Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany

Similar documents
Remote-Controlled Dismantling of the Thermal Isolation and Preparations for the Primary Shield Removal

AREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals

Dismantling Techniques applied at MZFR

RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED

Wälischmiller Engineering

VVER-440/213 - The reactor core

Long Reach Tooling Solutions

DECOMMISSIONING PROGRAMS AND TECHNOLOGY DEVELOPMENT IN JAPAN ATOMIC ENERGY RESEARCH INSTITUTE

Dismantling of the Obrigheim NPP Reactor and Waste Management 14500

Decommissioning of Dairyland Power s Lacrosse Boiling Water Reactor

DECOMMISSIONING STRATEGIES AND PLANS. By: Elna Fourie Necsa South Africa Manager: Decommissioning Services

The following considerations are taken into account for designing the NUHOMS MP197 packaging.

F. BODIN 1, Ph. FOURNIER 1, L. MARTIN 2 1 COGEMA La Hague BEAUMONT HAGUE Cedex - France 2 SALVAREM BEAUMONT HAGUE Cedex - France

Characterization of Contaminated Stacks at Nuclear Facilities

WM2015 Conference, March 15-19, 2015, Phoenix, Arizona, USA

ESS Target Facility Design. John Haines for the ESS Target Project Team

TREATMENT AND STORAGE OF WASTE FROM THE DECOMMISSIONING OF THE WINDSCALE PILE REACTOR. D H Norton, Project Manager British Nuclear Fuels plc

Operating Instructions in compliance with Pressure Equipment Directive 2014/68/EU. FAS Welding and Solder Flange

Decommissioning of Nuclear Facilities. Dismantling Technologies

Decommissioning Studies for the Oskarshamn and Forsmark Nuclear Power Plants in Sweden

PRESENT STATUS OF LEGAL & REGULATORY FRAMEWORK AND DECOMMISSIONING PLANNING FOR DNRR. Prepared by NUCLEAR RESEARCH INSTITUTE, VAEC.

Development Status of Dismantling Technology for Old Steam Generator & RV in Kori unit 1

Lessons learned from ongoing decommissioning project of Fugen NPS

PRR-1 Decommissioning: Preparing for Dismantling and Decontamination. R2D2 Project Meeting, