Tapping Spout. Hot Swt. Typical Steelmaking Cycle

Similar documents
Optimization of EAF Operations Through Offgas System Analysis INTRODUCTION

EAF Technology and process

PYREJET A MULTI-FUNCTION COMBUSTION/INJECTION SYSTEM FOR EAF STEELMAKING

Steel Making Prof. Deepak Mazumdar Prof. S. C. Koria Department of Materials Science and Engineering

^ Springer. Innovation in Electric. Arc Furnaces. Ilyaz Y. Zinurov. Scientific Basis for Selection. Yuri N. Toulouevski. Revised and Supplemented

Steel Making Prof. Deepak Mazumdar Prof. S. C. Koria Department of Materials Science and Engineering

Steel is the most important material for the

Smart-Gas A New Approach to Optimizing EAF Operations

The Safe Use of High Power in a DC Arc Furnace

In the past few decades the importance of DRI as a

Lecture 17 Alternative Charge Materials in EAF

During the past 11 years, steel

THE MOST ADVANCED POWER SAVING TECHNOLOGY IN EAF INTRODUCTION TO ECOARC

Part III: Slag Practices and Oxygen/Carbon Injection when Melting Direct Reduced Iron

OPERATING EXPERIENCE AT A 170 t EAF WITH EPC SCRAP PREHEATING SYSTEM KNUT RUMMLER* DR. HEINZ MÜLLER**

Overview and EE&C of Steel Industry in Japan

Fast and reliable temperature measurement at end of melting cycle in EAF

EAF Steelmaking in North America An Overview

Realization of the coexistence of energy saving and environmental measure in the EAF - Concept of ECOARC TM -

Use of DRI in EAF s. Gregory L. Dressel Dressel Technologies Pawleys Island, SC. Part II: Feeding and Melting of Direct Reduced Iron.

EAF REFRACTORY PERFORMANCE AT PACIFIC STEEL NEW ZEALAND

Final Technical Report. Project Title: Melting Efficiency Improvement. Award Number: DE-FC36-04GO Project Period: (January 2004 June 2012)

This place covers: all treatments of molten iron or steel, including the apparatuses specifically related thereto, e.g. converter, electric furnace.

MELTING PROCESS INTENSIFICATION AT 20 t EAF - ŽĎAS, A.S.

Improving Steel Plant Work Environment

(12) Patent Application Publication (10) Pub. No.: US 2007/ A1

Chapter 2 Electric Arc Furnace as Thermoenergetical Unit

AGN Arc Furnaces

Steelmaking using Induction Furnace

PILOT PLANT PRODUCTION OF FERRONICKEL FROM NICKEL OXIDE ORES AND DUSTS IN A DC ARC FURNACE. Abstract

Operating results of Goodfellow EFSOP at Riva Galtarossa, Italy

Lecture 19: Emerging Steelmaking Technologies

HYL III: Status And Trends

RECYCLING PRACTICES OF SPENT MgO-C REFRACTORIES

SHADEED IRON & STEEL OMAN, SOHAR PORT THE FIRST HOTLINK STEEL PLANT

SINGLE BUCKET CHARGING PRACTICE WITH TELESCOPIC EAF ROOF CLOSURE

Improving EAF performance at Dongbu Steel

Manufacture of Iron & Steel. Prepared By: John Cawley

SHARC - Shaft arc furnace with efficient scrap preheating concept provides low conversion costs

EAF PROCESS OPTIMIZATION WITH AMIGE SMARTFURNACE SYSTEM

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

ENERGY ANALYSIS OF THE STEEL MAKING INDUSTRY

Development of EAF Dust Recycling and Melting Technology Using the Coal-based FASTMELT Process

< > The Experience of ArcelorMittal Lázaro Cardenas Flat Carbon. By R. Lule 1), F.Lopez 2), J. Espinoza 3) R. Torres 4) & R.D.

