Technology, Innovation and Information at Fingrid Kari Suominen, CIO

Similar documents
Power Technologies International. Industry Perspective on GIS Integration: Challenges, Solutions, Benefits and Case Studies

Challenges with implementation of CIM interfaces to TSO processes

Asset Optimization and Condition-Based Maintenance (CBM) Improving Reliability and Quality

OSIsoft and T&D Marketplace. Copyr i ght 2014 O SIs oft, LLC.

MANAGING SITUATION AWARENESS IN POWER DISTRIBUTION GRID DISTURBANCES

Connecting Space and Time

Towards a clean electricity system

Digital Transformation of Energy Systems

Kari Suominen. Datahub how digitalization is shaping the retail market of electricity

INTERACTIVE CUSTOMER GATEWAY FOR ELECTRICITY DISTRIBUTION MANAGEMENT, ELECTRICITY MARKET, AND SERVICES FOR ENERGY EFFICIENCY

SUBNET IoT to the PI System: A Bridge to Support Business Use Cases

SMART GRID SCENARIO. Marina Egea,

Digital Transformation of Energy Systems

TOWARDS THE MODERNIZATION OF THE SCADA SYSTEMS OF THE HELLENIC ELECTRICITY DISTRIBUTION NETWORK OPERATOR CONSIDERATIONS AND STEPS FORWARD

Practical Situational Awareness to Improve Safety & Reliability in Operations. September 15, Take Away

Automating LV Distribution networks using sensor technologies

Esri UC ADWEA's Digital Transformation: Geospatial Asset Management Initiative. Walid Abou Chacra K&A

MEETING TODAY S GROWING NEED TO UNDERSTAND ENERGY CONSUMPTION

Learnings from the Swedish Market. Mälarenergi Elnät AB

CIGRE STRATEGY Prelude to next Century

Information Technology. Classification Band 5. Position Objective

collaborative solutions core product features and benefits Construction Collaboration Software. SaaS.

Coming Soon! To a PI System Near You

What is Needed for the Enhancement of Successful Grid Scale Energy Storage Development

Advanced Enterprise Work and Asset Management for Performance-Driven Utilities

National Report 2016 to the Agency for the Cooperation of Energy Regulators and to the European Commission

AMR Data Hub. Architecture. Work Package 6.1.5: Enterprise Application Implementation Scenarios for Electricity Market

Connecting Space and Time

Leveraging Geography to Drive Utility Transformation and Business Value

Designated Entity Design Standards Task Force (DEDSTF) Minimum Design Requirements for FERC Order 1000 Projects. System Protection Subgroup

EcoGrid EU A Real-Time Smart Grid Demonstration in Denmark

Laura Butler - AMI Team Leader, Central Hudson Gas & Electric Corporation NY, USA

Implementation of data hubs in the Nordic countries

Circuit Breaker Asset Management Using Intelligent Electronic Device (IED)- Based Health Monitoring

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

The Digital Transformation of Electricity Markets

Siemens perspektiv på den digitala utvecklingen inom Energisektorn

Grid Solutions. ASSET PERFORMANCE MANAGEMENT for Electrical Substations

The Single Window. Solution: X Road. for Logistics. Valdo Kalm Chairman of the Management Board Port of Tallinn

Restricted Siemens AG 2017 siemens.com.cn/ingenuityforlife

Industry Solution. Real-time Historian for Synchrophasor Data Management

The Smart Grid Choice

Opportunities to Accelerate Smart Grid Deployment through Innovative Market Design

Intelligent Water and Organizational Culture

Gurgaon City Statistics

National Report 2017 to the Agency for the Cooperation of Energy Regulators and to the European Commission

Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

DA concept for higherquality. supplies. 24 ABB Review 4/1996

ADWEA's Digital Transformation: Geospatial Asset Management. Khalid Saddique Akbar

Siemens Power Technologies International. Bridging the Gap Enterprise Model Management for Operation and Planning

Slide 1. ABB August 23, 2016

Smart Energy Software Solutions

SHARED SERVICES CAPITAL - INFORMATION TECHNOLOGY

OMS/DMS Implementation at SDG&E

Digitalization of the energy sector: the case of Estonia. Karla Agan Head of Retail Business, Enefit (Eesti Energia)

Copyright 2012 OSIsoft, LLC. 1

CHANGING THE DSO TO REAP THE FULL BENEFITS OF SMART GRIDS

NordREG opinion on Harmonised rules for information exchange (technical level) - the Business Requirements Specification report 1

Energy Industry Challenges

Electricity North West Future Challenges. Dr Geraldine Bryson Innovation Implementation Engineer

Building a Real-Time Event-Driven Enterprise Infrastructure. Ann Moore Business Development Executive

(D2-01_28) ROLE OF ICT in Power System

Grid Strategy Perspectives Integrating Grid Modernization, DER and Grid Operations Objectives

The following is a complete list of Siemens technology solutions that you will see in our booth:

DISCOVER FUTURE SOLUTIONS TODAY

Enabling Smart Grid with GIS, Common Information Model and Utility Network

Pillsbury & UtiliPoint AMI/MDM Webinar. Jon Brock, Utilipoint Michael Murphy, Pillsbury. September 17, 2008

INFORMATION TECHNOLOGY PROGRAM DESCRIPTIONS OPERATIONAL INVESTMENTS

Second Opinion on Fingrid s Green Bond Framework

Partnering for reliable distribution

A Unified, Intelligent & Evolvable Solution to Enable NERC CIP Compliance and Substation Knowledge

Response 1 (5) Public

Water and waste water energy specialists

Digital Transformation and Operational Intelligence in Utilities. Agendra Kumar President, Esri India

Increase Power Grid Stability and Reliability with Enterprise Historians for Synchrophasor Data Management

WHITE PAPER MONETIZE IOT DATA WITH ANALYTICS

Walk-through of long-term utility distribution plans: Part 1 - Traditional Distribution Planning

SMART GRID CONCEPTUAL MODEL

Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content

Critical Power. Power Distribution Solutions.

Utilizing CIM Integration Platform for Utility Analytics. Matija Gruden, GDB d.o.o., Slovenia

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

Monitoring of T&D Systems

NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2014

Itron Analytics Maximize the Value of Your Smart Grid

Your next transformation, one click away.

Industry Digitizing the Shop Floor to Achieve Operational Excellence & Customer Successes

SAP Jam Collaboration, advanced plus edition

CIP 2019 Project Outline ~ Electrical Engineering

Energy & Environment Seminar / Visa Yliluoma

Re-defining Energy Management

Cloud-iPad Era. Real-time Industrial automation software, evolving with technology!

Smart Grids The Norwegian situation.

End-to-end electrical solutions for the biggest challenges involved with connecting wind energy to the grid. Solutions for Wind Energy Integration

Smart Metering End-to-End Solutions from the Meter Data Management System to the Meter

SAP Jam Collaboration, advanced plus edition

Years of experience, customized for you.

Long-term forecasting of reactive power demand in distribution networks Dr Christos Kaloudas / Dr Rita Shaw. 3 rd November 2017

Ekip SmartVision Understanding power

Connecting the Real-time World How and Value Gretchen Schwenzer, PhD

Transcription:

Technology, Innovation and Information at Fingrid 12.6.2014 Kari Suominen, CIO

Agenda Fingrid in general Innovative use of Technology and Information in running the business Fingrid's condition monitoring system Current use cases with PI Elvis Future plans Elvis and PI Datahub

3 Fingrid is the Finnish transmission system operator (TSO) We are responsible for the functioning of the entire power system in Finland. We keep the transmission grid in a good condition and construct it on the basis of the needs of the electricity market. We transmit electricity continuously from electricity generating companies to distribution network companies and industrial companies. 75% of the electricity in Finland is transmitted in our grid. We take care of the cross-border connections of electricity transmission. There are direct connections to Finland from Russia, Sweden, Norway and Estonia. We promote the functioning of the electricity market by keeping the transmission connections between various countries in working order.

4 Balanced vision Customers and stakeholders Reliable electricity - Functioning electricity market High quality services - Affordable tariffs Finance Cost efficiency - Value creation for owners Internal processes Adequacy of transmission system Capital investments and maintenance work efficiently, safely and at the right time System operation Proactive and reliable system operator Personnel and expertise Productive - Innovative - Healthy ICT Promotion of market functioning Active maintainer and developer of the electricity market

5 Fingrid in Brief Fingrid's key figures 2013 Mutual Pension Insurance Company Ilmarinen; 19,9 % Varma Mutual Pension Insurance Company; 12,2 % Ownership (shares) State of Finland; 53,1 % Other (institutional investors); 14,8 % Fingrid's power system Transmission lines (km) Substations (qty) Transformers (qty) 400 kv 4 300 39 220 kv 2 600 19 110 kv 7 500 55 17 600 MVA 1 900 MVA 3 700 MVA Total 14 400 113 44 5 23 1300 MW DC link between Finland and Sweden 935 MW fast disturbance reserve power plants

6 Efficient operating model We develop the power system in close cooperation with our customers. We are a proficient client: we have outsourced the construction and maintenance of the grid to outside service providers. We take care of power system operation ourselves.

