Q3 FY Analyst Meet Mumbai February 10, 2017

Similar documents
Fastest Growing Electric Utility in Asia for 3 rd successive year. An S&P BSE SENSEX Company Q2 FY Press Meet New Delhi November 9, 2016

Power Transmission in India

IMPLEMENTATION OF USE OF COUNTRY SAFEGUARD SYSTEMS IN POWERGRID (A CASE STUDY) POWER GRID CORPORATION OF INDIA LTD. ENVIRONMENT AND SOCIAL MANAGEMENT

Press Meet Mumbai 29 May, 2013

TRANSMISSION OPPORTUNITIES, CHALLENGES & WAY FORWARD. Confederation of Indian Industry NEW DELHI November 2, 2012

Flexibility in Indian Power System

PROJECT TECHNICAL DESCRIPTION

Overview of Indian Power Sector & Opportunities for for promoting Social Inclusion in Indian power sector

IEEJ:August 2018 IEEJ2018 JICA- ENERGY POLICY-2018 INDIA Ammi Ruhama Toppo Director Central Electricity Authority DATA TAKEN FROM CENTRAL ELECTRICITY

Renewable Energy Market Potential and Policy Overview in India

Status - Indian Electrical Industry April to March

EEC Conference. 31 th August, 2015, New Delhi. Large Scale Integration of Renewables. Power System Operation Corporation New Delhi, India

Tamil Nadu Moving towards 24/7 Sustainable Power Supply

May 24, 2018 I Industry Research. Power: Yearly Update and Outlook. Graph 1 Electricity Generation Mix (FY18)

CHAPTER 6 TRANSMISSION SYSTEM EXPANSION PLANNING AND APPLICATION OF FACTS CONTROLLERS

Q /11/17. Jon Skule Storheill. Øyvind Ryssdal

MAGADH Sugar & Energy Limited

AUSTRALIAN CLEAN ENERGY SUMMIT

Swelect Energy SystemsLtd.

Q4 & FY 14 PERFORMANCE HIGHLIGHTS

Q1 FY 18. Industry Update & Key Performance Highlights. 8 th August, 2017

FY18 RESULTS PRESENTATION

UK Generation. BAML lunch - 29 th March Alison Kay Commercial Director Transmission

RE Tariff Setting Approach

ENGINEERING AND CAPITAL GOODS

A Multi Stakeholder Perspective

Leading the way towards a Smart Grid Capital Market Day London, December 5, 2013

Electronics Limited. Inve. Results Presentation Q3 FY16

Dr. Jyoti Parikh Executive Director Integrated Research and Action for Development (IRADe)

UK Future Energy Scenarios. Richard Smith Future Transmission Networks Manager

POWER SECTOR A STUDY OF INDIA

Objects of the Issue

Tanla Solutions Ltd. acquires Karix Mobile for

HAMBURGER HAFEN UND LOGISTIK AG COMPANY PRESENTATION

Bandra Kurla Complex, Sandra East, Mumbai Script Symbol: FSC ISIN: INE93SQ01015

Cement Industry: Stable credit outlook - Demand recovery and higher sales realization to result in improved profitability in FY15

India s Grid Transmission Infrastructure Needs Further Modernisation, Urgently

IntraSoft Technologies Limited

/ IBE-WATCH FACT SHEET Q1 2017

Financial Performance Q1 & FY 19. Platforms and services for content creation, production, and distribution

MOL CEZ Joint Venture. Budapest, 20 Dec 2007

HAMBURGER HAFEN UND LOGISTIK AG COMPANY PRESENTATION

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

Flexibility Options in India

Q earnings. Investor Presentation

DTI GROUP LTD DTI GROUP LTD Interim Results Presentation 26 February Interim Results Presentation [_] February 2017

RENEWABLE ENERGY INTEGRATION IN TAMILNADU

Initiatives taken for Facilitating Large Scale Integration of Renewable Energy in India

ETHOS Limited. Result Update Presentation April 2018 Q4 & FY18

Hydro & Small Hydro Outlook in India 2017

Q /08/18. Jon Skule Storheill. Øyvind Ryssdal

For personal use only

Analyst Meet Siemens Ltd. November 23, 2012

POLICY BRIEF #25 BUILDING GLOBAL ENERGY INTERCONNECTION (GEI) TO PROMOTE 2030 AGENDA FOR SUSTAINABLE ENERGY DEVELOPMENT.

