL FOR ISO 9001:2008. Document: PM-9001:2008 Date: April 7, Uncontrolled Copy

OFFICIAL ONR GUIDE NUCLEAR SUPPLY CHAIN MANAGEMENT. Nuclear Security Technical Inspection Guide. CNS-INSP-GD-4.0 Revision 0

ABSTRACT INTRODUCTION

Canadian Regulatory Perspective on Safety Challenges for New NPP

PROBABILISTIC SAFETY ANALYSIS IN SAFETY MANAGEMENT OF NUCLEAR POWER PLANTS

Our Ref. April 28, 2005 Page 1/9. 1. Introduction References Certification... 4

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC

Identifying and Addressing the Support Needs in Member States Intending to Expand Existing Nuclear Power Programmes and Lessons Learned

ITER Quality Assurance

PS5 Policy on Measurement Traceability Issue 7 June 2018 Page 1 of 5

Global Manager Group

AUDIT COMMITTEE TERMS OF REFERENCE

Certification program "Quality Mark TMT" Checklist initial surveillance inspection

ANNEX 5 -QUALITY OVERSIGHT 1. INTRODUCTION 2. SCOPE

LEARNING OBJECTIVES FOR SECTION 4. Inspection and Enforcement by the Regulatory Body

Integration of Human and Organization Factors in Canada

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

BROOKHAVEN NATIONAL LABORATORY SBMS Interim Procedure

IAEA activities related to construction and risk management

Services Description. Transformation and Plan Services. Business Transformation and Plan Services

GUIDELINES FOR THE INTERNAL CONTROL AND RISK MANAGEMENT SYSTEM OF THE TOD'S S.P.A. GROUP

Vendor Qualification Survey

GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN

C-40 (May 13) Managing integration of pre-closure activities and post-closure safety in the Safety Case for Geological Disposal

SMITH & NEPHEW PLC TERMS OF REFERENCE OF THE AUDIT COMMITTEE

8. Target & Vital Areas

NRC INSPECTION MANUAL

The specific tasks of RF TSO - FSUE VO Safety, related with Implementation of Obligations under the Convention on Nuclear Safety

ONR GUIDE. ONR Transport Permissioning External Guidance. TRA-PER-GD-016 Revision 0. Date Issued: June 2016 Review Date: June 2019 TABLE OF CONTENTS

ONR Guide. Design Safety Assurance. Nuclear Safety Technical Assessment Guide. NS-TAST-GD-057 Revision 4

SNRIU Nuclear installation modifications

INTERMEDIATE QUALIFICATION

CHARTER OF THE AUDIT COMMITTEE OF THE BOARD OF DIRECTORS OF ISRAMCO, INC.

EUROPEAN COMMISSION Directorate-General for Internal Market, Industry, Entrepreneurship and SMEs

INTERMEDIATE QUALIFICATION

Surveillance and CoP clearance

Consultation Paper CP26/17 Model risk management principles for stress testing

Construction Safety Audit Scoring System (ConSASS) Audit Checklist

QUALITY MANUAL ECO# REVISION DATE MGR QA A 2/25/2008 R.Clement J.Haislip B 6/17/2008 T.Finneran J.Haislip

REQUIREMENTS FOR SAFETY RELATED SOFTWARE IN DEFENCE EQUIPMENT PART 1: REQUIREMENTS

IECQ OPERATIONAL DOCUMENT

A new environment for nuclear safety: Main challenges for the OECD/NEA

SYSTEMKARAN ADVISER & INFORMATION CENTER QUALITY MANAGEMENT SYSTEM ISO9001:

Transcription:

MDEP MDEP Common Position CP-STC-01 Common Position addressing First-Plant-Only-Tests (FPOT) Participation Regulators involved in the MDEP STC discussions: All MDEP members Regulators which support the present report: All MDEP members Compatible with existing IAEA related documents: Yes - 1 -

