Petro-Canada Refinery Conversion Project. Presentation to AACE, Calgary. November 9, 2005

Similar documents
Brownfield Projects. Equinox Engineering

ISA Calgary. September 26, 2013

Original Plan Phase 1 - Work progress (cumulative) 90% 94% 95% 97% 97% 99%

Bolt-On Thermal Maintenance System in new SRU challenges old design rules

Refining. Capability & Experience

ECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP

OPTI. October 2002 SHELL GLOBAL SOLUTIONS CANADA INC.

Hydrogen for the NWR Upgrader by Lurgi MPG Technology A challenging Project

Life In The Heartland Sturgeon Refinery Update. October 27 th, 2014

DHL INDUSTRIAL PROJECTS SPECIALIZED LOGISTICS SAFELY AND SKILLFULLY EXECUTED

AFPM 2018 Operations & Process Technology Summit

Achieving Process Energy Efficiency via Innovation Honeywell. All rights reserved.

Section 4: Project Execution

Advanced Work Packaging IMPLEMENTATION

Essential Duties (Roles and Responsibilities)

GTC TECHNOLOGY. GT-UWC SM How a Uniting Wall Column Maximizes LPG Recovery. Engineered to Innovate WHITE PAPER

Building Foreman s Workface Packages. WFP Conference 2010 Calgary, Alberta December 1, 2010

Delayed Coking Process Design, Operations and Optimization. Canada Coking Conference October 22-26, 2012 Fort McMurray, Alberta

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects

Balancing Hydrogen Demand and Production: Optimising the Lifeblood of a Refinery Luigi Bressan Director of Process and Technology Foster Wheeler

Strathcona County. Living.Refined.

Procurement and Supply Chain In a Work Face Planning Environment

ADVANCED WORK PACKAGING BACK TO BASICS for MANAGING ENGINEERING

Gasification...Meeting the Challenges of Oil Sands

Corporate Profile. Synopsis. HEAD OFFICE Ave. S.W. Calgary, AB T2R 0C9. Tel: (403) Fax: (403)

HEAVY CRUDE UPGRADING: AN OPTION FOR GASIFICATION

Bitumen Upgrader Residue Conversion to Incremental Synthetic Fuels Products

INDUSTRY EXPERT PANEL SESSION

Identification Selection Definition Execution. Schedule.

Upgrading with a soft touch

Leading Indicators and Dashboarding for Advanced Work Packaging. Lloyd Rankin

Path of Construction Enhancing the Best Practice for Engineering & Supply Chain to Support AWP Implementation

Construction Simulation An Introduction

Hydrogen: The Lifeblood of a Refinery Options for Refiners

Reducing FCC Turnaround Costs Focus on Speed & Safety. Brent Dell Sr. Technical Engineer

Reducing FCC Turnaround Costs Focus on Speed & Safety. Brent Dell Sr. Technical Engineer

Representation from leading Owner & Contractor Organizations - Diverse Experience

A Maintenance View. Presenter David Kay

Janice T. DeVelasco, P.E.

Canada s Oil Sands - A World-Scale Hydrocarbon Resource

1. Refinery Operations 1 2. Mechanical Maintenance and Inspection 3. Instrumentation and Electrical Maintenance 4. Refinery Management

MATERIAL VISIBILITY. for Owners/Operators: The Importance of A CASE STUDY

Project Production Institute Challenges and Myths of Offsite Fabrication for Mega Projects

Heavy Oil Upgrading from mine to motor

Self Lubricated Transport of Bitumen Froth from Concept to Commercial Demonstration

Taking AWP to the Next Level

Changing US Crude Oil Imports are Driving Refinery Upgrades, Creating Opportunities

Monday March 10, 2008 Afternoon Sessions

Memoranda On Front-end Crude Fractionation.

Many in situ bitumen producers face a challenge how to recapture

Oil and Gas : Engineering, Procurement, Construction & Maintenance solutions

Project Management Consultancy Services. Ensuring safe and successful execution of your projects

Project Agreements, Risk Management and Litigation Risk Sean Ralph, General Counsel, Sasol Canada Phil Scheibel, Partner, Rose LLP

Taravosh Jam Design & Engineering Co.

