Bi-Directional Static Load Testing of Driven Piles

Similar documents
SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DRILLED SHAFTS

REPORT ON DRILLED SHAFT LOAD TESTING (OSTERBERG METHOD) I-215 Airport Connector - Las Vegas, NV - TS-1 Las Vegas, NV (LT )

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts

O-CELL TESTING CASE HISTORIES DEMONSTRATE THE IMPORTANCE OF BORED PILE (DRILLED SHAFT) CONSTRUCTION TECHNIQUE

Evaluation of PDA Data to Identify Pile Issues Presented at Annual KC Specialty Seminar January 9, 2015

Conference: IFCEE International Foundations Congress and Equipment Exposition

STATNAMIC LOAD TESTING OF HIGH CAPACITY MARINE FOUNDATIONS

CASE STUDY: LOAD TRANSFER ANALYSIS ON AN INSTRUMENTED AUGERCAST PILE USING EDC STRAIN GAUGES AND GEOKON REBAR STRAINMETERS

SECTION DUCTILE IRON PILES

Steven Dapp, Ph.D., P.E. Steven Dapp, Ph.D., P.E. Dan Brown and Associates

Rapid Axial Load Testing of Drilled Shafts

Tip-Grouted Drilled Shaft Foundations for the Audubon Bridge. Acknowledgements

Deep Foundation Testing, Analysis and Consulting Services

Typical set up for Plate Load test assembly

Soil-Structure Interaction (SSI) Testing Facility and Capabilities at Lehigh University

Pile Driving Analyzer (PDA) and CAPWAP Proven Pile Testing Technology: Principles and Recent Advances

RIGOLETS PASS BRIDGE ~ TEST PILE PROGRAM

RIGOLETS PASS BRIDGE ~ TEST PILE PROGRAM

Innovation in Instrumented Test Piles in Malaysia: Application of Global Strain Extensometer (GloStrExt) Method for Bored Piles

Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project

STATE-OF-THE-ART TECHNOLOGY OF Y-JACK IN BI-DIRECTIONAL PILE TEST

Using Load Testing to Save Money and Time on the I-35W Bridge Project

560 IN SITU TESTING, ANALYSIS, AND RELIABILITY OF FOUNDATIONS. Lateral Load Capacity of Cast-in-Place Shafts behind an MSE Wall. *corresponding author

Experimental study on axial and lateral bearing capacities of nonwelded composite piles based on pile load test results

3.1 Scope of the work-capacity Estimation of Drilled Shaft Bearing on Rock

STANDARDIZED STRUCTURES

Overburden Effect on the Axial Resistance of Instrumented CFA Piles. Knoxville, TN 37922, ph ,

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

Pier Pressure in Natchez, Mississippi Post Grouted Drilled Shafts Pass Test

SAMPLE SPECIFICATION for HIGH STRAIN DYNAMIC TESTING of DRIVEN PILES

UPDATE ON ISU DRILLED SHAFT LRFD CALIBRATION STUDY. Jeramy C. Ashlock, Ph.D. Richard L. Handy Associate Professor

Pile Driving Issues. Mark McClelland, P.E. Geotechnical Branch Manager Texas DOT

Post-Grouting of Drilled Shaft Tips on the Sutong Bridge: A Case History

THE STUDY OF t-z AND q-z CURVES ON BORED PILE BASED ON THE RESULTS OF INSTRUMENTED PILE LOAD TEST IN MEDIUM AND STIFF CLAYS

EXPERIENCES WITH BASE GROUTED DRILLED SHAFTS IN THE

Testing Methods of Driven Piles on INDOT Demonstration Projects

VW Total Pressure Cell

Design and Construction of Drilled Full Displacement Piles using the Penetration Resistance Method

Comparative Study between Design Methods and Pile Load Tests for Bearing Capacity of Auger-drilled PHC Piles

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

Analysis of Four Load Tests on Augered Cast-in-Place Piles in the Texas Gulf Coast Soils Raghu Dass, PE, Woodward Vogt, PE, and Frank Ong, PE

Foundation Innovations Ensure Successful Bridge Replacement

DESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK

Ching Guan Kee ABSTRACT

On-site determination of pile capacity Distribution of pile load between the shaft and tip, and Detection of possible pile.

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

APPENDIX 1 Homework - 20 Problems

SPECIAL SPECIFICATION 4492 Tie Back Anchors

CHAPTER III DYNAMIC BEHAVIOR OF A LABORATORY SPECIMEN

The experience in applying of static load and O-cell pile testing geotechnologies in problematical soil conditions of Astana

OFFICE OF STATE AID ROAD CONSTRUCTION MISSISSIPPI DEPARTMENT OF TRANSPORTATION

Pipe Ramming with HDD. Presentation Outline

SPECIAL SPECIFICATION 4401 Prestressed Ground Anchors

Method Statement of load Test for Steel Tubular Load Test Trial Piles Rev.3

Experimental study on axial and lateral bearing capacities of nonwelded composite piles based on pile load test results

Pile Design from Constructability Perspective

Lantz-Boggio Architects, P.C LBA Project No

1. Cast-in-place concrete is specified in Section

Malaysian Journal of Civil Engineering 27 Special Issue (1):1-18 (2015)

Our Tour Stops. A Foundation Engineering gtrip down the Mississippi River. Dan Brown, P.E. Dan Brown and Associates 9/6/2010.

John James Audubon Bridge

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013

INTERPRETATIONS OF INSTRUMENTED BORED PILES IN KENNY HILL FORMATION

Typical Specifications of Compaction Grouting Scope

A Case History of Pile Freeze Effects in Dense Florida Sands

RECORD KEEPING AND INSPECTION NOTES FOR FUTURE NEEDS

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

Proper Practice. 2015, Pile Dynamics, Inc.

Anchor Load Cells Installation - considerations

Deep Foundation. Deep Foundation Applications

twenty four foundations and retaining walls Foundation Structural vs. Foundation Design Structural vs. Foundation Design

Misan University - College of Engineering Civil Engineering Department

Non-destructive Testing of Installed Soil Nails Using Sonic Echo Test Method

In-plane testing of precast concrete wall panels with grouted sleeve

APPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system.

This document downloaded from vulcanhammer.net vulcanhammer.info Chet Aero Marine

twenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

High strain dynamic testing in micropiles. Comparison of static and dynamic test results

Safe, fast and simple: the DUKTUS pile is loadtested in South Africa

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

Soil Improvement by Compaction Grouting

Lesson 7 REINFORCING CAGE. Version 1-1/

Deep Foundations By. J. Paul Guyer, P.E., R.A. PDHLibrary Course No PDH HOURS

LADOTD DRIVEN PILE DESIGN & VERIFICATION. Jesse G Rauser, PE USING LRFD

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

SUPPLEMENTAL TECHNICAL SPECIFICATION

Deflection of Helical Piles: A Load Test Database Review

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE

Penang Second Bridge

Dynamic Testing Applications for driven piles using Pile Driving Analyzer & CAPWAP

Chapter 21 GEOTECHNICAL REPORTS

HMA GROUP AUSTRALIA - NEW ZEALAND - INDONESIA - SOUTH AFRICA SINCE 1966

Multi-Institutional Academic Health Science & Research Center Evansville, IN

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

MICROPILE LATERAL LOAD TESTING IN CHARLESTON, SOUTH CAROLINA, USA

Florida Method of Test for NONREPETITIVE STATIC PLATE LOAD TEST OF SOILS AND FLEXIBLE PAVEMENT COMPONENTS

Concrete Prestressed Concrete Pretensioned Concrete Posttensioned Concrete Typical Tendon Layout

Transcription:

Bi-Directional Static Load Testing of Driven Piles Paul J. Bullock, PhD Fugro Consultants Inc. Loadtest

Bi-Directional Osterberg Cell Testing Specialized jack in pile uses bearing to mobilize side shear Developed by Dr. Jorj Osterberg and AEFC LOADTEST Inc. founded 1991 (purchased by Fugro in 2008) First O-cell tests on driven steel pipe piles 1987 >2000 O-cell tests to date, mostly drilled shafts (300+/yr) ~ 30 driven piles since 1987 (12-66, 52 tons 1,480 tons)