1. Introduction 2. Definitions of First-Of-A-Kind (FOAK) tests and First-Plant-Only-Tests (FPOT) 3. Examples of justifications for performing a test only on the first unit commissioned 4. MDEP Common Position on FPOTs Appendix 1: Preconditions for crediting FPOTs - 2 -

1 Introduction The Multinational Design Evaluation Programme (MDEP) design specific working groups (DSWGs) are engaged in discussions on commissioning related issues as some of the member countries are entering commissioning phase of new build nuclear power plants. A number of workshops have been held by AP1000 and EPR working groups to address commissioning related issues for the eight AP1000 reactors and five EPR reactors being built in their respective member countries. One of the common topics identified in these workshops and other interactions is the concept of First-Plant-Only-Test (FPOT) proposed by the reactor vendors. An FPOT, if accepted by the applicants/licensee s and regulators, will allow a test performed on the very first reactor of a specific design to be credited for the subsequent units of similar design. MDEP has prepared this document to provide a high-level guidance for applicants/licensees wishing to take credit for a test performed during the commissioning of the first unit of a similar type. 2 Definitions of First-Of-A-Kind (FOAK) tests and First-Plant-Only-Tests (FPOT) A test is a FOAK test, if it tests a new feature of the design or a new concept applied to the design, and the test has never been performed before (e.g. during Factory Acceptance Tests). A FOAK test is not necessarily an FPOT. A test that is a FOAK test on the first unit to be commissioned can be performed also on the other units to be commissioned later on, only then it would not be a FOAK test anymore. An FPOT is a FOAK test that is performed only on the very first unit of a specific design to be commissioned. The test results from the first unit would then be credited for the subsequent units of similar design. 3 Examples of justifications for performing a test only on the first unit commissioned The following are some of the examples of justification cited for performing a test only on the first commissioned unit: Test is complex to implement (e.g. requires specific instrumentation); Test causes severe loads to the plant structures/equipment; Test is time consuming (e.g. includes testing in various configurations). The test results are valid on all subsequent units only if the test conclusions are not affected by design differences between the units or regulatory differences between countries. - 3 -

4 MDEP Common Position on FPOTs The licensee is responsible to assess the potential use of each FPOT results for its unit(s) and to conclude such FPOT results can be credited in the commissioning process before formally presenting the case to the regulator. The obvious precondition for crediting FPOT results is that the design, implementation, and plant conditions are so similar that the possible existing differences do not affect the applicability of the results to the unit where the test will not be performed. In addition, the regulators of different countries have different requirements and review processes. The requirements may concern the acceptance criteria of the tests, the documentation, reporting of results, the processes of the licensee etc. Some regulators may also expect that a representative of the regulator witnesses the performance of the FPOT. More detailed preconditions for crediting FPOT are presented in Appendix 1. If all preconditions listed in Appendix 1 are all fulfilled, tests performed on the very first specific reactor unit to be commissioned may be credited for the subsequent similar units in any member country of the applicable MDEP design-specific working group. It is important to note that a key concept throughout the work of the MDEP is that national regulators retain sovereign authority for all licensing and regulatory decisions. It is also recommended that the licensee seeks early discussions with the regulator to leave the least room possible to interpretation of the guidance and to reach the best common understanding. Future nuclear power plant projects of similar design may wish to credit FPOTs that have been performed before the start of the project in question. In that case, it is obvious that preconditions 4.3 and 4.4 cannot be fulfilled. To compensate for that, special attention must be paid to the other preconditions, especially those concerning access to data and documenting the performance and results of the tests. The licensee s proposal should include appropriate mitigating arguments. - 4 -