Metallurgical Gas Cleaning System Design for Emissions Control and Energy Efficiency

Toxic Reduction Act Gerdau Ameristeel Corporation Whitby Mill Phase 2 Toxics Reduction Plan Summaries

Model Fitting for Electric Arc Furnace Refining

ELECTRIC INDUCTION FURNACE

Installation of Praxair s CoJet Gas Injection System at Sumikin Steel and other EAFs with Hot Metal Charges

Production of Iron and Steels

Lecture 14 Modern trends in BOF steelmaking

FIRST OPERATING EXPERIENCES WITH POST-COMBUSTION LANCES AT BOF SHOP LD3

The economics of electric arc furnace (EAF) technology

GAS METAL ARC WELDING (GMAW)

Choosing the Right Technologies for Reverb Furnaces. Russell Hewertson, Manager of Combustion Technology

Sensors and measurement techniques for monitoring and control of the EAF process

Two integrated steel plants (Phase 1 and 2), both

MODULE TECHNOLOGY OXYGEN, CARBON AND LIME SIDE WALL INJECTION TECHNOLOGY FOR ELECTRIC ARC FURNACES

Casting & Welding Engineering (IE 203)

The KT injection svstem for high-perfo electric-arc furnaces

Optimising Consteel continuous scrap feeding with roof-fed DRI

ArcSave, Innovative Solution for Higher Productivity and Lower Cost in the EAF

Introduction to Welding Technology

Welding Engineering Prof. Dr. D. K. Dwivedi Department of Mechanical and Industrial Engineering Indian Institute of Technology, Roorkee

ENERGIRON DR TECHNOLOGY AND NATURAL GAS: THE NORTH AMERICA PERSPECTIVE

Lecture 12 Converter Steelmaking Practice & combined blowing. Key words: Top blown steelmaking, combined blowing, bottom stirring, hot metal refining

3 TIG welding. 3.1 A description of the method. 3.2 Equipment

High-Carbon DRI: the feeding material to improve performances and decrease

Importance and Effect of Foaming Slag on Energy Efficiency

FURNACES. A furnace is a device used for heating. The name derives from Latin Fornax; oven.

Metal 2003 May Hradec nad Moravici, Czech Republic. CONARC - All purpose Steelmaking by SMS Demag By: K. Schmale; D.

A New Approach to EAF Melted Steels

AGENDA. - Conclusions. - i EAF. - i Recovery. - Definition. - Implementation. - Results

DIRECT SMELTING OF STAINLESS STEEL PLANT DUST

Simultaneous Oxygen, Nitrogen and Hydrogen Determination of Metals. Dennis Lawrenz, John Hawkins

OPERATIONAL RESULTS AT NUNKI STEEL

Improved Quality by Electro Slag Re-Melting

CHAPTER - 3 PERFORMANCE ANALYSIS OF INDUCTION FURNACE

Strong under tension and compression. Malleable. Low density. Have a dull appearance. Good conductors of electricity and heat

Implementation of Slag Engineering Techniques at CO-Steel Raritan to Improve Melting and Refining Practices

Lecture 23: Injection ladle metallurgy

Pyrometallurgy of iron is still the most important pyrometallurgical process economically.

Final Report on Energy Efficiency and Energy Savings in Recycling. S. Bell, B. Davis, A. Javaid and E. Essadiqi. Report No (CF) March 2006

Technology Improving Your Meltshop Performance

Development of a Process to Continuously Melt, Refine, and Cast High-Quality Steel

Leadership in Soft Magnetic Alloys

3. HOT ROLLING SHOP 4. COLD ROLLING SHOP

Atlantis, The Palm, Dubai, U.A.E December 10, 2014

FERRO ALLOY DESIGN, FERRO ALLOY SELECTION AND UTILISATION OPTIMIZATION WITH PARTICULAR FOCUS ON STAINLESS STEEL MATERIALS

NAME 345 Welding Technology Lecture 09 SAW, ESW & Resistance Welding

Materials & Processes in Manufacturing. Introduction. Introduction ME 151. Chapter 6 Ferrous Metals and Alloys

Alloy Recovery and Control in Steel Melting

Lecture 26 Degassing Practice

Forno elettrico. The LM.3 - the new era of efficient energy input optimization in the EAF

Lecture 42: Self Assessment questions. 1a) Explain the role of a basic oxidising slag in steelmaking. (04)