Conventional Test Reaction System Osterberg Cell Test P O = F = Q = P/2 O = F 1 = (F 2 +Q) P = F+Q Pile Provides Reaction F 1 F F O O F 2 Q Q Q

Driven Pile O-cell Installation O-cell cast into or welded to pile before driving O-cell grouted into pile after driving 30 PSC Pile, Morgan City, LA 66 Cylinder Pile, Harrison County, MS

O-cell Features Robust for installation Aligned with pile axis Special seal for eccentricity Water used for hydraulic fluid Rated at 10,000 psi Calibrated by AEFC (NIST Traceability) 24 PHC Korea Linear & Repeatable Strain gauges also confirm load

O-cell Instrumentation O-cell Pressure monitored by gauge and transducer Pile Top Movement O-cell Expansion Transducers O-cell Top Telltales Pile Bottom Telltales Embedded Strain Gauges Embedded Pile Compression Transducers

O-cell Test Setup ASTM D1143 Quick Test (new standard coming) 20 Loads to failure 8 min load intervals (identify creep limit) All instruments monitored by datalogger Real-time load vs. deflection plot Reference beams replaced by electronic levels

O-cell Sizes O-cell Size Rated Capacity Max. Test Load 6 100 tons 200 tons 9 225 tons 450 tons 13 438 tons 875 tons 16 700 tons 1400 tons 20 1125 tons 2250 tons 24 1550 tons 3100 tons 26 1950 tons 3900 tons 34 3000 tons 6000 tons Cells typically welded to load plates Cells can be grouped together 6 stroke standard, 9 stroke available

Special Features of Driven Pile O-cells AEFC welds plates to O-cell that fit pile form (or pile ID) O-cell welded shut for safe pile handling O-cell placed at pile bottom O-cell skirt / enclosure provided (if driven) Rebar anchors cell to pile Vent pipe to minimize disturbance at cell opening Instrumentation cables and hoses coiled at top of pile

Example: 18 Steel Pipe Piles, MA Saugus River Bridge Pines River Bridge Delmag D62-22 Refusal 10 blows /0.5 142 tons O-cell Load 0.28 tsf Side Resistance Failure (0.3 ) 80 tsf End Bearing (not failed) 284 tons Capacity Delmag D36-13 Refusal 10 blows /0.5 215 tons O-cell Load 0.39 tsf Side Resistance Failure (0.3 ) 122 tsf End Bearing (not failed) 430 tons Capacity

FL Research Pile Setup Five 18 PSC Piles PDA Tests Long-term, staged static tests (25) Osterberg Cell in tip Strain Gages Telltales Piezometers DMT Stress Cells O-cell Bottom Telltale (through center of pressure pipe) Friction Collar for Gage Support Hydraulic Pump with Gage & Piezometer Dilatometer Cell (L) & VW Piezometer (R) on Pile Face Pile Side Shear VW Strain Gage (in pairs, tied to prestress strands) Osterberg Cell Cast Into Pile, with XXS Pressure Pipe to Top O-cell Tee Wireline & Scale O-cell Top Telltales Inside PVC Pipe (not to scale) Pile End Bearing

FL Research Pile Setup: O-cell

FL Research Pile Setup Arithmetic Plot Pile Side Shear QS (kn) 2500 2000 1500 1000 60 min 500 15 min Bullock et al. (1995) in FL 1 min 18 PSC, O-cell at bottom 0 0 50 100 150 200 250 300 Aucilla, Dynamic Test Aucilla, Static Test = 225 tons Elapsed Time, t (days) 1727 days

FL Research Pile Setup Log-linear Plot Pile Side Shear QS (kn) 2500 2000 1500 1000 500 1 min (EOID Capacity plotted at 1 min) 0 0.001 0.01 0.1 1 10 100 1000 Aucilla, Dynamic Test Aucilla, Static Test = 225 tons Q S0 =1021 kn (at t 0 = 1day ) 15 min 60 min m S = 293.4 kn Elapsed Time, t (days) Bullock et al. (1995) in FL 18 PSC, O-cell at bottom