Value of Canadian Oil Sands

OIL & GAS DOWNSTREAM ASSET OPTIMISATION AND COMPLIANCE FOR PROCESS INDUSTRIES, STORAGE AND DISTRIBUTION

Successful Migration of a Legacy Control System At Marathon Petroleum Company LLC

Project Management Consultancy Services. Ensuring safe and successful execution of your projects

Bitumen Upgrader Residue Conversion to Incremental Synthetic Fuel Products

Units Capacity Location. PRFCCU MMTPA 3 Mumbai Refinery. SRU MT/D 165(note 1) Mumbai Refinery. POLYPROPYLENE UNIT KTPA 450 Rasayani

WFP GLOSSARY. COP-WFP-TMP v1. Authorization for Expenditure

AWP: The Silver Bullet for Solving Productivity Problems on Projects?

Addressing Complex Challenges With Rundown Blending in Aspen Refinery Multi-Blend Optimizer. White Paper

Doseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers

Products CONSTRUCTION REVAMPS STUDIES MANGAGEMENT. Steam Methane Reformers. Ethylene Crackers. Fired Heaters. SCR Systems. Waste Heat Recovery Units

TRANS MOUNTAIN PIPELINE ULC

CAPABILITY STATEMENT PRIZM Engineering Pty Ltd ABN

Husky Increasing Resiliency with Thermal Momentum and Downstream Integration

Process, Power and Marine Division

Cost-Effective Refinery Expansion Enables Lighter Crude While Maximizing ULSD

Meadow Creek West. Project overview:

What is InterEnerStat

engineering. procurement. construction. management

WWT Two-Stage Sour Water Stripping

Selected References. Client Place Country Start End Project description Services and supplies by Pörner Remark

Latest Development of Lurgi s MPG-technology Update on Hydrogen Unit for NWU Project

Coker Safety and Reliability Lessons Learned

Corrosion monitoring solution for sour water stripping units

We understand that carbon pricing and emission reduction targets are going nowhere but up.

GT-LPG Max SM. Maximizing LPG Recovery from Fuel Gas Using a Dividing Wall Column. Engineered to Innovate

ENGINEERING, PROCUREMENT & CONSTRUCTION MANAGEMENT

CII Performance Assessment Report Industrial Projects Construction Phase

Current State of PSM

Tackling the Unique Challenges of Mega Projects. ECC Annual Conference September 26-29, 2007 Colorado Springs, Colorado

Meeting the Challenge of EPC Project Proposal Schedules. Project Proposal Schedules

TABLE OF CONTENT

Abstract Process Economics Program Report 229 REFINERY RESIDUE GASIFICATION (June 2001)

This document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering

Neal E. Cammy, BLAC INC. Engineering Manager

LNG Experience. Owner & Investor Project Management

The Egyptian Refining Company

MARKET STRATEGY AND DEVELOPMENT OF ADVANCED CATALYTIC PYROLYSIS TO DROP-IN HYDROCARBON FUELS

Operational Excellence: the key role of integrated planning and scheduling in a merchant oil refinery. Budapest, 14th October 2015

SOLUTIONS FOR HEAVY OIL

Investor Presentation. Syria, October 2010

Crude Oil Quality Group (COQG)

Best Practices Awards Nomination Form

BPPII Pilot Project (Year-2) Prof. Bon-Gang (BG) HWANG (Dr.), NUS Prof. Carlos H. Caldas (Dr.), UT-Austin

SOLUTIONS FOR HEAVY OIL

OWN The Owner s Estimate Requirements Document

Transcription:

Petro-Canada Refinery Conversion Project Presentation to AACE, Calgary November 9, 2005

TLM MOMENT All Losses are important and represent an opportunity to improve Health Safety Environmental Quality

BUILDING ON SUCCESS RCP IS IN THE HOMESTRETCH Execution phase is culmination of over 10 years of work RCP completes transformation of Edmonton Refinery & is critical to the continued economic success of Petro-Canada s downstream business Tank farm, SIG, EDD & GOT projects have built and continue to build a foundation of success for RCP Collectively, Petro-Canada, Bantrel, Jacobs & their subcontractors will cap off the conversion journey with a successful RCP project!