7 Innovative use of Technology and Information in running the business Real business cases from "Internet of things" and "big data" in Fingrid's Asset Management, Power System Operations and Markets. Maximize the network reliability and minimize the maintenance and investment costs at the same time Discover the weak performing assets, components and hidden defeacts as early as possible Repairs, service schedules and replacement investments can be optimized Data analysis and exchange support new businesses like electric vehicle charging and market based development

Fingrid Application map Management, budgeting and reporting Cognos Electricity Markets Customer and stakeholder management Project budget and management Asset Management System Operation HR Finance Basse EMPS/Samlast LTJ Ekstranetit Primavera Maximo GE XA Vaksi Sympa Intime BID Syspower www.fingrid.fi Grid planning ODMS PSS/E CAPE ArcGis IPS Syclo NOIS EAS Aiolos isms SyncAlarm Tiima eoffice M2 Twin Messaging Video and security control Video monitoring Esmikko Energy measuring ION Management of measurements PI Stina PsGuard Idea management Orchidea Intranet Ohjeistuswiki PW Lync ICT & Communication Audio and video communication AD Microsoft SharePoint Microsoft Office Microsoft Exchange Microsoft BizTalk Efecte 12.6.2014 Under In use SaaS Kari Suominen development

Our vision of the Condition Monitoring System Smart visualization different kind of displays traffic lights based on alarm values gauges, embedded trend windows drill-down UI Easy analysis tools differences between two points maximum, minimum ratios (e.g. gas ratios) trend curves Automatic alarms notifications and alarms based on trigger rules generate tasks to our asset management system in the future

How it works? SCADA PI Server PI Asset Framework PI Processbook Analyzers real-time data storage asset model displays ERP/EAM Transformers, breakers, GIS, serie capacitors, reserve powerplants ~ 5 years of online data and ~ 20 years of offline data is ready to be used Light implementation by existing PI tools = system is easily configurable and users can make own displays

How does it look like?

Transformer fault Increasing oil gas ratio was noticed and taken under observation in May 2012. Strong correlation between LV current and oil gas ratio was detected by CMS and confirmed with diagnostics measurements. The early notice gave time to react and remedial actions were launched in time.

SF6 gas leaks in breakers and GIS Several gas leaks and detector failures has been detected by monitoring and automatic notifications.

14 Health index analysis tool for substations Health index identifies the priority in terms of additional maintenance or need of renewal Especially essential when the population of components is very large, e.g. circuit breakers and disconnectors. Based on the defect statistics in the asset management system over a long time period (>20 years) and weighting coefficients The tool enables the user to update all these views and visualize the affects by changing easily the free choice factors and source variables. This analysis can strengthen already known component weaknesses but may also point out additional needs for further clarification from different perspectives.

22.1.2013 Elvis for CS /M Stenstrand 15

16 Shared access to vital information - outsourcing is based on efficient knowledge management Grid models Analysis and planning tools GIS EAM Databanks utilisation of databases Fingrid s specialists team work Stakeholders co-operation occupational safety Co-operation forums Training Development projects Regular meetings Extranet for data management Compilation, storage and use of mobile data

17 ELVIS high level objectives Increasing operative efficiency Increasing proactivity in calculations, monitoring and maintenance Single source for power system information Improving information access and usability within stakeholders Adding cost aspect to operation and power system components Enhanced business planning through operational cost analytics Platform for further system development with modern solutions Mobile solutions and data analysis to support Asset Management and Power system operations A more efficient tool for Fingrid's asset and operation management by replacing existing tailor-made grid information systems by integrated best-of-breed standard software products

18 The foundation for Asset Management - provide great tools for the AM specialists Fault location and short circuit currents calculation Network model for relay settings (CIM-XML) Network model - PSS/E raw file - CIM-XML Network model - CIM-XML Both realtime and historical measuments (status, analog)

ELVIS will bring us new things Common accurate grid model Common grid model which is synchronized with asset management, operations planning, long term planning and network protection analysis All switch gear modeled with real and accurate description of components in the grid. Lot's of additional information about the grid model. Better utilization of saved measuring data Accurate planning grid model linked to real time status and metering data. Preparing of calculation model is easy by using status and metering data from the past. Better visualization of data, grid status and results Attributes for grid components available through the map Visualization of real time power and voltage measurements using colours on grid model or map Common model about the future Common database about future projects where schedules are in sync through the systems Easy to build different scenarios

Real time visualization capabilities Relative load of transmision lines Angle of voltage Voltages

21 Datahub for market data exchange

22 What are retail market data exchange? Processes where we need data communication between parties: concluding a contract termination of a contract moving supplier switch connection / disconnection meter reading transmitting meter information changes in the metering point information / contract balance settlement Suppliers ca. 100 kpl User points ca. 3,5 milj.l DSO ca.. 85 kpl Today's "spaghettimodell" Data-Hub

23 Possible functionalities of a datahub Primary functionalities: measurement database quality control DSO's balance settlement metering point registery key market processes legislative reporting Possible additional functionalities: open interfaces connect/re-connect operations larger metering point registery/multiutility support enable co-billing New businesses, such as electric vehicle charging, market based development

Fingrid's next steps 2014-2015 Improvement Additional internal resources to PI development and a solid PI architecture New improvements based on user experience and feedback e.g Improvements to delivered displays Elvis R2 and R3 are connecting PI with components like ODMS and ArcGIS Bigdata study focusing on PI Datahub business case analysis and implementation

Powering Finland.