Concrete Masonry Unit Block Fill Installation and Estimating Guide

Similar documents
Retrofit Installation Guide

Technical Bulletin. Open-Cell Spray Polyurethane Foam Equipment Set Up and Processing: (Please Review Technical Data Sheet)

Tech Tip: Cold Weather Roof Coating Recommendations

STAYCELL APPLICATION GUIDE

TREAT RISING DAMP AND REDECORATE IN UNDER 24HRS

OPERATION, SAFETY & PROCEDURE GUIDELINE MANUAL FOR

Application Specification:

SES FOAM 0.5 LB SPRAY INSTALLATION INSTRUCTIONS

5.0 NUDURA PRODUCTS ON SITE STORAGE PACKAGING, UNIT ASSEMBLY, USAGE

Application Specification:

Compliance Standards of Coated SPF System: inclusive of Permax 108 or Permax 115 Acrylic Elastomeric Coating ± 100

Seal the deal in a way no one else can.

SPECIAL SPECIFICATION 4703 Repair Of Impact Damaged Prestressed Concrete Bridge Beams

PRO-POXY 400 A.11. New technology for all weather anchoring... PRO-POXY 400! BENEFITS:

New SSPC Moisture Testing Guide and Pinhole Standard. Kenneth A. Trimber KTA-Tator, Inc.

droplet and volatilized occupational chemical exposure.

Table of Contents. 1 Introduction. 2 Description. 3 Tools and materials. 4 Footings or slabs. 5 Coursing placement. 6 Reinforcing steel

Standard practice for installing cellulose building insulation

DENVER PUBLIC SCHOOLS DESIGN AND CONSTRUCTION STANDARDS This Standard is for guidance only. SECTION MORTAR AND MASONRY GROUT

Insulation Adhesive The fast and reliable solution for bonding insulation materials

Standard Application Procedures for Sealing Leaking Cracks or Joints with Grouts

FIVE STAR PRODUCTS, INC. (800)

SECTION MAINTENANCE OF STONE ASSEMBLIES

GUIDE SPECIFICATION BAYSEAL INSULATION FOR RESIDENTIAL ENVELOPE INSULATION

EJOT Chemical Anchoring Systems. High strength anchoring of threaded resin studs into masonry blocks, cracked and non-cracked concrete

Ev erguard Adhesiv es Guid e. Updated: 3/ 17

Substrate/Ambient Temperature Standard 50 F to 120 F Polar 30 F to 80 F

INSTALLATION INSTRUCTIONS

Application Guide GARAGE & COMMERCIAL FLOORS

The only constant in the commercial

6x5. Assembly Manual CAUTION. Sharp Edges PATENTS ARE PENDING. Building Dimensions. Approximate Size. Storage Area. Interior Dimensions

PATENTS ARE PENDING. Building Dimensions. Exterior Dimensions Roof Edge to Roof Edge

DIVISION 04 MASONRY CAST STONE. A. Design Considerations. 1. Cast stone shall comply with ASTM C1364, Standard Specification for Cast Stone.

Product Information CHEMGLAZE B 9942 A/B. Coating for Casting Pits. Easy Application Chemglaze B 9942 A/B will bond to damp and wet surfaces.

Easy to Use A7 Saves You Time and Money

PATENTS ARE PENDING. Building Dimensions. Exterior Dimensions Roof Edge to Roof Edge

PS 3000 Installation Manual Step-By-Step Procedures C.9. DOOR AND WINDOW OPENINGS C.9.1 PREPARE IN ADVANCE. C.9.2 VBUCK CONSTRUCTION.

BEP Blue Barrier Installation and Application Guide

BEP Blue Barrier Installation and Application Guide

REINFORCED CONCRETE MASONRY SECTION

A-ONE Insulated Forms Installation Manual

POLYESTER INJECTION MORTAR Good Quality and Competitve Price

Construction. Universal anchoring adhesive. Product Description. Tests. Product Data Sheet Edition _1. 1 Sika AnchorFix S 1/6

the SureCoat Roof System.