Importance of Intra-day Forecasts in Renewable Energy Sector to Reduce Imbalance & Congestion Costs in UK Power Grid

Enhancing Power Grid Reliability through Synchrophasor Measurements

Graphite India Limited

Comparative study on power situation in the Northern and Central states of India

National Council on Electricity Policy Annual Meeting & Workshop Denver, CO. May 8, Jeff Bladen Executive Director Market Development

The Role of Gas in Decarbonizing Europe. Keith Martin, Chief Commercial Officer, Uniper SE The European Gas Conference, Vienna January 31 st, 2018

DTE Energy s Utility Growth Strategy. Gerard Anderson President & COO April 6, 2006

Grid Integration Of RE Challenges, Roadmap And Way Forward

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019,

For personal use only

JICA s Experiences in Renewable Energy and Energy Efficiency

OM HOLDINGS LIMITED Investor Presentation May 2018

PERFORMANCE OVERVIEW: Q1FY 10 V/S Q1FY 09 (Q1 FY 10 October December 2009); (Q1 FY 09 October December 2008)

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Initiating Coverage: ACCUMULATE HINDUSTAN PETROLEUM CORPORATION LTD

Q3 & 9M FY15 Results. Leading Diversified Renewable Energy Generation Company

JFSL - Bangalore. Retail (~10% of the volume)

EMERGING AND PERSISTENT ISSUES

Tata Sons Private Limited

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Agenda Note for Connectivity Applications in Southern Region as per CERC Regulations, 2009

TeamLease Services Limited Investor presentation August Putting India to work

Renewable Integration in India

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

2018 Q1 Investor Relations Presentation

Myanmar Power Sector Financial Analysis and Viability Action Plan. Key Findings & Recommendations

SECTOR ASSESSMENT (SUMMARY): ENERGY (RENEWABLE ENERGY GENERATION SOLAR)

Strong Fundamentals Sustainable Value

Promoting Utility Scale Solar using Viability Gap Financing (VGF) modality in Nepal

JAPAN ELECTRICITY MARKET AND THE ROLE OF RENEWABLES

Flexibility and the outlook for the GB power market

PRESS RELEASE. GE Shipping FY14 consolidated Net Profit at Rs crs

ABENGOA. Chile, changing the energy matrix. Completing Transformation. Ivan Araneda. Innovative Technology Solutions for Sustainability

Investor Presentation

PRESS RELEASE. GE Shipping Q1FY12 consolidated Net Profit at Rs cr GE Shipping Q1FY12 standalone Net Profit at Rs cr

ECONOMIC AND FINANCIAL ANALYSES I. ECONOMIC ANALYSIS

CORPORATE PRESENTATION. Triveni Turbine Ltd. (May 2017)

SECTOR ASSESSMENT (SUMMARY): ENERGY

SE4ALL INITIATIVES IN BHUTAN

Hafslund a pure play utility

Shares Live Presentation I 10 September 2016 LON: CYAN

CROSS BORDER ELECTRICITY TRADE

1H18 results and strategic progress update

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Metamorphosis. Feature - T&D Infrastructure

INVESTOR PRESENTATION

Transcription:

Q3 FY 2016-17 Analyst Meet Mumbai February 10, 2017

Disclaimer By attending the meeting where this presentation is made, or by reading the presentation slides, you agree to be bound by the following limitations: This document has been prepared for information purposes only and is not an offer or invitation or recommendation to buy or sell any securities of Power Grid Corporation of India Limited (the Company ), nor shall part, or all, of this document form the basis of, or be relied on in connection with, any contract or investment decision in relation to any securities of the Company. The information in this document is being provided by the Company and is subject to change without notice. The Company relies on information obtained from sources believed to be reliable but does not guarantee its accuracy or completeness. This document contains statements about future events and expectations that are forward-looking statements. These statements typically contain words such as "expects" and "anticipates" and words of similar import. Any statement in this document that is not a statement of historical fact is a forward-looking statement that involves known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. None of the future projections, expectations, estimates or prospects in this document should be taken as forecasts or promises nor should they be taken as implying any indication, assurance or guarantee that the assumptions on which such future projections, expectations, estimates or prospects have been prepared are correct or exhaustive or, in the case of the assumptions, fully stated in the document. The Company assumes no obligations to update the forward-looking statements contained herein to reflect actual results, changes in assumptions or changes in factors affecting these statements. You acknowledge that you will be solely responsible for your own assessment of the market and the market position of the Company and that you will conduct your own analysis and be solely responsible for forming your own view of the potential future performance of the business of the Company. Neither the delivery of this document nor any further discussions of the Company with any of the recipients shall, under any circumstances, create any implication that there has been no change in the affairs of the Company since that date. Annual Accounts for FY2015-16 have been approved by the shareholders.