APPENDIX 1: Preconditions for crediting FPOT # Precondition Licensee s responsibilities 1.1 The licensee shall evaluate and assess the possibility to credit tests performed on another unit. 1.2 The licensee shall approve crediting the FPOT before submitting the application to regulator. Justification and demonstration of the validity of the FPOT 2.1 The reasons for conducting a FPOT (cost, time, technique, safety) shall be defined, and a cost benefit analysis for conducting a FPOT shall be made. 2.2 Similarity of the unit on which the test was conducted and the one which will credit the FPOT shall be assessed. It shall be demonstrated that possible differences in design, manufacture and installation of the FPOT component or system, in the environmental and operating conditions and practices, or the codes and standards applied, do not affect the validity of the FPOT results to other unit(s). 2.3 A statement shall be made (e.g. by vendor or by operating organization) on any potential adverse consequences of claiming that the FPOT characterises the performance or behaviour of a component or system whose design, manufacture or installation do not adequately replicate that for the component or system subjected to the FPOT. 2.4 In designing the test, it should be considered whether the data could be used to design and validate a less complex or alternative test that may be used during commissioning of follow-on units to characterise the performance or behaviour of the component or system and thus help validate application of the FPOT data. 2.5 Where FPOT data is demonstrating the ability of a component or system to fulfil a critical nuclear safety function, for example primary circuit integrity/inventory or reactivity control, an independent third party panel of experts shall be appointed by each licensee to oversee all aspects of the FPOT. Consideration could be given to licensees jointly appointing such a panel. The terms of reference of such a panel shall include the production of a report recording its judgement on the validity of applying the resulting data to follow on units including in another country. This report is to record any caveats or conditions which, in the view of the panel, may constrain or exclude application of the data. Test results from the first unit must be reliable to the extent that any subsequent test would be expected to produce similar results. 2.6 It is necessary for the licensees to ensure the adequacy of the quality assurance programme of tests for the FPOT unit, considering the quality assurance requirements of the unit where FPOT may be credited. This includes - 5 -

# Precondition ensuring the adequacy of the quality assurance programme for instrument calibration. 2.7 Any physical verification(s) that have been or will be performed to demonstrate the validity of FPOT shall be identified. 2.8 All the test critical parameters, calculations and verification methods used during the initial test programme shall be identified. For calculated values, this includes the calculated validation methodology, software verification and validation (when applicable), and the actual data inputs and outputs from the initial test results to support calculated values. 2.9 The controls that vendors will have in place during the initial test programme to ensure that work performed to another language procedures or instructions are correctly translated from the original language of the procedures or instructions shall be documented. Data sharing 3.1 The licensee shall have access to all necessary data for crediting the FPOT (including information relating to design, manufacture and installation) for a period of time consistent with the licensee s obligations under country regulation. 3.2 Justification for crediting the FPOT, documentation concerning the testing (e.g. testing programme, result report) and quality assurance programme of the FPOT shall be submitted to the regulator. 3.3 It shall be possible to share other relevant data and results with the regulator as necessary (material data of equipment/structures involved in the tests, data about manufacturing and installation, quality assurance actions taken during those phases, etc.). Testing and testing programme 4.1 Documentation of the FPOT must be included in the commissioning programme of the subsequent unit. 4.2 The testing programme for the FPOT must address coverage of the testing, the acceptance criteria, prerequisites to the tests, the management of deviations and the appraisal of uncertainties. 4.3 The licensee and the regulator shall be provided with possibility to witness the FPOT. Regulators can participate in a joint inspection with the regulator overseeing the FPOT unit. To do so, they have to be informed of the expected schedule and programme and must be informed of any changes in the schedule and programme with sufficient time. - 6 -

# Precondition Other 4.4 Tests that demonstrate the correctness of manufacturing and installation must always be performed on the equipment/unit in question. 5.1 Following completion of the FPOT, the vendor shall make a statement on the appropriateness to not repeat the test on future units, including discussion on the significance of the test results, any unexpected behaviour (notwithstanding that the acceptance criteria may have been met) and any implications for the safety case/operation of the plant (normal and/or abnormal conditions). 5.2 Like any other commissioning test, it must be ensured that the FPOT provides adequate basic data on the operational properties of structures, systems and equipment for use as a basis for assessing the results of periodic testing during operation and for the assessment of changes in the operability of components. 5.3 Educational aspects must be considered. Consideration should be given to the loss of the opportunity provided by conducting the FPOT for operators to gain experience and familiarity with the component or system. - 7 -