SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

Similar documents
SITE ENVIRONMENTAL MANAGEMENT PLAN VIKING WIND FARM TECHNICAL SCHEDULE 2 POLLUTION PREVENTION PLAN

D EROSION AND SEDIMENT CONTROL. Table of Contents

CCSD#1 Stormwater Standards

Appendix 11. Erosion and Sediment Control Management Plan. Appendix 11

Borrow Pit and Quarry Management Procedure Environmental

Appendix 16 - Erosion and sediment control guidelines for earthworks

Temporary Watercourse Crossing: Culverts

Temporary Watercourse Crossing: Fords

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

10.1 Introduction This chapter describes the effects of the proposed Edinburgh Tram Line One on water resources along the route including:

Appendix 16 Erosion and sediment control guidelines for earthworks

Construction Sites Regulation by SEPA. Phil Leeks

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS

APRIL 2015 CONTINGENCY PLANS

DOORNVALLEI EXT 5 & 6

Schedule A DISTRICT OF MAPLE RIDGE Watercourse Protection Bylaw

Order of road works and servicing construction to be carried out in accordance with the staged contract construction sequence specified below.

Papua New Guinea LNG Project. Environmental and Social Management Plan Appendix 11: Reinstatement Management Plan PGGP-EH-SPENV

Pollution prevention (land and water)

GRADING, EROSION AND SEDIMENTATION CONTROL

CHAPTER 13 Environmental Guidelines for GENERAL CONSTRUCTION PRACTICES

Erosion & Sedimentation Control Policy

Erosion Control Inspection Form

Oweninny Wind Farm. Oweninny Environmental Impact Statement Appendix 5B

ENVIRONMENTAL RISK ASSESSMENT SHEET

Section 208. SOIL EROSION AND SEDIMENTATION CONTROL

MINNEHAHA CREEK WATERSHED DISTRICT BOARD OF MANAGERS REVISIONS PURSUANT TO MINNESOTA STATUTES 103D.341. Adopted April 24, 2014 Effective June 6, 2014

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

New South Wales Concrete by-product Recycling and Disposal Industry Guidelines

Pollution Prevention: Private, commercial and military airfields.


Storm Water Pollution Prevention Plan (SWP3) Checklist

Scottish Environment Protection Agency

Form 1: Application for resource consent

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Surface Water Management Procedure Environment

Town of Fortville Utility Street Standards

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

EnviroLeg cc NATIONAL WATER Reg p 1

Low Gradient Velocity Control Short Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1]

STATE OF MISSOURI CLEAN WATER ACT SECTION 401 WATER QUALITY CERTIFICATION 2012 GENERAL AND SPECIFIC CONDITIONS

A tank filtration and settling system set up to dewater groundwater for excavation work near the Upper Truckee River.

14.0 MONITORING AND CONTINGENCY 14.1 Effects Monitoring

Builder s enviro guide

EROSION AND SEDIMENTATION CONTROL SECTION 1 - GENERAL 1.1 SUMMARY

2.1 MINIMUM WATER QUALITY PROTECTION REQUIREMENTS FOR DEVELOPMENT CONSTRUCTION PROJECTS

Water Pollution Control for Work in Sensitive Areas

Building on small sites

1.2 REGULATORY REQUIREMENTS

STORMWATER MANAGEMENT PLAN CONTENTS CHECKLIST Stormwater Management Plan Contents. SWMP Page # or Reference Location Yes/No

CEAA ENVIRONMENTAL ENVIRONMENTAL IMPACT ASSESSMENT AMBASSADOR BRIDGE ENHANCEMENT PROJECT. Replacement Span and Plaza Expansion APPENDIX E

Construction Management Plan (CMP) 227 Princess Highway, Dandenong

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

Annex F Scoping Checklist

13 Land Use Activities and Indigenous Biological Diversity

Chapter 2: Selecting Best Management Practices (BMPs)

SECTION TEMPORARY ENVIRONMENTAL CONTROLS

Refer to Chapter 3.0 (Description of Development) for a detailed site and development description.

Chapter CONSTRUCTION SITE EROSION CONTROL

No. 6 December, Wisconsin s Forestry Best Management Practices for Water Quality Forest Roads

Environmental Management Plan (EMP)

Contractors, Illicit Discharges, & Best Management Practices. Chris Allen Stormwater Inspector

ATTACHMENT C RISK LEVEL 1 REQUIREMENTS

Water Resources Management Plan

SACHSE EROSION CONTROL GUIDELINES

Performance Standards Compliance Checklist

STORM WATER POLLUTION PREVENTION PLAN TEMPLATE

Appendix D. Erosion Management Sub- Plan

8 Geology, Hydrology & Hydrogeology

Paving and Grinding Operations

Alberta Transportation The City of Edmonton The City of Calgary

E7. Taking, using, damming and diversion of water and drilling

WI-ENV-PER-0013 GROUND DISTURBANCE PERMIT

H28. Special Purpose Quarry Zone

10. STAGE FOUR: MONITORING OF ENVIRONMENTAL AND SOCIAL MEASURES (MESM) DURING ROAD CONSTRUCTION

PHASE 1 UPDATES TO DESIGN AND CONSTRUCTION STANDARDS INITIAL DRAFT FOR. Chapter 6 EROSION PREVENTION AND SEDIMENT CONTROL

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS

Filter Tube Barriers (Instream)

FORM B: DAMMING AND DIVERSION OF WATER

ethekwini Environment al Health Department.

APPROVED FOR ISSUANCE REFER TO ENCROACHMENT AND/OR CONSTRUCTION PERMIT AND PLAN COVER SHEET FOR SPECIAL CONDITIONS AND PERMIT NUMBERING

Modular Sediment Barriers (Instream)

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan

TIMBER PLANTATIONS (HARVEST GUARANTEE) REGULATION 1997 under the TIMBER PLANTATIONS (HARVEST GUARANTEE) ACT New South Wales

GENERAL SPECIFICATION FOR TEMPORARY FLOW CONTROL FOR CONSTRUCTION IN WATERBODIES

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators

Petra Diamonds (Finsch) Storm Water Management Plan Update. Project No: PET-FIN Shangoni Management Services (Pty) Ltd

Non-Technical Summary

Application for resource consent Form B Damming and diversion of water

ROADS: OPERATION AND MAINTENANCE

Development on Peatland Guidance Waste. Objective

Project Information. Check all that are applicable to the construction project site: RIPDES CGP (construction) RIPDES RGP (dewatering)

The Construction General Permit and Erosion Prevention and Sedimentation Control

Building Better Storm Water Quality

Division of Water Quality (701)

EXIST PIPE 12 FT LANDSCAPING PROPOSED PLAN LEFT EXIST. R/W REPLACE INLET TOP EXIST PIPE

Flow Diversion Banks: General

Environmental Control Plan

Permeable Pavement. Pavements constructed with these units create joints that are filled with permeable

Appendix 14-I Description of Stream Crossing for Electrical Interconnect

Transcription:

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS Version 2 June 2006 1. Purpose These Guidelines are supplementary to SEPA s "Special Requirements", which are a definitive list of clauses for incorporation into contractual documents. These guidelines are intended to be used for advice only and are not such a definitive list. Engineering or construction work carried out in or in the vicinity of inland waters now requires authorisation from SEPA under the Water Environment (Controlled Activities) (Scotland) Regulations 2005. Your local SEPA office to discuss any requirements under these regulations. Further guidance to assist those in the civil engineering industry on how to minimise the environmental impact of their activities can be found in the range of Pollution Prevention Guidance Notes (produced by SEPA, the Environment Agency and the Environment and Heritage Service Northern Ireland). Note that the Contractor is fully responsible for the design, construction and maintenance of pollution prevention facilities on the construction site. The Agency's formal authorisation under the Water Environment (Controlled Activities)(Scotland) Regulations 2005 must be obtained by the Contractor before the commencement of any engineering activities that fall under the requirements of these regulations. 2. The Water Environment (Controlled Activities)(Scotland) Regulations 2005 The Water Environment (Controlled Activities)(Scotland) Regulations 2005 were passed by the Scottish Parliament on 1 June 2005. These regulations mean that from 1 April 2006 it will be an offence to undertake any of the following activities without a CAR authorisation: Discharges to the water environment (including discharges to land) Abstractions from the water environment Impoundments (dams and weirs) of surface waters or wetlands Engineering works in inland surface waters and wetlands (not in coastal or transitional waters) Guidelines for the special requirements V2 June 2006 Page 1 of 8

The water environment is defined in the Water Environment and Water Services (Scotland) Act 2003. The water environment includes wetlands, rivers, lochs, transitional waters, (estuaries), coastal waters and groundwater. 3. Guidelines for the special requirements for the prevention of pollution from civil engineering contracts 3.1 Pre-Construction Requirements (i) It is essential that the Contractor contacts SEPA at the planning stage prior to submitting his bid price for the work. Contractors should establish with SEPA the type of pollution prevention measures that are required for the project, as certain works may call for the acquisition of additional land area requirements, over and above that needed for construction, in order that appropriate treatment facilities may be installed (if required). Moreover, the contract may be suspended until facilities have been installed to the satisfaction of SEPA. If pollution occurs, the Contractor could be prosecuted under the Water Environment (Controlled Activities)(Scotland) Regulations 2005. (ii) In addition to consulting with SEPA at an early stage, Contractors must contact riparian owners, fishery and angling concerns in the vicinity of and downstream of the proposed project so that the interests of these parties, which are completely separate to those of SEPA, are protected. 3.2 Responsibility The party or company to whom the contract is granted will normally be solely responsible for pollution prevention during the project and, in some instances, for a specified time following the completion of the work. This responsibility will include the actions of any third party who is contracted or otherwise involved in the project. If a Contractor is exempted from third party responsibility within the contract document, they should advise SEPA of this arrangement prior to construction commencing. 3.3 Main Polluting Sources of the Water Environment Guidelines for the special requirements V2 June 2006 Page 2 of 8

There are a number of ways in which civil engineering contracts may lead to the pollution of the water environment and these can generally be categorised as follows:- (i) The discharge or entry into the water environment of contaminated site runoff or pumped contaminated surface/groundwater. (ii) Direct disturbance of the beds of the water environment by excavation or fording of watercourses. (iii) Loss of oil from machinery, during delivery or from storage areas. (iv) Cement and cement wash from batching plants, storage areas and other areas where cement grout or concrete is being applied. Guidance on how to minimise the risks of pollution from civil engineering works can be obtained in the various PPGs referred to in Section 4 of this document. This document focuses on minimising the risks of soil erosion. 3.4 Preventing Soil Erosion (i) Erosion is the process whereby soil is transported by wind and/or water. Erosion does occur naturally but usually at a very slow rate. Activities which alter the landscape, such as road building, house construction and industrial site developments, can greatly accelerate this process. The removal of established vegetative cover can lead to the loss of large quantities of soil particles to watercourses which can then cause significant pollution of water. The discharge of eroded soil may not only result in pollution but can also induce long term damage to fish stocks and to the general biology of a watercourse. Fine solids may kill fish by coating their gills, or may reduce growth rates and resistance to disease. In addition, accumulation of sediment on the bed will adversely affect the biological diversity of a watercourse, thereby reducing the abundance of food available to fish. The successful development of fish eggs and larvae may also be inhibited. It is essential that the degree of land disturbance and subsequent erosion is controlled and kept to a minimum. Therefore, any earth moving works or other similar operations giving rise to contaminated drainage must be carried out in accordance with Guidelines for the special requirements V2 June 2006 Page 3 of 8

BSI Code of Practice for Earth Works, BS6O31:1981. Before any discharge of contaminated site drainage is made, prior agreements must be made with SEPA regarding the quality and quantity of effluent to be discharged. Where appropriate, SEPA may grant a temporary authorisation to discharge treated site drainage to the water environment, following the submission of an application for such authorisation. (ii) Sedimentation is the settling out of soil particles which have been transported by wind and/or water. The rate of deposition depends primarily on particle size and run-off flow rates. Heavier particles, such as gravel and sand, settle out quicker than fine particles, such as clay, which may become electrostatically charged and stay suspended in water for long periods, contributing to water turbidity and discolouration. i) An Erosion and Sediment Plan should be prepared for each site and fully discussed with SEPA prior to the commencement of any mechanical works. Such a plan should incorporate the following: a) Pollution risk assessment for the site. b) Planning and design of appropriate control measures. c) Management of the system, including the safe disposal methods for settled sludge and dirty water. d) Contingency planning and emergency procedures. This should include relevant telephone numbers (e.g. SEPA Emergency Hotline number on page 5, downstream landowners and water users etc.) and record the availability of equipment to carry out any emergency remedial work. iv) Principles of control are based on the protection of the soil surface from rainfall and run-off, and on containing eroded soil particles on-site. Fine particles can be very difficult to contain once they have been mobilised and the best way to control the generation of sediment is to prevent erosion from taking place. The following principles should be incorporated into the planning, design, construction and management of any measures to control Guidelines for the special requirements V2 June 2006 Page 4 of 8

erosion and sedimentation: a) Obtain all necessary agreements and consents before staring work. b) Schedule construction activities to minimise the area and period of time that soil will be exposed. Account should be taken of the time of year and, in the case of sensitive operations, the weather forecast. Limit the area of construction. c) Stage the project where practicable e.g. in 100 metre lengths, with complete rehabilitation of each stage before progressing to the next. Only those areas which can be fully developed in a construction season should be worked. d) Intercept run-off from undisturbed areas surrounding a site (e.g. by using cut-off trenches) and divert this around the works. Temporary, erosion proof, outfalls should be utilised where necessary. Isolate the works. If drainage water is clean, keep it clean. Work in dry areas by diverting/pumping the water body around the working area or alternatively by forming temporary culverts through the working area, after obtaining agreement from SEPA. e) Keep run-off velocities low and reduce erosion by the provision of appropriate drainage, buffer strips of vegetation, and short slopes with low gradients. Removal of vegetative cover increases the volume and rate of run-off. f) If some erosion is unavoidable, then contain resultant suspended particles on site. Plan and implement control measures before undertaking earthworks. g) Stabilise disturbed areas as soon as construction has finished. This may be achieved through structural methods, utilising synthetic fabrics, hydroseeding and other quick stabilisation/re-vegetation techniques as necessary. Guidelines for the special requirements V2 June 2006 Page 5 of 8

h) Inspect all control measures regularly for structural defects and associated leakage. If not properly maintained, some control measures may cause more damage than they prevent. Regular inspections should also be undertaken to ensure that the water environment has not become polluted. The frequency of inspections should be increased at times when the risk of pollution is high, such as during and after heavy rainfall. i) Ensure that developers, Contractors and others involved in earthworks which could pollute the water environment are aware of their statutory responsibly not to cause water pollution or damage habitats. All such persons should be aware, and should make their employees aware, of the likely causes and consequences of environmental pollution and should be familiar with any control measures and emergency procedures to be deployed. j) Develop and maintain a contingency arrangement to deal with environmental pollution incidents (as part of the Erosion and Sediment Control plan). A sketch plan showing the location of the drainage system should be prepared and equipment should be available for emergency situations to plug drains, dam ditches, excavate catchpits or retain oil spillages by placing oil absorbent materials or wooden scum (or baffle) boards across watercourses. k) Be aware that sediments commonly act as transporting agents for other contaminants. Usually the finer grained sediments are prominent in this regard, as they take longer to settle than coarser particles. Consequently, the standard techniques for controlling erosion and sedimentation may not be effective in limiting the off-site transfer of contaminants. Thus, other measures may be necessary, such as tankering off-site for suitable disposal to a licensed landfill site or the use of chemicals to promote settlement prior to discharge. l) Where necessary, provide settlement ponds or lagoons to remove the sediment which will invariably be present in site drainage (although minimisation of the amount of erosion must always be the first priority). Such facilities will also be required for the drainage from borrow pits and Guidelines for the special requirements V2 June 2006 Page 6 of 8

any on-site quarrying activities. The design and satisfactory operation of settlement ponds or lagoons depends on a number of factors, including the anticipated flow rate of the drainage, the settleability of the soil particles, influence of wind and wave action and the quality which the discharge must meet in terms of SEPA s requirements. Developers/contractors should consider long term rainfall figures for the area where construction is taking place as this varies significantly in different regions and is an important criterion when determining the size of settlement ponds/lagoons. The location of settlement ponds/lagoons on natural watercourses should be avoided and, where practical, the location of treatment facilities for the construction phase should be considered with a view to these facilities being utilised as method/treatment systems for any permanent drainage from the site. Discharges to the water environment from treatment facilities will require the formal authorisationof SEPA under the Water Environment (Controlled Activities)(Scotland)Regulations 2005. m) Provide temporary culverts and/or bridges to enable vehicles to cross waterbodies and thus prevent disturbance of the river bed. n) Locate stockpiles and spoil heaps as far away as possible from waterbodies and drainage ditches. 3.5 Miscellaneous Blast furnace slag is not considered suitable for use in shot blasting adjacent to the water environment (such as bridge works). The demolition of old concrete structures such as culverts can give rise to potentially toxic dusts and care should be taken to prevent these from entering the water environment. 4. References PPG2: Above Ground Oil Storage Tanks PPG4: Disposal of Sewage Where No Mains Drainage is Available Guidelines for the special requirements V2 June 2006 Page 7 of 8

PPG5: Works In, Near, or Liable to Affect Watercourses PPG6: Working at Construction and Demolition Sites PPG8: Safe Storage and Disposal of Used Oils PPG13: High Pressure Washers and Steam Cleaners PPG18: Managing Fire Water and Major Spillages The telephone number of SEPA s three Regional Headquarters are: North Region (Dingwall) 01349-862021 East Region (Edinburgh) 0131-449-7296 West Region (East Kilbride) 01355 574200 SEPA may be contacted 24 hours-a-day on an Emergency Hotline 0800-80 70 60. Guidelines for the special requirements V2 June 2006 Page 8 of 8