Install & Maintenance Instructions

V-Pur S-84L V-PUR S-84L. Polyurethane Spray Foam System certified according to EN Description

ROOFING APPLICATION STANDARD (RAS) No. 109

ROOFING APPLICATION STANDARD (RAS) No. 109

PRODUCT DATA SHEET Sika AnchorFix -S

Masonry Wall Bracing. A Simplified Approach To Bracing Masonry Walls Under Construction. Masonry Bracing Task Force.

Construction. Universal anchoring adhesive. Product Description 1 1/7. Product Data Sheet Edition _1 Sika AnchorFix -S

Brick Walls MTI. Rainscreen Retrofit for. Flood Recovery Hurricane Recovery Restoration Flood Resilient Retrofit. Guide to Wet Flood-Proofing

AC50 Silver Adhesive Anchoring System

A Concrete Masonry Unit Wall

ICYNENE INSTALLATION INSTRUCTIONS

Construction Chemicals. Hilti. Outperform. Outlast.

1 Exam Prep Guide to Shotcrete Questions

Installation Guide Wall Panels

SECTION INSULATED CONCRETE FORMS - RASTRA 1.01 SUMMARY

WCU ALUMNI TOWER MASONRY & ENVELOPE REPAIRS

Trutek TCM380 PRO. Trutek Fasteners Polska Al. Krakowska 55 Sekocin nowy Rasxyn Poland T:

APPENDIX 5: CONSTRUCTION CHECKLISTS

Originally Issued: 12/12/2014 Revised: 12/29/2017 Valid Through: 12/29/2018

CONCRETE MASONRY UNITS Sizes & Shapes Manual

Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION

Installation Manual Advantage One Truncated Dome Attention Indicator/ Directional Bar

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

INSULATED CONCRETE MASONRY UNITS Section 04220

Fast Cure Acrylic Adhesive

CONCRETE REPAIR IN ACTION: USING THE MANUAL AS A GUIDE. Christen Longoria, P.E. San Antonio District Project Engineer

SECTION UNIT MASONRY SYSTEM

DIVISION 04 MASONRY. Section Title Number MASONRY Maintenance of Masonry Masonry Mortaring Masonry Accessories

SECTION MASONRY ACCESSORIES

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

TL-225-NS Teflon Filled, Vinyl Ester Coating & Lining

ATT-42/95 SAMPLING, Asphalt

DURA 500 THERMOPLASTIC FLAT ROOF COATING SYSTEM BY SUPERIOR POLYMERS INC.

PILGRIM PERMOCOAT, INC. 402 S.22nd Street, Tampa, FL (813) FAX# (813)

3 Scotch-Weld. Control Joint Sealant DP-5106, Self-Leveling, Gray. Technical Data July, 2006

PART 1-SAWN THIN VENEER GENERAL

Proposed specification - For review by qualified architects and engineers.

GigaHouse Specifications

DIVISION: MASONRY SECTION: MASONRY ANCHORS REPORT HOLDER: MITEK USA, INC.

CertainTeed OPTIMA. Installation Instruction Manual

Mapefix PE Wall. Chemical anchor for masonry and light loads

SHEP POXY ROADS & HIGHWAYS FAST SET HIGH MODULUS, STRUCTURAL, EPOXY GEL

Continuous Insulation Systems for Exterior Walls

Dutchman Repair For Limestone. Proposed Specification For Review by Qualified Architects and Engineers

TECHNICAL DATA SHEET SIKA ANCHORFIX-1 GREY 300ML (6's)

EXTERIOR WALLS. exterior wall systems, cladding w/ masonry. chapters SUBJECT

Important: Before You Start

Construction. Sikadur 31, Hi-Mod Gel. Application Instructions. Sika Corporation

3M Scotch-Weld Urethane Adhesives DP601 Self-Leveling and DP601NS

TEK. INSTALLATION CHECKLISTS FOR FIBERTEK FIBER GLASS UltraTEK Wall Spray Sytem (UWSS)

High Performance Coatings & Foam Equipment

WATERPROOFING CONCRETE TIE HOLES USING XYPEX

Installation and Fabrication Guidelines Sensitile Terrazzo - Terrazzo Lumina - PIXA

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

4.16. APPLICATION INSTRUCTIONS Construction Joints & Details

Transcription:

Concrete Masonry Unit Block Fill Installation and Estimating Guide Required Equipment EQUIPMENT AND ACCESSORIES Same Proportioner, Hoses and Gun as used for Gaco s Open Cell and Closed Cell Foam. Pour Nozzle/Air-Cap Kit Assembly for Gun - recommended models include the following: Graco Fusion Air-Purge (AP) Pour Adapter Kit, Part # 248528. This kit includes an Air Cap, 2 Teflon Rings (1 for flat mixing chamber and 1 for round mixing chamber), and 2 feet of hose. Pour kits are also available for the P2, Probler and PMC guns. Tips and Kits are available from your regular parts supplier. Plastic Tubing recommended size: 1/4 interior diameter & 3/8 exterior diameter; approximately 4 to 6 in length. Tubing is available at your local hardware store. Drive Drill and Wooden Dowels 3/8 or ½ Drive Drills with 3/8 and 7/16 masonry bits are recommended for drilling holes for block fill applications; Use 3/8 to ½ wooden dowels to plug holes after filling. Drills, Bits and Dowels are available at your local hardware store. Block Mortar Mix - Check with the masonry contractor on site for a block mortar mix and recommended tools for spot patching of holes made in the block and mortar joints. The masonry contractor can help you with your selection of materials and tools to make patching the holes fast and easy. Suggested Additional Tools InfraRed Thermal Imaging Camera, i.e. FLIR While not required, a thermal imaging camera does help you locate rebar and bond courses. It is also a valuable tool during installation to help monitor the filling of block cavities to ensure you are completely filling each cavity. The best images are often obtained from the inside it only takes one to two minutes for the heat signature to show through the sheetrock.

GacoProFill CMU Block Fill Installation Guide, Page 2 Proper PPE Personal Protective Equipment (PPE) is essential. Ensure all workers involved in the installation of GacoProFill are assigned the appropriate PPE and have it available when arriving on jobsite. PPE for Installation from INTERIOR of Building - Applicators and Assistants should wear: A NIOSH-approved full face or hood-type supplied air respirator (SAR) as outlined in your company's Respiratory Protection Program MDI-resistant chemical gloves (e.g., nitrile), or fabric gloves coated in nitrile, neoprene, butyl, or PVC Chemically resistant long-sleeve coveralls or chemically resistant full body suit with hood MDI-resistant fitted boots/booties PPE for Installation from EXTERIOR of Building - Applicators and Assistants should wear: A NIOSH-approved full face-piece Air Purifying Respirator (APR) with organic vapor/particulate (P100) cartridges or a supplied air respirator (SAR) Safety goggles (where respirator does not cover the eyes) MDI-resistant chemical gloves (e.g., nitrile), or fabric gloves coated in nitrile, neoprene, butyl, or PVC Chemically resistant long-sleeve coveralls or chemically resistant full body suit with hood MDI-resistant fitted boots/booties Please visit www.spraypolyurethane.org for additional information. Jobsite Prep & Material Estimation GENERAL PROCEDURES A jobsite walk through to review the planning and start-up of the block fill project is recommended to coordinate the project with all other personnel on site. Before starting work, a thorough review of the drawings for the block fill project will help the applicator locate concrete, rebar-filled bond courses and areas above and below windows and verticals. Again, a thermal imaging camera may be useful in finding these core filled areas when doing a jobsite walk through. Steel wire block reinforcement is generally used in every other course. Rebar is placed vertically in the block and anchored with concrete approximately every 4 on center in many CMU structures. Headers and lintels usually contain rebar above and below in these areas for added strength. Bond courses may occur every 6-10 courses and these are filled with concrete. Check these areas before attempting to add foam as this will save you a lot of time during the drilling process once they are located. See Unit Volume Calculation on next page for more information.