Recent Highlights Power Transmission Opportunities in India POWERGRID Today Performance (Q3FY17) Performance (Q3FY17) Transmission Consultancy Telecom XII Plan Performance Investment Outlook 3

4

±800kV HVDC Champa-Kurukshetra Pole-I Power Flow Test Charged Commissioning targeted in Feb 17 Power Transfer: 3000MW Between Champa in WR and Kurukshetra in NR Being implemented in Phases Phase-I, Pole-I: 1500 MW (~ 6,000 crore) Phase-I, Pole-II: 1500 MW (~ 3,200 crore) Line Length: ~ 1,300 km. Upgrade to 6000MW in Phase-II Largest 400/200 kv GIS in India: 51 bays 5

-400/+600MVAr SVC - Commissioned at Ludhiana One of the Largest Range Swing SVCs in the World Envisaged to improves Power Quality & Grid Stability Project included a high degree of local engineering & local production (Make-in-India) Thyristor Valves, Protection & Control Systems manufactured and tested locally in India 6

Project Execution Major Elements Completed since Oct 16 ER-SR Interconnection Angul-Srikakulam-Vemagiri Strengthening in SR Nagapattinam PS Salem Dharmapuri; Tuticorin-Dharmapuri Strengthening in Western UP Dehradun-Baghpat-Saharanpur; Dehradun-Roorkee 7

Commissioning/ Capitalization Completed/ Commissioned in FY17 (Apr 16-Jan 17) ~ 26,700 crore: Completed (including Champa- Kurukshetra HVDC & TBCB) ~ 20,700 crore: Commissioned/ Capitalized (incl. TBCB) 8

Special Highlight POWERGRID Market Capitalization crosses 1 lakh crore POWERGRID Stock crosses 200 mark 200 Snapshot: BSE 01.02.17 9

10

Glimpse of Indian Power System Broad Parameters Capacity (GW): Source-wise Segmentation (%) Total Installed Capacity ~ 310 GW CAGR (Mar12-Dec16): 9.7% Annual Consumption 1200 BU Growth: 5.64% (y-o-y) Peak Demand Met: 157 GW Power Market 9-10% Coal, 189, 61% Hydro, 43, 14% Diesel, 1, 0% Nuclear, 6, 2% Gas, 25, 8% RES, 46, 15% Wind, 28, 9% Small Hyd, 4, 1% Biomass, 5, 2% Solar, 9, 3% As on Dec 2016, CEA Reports 11

Indian Power System- Changing Paradigm Renewable: 46 GW CAGR (Mar12-Dec16): 14.1% Wind Solar Total RE Wind Solar Total RE 175.0 32.7% RE Installed Capacity (GW) RE/Total Installed Capacity (%) 25.0 28.1 31.7 34.2 17.4 19.1 21.1 22.6 42.6 26.9 0.9 1.7 2.6 3.4 6.8 60.0 100.0 0.5% 0.8% 1.1% 1.2% 2.2% 18.7% 12.5% 12.6% 12.9% 12.6% 14.1% 11.2% 8.7% 8.5% 8.6% 8.3% 8.9% Mar'12 Mar'13 Mar'14 Mar'15 Mar'16 FY22 Mar'12 Mar'13 Mar'14 Mar'15 Mar'16 FY22 12

Indian Power Sector - Outlook 24x7 Affordable Power for All by 2019 Renewable Integration : 175 GW by 2022 Per Capita Consumption : about 4000 units by 2030; CAGR:10% Seamless SAARC Power Grid 13

Towards 24x7 Power For All by 2019 One Nation One Grid One Price Power Market Bringing Efficiency Into the Sector 20 Dec 16 at 9:45 pm Snapshot 14