WELDING Topic and Contents Hours Marks

Lecture 21: Evolution of ladle Treatment and Requirements

United States Patent (19) Udo

IRONMAKING and THEORY AND PRACTICE. Ahindra Ghosh Amit Chatterjee

Production and Use of Industrial Gases for Iron and Steelmaking

Transcription:

Introduction Over the past two decades the use of electric arc furnaces (EAFs) for the production of steel has grown dramatically in the United States. In 1975 EAFs accounted for 20% of the steel produced; by 1996 the figure had risen to 39% and by the year 2000 (or shortly thereafter) could approach 50%. There are two major reasons for this trend-lower capital cost for an EAF steelmaking shop and significantly less energy required to produce steel by the EAF versus the blast furnace/basic oxygen furnace method of the integrated steelmaker. EAFs range in capacity from a few tons to as many as 400 tons, and a steelmaking shop can have from one to five furnaces. In brief, EAFs can be either ac or dc powered and they melt steel by applying current to a steel scrap charge by means of graphite electrodes. It requires about 360 to 400 kwh of electricity to melt a ton of steel; consequently, these furnaces use a tremendous quantity of power. Transformer loads may reach 150 MVA. The features of EAFs are described in a prior CMP TechCommentarytitled Introduction to Electric Arc Furnace Steelmaking (TC-107713). The purpose of this TechCommenraw (TC-107714) is to give utilities a more comprehensive understanding of the electrical operations and energy usage, and to review some of the innovations that are making the EAF a very energyefficient steel melter. Arc Ignition Period (Start of Power Supply) Long Arc! Main Melting Period n! Tapping Spout Hot Swt Typical Steelmaking Cycle Meltdown Period Figure 1. Steel Melting Cycle. Figure 1 shows a typical heat cycle, commonly referred to as the tap-to-tap cycle, for the EAF. The cycle starts with the charging of the furnace with steel scrap. After the furnace is charged and the roof is in place, the operator lowers the electrode or electrodes, each of which has its own regulator and mechanical drive. Current is initiated and thelectrodes bore through the scrap to form a pool of liquid metal. The scrap helps to protect the furnace lining from the high- L Liquid Bath Molten Metal Formation Period Short Arc I-l!! Bath Meltdown-Heating Peiiod intensity arc during meltdown. Subsequently, the arc is lengthened by increasing the voltage to maximum power. Most modern furnaces are equipped with water-cooled panels in the upper half of the sidewall, rather than refractories, which allow for longer arcs and higher energy input to the furnace. In the final stage, when there is a nearly complete metal pool, the arc is shortened to reduce radiation heat losses and to avoid refractory damage and hot spots. After rneltdown, oxygen is injected to oxidize the carbon in the steel or the charged carbon. In some opera-