FL Research Pile Setup Non-dimensional Plot Pile Side Shear Ratio, ( Qs / Qs0 ) 2.2 2.0 1.8 1.6 1.4 1.2 A = (m S / Q S0 ) = 0.30 1.0 R 2 = 0.99 0.8 +30% 1-3d +14 % 0.6 +30% 60 min 1-28d +43% or 0.4 1-7d about half of 15 min +30% 0.2 +25% EOD-1d change 0.0 1 min 0.001 0.01 0.1 1 10 100 1000 Aucilla, Dynamic Test Aucilla, Static Test Σ = +90% in 1 day (or 9X 1 min capacity) Bullock et al. (1995) in FL 18 PSC, O-cell at bottom Elapsed Time Ratio, ( t / t 0 ) with t 0 = 1 day

Example: Morgan City, LA - 30 PSC HPSI 2500, 300 bpf 30 PSC, 18 Void, 143 ft long Pile Setup Clay/Sand 950 ton O-cell Max. O-cell Load 493 tons Buoyant Pile Weight 29 tons 464 tons at 5 wks 416 tons at 3 wks 369 tons at 1wk

Example: Busan, Korea - 24 PHC Prestressed Spun High Strength Conc. 24 OD, 16 ID, 103 ft long, 46 ft sections Sand / Clay / Sand 875 ton O-cell, 7 Strain Levels, Grouted Max. O-cell Load 472 (944 ton test) Buoyant Pile Weight 16 tons Max. Side Shear 456 tons Unit Side Shear 0.14 to 1.98 tsf Max. End Bearing 155 tsf

Example: Harrison County, MS - 66 Cylinder Conmaco 300, 128 bpf EOID 66 OD, 54 ID, 108 ft long Silt / Sand / Dense Sand 3000 ton O-cell, 4 Strain Levels Max. O-cell Load 740 tons (1480 ton test) Buoyant Pile Weight 114 tons Max. Side Shear 626 tons Unit Side Shear 0.23 to 4.10 tsf Max. End Bearing 45 tsf

Efficient O-cell Test Applications End bearing side resistance (use ultimate!) Restricted site access (remote location, existing structures, environmentally sensitive, water) Prove capacity distribution (end bearing vs. side resistance, unit side resistance) Accelerated construction schedule Large test loads required Site safety restrictions (personnel & equipment) Repeated tests (setup) Multiple test piles (but only one test frame) Compare with total cost of conventional testing

O-cell Test Limitations Pile preselected for testing Maximum load limited by the weaker of the end bearing or side shear (add top load?) Top of pile not structurally tested Subtract buoyant weight of pile above O-cell to calculate side resistance Must construct equivalent top load movement curve use the sum of measured behavior use the sum of modeled behavior use finite element or t-z approach

Typical O-cell Test Result 2,700 tons (1 MN = 112.4 tons)

Equivalent Top-Load Curve

Equiv. Top-Load + Elastic Shortening

RIM-CELL RIM-cell pressurizes pile cross-section Full-scale static bi-directional load test Install a RIM-cell in any pile Economical testing QA/QC device eliminates uncertainty End-bearing engaged during test, stiffens shaft response under load 60 RIM-cell

RIM-CELL TESTING Cross-section of a RIM-cell installed at the shaft toe.

RIM-CELL TESTING The RIM-cell confines the fluid pressure, creating a hydraulic cylinder at the shaft toe capable of applying high static loads.

RIM-CELL TESTING Fluid grout is pumped through the hydraulic hoses creating a fracture across the shaft, pressurized within the RIM-cell.

RIM-CELL TESTING As the internal grout sets, more grout is pumped into external pipes to fill the annular fracture around the RIM-cell.

