LINKY : 35 million Smart Meters in France

Similar documents
The French experience of smart metering roll out. Smart utilities Forum Bengaluru - India

EDF EVALUATES SMART METERING IN MARTINIQUE: EXPECTATIONS & LOCAL REVIEW

Making Smart Cities Sustainable

Smart grids summit, Nice February 2015, 19th

Enel - the long term experience from Smart Metering Implementation

The Changing Definition of Smart Metering. Frits Bruggink Echelon Corporation

Successfully operating smart metering Lessons learnt from the Nordics Dr. Michael Trampert Bratislava, September 29, 2011

Smart Metering End-to-End Solutions from the Meter Data Management System to the Meter

Embedded microgrids within the InterFlex project

Photovoltaics, public authorities and citizens colloquium - Lyon From a DNO s point of view

Advance Metering Infrastructure (AMI) in South Africa Eskom s Challenges and Lesson s Learnt

Imraan Mohamed Marketing Manager Itron South Africa

SMART GRID PRODUCT TESTING AND QUALIFICATION

The liberalisation of the electricity market in France

Energy & Telco synergies EU Brussels 3th Workshop 11 jan.2012

1 Workshop on Power System Testing

Modelo de regulação do setor elétrico na Inglaterra. Paul Whittaker Diretor de Regulação da National Grid

Improving the Test Process

Smart grids. Socioeconomic value and optimal flexibility portfolios JUNE 2017 RTE SUMMARY

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Analysis of Distributed Generation and Power Losses Viesgo Distribución

Introduction to GRID4EU Large-Scale Demonstration of Advanced Smart Grid Solutions in Europe

active demand Active Demand: main results, lessons learnt and recommendations from the ADDRESS European project Régine Belhomme, EDF SA

Study on the value of flexibility in the management and design basis of distribution networks in France

SEDC event EDF Vision of demand response and new opportunities for Power System

ICT opportunities in future Smart Grids

What are the major impacts of SES that the CIO have to address? Data Tsunami

INOVCITY - BUILDING SMART GRIDS IN PORTUGAL

Emad El Sewedy Chairman & CEO El Sewedy Electrometer Group Egypt

The Low Carbon Transition in Europe: Perspectives from an Infrastructure Investor

The (future) role of the European DSOs - What can we expect? A German perspective

French initiative: Industry of the Future Alliance. Céline Chauveau, Projet Lead

Technology, Innovation and Information at Fingrid Kari Suominen, CIO

Learnings from the Swedish Market. Mälarenergi Elnät AB

SMART METERING PROJECT PHASE 1 INFORMATION PAPER CER/09/024

EDF EU Group entities are regulated under EU ETS and EDF operates on the carbon market (EUAs and CERs/ERUs) through EDF-T, its trading entity

SMART GRID SCENARIO. Marina Egea,

Revenue Enhancement Project Naledi Local Municipality. August 2016

NSMP Business Requirements Work Stream Smart Metering Infrastructure Vendor Request for Information

CLICK HERE TO KNOW MORE

A Disruptive Technology

Raj Chetty Senior Engineer Eskom RT&D South Africa

Smart grids. Socioeconomic value and optimal flexibility portfolios JUNE 2017 RTE SUMMARY

Project overarching objectives

PECC Seminar in Perth

Smart Meter Implementation Plan Ontario Energy Board

Frequently Asked Questions

Bosch Energy Storage Solutions Smart integration of storage

HOW INTELLIGENT AND ADAPTIVE LIGHTING IS DRIVING MODERN LIGHTING PROGRAMS

DNV GL *Our testing, certification and advisory services are independent from each other

The future Role of VPPs in Europe Pan European Balancing Market: EU-FP7-Project ebadge

TOWARDS THE MODERNIZATION OF THE SCADA SYSTEMS OF THE HELLENIC ELECTRICITY DISTRIBUTION NETWORK OPERATOR CONSIDERATIONS AND STEPS FORWARD

Update on the 2013 Project Tender. Board TKI Switch2SmartGrids

iheps - an energy optimisation solution for large facilities

Using Low Voltage Smart System (LVSS) Data for Intelligent Operations and Customer Support

Nexo 2016 Annual Conference Arnaud Crouzet. Lessons learned in implementing and deploying standards

REPLY COMPANY PROFILE

Smart Grid Program. Andres Carvallo, CIO. Austin Energy. November Austin Energy All Rights Reserved

How to build an Innovative and Smart Water System with the PI System

Consumer. Engagement. A Playbook for Utilities. January, 2017

Microgeneration and new end-use technologies in ADDRESS, INCA and SEESGEN-ICT

2014 Software Global Client Conference

Making a business case for smart meters: Some additional benefits from SP AusNet s smart meter rollout

ISO Maturity analysis in a Swiss grid electricity company. Alain Ruffieux

ACCESS Power Management and Control Systems Access the Advantages. power p managementg. Global network of innovation

Edison SmartConnect. The Role of IT in. John Bubb Southern California Edison Edison SmartConnect TM May 20, 2008

How to build an Innovative and Smart Water System with the PI System

Acquiring and Processing Data at the Edge of the Energy Grid

IDE4L project overview and ANM concept. Distributed automation system

REQUEST FOR PROPOSALS FOR AUTOMATED METERING INFRASTRUCTURE

Opportunities & challenges in current markets & gearing up for the future

Electricity Grid Evolution in EU pre-access Countries: the Turkish case. Gaia Moretti

Integrated Multi-Client Platform for Smart Meters

What utilities must consider in implementing STS smart metering systems. Lawrence Juku PIESA - VICTORIA FALLS SEPTEMBER 2015

Demand as an Active Actor Day 2, Item 1. Presented by: Flora Flygt XM Medellin, Columbia December 12-13, 2012

Towards being a smart energy enabler - meeting customers expectations on the energy market. Annika Viklund, CEO Vattenfall Eldistribution, Sweden

A sound business model and a proven technology

Metrics for Addressing Smart Grid Issues, Including the Importance and Necessity of Protocols

Business Impact of Using the Remote Disconnect Switch October, 2013

Pillsbury & UtiliPoint AMI/MDM Webinar. Jon Brock, Utilipoint Michael Murphy, Pillsbury. September 17, 2008

Electricity System Operator Forward Plan 2018/19

Open Data Access Framework

SOLUTIONS FOR GAS DISTRIBUTION SYSTEM OPERATORS (GDSO)

Energy Efficiency A Major Challenge for Future City Infrastructure. Dr. Fritz Rettberg Sydney

DEMAND PREPAYMENT METERING, TAMPERING AND LOSS REDUCTION SARPA CONVENTION 2017

Impact of AMI on Load Research and Forecasting

Digital Transformation of Energy Systems

EDF and Smart Cities. Michel Maschi EDF R&D VP International and Partnerships

Preparing the Danish electricity grid for 50% wind power by 2020

Engage Consulting Briefing Note: Smart Metering Implementation Programme: Prospectus

Whitepaper March Reference Design: Faster Time to Market for Robust, Responsive Internet of Things Devices

Smart metering implementation guidelines

GreenTech Business Network Event Smart Energy City: Future Energy Solutions

Advanced Intelligent Energy Management. Energy Huntsville 08/11

INFORMATION TECHNOLOGY PROGRAM DESCRIPTIONS OPERATIONAL INVESTMENTS

European Commission s proposal for a revised Electricity Directive

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

Delivering outputs in innovative and lower cost ways REORGANISING RENEGOTIATING REENGINEERING

The role of smart grids in integrating variable Renewable Energy sources

Call for Papers. August 16-17, Melbourne Park Function Centre Melbourne, Australia. Australian. Submit your abstract by March 28

Transcription:

LINKY : 35 million Smart Meters in France EU Smart Grid Workshop Marc DELANDRE Metering Division Director marc.delandre@enedis.fr ENEDIS

Enedis : the major DSO within the French electricity market CRE (FRENCH REGULATOR) 400 kv, 225 kv, 90 kv, 63 kv 20 kv (15 kv, ) 400 V High Voltage (HTB) Medium Voltage (HTA) Low Voltage (BT) HV/MV Substations MV/LV Substations Mainly EDF EDF, Engie, Direct Energy (+ 157 locals) GENERATION TRANSMISSION DISTRIBUTION SUPPLY Deregulated Regulated Deregulated

Enedis Key Figures 39 033 EMPLOYEES 12 MILLION ON-SITE INTERVENTIONS TURNOVER 13 548 MILLION EUROS 35 MILLION CUSTOMERS 392 000 NEW CLIENTS CONNECTED TO THE NETWORK 410,5 TWh OF ELECTRICITY TRANSMITTED ON THE DISTRIBUTION NETWORK NEW DISTRIBUTED GENERATION FACILITIES 1 340 896 km OF POWER LINES (HIGH AND LOW VOLTAGE) 26 800 MILLION EUROS 3 170 INVESTMENT

Overview of the Linky Program 6 YEARS 35 5 Bn investment 2015 2021 Equipment Lifespan requirement: 20 years. A process of qualification and a dedicated lab, The Linkylab Million Smart Meters 700,000 Data Concentrators Offset by savings on -Non technical energy losses -Remote operations and meter reading - Optimization on Grid management Targets for the mass roll-out -At the peak of the rollout, 30 000 meters and 800 data concentrators installed per day -35 million meters replaced till the end of 2021 -A data collection rate close to 100% (daily basis) 10,000 jobs created in France (direct or indirect) (5,000 jobs for mass rollout)

Linky global benefits DSO New rates / offers Energy cost reduction Better customer care Customer Financial asset management Energy transition plans Employment Grid Adaptation Smart Grids Operational cost reduction Supplier Charge based on measurements vs estimates Remote and quicker services Rich rates and services and enhanced Demand control Local authorities

The Linky system at a glance Radio link TOU switch Meter PLC Concentrator GPRS Telco GW Linky IS Enedis IS

A tendering process to select partners The timetable for the qualification process : July 2013 August 2014 December 2015 Specifications Pilot series qualification Manufacturing steering Vendor RFP launch Vendor RFP award Mass roll out Start France Prime Minister announces the launch of the RFP to replace meters Awardees: Scaling up the qualification process

Linky meter : main features Electronic Meter ON OFF 1 Breaker The Smart meter is based on its predecessor platform (Solid state meter), and holds the same volume 2 Real time clock It implements 5 new major features 3 Firmware 4 PLC modem 5 Security

Technical requirements Requirements discussed with and validated by the main Stakeholders A technical architecture based on a worldwide standard, supported by the G3-PLC Alliance Services dedicated to the suppliers, the end customer, and the network operator A fully secured solution, with: G3-PLC embedded security mechanisms Encrypted data on the whole chain Phy secured elements at the concentration level Key information systems in a militarized zone Work running Linky organization with firewalls and limited individual possibilities A Linky system validated by ANSSI (same level as BSI in Germany or NSA in the US) A technology already exported in many other countries For any further information, please visit G3-PLC Alliance booth

Metering tests In addition to the suppliers tests, other tests are run or steered by Enedis, on prototypes and pilot series. Some tests are run by EDF R&D and external laboratories Firmware qualification Tests run by Enedis LinkyLab Unitary testing - conformance Protocol Functional Performance DC & M Hardware qualification Interoperability By supplier By production versions DC-M & M-M Stress tests Robustness Endurance Performance 1DC nm Enedis LinkyLab Pre-integration Detection Downloading Collect Services 1DC 1M EDF R&D tests Environment CEM Breaker & Relays TIC / Euridis / Other Metrology / Functional power tests DC & M DC & M M DC & M M Outsourced tests DC = Data Concentrator M = meter FW = Firmware HW = Hardware

Linky Lab : the largest metering lab in the world

Linky Roll Out : a leopard pattern strategy

A six years mass Roll Out 2016 2017 2016 2017 2018 2019 2020 2021 MASS ROLL-OUT Up to 8 million meters installed per year 35 000 000 2018 2019 2021

Roll Out status update Meters with G1 technology 2.5 million meters Meter with G3 technology 500 000 meters Communication system performance Data concentrator correctly mapped with the Linky system Meters correctly mapped with the Linky system Average rates 99 % 98 % Field Force Partners : More than 150 ongoing contracts Around 2000 people on the field > 8 meters installed per day per operator Daily meters reading 98 % Remote operations (one shot without retry) 96 %

Data journey Customer Once a day From the portal, the customer can access daily measurements and activate load curve recording (10, 30 or 60 minutes) Energy company (supplier) Once a day kwh Once a month Customer is charged monthly, based on a single register (at the end of the billing period) on request City, local authority The city monitors the results of energy efficiency upgrades of ecodistricts Data are agregated at various scales and anonymous

A set of tools for Roll Out and maintenance

A strategic Roll Out operational center Roll out manager Analysts Supply-Chain manager Operational planner Mid term planning Meters and data concentrators avalibility Planificateur opérationnel Planifie sur le moyen terme Pilote les flux de compteurs, concentrateurs et autres matériels Downstream coordinator Coordinateur Aval Optimization of stocks and deliveries, regional forecasts coordination Optimise la répartition des stocks et des livraisons Anime les prévisions Régionales Responsable supply chain Pilote l'équipe Supply Chain Sécurise et fluidifie les processus Supply Chain Supply chain manager 20 people Planificateur Long terme Long term planner Development base des scenarii and validés planning par le based Programme on longterm Suit et coordonne les actions au sein de l'équipe scenarios Prépare & anime la planification long terme sur la Supply Chain Coordinateur Upstream coodinator Amont Constructeurs Performance Contribue au of pilotage the manufacturers de la performance monitoring des constructeurs and securization & sécurise of les the risques risks Constructeurs et Serval

An hypervision center Linky activity on a daily basis. Key figures for 3 million meters in the field 1200 record books created 800 000 events LinkySup 90% issues solved automatically 200 000 events rejected 600 000 events checked 300 updates on a daily basis 5 000 actions launched 80% of them automatically created by the system

PDA for each fitter, connected to the Roll Out IS The PDA is connected to the meter /data concentrator during the intervention in order to program the device and to insure each step of the procedure is respected

Expresso : an app to fix communication issues Field diag requested by the hypervision system Detect the noise generators in the field

THANK YOU FOR YOUR ATTENTION Marc DELANDRE Enedis Metering Division Director marc.delandre@enedis.fr