PETRO-CANADA CONTINUES TO PURSUE A FULLY INTEGRATED OIL SAND STRATEGY 2008+ 27,000+ bpd bitumen MacKay River Suncor 22,000+ bpd sour synthetic 26,000 bpd purchased sour synthetic In Situ 3035,000-40,000 bpd bpd purchased In Situ II bitumen blend 26/9 ~50,000 bpd sweet synthetic crude Edmonton Refinery 135,000 bpd refined products to market Syncrude

DESULPHURIZATION & RECONFIGURATION Edmonton Edmonton Refinery Refinery Edmonton Infrastructure Refinery Sulphur Pre Diesel Conversion Low in Support Sulphur Desulphurization Gasoline Program (Tank Fuels (SIG Operation Farm (RCP - 2004) (EDD 2-1 2008) 2003) --2001) 2006) Sweet Synthetic Synthetic Crude Unit Sour LightSyn & Crude Bitumen Conventional Sour Crude Crude & & Vacuum Vacuum Unit Unit BDS (Naphtha & Naphtha Distillate) Hydrotreater Distillate Hydrotreater Secondary Units & Product Blending Refined Products to Market Gasoil Hydrotreater 16.6 Delayed KBPD Delayed Coker Coker RCP Sulphur Sulphur Plant Plant Hydrogen Plant EDD Hydrogen Plant RCP Hydrogen Plant Tank Farm 1 Tank Farm 2

PROJECT SUCCESS CRITERIA PROJECT GOAL: To safely deliver a first quartile facility that will utilize bitumen derived feedstocks to meet the product demands as forecasted.

PROJECT SUCCESS CRITERIA Project Critical Success Factors: Zero harm to all who work on the project Acceptable project economics achieved by: Optimizing project execution - Execution excellence Delivering the FEED scope inside $1550MM Mechanical Completion by Q2 2008 Full nameplate capacity in < 45 days after mechanical completion Zero production impact on the existing facilities during commissioning People make projects work Communicate often, openly, & contracting for action

REFINERY CONVERSION PROJECT PROFILE Conversion of the Edmonton Refinery to Process 85,000 BPSD of heavy oil and Bitumen by 2 nd Quarter 2008 Scope Crude Unit Vacuum Unit Delayed Coker Revamp of Existing Units Sulphur Complex Associated U&O, Automation and Site Prep

RCP PROCESS AREAS Sulphur Complex Plant 63 Revamp Crude / Vacuum Delayed Coker Plant 2-4 Revamp Coker

CRUDE/VACUUM Crude Heater Vacuum Heater Vacuum Tower Desalter Substation & I/O Crude Tower

DELAYED COKER Coke Drums Rail Car Handling System Coker Fractionator Coker Heater

REVAMPS PLANTS 1, 2 & 4

REVAMPS PLANT 63

SULPHUR COMPLEX Amine Regeneration Area Sour Water Stripping Units Superclaus Unit Incinerator Sulphur Storage Amine Pumphouse & Surge Tank Sulphur Recovery Units

UTILITIES AND OFFSITES

PROCESS AUTOMATION OBJECTIVES: Provide fully integrated process control system integrating existing and new units Ensure all areas of system design and execution comply with existing standards and are consistent across areas SCOPE CAN BE DIVIDED INTO 2 PARTS: Upgrade existing control system to new Experion operating Platform Process Control implementation

PROCESS AUTOMATION

CURRENT STATUS Feed completed Long lead equipment order placed Stage Gate Review completed Baseline established Petro-Canada Board approval received Execution Phase Kick-off November 7 th, 2005

PROJECT BASELINE Capital cost $1.55 Billion Schedule completion April 2008 Project Approval October 2005 Site Prep complete March 2006 Construction start April 2006 Engineering 80% complete November 2006 Module fabrication commences March 2006 Construction completion in Shutdown April 2008 Full production 2 nd Quarter 2008 Zero Harm, Zero Loss, Zero Impact