~~ ~~ 1OOO- Utm-High 900-800 - 700 I 600 - High ooo- 400 300 - Medium 200 Low 100 Examples Ttim Nucor Hidaan chaparral Northstar/BHP CO-Steel Raritan Inland Lukens Ameri-Steel Caparo Steel w Chemical 6045% Figure 2. EAF Power Classifications. Figure:3. Energy Patterns in an Electric Arc Furnace. tions, oxygen injection is started as soon as a liquid pool of metal is formed. The decarburization process is an important source of energy. In addition, the carbon monoxide that evolves helps to flush nitrogen and hydrogen out of the metal. It also foams the slag, which helps to minimize heat loss and shields the arc-thereby reducing damage to refractories. Energy Needs The International Iron and Steel Institute classifies EAFs based on the power supplied per ton of furnace capacity. The power classification ranges and some representative furnace installations are shown in Figure 2. Most modern EAFs found in steelmaking shops are at least 500 kva per ton and the trend is toward ultra-high-power furnaces in the range of 900 to 1000 kva per ton of furnace capacity. A typical energy balance (Sankey diagram) for a modern EAF is shown in Figure 3. Depending upon the meltshop operation, about 60 to 65% of the total energy is electric, the remainder being chemical energy arising from the oxidation of elements such as carbon, iron, and silicon and the burning of natural gas with oxy-fuel burners. About 53% of the total energy leaves the furnace in the liquid steel, while the remainder is lost to the slag, waste gas, and cooling. I Just a decade ago tap-to-tap times had decreased from over 2 TechCommentarv hours to 70-80 minutes for the efficient melt shops. Continuing advancements in EAF technology now make it possible to melt a heat of steel in less than one hour with electric energy consumption in the range of 360 to 400 kwhhon. EAF operations utilizing scrap preheating such as the CONSTEELQ Process and the Fuchs Shaft furnace can achieve even lower cycle times. Most new EAF shops now With the increased availability of lower cost oxygen due to new air separation technologies, oxygen use in the EAF has grown. Oxygen usage has increased from about 300 scfhon (8.8Nm3honne) in 1985 aim for tap-to-tap times of between to as much as 1300 scfhon (37.4 50-60 minutes. These times are Nm3honne), saving 50 to 100 kwh rapidly approaching those for basic of electric energy per ton of steel oxygen furnace operations used in produced and reducing tap-to-tap integrated steel mills. times by 3 to 6 minutes. The relationship between electric energy Charge Materials and oxygen consumption for the EAF is shown in Figure 4. It is now In the past, EAF shops essen- common for between 30 to 40% tially charged 100% scrap to the of the total energy input to the EAF furnace. Although most EAF steel- to come from oxy-fuel burners and makers producing long products, oxygen lancing. such as rebar and merchant bar, Oxy-fuel burners are currently continue to use all scrap, some standard equipment on EAFs. The EAF shops today are supplement- first use of burners was for melting ing the charge with other materials the scrap at the slag door where arc for producing higher quality prod- heating was fairly inefficient. In ucts. This is the case for some ultra-high-power (UHP) furnaces, it producers of high-quality bars and highly formable sheet products for automobiles. These charge materials include direct reduced iron, iron carbide, and pig iron. For more information on scrap quality and direct reduced iron see CMP Report 95-1. The trend toward the use of direct-reduced materials will continue to grow as more high-quality scrap containing low levels of residuals or undesirable elements becomes scarce. Oxygen Usage Much of the EAF productivity gain achieved in the past decade is related to increased oxygen use. is common for cold spots to exist in the areas lying between the electrodes on the periphery of the furnace bottom. Burners are often installed to help melt scrap in these cold spots. This results in more uniform melting and decreases the time required to reach a flat bath. Also, burners are beneficial for heating the cold spot around the tap hole of eccentric bottom tapping furnaces. Typically burners are installed in the side wall and roof of 2

