EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT

Similar documents
Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100

Operation and Control of Multiple BNR Processes in One WWTP

Wet Weather and Advanced Treatment: Procurement Strategies to Secure the Right Technology

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

Water Treatment Plant Design at the Idaho Cobalt Project

A Battle to Be the Best: A Comparison of Two Powerful Sidestream Treatment Technologies: Post Aerobic Digestion and Anammox

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

NEWEA 2015 Annual Conference Session 16

A Review of the Current State of Knowledge on Phosphorus Removal

MEETING COLUMBUS S TREATMENT LIMITS

Presentation Outline

Are You Getting Your Money s Worth?

Description: D05_100_OVW_015_PlantOverview.htm Plant Overview Durham Plant Overview Last Update: October 30, 2013 Purpose:

Zero Liquid Discharge Project Extends Potable Water Supplies

East Coast P Removal Technology Performance Summary

Conceptual Design for a Future Wastewater Treatment Plant

Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility

WWTP Energy Audits Provide System-Wide View to Reducing Energy and Optimizing Processes

Chapter 5: Treatment Assessment Future Condition

The Development of Operational Tools for City-Wide Implementation of BNR in New York City. Sarah Galst, P.E. Hazen and Sawyer, P.C.

Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement Plan Existing Conditions Report. February 2017

PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ

OPTIMIZATION STUDY OF THE ST. MARY'S WASTEWATER TREATMENT PLANT

BOD5 REMOVALS VIA BIOLOGICAL CONTACT AND BALLASTED CLARIFICATION FOR WET WEATHER M. COTTON; D. HOLLIMAN; B. FINCHER, R. DIMASSIMO (KRUGER, INC.

Palmer Wastewater Treatment Plant Environmental Impacts. A summary of the impacts of this treatment alternative are listed below:

Chapter 2: Description of Treatment Facilities

STRUVITE HARVESTING: A UTILITY S PERSPECTIVE

Wastewater Treatment Processes

WATER AND WASTEWATER FACILITY CLASSIFICATION APPLICATION FORM

HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE

A Novel Testing Approach for BNR Optimization in NYC. Vera Gouchev, P.E. January 23, 2017 NEWEA 2017 Annual Conference

Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015

Meeting Manganese Removal Goals: A Pilot Study

Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project

Taking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses

CHAPTER 4 DESCRIPTION OF EXISTING FACILITIES

A STRUVITE CONTROL AND PHOSPHORUS REMOVAL PROCESS FOR CENTRATE: FULL-SCALE TESTING. 850 Pembina Highway Winnipeg, MB

City of Elk River Wastewater Treatment Facility Improvements. Achieving Wastewater Treatment Goals

WWETCO FlexFilter and Bio-FlexFilter

Thickening and Dewatering Optimization Matt Van Horne, PE Hazen and Sawyer July 14, 2016

Water and Wastewater Residuals Management Optimization Study - FINAL

PERMIT TO OPERATE SILVER CLOUD CT., MONTEREY, CA TELEPHONE (831) FAX (831)

Town of North Castle, NY Sewer District No. 2 WWTP

Report on Piloting of the Volute Dewatering Press at the Boonsboro WWTP in Boonsboro, MD July 25 th - July 29 th, 2016

Biosolids Monthly Report

Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation

PHOSPHORUS REMOVAL: TREATMENT

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Chapter 9: Alternative Analysis

Feel free to contact me should you require any additional information regarding the report. I can be reached at

AMPC Wastewater Management Fact Sheet Series Page 1

AMPC Wastewater Management Fact Sheet Series Page 1

Efficient Design Configurations for Biological Nutrient Removal

Review of WEFTEC 2016 Challenge & Overview of 2017 Event. Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng

Filtrate Treatment Facility Update

Comparison of Three Wet Weather Flow Treatment Alternatives to Increase Plant Capacity

Appendix D JWPCP Background and NDN

Capital Improvement Plan Update:

CASE STUDY: BREAKTHROUGH CENTRATE TREATMENT AT REDCLIFFE WASTE WATER TREATMENT PLANT

U. S. Army Corps of Engineers Metals Precipitation Checklist

Carbon Heat Energy Assessment and. (CHEApet) Tutorials: Carbon Footprint Primer

Table 1. Existing Anaerobic Digesters

Environmental Improvements Associated with Springfield WWTP EHRT. Using the Compressed Media Filter Technology

Pollution Control in the City of Windsor Wastewater & CSO Management 2013 Status & Update

North Side WRP Master Plan Research and Development Department 2006 Seminar Series October 27, 2006 Metropolitan Water Reclamation District of

Thermal Process Systems. Quality Biosolids Through Advanced Technologies

New York State Department of Environmental Conservation

Engineering Report ENVIRONMENTAL ENGINEERS, SCIENTISTS AND PLANNERS

APPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1

Lowering The Total Cost Of Operation

Phosphorus Removal Treatment Alternatives

Ali Leeds, MWH Austin Peters, MWH

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment

Algae Removal from a Facultative Lagoon System Using Dissolved Air Flotation. J. Patrick Pierce, P.E. Environmental Treatment Systems, Inc.

Prepared by the Operation of Municipal Wastewater Treatment Plants Task Force of the Water Environment Federation

Submerged Membranes to Replace Media Filters to Increase Capacity 4X for a Small Community. Richard Stratton, PE HDR Engineering, Inc.

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis

Application of the AGF (Anoxic Gas Flotation) Process

Innovative technology for phosphate removal from dewatered sludge supernatant

20 Years of Nutrient Removal City of Beloit

Comparison of Three Wet Weather Flow Treatment Alternatives to Increase Plant Capacity

Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1

Watertown Wastewater Facility Plan. August 11, 2015

Appendix C: TM T-49 Nampa WWTP Capacity Assessment

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES

World Pulp & Paper THE INTERNATIONAL REVIEW FOR THE PULP AND PAPER INDUSTRY

Why THP Made Sense for TRA

WWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project. Erika L. Bailey, PE, City of Raleigh

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017

Wastewater treatment objecives

High Value Resources from High Strength Wastes: Leveraging Food Production Byproducts to Reduce BNR Costs

WASTEWATER DEPARTMENT. Bentonville Wastewater Treatment Plant Facts:

Meeting SB1 Requirements and TP Removal Fundamentals

Masses at Massillon: IFAS for Industrial Loads and Nutrient Removal

Influent preheating (note that the heat will be recovered before discharge);

Advanced Aerobic Digestion. ThermAer. Autothermal Thermophilic Aerobic Digestion. Biosolids Treatment. Thermal Process Systems ThermAer Process

Minnesota Pollution Control Agency

COMPARISON OF PROCESS ALTERNATIVES FOR ENHANCED NUTRIENT REMOVAL: PERSPECTIVES ON ENERGY REQUIREMENTS AND COSTS

Transcription:

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT Matthew Valade, P.E. July 25, 2014 Barboe.pptx

Presentation Outline Project Background Why Dewater Croton Residuals Offsite? Pilot Study at Hunts Point WWTP Final Resolution Conclusions

New York Water Supply: Tunnels and Aqueducts 3

Croton WTP - A Brief History 1842 Croton begins supplying water to NYC 1997 Consent Order required Croton filtration 1999 Mosholu Golf Course (Bronx) site selected 2001 Design stopped due to legal clarification of use of public park land this design included residuals dewatering facilities on site 2002-04 Several sites evaluated MGC again selected but smaller footprint required Design does not include on site residuals dewatering 2005 Construction work for Croton WTP begins 2014 Startup is underway

Treatment Process Sodium hypochlorite (intermittent) Mixer 1 Mixer 2 Coagulant Polymer Mixer 3 Filter Aid Polymer Flocculation Sodium hypochlorite Solids Dissolved Air Flotation Fluoride Corrosion inhibitor Sulfuric Acid ph Balance Coagulant Backwash Filtration Waste Washwater UV Sodium hydroxide Sodium hypochlorite

Overview of the Facility Location Jerome Park Reservoir Plant Site Mosholu Golf Course Woodlawn Train Station Jerome Avenue Woodlawn Cemetery Photograph taken in 2004 before construction