National Grid Augmentation Creation of Energy Highways based on envisaged load growth - 11 high capacity corridors - each capacity of about 4000 MW - 3 high capacity HVDC system (6000 MW each) 11 nos. High Capacity Transmission Corridors Wide Area Measurement System (WAMS) - Making Smart Grid 15

Renewable Integration Challenges Intermittency Variability Matching Transmission Development Load- Generation balance Remedial Measures Green Energy Corridors Green Energy Corridors-II (Solar Park Integration) Dynamic Compensation Renewable Energy Management Centres Storage Renewables involves Integration i.e. bringing together separate elements to create a whole unit 16

Development of Green Energy Corridors Green Energy Corridors for Renewables (Inter-State Transmission Systems) 17

Green Energy Corridors-II: Solar Parks Integration 34 Solar Parks 20 GW Locations of Ultra Mega Solar parks Inter-State transmission 13 solar parks ~ 9,220 MW capacity Intra-State transmission 21 solar parks ~ 10,780 MW capacity 18

Dynamic Compensation Maintaining Grid Parameters Hybrid STATCOMs 14 Nos. 400 600 MVAR SVCs 4 Nos. 500-1000 MVAR 19

Renewable Energy Management Center REMC Co-located with RLDC/SLDC RE Forecasting & Scheduling Real Time tracking of RE Generation 11 no. of REMC : 7 States + 3 Regions + 1 National level 20

SAARC Interconnections Geographically widely spread Indian Grid can facilitate interconnections with Neighboring countries India can provide a good demand market to harness energy resources of other countries Optimal utilization of energy resources 21

Sectoral Investment Envisaged (2017-2022) Investment Envisaged: ~ 2,60,000 cr. (includes 30,000 crore for investments in Trans. Systems below 220kV levels) Physical Additions Planned: 106,000 ckm of Transmission lines 292,000 MVA Transformation Capacity 14,000 MW HVDC Bipole line Source: CEA Draft National Electricity Plan(Vol-II) Transmission, 2016 22

23

POWERGRID Today >90% ISTS Transmission Network owned by POWERGRID POWERGRID s Transmission Assets: Trans. Lines: 134,750 ckm Sub-stations: 217 Nos. - 280,362 MVA 400kV & above: >90% Availability: 99.76% (Apr16-Dec16) >45% power generated in India transmitted through POWERGRID POSOCO, POWERGRID s wholly owned subsidiary, hived off into a separate independent company, as per Govt. directives Market Capitalization 1 : 1,08,059 crore Physical parameters as on 31 st January, 2017 1- Based on BSE Closing Price of 206.55 per share on 31.01.2017 24

25

Performance- Financial (Q3 & 9mths FY17) Description Revenue - Transmission Charges - Consultancy Income: Services 31.12.2015 As per Ind AS Quarter ended 31.12.2016 As per Ind AS 5,153 6,336 114 164 % change 23% 44% 31.12.2015 As per Ind AS Nine Months ended 31.12.2016 As per Ind AS 14,335 18,196 302 438 ( in crore) % change - Telecom 103 130 26% 288 371 29% - Other Income 107 158 334 522 Total Income 5,477 6,788 24% 15,259 19,527 28% -Operating Expenses 583 679 1,696 2,035 EBITDA-Gross Margin 4,894 6,109 13,563 17,492 Depreciation 1,585 1,965 4,411 5,599 Finance Cost 1,288 1,643 3,615 4,748 Tax 415 571 1157 1541 Profit after Tax 1,606 1,930 20% 4,380 5,604 28% Other Comprehensive Income/ (Exp) net of Tax 10 (30) (12) (14) Total Comprehensive Income 1,616 1,900 4,368 5,590 27% 45% 26

Performance Financial (Q3 & 9mthsFY17) ( in crore) As on 30.09.2016 As per Ind AS As on 31.12.2016 As per Ind AS As on 31.12.2015 As per Ind AS Gross Fixed Assets 1,58,937 1,65,757 1,44,795 Capital Work-in-Progress 46,335 45,991 46,000 Debt 1,12,284 1,15,924 1,05,387 Net Worth 46,391 48,290 42,598 Earning Per Share ( ) 7.02# 10.71# 8.37# Book Value per Share ( ) 88.67 92.31 81.43 Key Financial Ratios Debt : Equity 71:29 71:29 71:29 Return on Net Worth 7.92%# 11.60%# 10.28%# # Not Annualized 27