5 350 6, 5 0 600 1200 Oxygen Consumption (Standard cubic feet per ton) -igure 4. Eleptrical Energy vs. Oxygen Consumption. the furnace as well as in the slag door. Productivity increases of 5 to 20% have been reported from the use of burners. Oxygen lancing has also become an integral part of EAF melting operations over the past decade. Modern furnaces use oxygen lances to cut scrap, decarburize (refine) the bath, and foam the slag. Energy savings due to oxygen lancing arise from both exothermic reactions (oxidation of carbon and iron) and due to the stirring of the bath which leads to temperature and composition homogeneity of the bath. Oxygen lances can be of two forms, water cooled and consumable. Watercooled lances are generally used for decarburizing; however, in some cases they are used for scrap cutting. The first consumable lances were operated manually through the slag door. Today, remotecontrolled lance manipulators are available to optimize the injection process. These robotic units, Figure 5, can be used with multiple, individually controlled, consumable lances for scrap burning and decarburizing, as well as for injecting oxygen, carbon, and lime. Foamy Slag Practice bath declines as more heat is radiated from the arc to the sidewalls. By covering the arc in a layer of slag the arc is shielded and more energy is transferred to the bath. Oxygen injected with granular coal or carbon produces carbon monoxide (CO) which foams the slag. In some cases, only carbon is injected and it reacts with the iron oxide in the slag to produce CO. This is called a foamy slag practice and is now commonly used by EAF operators. When foamed, the slag cover normally increases from 4 inches (0.1 meter) to 12 inches (0.3 meter) thick. Claims for thermal efficiency range from 60 to 90% with slag foaming compared to 40% without foamy slag. If a deep foamy slag is achieved, it is possible to increase the arc voltage considerably. This allows a greater rate of power input. Slag foaming is usually carried out once a flat bath is achieved. However, with hot heel operations (residual liquid steel in the furnace bottom) it is possible to start foaming much sooner. Post Combustion CO gas is produced in large quantities in the EAF both from oxygen lancing and slag foaming. If the CO is not combusted in the furnace freeboard then it must be burned in the fourth hol evacuation system conveying the off-gases from the furnace to the baghouse. The heat of combustion of CO to C02 is three times greater than the heat of combustion of C to CO. Thus, this represents a very large potential energy source for the EAF. If the CO is burned in the EAF it is possible to recover the heat while reducing the heatload on the off-gas system. This is called post combustion. Results of studies have shown that by practicing post combustion, i.e., injecting oxygen into the EAF to burn the CO to COz, 35 to 60 percent of the heat in the off-gas can be recovered. EAF operators are now moving toward adopting this practice and typical electric energy savings are about 0.1 kwh/scf (4 kwh/nm3) of oxygen injected). EAF Bottom Stirring For conventional ac furnaces there is little natural electrically induced turbulence within the bath compared to dc furnaces which have more convection stirring. If there is little bath movement, large pieces of scrap can take a long time to melt and may require oxygen lancing. The concept of stirring the bath is not a new one and records indicate that electromagnetic coils were used for stirring trials as early as 1933. Today most EAF stirring operations use inert gas as the stirring medium. The gas is introduced through the bottom of the furnace using porous plugs. In a conventional ac furnace, three plugs are used with a plug located midway between each of the thfee electrodes. Primarily argon or nitrogen gases are used; however, some trials have been conducted with At the star! of meltdown the radiation from the arc to the sidewalls is negligible because the electrodes are surrounded by the scrap. As melting proceeds, the efficiency of heat transfer to the scrap and TwhCornrnentarv Figure 5. Lance Manipulator. 3

natural gas and carbon dioxide. existing furnace electrics. A good transformer secondary voltage is Advantages for bottom stirring foamy slag practice can allow volt- increased (sometimes to as high as include yield increases of 0.5 to 1%, age increases of up to 100% without 800 to 1100 volts) allowing operation average tap-to-tap time savings adversely affecting flare to the fur- at higher arc voltages and lower of about 5 minutes, energy savings nace sidewalls. Energy losses can electrode currents. Some of the of about 10 to 20 kwhhon, and be minimized when reactance is benefits attributed to ac operation reduced electrode consumption. associated with the primary circuit. with supplemental reactance are: Supplementary reactors are More stable arc than for Scrap Preheating standard operations. Electrode consumption reduced by 10%. Secondary voltage increased by 60 to 80%. being used to increase the operating voltages on the EAF secondary Of the total energy consumed circuit by connecting a reactor in directly in EAF steelmaking, about 20% normally leaves the furnace in the waste gases, see Figure 3. The loss can exceed 130 kwhhon of steel produced. A significant portion of this energy can be recaptured by using the offgas to preheat the scrap. Two methods for preheating scrap, the CONSTEEL@ process and the Fuchs shaft furnace have been installed on several new installations in recent yeap. The CON- STEEL@ process utilizes a conveyor to continuously feed scrap into the EAF. Hot furnace gases leaving the EAF travel countercurrento the scrap on the way to the baghouse thereby preheating the scrap. The Fuchs furnace has a shaft situated on top of the EAF which holds a scrap charge that is preheated by the off-gases rising up through the shaft. Energy usage has been reduced by 15 to 20% over conventional EAF operations using these technologies. High Voltage AC Operations Some EAF steelmakers have retrofitted their shops and installed new power supplies to obtain higher operating voltages. An ac E furnace electrical circuit is shown in Figure 6. Energy losses in the secondary circuit are dependent on the secondary circuit reactance and to a greater extent on the secondary circuit current. If power can be supplied at a higher voltage, the current will be lower for the same power input rate. Operating with a lower secondary circuit current will also give lower electrode consumption. Thus, it is advantageous to operate at as high a secondary voltage as is practical. Of course, this is limited by arc flare to the furnace sidewall and the Utility System: - Generation - Distribution Supply Metering Substation: Transformer P.F. Correctidn Surge Protection - Supplemental Reactors H.V. Distribution (Cables) Furnace Metering Furnace Transformer _I Metering for Arc Regulation Secondary Conductors R= Resistance X,= Inductive Reactance X,= Capacitive Reactance Zo= Arc Impedance DC Furnaces In recent years a number of dc furnaces have been installed. Essentially, the equipment needed for dc melting has the same configuration as that of a conventional ac furnace shown in Figure 7. The exceptions are the addition of a bottom electrode (anode), a dc reactor, and a thyristor rectifier all of which add to the cost of the dc furnace. These furnaces use only one graphite electrode with the return electrode installed in the bottom the of furnace and operate with a hot heel practice in order to ensure an electrical path to the return electrode. Figure 8 shows several types of return electrodes. These include conductive refractories with a copper external base plate and the multipin type made up of conductive rods passing through the hearth and connected to a bottom steel plate. A third type consists of one to four large diameter steel rods fitted in the furnace bottom, the steel rods being water cooled where they emerge from the furnace. During startup from cold conditions, a mixture of scrap and slag is used to Figure 6. Simplified Schematic of the aceafarccircuit. series with the primary windings of provide an initial electrical the EAF transformer. This allows path. Once this is melted in, the operation at a power factor of furnace can be charged with scrap. approximately 0.707 which is the Advantages claimed for dc furnaces theoretical optimum for maximum over ac furnaces include: circuit power. This is made possible 50% reduction in elecbecause a large storage device is trode consumption. placed in the circuit, which in effect 5 to 10% reduction in acts as an electrical flywheel during power consumption. operation. The insertion of the series reactor drops the secondary Reduced refractory consumption. voltage to limithe amount of power transferred to the arc. In order Uniform melting. to compensate for this, the furnace 50% reduction in flicker. Techcommentary 4