Croton Water Treatment Plant

Final Excavation - July 6, 2007 N 555-ft 90-ft Treated Water Tunnel 683-ft Raw Water Tunnel 9.2 Acres

Construction as of May 2010

Construction as of May 2014

Why Dispose Croton Residuals Offsite? Dewatering residuals on-site: Limited space on site No truck access to Operating Level below grade Concerns with truck exhaust Space Constraints Reduce truck traffic to and from the WTP Considerably higher Cap/Op costs Issues with dewatering Croton residuals on-site led DEP to consider dewatering residuals offsite at Hunts Point WWTP

Why Hunts Point? Discharging Directly to Sewer was Banned Closest WWTP to site Existing Dewatering Facility Sufficient space for any required facilities Sufficient Dewatering capacity 13 dewatering centrifuges Space for 3 new centrifuges 7.5 mile Force Main Required Croton WTP Hunts Point WWTP

Croton WTP Flow and Residuals Solids Loads Croton WTP Flow, MGD Total Suspended Solids, lb/day Average Design Conditions Maximum Design Conditions 144 17,300 290 44,500

Characteristics of Croton WTP Residuals WTP Residuals Dissolved Solids Parameter Concentration TSS 30 mg/l Aluminum 1,700 mg/l Iron 150 mg/l Manganese 55 mg/l Heavy Metals Trace Amount Toxic Or hazardous None ph ~ 6.2 units Aluminum Hydroxide 50% Organic 41% Other inert (metals, non-organic solids) 9%

Hunts Point WWTP Background Biosolids loads Hunts Point WWTP: 100,000 lb/day Imported Sludge: 214,000 lb/day Dewaters thickened, digested biosolids Hunts Point and imported biosolids from other NYCDEP WWTPs separately Pelletize dewatered biosolids prior to off site disposal

Croton Residuals Dewatering Alternatives at Hunts Point Separate Dewatering Dewater water treatment residuals and wastewater biosolids sludge separately Blend Croton residuals with Hunts Point sludge Introduce at primary/secondary settling and dewater water treatment residuals and wastewater biosolids sludge together

Separate Dewatering Advantages Uses specific conditioning for WTP residuals No effect on WWTP biosolids dewatering Disadvantages Requires new polymer system and dedicated centrifuges May impact cake disposal options Pilot testing needed to confirm impacts Net decrease likely in % solids in cake Requires dedicated storage for alum sludge

Blended Dewatering Advantages Use existing polymer to condition the two sludges Use existing centrifuges Possible to blend the Croton WTP sludge with Hunts Point sludge prior to dewatering Disadvantages Possibility of lower dewatered cake percent being produced with blended sludge

Effects of Aluminum Hydroxide on Wastewater Limited Research/Literature Therefore, it was decided to pilot test to study the alternatives Full scale using existing Hunts Point WWTP dewatering centrifuges BioWin Computer Modeling used to estimate theoretical effects of introducing WTP residuals to Hunts Point WWTP process

Hunts Point WW Process Concerns BNR Consent Order requiring Total Nitrogen (TN) to under 44,200 lb/d at 2017 influent flows and loads Biowin Analysis included three Croton Residual addition points Primary Settling Tanks Final Settling Tanks Gravity Thickeners

Biowin Model Predictions (1 of 2) Primary Settling (PS) Tanks Increased sludge settling Increased solids can potentially overload Gravity Thickeners & Digesters, and decrease sludge quality from Gravity Thickeners Increases CBOD removal (source of carbon for denitrification process in BNR treatment) 78% increase in PS load, reduces HRT and VSS destruction in digesters, increased methanol demand

Biowin Model Predictions (2 of 2) Final Settling Tanks (FSTs) Addition prior to FST s increased solids loading to clarifiers, lower effective SRT (30% drop) 38% higher solids to digesters, reduced HRT and VSS destruction Gravity Thickeners Potentially higher removal of solids (+37%) No significant drop in PE VSS/TSS ratio, no SRT effects, no increased methanol demand Solids Loading Rates matched WEF MOP Best Alternative of 3 Locations

Previous Bench Scale Tests Results Separate Dewatering Results: WWTP ~ 22 to 27% WTP ~ 18 to 20% Combined Dewatering Results Indicated that dewatered solids from combining sludges ranged between 8 22%

Pilot Study Scope Dewatered alum residuals from Warner WTP at Hunts Point WWTP Warner WTP: similar raw water quality & treatment process to Croton WTP 6,000 gallon truck for residuals 2.5-3% solids Study polymer types and dosage rates that produce high solids cake Polymer for Alum Sludge: Flopam NE1619 Polymer for Wastewater Sludge: Flopam NE1516

WTP Residuals vs. WWTP Biosolids Critical difference that dictates sludge conditioning is Difference in the cationic demand between alum residuals and anaerobically digested biosolids WTP (alum) residuals has a low cationic charge Anaerobically digested biosolids has a high cationic charge Therefore need to study both single (WTP residuals alone) and dual conditioning (combined WTP residuals with WWTP biosolids)

Single & Dual Charge Conditioning Single Conditioning 80% Charge Existing WWTP Polymer, a High Charge Cationic Polymer Dual Conditioning 10% Cationic Charge Polymer 80% Cationic Charge Existing WWTP Polymer

Preliminary Jar Testing Results: Existing Polymer was effective for dewatering the blended sludge Recommended using both types of charged polymers to maximize cake solids Pilot Test: 10% charge polymer into alum feed 80% charge Polymer into WWTP biosolid feed.

Figure 1: Pilot Test Design Imported Sludge Hunt s Point Sludge Feed Centrifuge Alum Sludge Aquarium WTP Alum Feed Pump M Drain Centrate Polymer Tote Existing Polymer Existing Metering Pump Polymer Make Down System Existing Tank Polymer Feed Pump Figure 1: Pilot Test Design Dewatering Dewatered Cake

Figure 2: Pilot Arrangement

Figure 3: Polymer System

Single Conditioning Results (Not Optimized) As alum residuals:biosolids INCREASED Cake solids DECREASED (polymer constant). The lowest cake solids was 22.6% at 4:1 alum to wastewater sludge ratio

Dual Conditioning Results Results at 16-38% alum to wastewater sludge ratios 6:1 blended sludge ratio produced a high cake solids (29%) with 60 lb/dt (neat) Existing Polymer and 45 lb/dt (neat) 10% charge polymer. 4:1 blended sludge ratio, the same cake solids were produced but required 20-30% more polymer 2.5:1 blended sludge ratio, increase in the polymer dosage did not increase the cake solids.

Figure 4: Recommended Operations

Conclusions Dual conditioning produced better cake Maximum Flexibility Allows the flexibility to treat the solids mixture with a proper combination of low and high charge polymers. And..confirmation of existing Hunts Point dewatering equipment will work on Croton WTP residuals, BUT

Direct Sewer Discharge Part Deux NYC DEP Operating Bureau allows Croton Sludge to be pumped to sewer Existing infrastructure has been utilized Sludge monitoring via industrial discharge permit: routine sampling req'd Monitoring of BNR process at WI WWTP shows no impact to treatment Pumping strategy during Wet Weather to mitigate CSO events

Overview of the Facility Location Croton WTP Ward s Island WWTP Hunt s Point WWTP

Questions? Thank you!

Alum Sludge Addition Impacts On Gravity Thickening Need higher GT underflow to digesters Solids Loading Rate does not exceed WEF MOP values (7.1 to 9.5 lb/ft^2/d) On Digestion 5,000-10,000 lb/day additional must be landfilled due to: Under 15-day HRT requirement reducing %VSS destruction Hunt s Point won t meet PSRP compliance for Class B sludge with current online infrastructure May reduce digester performance with decrease in total gas production, Methane production, COD reduction, and organic N decomposition

Alum Sludge Addition Impacts On Dewatering Increase digested sludge load 60-70% Evaluation whether centrifuge capacity exists for additional sludge load necessary Combined sludge produces cake solids of 24% On Biological Nitrogen Removal (BNR) Potential decrease in ammonia production Beneficial reduction of influent N load to secondary treatment May inhibit nitrification which would require supplemental Sodium Hydroxide