GacoProFill CMU Block Fill Installation Guide, Page 3 Unit Volume Calculation The following information can be used as an estimating guide for filling concrete block cores with polyurethane foam. Please be advised that it is always recommended that a moisture resistant coating or sealer be specified to be applied on the exterior of CMU construction when using GacoProFill for filling concrete block cores. 6" block requires 0.17 cubic feet of insulation 8" block requires 0.25 cubic feet of insulation 10" block requires 0.33 cubic feet of insulation 12" block requires 0.39 cubic feet of insulation Example: A project requires 8,000 8 block; 12 board feet = 1 cu ft 8,000 x.25 = 2000 cu ft x 12 bf/cf = 24,000 board feet Using a yield of 15,000 bf/set, 24,000/15,000 bf/set = 1.6 sets of GacoProFill If you prefer to figure by the square feet of wall space, use the following information: 6" block wall will require 0.19 cubic feet of insulation per sq ft of wall 8" block wall will require 0.28 cubic feet of insulation per sq ft of wall 10" block wall will require 0.37 cubic feet of insulation per sq ft of wall 12" block wall will require 0.44 cubic feet of insulation per sq ft of wall Example: A project has 10,500 square feet of 12 block; 12 board feet = 1 cu ft 10,500 sq ft x.44 cu ft/sq ft = 4,620 cu ft x 12 bf/cf = 55,440 bf Using a yield of 15,000 bf/set, 55,440/15,000 = 3.7 sets of GacoProFill Don't forget to exclude the bond beams and verticals, as they will be full of concrete. Verticals are normally on 2', 3' or 4' on centers and bond beams can be anywhere from the bottom and top course on walls shorter than 10' to every 2'. The elevation plans will show the number and locations of the bond beams and verticals. Schools can be very difficult as the government normally dictates 24" verticals and bond beams. That only leaves a 16" x 16" void to be filled per every 24" x 24" of wall. Also remember lintels will normally extend 16" to 24" beyond the openings and they will be full of concrete. There isn't going to be as much foam required as you would think because of all the mortar and other debris inside the walls. Consult with the masonry contractor as they can show the applicator how to drill the mortar lines and repair the holes without leaving a trace. If the walls are going to be covered with some sort of facade, the applicator can drill in the center or each core. Remember, the holes must be filled to ensure the fire rating integrity of the walls. Don't attempt to get the foam to run down the back side of the wall much beyond 16" as it will start frothing before it settles on the bottom of the cavity. If you can spray straight down into the blocks, you can use a cannon or extension tip which shoots a straight stream of foam. You can probably shoot down 5 or more inside the blocks with the cannon tip.

GacoProFill CMU Block Fill Installation Guide, Page 4 Drilling Fill Holes Using a 3/8 to ½ drive drill with a 3/8 or 7/16 masonry bit, begin drilling holes 4 courses off of the floor into the 3/8 mortar joint centering over the core of each half block. Holes should be drilled every 4 to 5 courses. Care should be taken to avoid drilling on mortar joints with wire block reinforcement. If block reinforcement is encountered, move up or below a course and begin drilling or drill on the block itself. Holes should be drilled in each half block side by side at the mortar joint or between mortar joints in the center of each half block itself to ensure drilling into the core. Filling Cores with GacoProFill Foam Always perform a test spray into a trash bag first to check for mix and rise before installation in walls. NOTE: It will splatter if a trash bag is not used. With pour cap and tube installed on gun, place tube into cavity working from the bottom of the wall up, taking care to fill each and every cavity. Again, a check with a thermal camera helps ensure every core cavity is being filled. A record of the thermal images can also be recorded for the building owner as a proof of performance for the project. When foam is installed in an 8 concrete block, it can travel 4 courses or more on a 6 second trigger pull using a Graco AR4242 (01) mixing chamber in a Fusion AP gun depending on machine temperature, pressure settings and concrete block temperature. This will be trial and error and must be tested and checked on every job. When injecting, count down the number of seconds you are injecting to develop a feel for how much foam is required to fill a core. Doing this preliminary trial will develop the hole/fill pattern for the entire project. Core fill times may vary from core to core as Brick Masons can throw varying amounts of mortar in block cores. Larger concrete blocks will require longer trigger pulls and larger diameter mixing chambers. Again, this can all be checked using a thermal imaging camera and by viewing the travel distance of the foam in the block.