ESTIMATE BREAKDOWN Sour Crude/Vacuum Sulphur Complex Delayed Coker Existing Plant Revamps U&O (including Site Prep & Automation Owners Cost

EXECUTION STRATEGY Petro-Canada Managing Contractor EPC Silo Execution (Jacobs and Bantrel) Sub-contractor and DFL Construction Supplier of Choice Agreements Work Package approach to E P & C 80/100 strategy for construction packages WBS supports Execution Plan Bag and Tag approach to Revamp work RFO integral part of Project Team Site preparation to be completed in early 2006

PROJECT SILO STRUCTURE RCP Crude Vac Coker Automation F&I Sulphur Complex Revamps U&O Bantrel Bantrel Bantrel Bantrel Jacobs Bantrel Bantrel

PROJECT EXECUTION STRUCTURE General Automation Contractor, GAC Crude/ Vaccume Delayed Coker Sulphur Complex Utilities & OffSite Revamp Construction Facilities and Site Infrastructure, F&I

EXECUTION STRATEGIES Scope is defined robust FEED package Funds are allocated the resources are available Teams are experienced - and know how to do it They know the Refinery, its people and requirements They have the systems, structures, methodologies, procedures and lessons learned RCP will Build on Success of recent successful projects RCP is larger than EDD, it is much more complex Market conditions, complexity, site congestion, integration We will take it to the next level!

EXECUTION STRATEGIES The Project participants are working together to further a culture of cooperation, no surprises and no changes. Open and honest communication Regular and frequent contact Clear expectations of roles and responsibilities Discussion and alignment with success criteria Adherence to procedures and execution plans Identify potential issues when they arise No Surprises Proactive versus reactive

PROJECT CHANGE CRITERIA Scope is defined Execution Plan has been optimized by the team Non-discretionary changes affecting design, only if: It is not safe or environmentally acceptable It won t work It s not operable or maintainable It doesn t meet regulatory requirements Discretionary change: Return on investment > 50% / 1 year payout for proposed scope versus design specifications No schedule impact

COST & SCHEDULE Schedule Schedule basis is backward driven from RFO completion Level 3 FEED is baselined Cost Control Sanction is $1550 Million, including Owner s cost The project is cost driven and must deliver Trend surveillance, especially on quantities, as design progresses is the key The projects needs everyone to play a role Progress Measurement Key quantities and deliverables updated on a regular basis IFCs must be linked to the schedule

CONSTRUCTION EXECUTION ZERO HARM, ZERO REWORK, ZERO IMPACT Basis for construction sequencing is Systems Handover priorities This drives engineering IFC issues Engineering planning is driven back from RFO handover EWP-CWP- IWP PIPE INSTALL HYDRO FLUSH REINSTATE PRE-COM HANDOVER Management of Interfaces across the silos is key to successful RCP construction completion U & O Team to lead RCP Team to make Edmonton Refinery the site of choice for Trades THOR

PROCUREMENT EXECUTION The very hot market makes it critical that we complete vendor awards quickly with quality packages and control changes This requires diligent inspection in the vendor shop throughout the process Expediting and Quality control starts with the order and continues until the material is satisfactorily delivered at site Procurement Quality on schedule, meets specs and complete PC has established Supplier of Choice (SOC) agreements for key bulk piping materials that will be used by the EPCs

ENGINEERING EXECUTION Maintain the 80/100 rule with all deviations processed through the MOC Procedure Engineering execution is quality and timely delivery adhering to the schedule Ensure data is received early to support design Consider all avenues to advance required vendor information Early planning reviews have been conducted for: Constructability Operability Maintainability Construction sequencing Regular quantity trending as design progresses

MOVING FORWARD To meet Petro-Canada s expectations, the project is focusing on the road ahead with energy, vigor, rigor and diligence The FEED package is robust. The project has a very experienced project team However, we have risks

SIGNIFICANT RISK TO SUCCESS Competitive Market Place Home office personnel availability Equipment cost and delivery schedule Bulk material cost and availability Fabrication shop loading Subcontractor availability Labour cost and availability Construction supervision Construction equipment availability

BUILDING ON SUCCESS

QUESTIONS?