~~ Voltage Hiah rc I - AC Furnace High Voltage AC Line DC Furnace Graphite n Figure 7. Layouts for ac and dc Furnaces. P W ic Electrode T I 0 0 0 Sin Multi-Pin Conductive Refractories Metallic le Piece detallic Conductor conductor Figure 8. Bottom Electrode Designs for dc Furnaces. Reducing Electrical Disturbances TechCommentan. Many ways exist to reduce the effects of arc disturbances. These are determined by the utility system to which the furnace furnaces or are to be connected, and they are influenced mainly by the size and stabili- The melting process involves the use of large quantities of energy in a short time (1-2 hr) and in some ty of the power grid. Some sizable instances the process has caused shops require no particular flicker disturbances (flicker & harmonics) control equipment. It is quite possiin power grids but this problem is ble that, if a furnace shop is fed being minimized with the installa- from a 220 kv or higher system with tion of modern furnaces and a short-circuit capacity of 6500 MVA improved operating practices. or more, the utility will experience very little load disturbance, and the steelmaker can have considerable flexibility in configuring his internal plant power system. Most utilities require power factor correction. Shops with large EAFs would more than likely use static capacitors; synchronous condensers of sufficient capacity would be prohibitively expensive for a multifurnace shop. Before such systems are installed, transient analysis is required to determine: 1) Capacitor bank configuration. 2) Need for harmonic tuning of sections. 3) Switching procedure (This is important to avoid a power factor penalt and does not eliminate flic 1 er). As mentioned earlier, use of dc EAFs and improved operating practices such as scrap preheating, foamy slags, and use of hot heels all work to reduce flicker. If additional regulation is needed, installation of a static var control (SVC) may be required. Many EAF shops have installed SVC systems not only to minimize flicker problems but also to increase productivity. Ladle Refining Furnace During the past decade, the EAF has evolved into a fast and low-cost melter of scrap with the major objective being higher productivity in order to reduce fixed costs. In addition, refining operations to improve product quality are (for the most part) carried out in a ladle refining furnace (LRF). This allows the EAF to concentrate on melting the scrap and removing impurities via oxidation reactions. Temperature and chemistry adjustments are carried out more optimally in the LRF. For more information on the operation and role of the LRF see CMP TechCommenrary CMP-07 1. EAF Dust The dust exiting the furnace with the off-gases has been classified as a hazardous waste (KO61 by the Environmental Protection Agency (EPA) because it can contain lead, cadmium, chromium, and nickel. As a result, the dust must be treated prior to disposal in order to meet EPA requirements. There are various methods for treating the dust-for more information on these processes refer to CMP Report 93-1.3 5