GacoProFill CMU Block Fill Installation Guide, Page 5 Filling Cores with GacoProFill Foam (cont.) As the cores are filled, a tapered wooden dowel pin should be inserted into the fill hole once the tubing is removed to keep the foam from spilling out of the fill hole as the applicator moves down the wall. Develop a sequence for filling that will complete the job in an efficient and cost effective manner. Make sure that personnel drilling fill holes are well ahead of the fill applicator. Cleaning and Patching Fill Holes Clean the fill holes with a drill/wire brush attachment to insure a clean hole before patching. The GacoProFill foam is very easy to clean and remove from concrete block. Visit with the Masonry contractor on site to get the mortar mix for patching the mortar joints and holes. If the contractor is not available, a visit to a local home center will get you the materials needed to make the repairs on the fill holes. These are small repairs; take care in making sure they are done neatly and correctly and they should not be noticeable after making the repairs. Fill holes may be cleaned and repaired four hours after the foam has been injected. Do a final walk through of the project to make sure that all of the loose foam has been cleaned up and disposed of. Make sure there are no areas on either side that may have had some foam bleed through gaps and openings that were not noticed beforehand and make sure that they are cleaned and taken care of before leaving the project site. Coating/Sealer Please be advised that it is always recommended that a moisture resistant coating or sealer be specified to be applied on the exterior of CMU construction when using GacoProFill for filling concrete block cores.

GacoProFill CMU Block Fill Installation Guide, Page 6 APPLICATION PROCEDURES Drum Storage Store GacoProFill Poly drums at 50 F to 100 F when not in use. Drum Prep Prep GacoProFill Poly drums to 60 F to 80 F. In order for the drum to be serviceable (ready to spray), it must be in a temperature range that the proportioner can take it the rest of the way to spray temperature. Example: If your drum temp is 80 F and you have an E-20 with a delta T of 50 F, your max spray temperature can only be 130 F. With this information it is important to know the delta T of your proportioner and drum temperature to achieve the proper spray temperature. For those of you with Recirc capabilities, you can recirculate GacoProFill Poly to raise the drum temperature, but do not recirculate the product over 100 F. Mixing GacoProFill Poly must be mixed at a low speed for 30 minutes prior to application and must be continuously mixed while spraying. Do not mix aggressively. No special mixer required. If GacoProFill Poly is in the line from the previous spray, it must be recirculated into the drum and mixed before spraying can take place. Flushing When changing from a closed cell product to GacoProFill, pre-mix the GacoProFill Poly drum prior to flushing. Purge the Poly side of the system with water to get the closed cell product out of the system, then come in behind with pre-mixed GacoProFill Poly to flush out the water. Remember to flush the entire Poly system including recirc lines, proportioner and spray hose. Use water again to flush the GacoProFill Poly out of the system before you go back to the closed cell product. NOTE: When changing from GacoProFill to another open cell product or vice versa, flushing is not necessary. Substrate Limitations Substrates should be: clean, dry, and warm. While clean and dry offers the best success for adhesion, warmer substrates provide better yields. The colder the substrate the lower the yields we can expect. Do not spray if surface temperatures are within 5 degrees of the dew point. Substrate moisture levels should be at or below 18%. Spray Pressures 800 to 1,200 psi for optimal performance. Look for good atomization and mix of chemical with proper spray pattern. At 70 F ambient temperature: Recommended starting pressure setting is 1,000 psi using an AR-4242 (01) mixing chamber. Recommended starting pressure setting is 1,200 psi using an AR-5252 (02) mixing chamber Spray Temperatures 105 F to 135 F. The lower temp spectrums are used in warmer climates/seasons and the higher temp spectrums are used in colder climates/seasons. If the foam is reacting slowly it is too cold and requires more heat or pressure. If the foam is reacting too fast, then it is too warm and temps need to be dialed down or the pressure needs to be reduced. At 70 F ambient temperature: Recommended starting temperature setting for A, B & Hose Heat is 115 F. Equipment Settings Pre-Heat - Iso (A): Pre-Heat - Poly (B): Hose Heat: Recommended Spray Pressure: 105 F - 135 F (41 C - 57 C) 105 F - 135 F (41 C - 57 C) 105 F - 135 F (41 C - 57 C) 800-1,200 psi (dynamic) Reactivity Time Cream Time: Tack Free Time: Cure Time: 2-4 sec 8-12 sec 4 hours