USING THE RIM-CELL PROOF TEST Install in every pile Load shafts to design load or higher (2000 5000 psi) Eliminate uncertainty of site variability Use higher LRFD factors Detect / remediate a soft toe POST-STRESSING Consolidate loose material at shaft toe Engage end bearing without losing side shear Limit settlement at service load

RIM-CELL ASSEMBLY Designed for drilled shaft construction. RIM-cell fits inside reinforcing cage. Hydraulic hoses and instrumentation pipe installed on the cage. Add strain gages, etc. to isolate and analyze different soil strata. 60 RIM-cell 24 RIM-cell installed with 8 levels of strain gages RIM-cell welded to frame below O-cell assembly for a multi-level test shaft.

RIM-CELL INSTALLATION After shaft excavated and approved, hang cage with RIM-cell at the desired elevation. Large center opening allows tremie pipe to pass during concrete placement. Low cross-sectional area does not inhibit concrete flow or trap loose materials. 24 RIM-cell at toe of an O-cell test shaft 20 RIM-cell installed at the toe of 30 shaft 60 RIM-cell installed into 78 rock socket

RIM-CELL TESTING Perform test after concrete obtains strength. Cement grout is mixed and pumped through the hydraulic hoses into the RIM-cell. Measured pressure is converted to load using calibration factor of the RIM-cell. Load is increased to 1.2 to 1.5 times design load. Shaft movement is measured and recorded. Grout will set up to restore integrity to the shaft. RIM-cell Load-Displacement 0.9 0.7 Upward Top of RIM-cell 0.5 0.3 Displacement ( in ) 0.1-0.1-0.3-0.5-0.7-0.9-1.1-1.3 Downward Base of RIM-cell -1.5 0 100 200 300 400 500 600 RIM-cell Load ( kips ) 24 RIM-cell Test Curve 36 RIM-cell Test Curve

RIM-CELL REPORTING The RIM-cell report similar to O-cell test report. Load-Displacement plot generated in real time during test. Electronic preliminary results available the same day as the test. 60 RIM-cell Schematic section of RIM-cell shaft Equivalent Top Load Plot

RIM-CELL LIMITATIONS Internal friction unknown (but small) Preselect shaft (install in every shaft, test as required) Reduced pressure vs. O-cell (but large area) Typically will not test to failure Grouting required to restore shaft integrity Maximum load limited by the weaker of the end bearing or side shear (add top load?) Top of pile not structurally tested

24 RIM-CELL TESTS MISSOURI RESEARCH PROJECT 24 bi-directional test piles on two different sites Two piles on each site were tested using RIM-cells 24 RIM-cells in 36 piles 20-30 feet deep shafts in unweathered and weathered shale Side by side comparison to O-cell tests

24 RIM-CELL TESTS Similar piles on same site. O-cell test (red) taken to ultimate capacity. RIM-cell test (blue) taken to design load. Plots show similar deformations at design load.

RIM-CELL Tests to Date RIM-cell Size Shaft Diameter Max Pressure Max Cell Load Test Result 14" 24" 2500 psi 350 kips Side Shear Failure 14" 24" 1780 psi 250 kips End Bearing Failure 20" 30" 1530 psi 450 kips Side Shear Failure 20" 30" 1360 psi 400 kips Side Shear Failure 24" 36" 2560 psi 1100 kips RIM-cell Capacity Maxed Out 24" 36" 1980 psi 850 kips RIM-cell Capacity Maxed Out 24" 36" 640 psi 275 kips End Bearing Failure 24" 36" 1170 psi 500 kips End Bearing Failure 24" 30" 940 psi 400 kips Test stopped at 1" Expansion 36" 54" 475 psi 450 kips Side Shear Failure 96" 60" (76"rock socket) 4950 psi 13,000 kips Test stopped at 1/2" Expansion

Summary O-cell test proven for driven piles Compare overall cost and quality of test results for conventional top-down testing with O-cell testing RIM-CELL tests to verify production pile capacity (QA/QC) Coming Attractions: New ASTM Standard Bigger piles, higher loads Mid-pile O-cell placement for spliced concrete piles Mid-pile placement for steel pipe piles

Thank You