Design Criteria For the Modem UHP Electric Arc Fumece Wth Auxiliaries, Be man K., Gottardi R., 3rd European Electric 2 tee1 Congress, 1989. Direct Current Electric Arc Furnaces, CMP TechCommentary CMP-063, January 1991. Electric Arc Furnace Dust-1993 Overview, CMP Report 93-1, July 1993. Electric Arc Furnace Efficiency, CMP Report 92-10, December 1992. Electric Arc Furnace Technology, Recent Developments and Future Trends, Teoh L.L., lronmaking and Steelmaking, Vol. 16,1989. Giving EAFs the Shaft to Recoup Energy, 33 Metal Producing, November 1990. Ladle Refining Furnaces, CMP TechCommentary CMP-071, August 1991. New Developments in Electric Arc Furnace New Tools for Improved Operation of High Efficiency Electric Arc Furnaces, Aderup M., Ljunggren R., Frisk L., Anderson F?, Gustafsson A., Samuelsson F?, 1992 Electric Furnace Proceedings. Optimal Distribution of Oxygen in High Efficiency Arc Furnaces, Gripenberg H., Brunner M., Iron and Steel Engineer, July 1990. Oxy-Fuel Burner Technology for Electric Arc Furnaces, Wells M.B., Vonesh F.A., Iron & Steelmaker, November, 1986. Reflections on the Possibilities and Limitations of Cost Saving in Steel Production in Electric Arc Furnaces, Klein K., Paul G., Metallurgical Plant and Technology, Vol.1, 1989. Review of New lronmaking Technologies and Potential for Power Generation, CMP Report 95-1, February 1995. The Electric Power Research Institute (EPRI) conducts a technical research and development program for the U.S. electric utility industry. EPRl promotes the development of new and improved technologies to help the utility industry meet present and future electric energy needs in environmentally and economically acceptable ways. EPRl conducts research on all aspects of electric power production and use, including fuels, generation, delivery energy management and consewation, environmental effects, and energy analysis. The EPRl Center for Materials Production Carnegie Mellon Research Institute P.O.Box 2950 Pittsburgh, Pennsylvania 15230-2950 4 412-268-3243FAX:412-268-6852 The EPRl Center for Materials Production (CMP) is an R&D application center funded by The Electric Power Research Institute and operated by Carnegie Mellon Research Institute, Carnegie Mellon University. CMP is a service of the Industrial and Agricultural Technologies and Services Business Unit of the Customer Systems Group of EPRI. The mission of the Center is to discover, develop, and deliv er high value technological advances through networking and partnership with the electricity industry. EPRl Preston Roberts, Manager, Materials Production and Fabrication CMP Joseph E. Goodwill, Director This TechCommentarywas prepared by Dr. Jeremy Jones, Consultant. It supercedes a 1987 TechCommentarywith a similar title. Technical review was provided by Robert J. Schmitt, Associate Director at CMP, and Joseph E. Goodwill, Director of CMP. Edited by John Kollar, CMP For additional copies of this Techcommentary call ECAC 4 1-800-4320-AMP Key Words: Electric Arc Furnace, Electrical Operations Applicable SIC Codes 3312,3325 01997 Electric Power Research Institute, Inc. All rights resewed. Printed 2/97 I I LEGAL NOTICE This TechCommentarywas prepared and sponsored by The EPRl Center for Materials Production (CMP). Neither members of CMP nor any person acting on their behalf (a) makes any warranty, expressed or implied, with respect to the use of any information, apparatus, method, or process disclosed in this TechCommentaryor that such use may not infringe privately owned rights; or (b) assumes any liabilities with respect to the use.of, or for damages resulting from the use of, any information, apparatus, method, or process disclosed in this TechCommentary. 50% TOTAL RECOMRD FIBER 20!4 POST-CONSUMER FIBER TechCornmentary~TC-107714 6