Performance - Financial (Billing & Realization) As on 31.12.2016 Total Outstanding Transmission Outstanding (beyond 60 days) Billed but not outstanding (<60 days allowed as per CERC) ~ 3,749 crore (53 days billing # ) ~ 792 crore (11 days billing # ) ~ 2,958 crore (42 days billing # ) # Avg. Monthly Billing: 2,126 => 2 months 60 days) billing = 4,252 crore Tripartite Agreement signed by 12 States; Others in Progress 28

Performance: Projects- Q3 & 9mths FY17 Chart Title Till Jan 17 Capitalization 2,462 6,688 6,820 15,970 ~ 20,700 cr. (*) (Commissioning) Capex 5,585 5,291 5,170 16,046 ~ 17,908 cr. Q1FY17 Q2FY17 Q3FY17 (*) excluding Champa- Kurukshetra ±800kV HVDC FY16 (Apr-Dec) FY17 (Apr-Dec) Investment Approvals 9,490 28,133 Contracts Awarded 13,465 21,942 Investment Approval in FY17 till date: 34,809 crore 29

Performance - Physical Apr-Dec16 (9mths) Tr. Line: ~ 4,650 ckm S/S: 7 Nos.; ~24,000 MVA Inter-Regional Capacity: 3,600MW Targeted for Q4FY17 Tr. Line: ~ 4,750 ckm S/S: 7 Nos.; 14,000 MVA Inter-Regional Capacity: 11,400MW 30

Performance- Operations: FY17 (till Dec-16) Assets (Dec 16) Trans. Lines: Sub-stations: 1062 Nos. ~ 134,000 ckm 214 Nos. ~ 278,860 MVA Performance (Apr-Dec 16) Availability: 99.76% Reliability: 0.57 * * Trippings per line 31

32

Consultancy Q3FY17 Overall Consultancy Income 44% (over Q3FY16) New Orders in Q3FY17 Domestic: 8 Nos. (Project Cost: ~ 1300 crore) International: 3 Nos. (Project Cost: ~USD 3.3 mn) Assignments in Hand (Dec 16) Domestic: 105 Nos. (~ 16,700 crore) International: 17 Nos. 33

Telecom Q3FY17 Increase in Income 26% w.r.t Q3FY16 Infrastructure: Fiber Optic Network : ~ 36,500km Points of Presence : 595 Backbone Availability : 100% Major Projects: National Knowledge Network (NKN): Project completed & Under Operation National Optic Fiber Backbone (NOFN): Work in progress Scope of work enhanced to connect 9,372 Gram Panchayats - 5,447 Gram Panchayats connected 34

35

XII Plan Performance Planned Capital Outlay 110,000 crore FY12-13: 20,037 cr. (Achieved) FY13-14: 23,158 cr. (Achieved) Annual Capex Plan FY14-15: 22,456 cr. (Achieved) FY15-16: 22,584 cr. (Achieved) FY16-17: 22,550 cr. [Achieved 17,908 cr.] ~ 106,143 crore achieved in XII Plan (Apr12 till Jan17) Physical Parameters (Ap12-Jan17) Target Achievement Transmission Lines 40,000 ckm 41,769 ckm (104%) Sub-stations 60 Nos. 67 Nos. (112%) X-formation Capacity 100,000 MVA 155,837 MVA (155%) 36

37

POWERGRID Outlook (as on Dec 16) Ongoing Projects approx. 1,10,000 crore New Projects approx. 13,000 crore TBCB Projects approx. 16,000 crore (as per Empowered Committee Estimate) Total Works in Hand approx. 1,39,000 crore 38

Investment Potential Transmission (TBCB)- under various stages of bidding Inter-State: 8,697 crore - 7 projects Intra-State: 5,265 crore - 10 projects in 4 States 14,000 crore Thrust of Railways on upgradation and modernisation: Railways Target to achieve electrification of 90% tracks in next 5 years from current levels (<50%) 24,000 rkm to electrified by 2021 (Target: 2000 in FY17; 4000 in FY18, 6000 annually during FY19-FY21) POWERGRID already implementing a pilot for 761 rkm 39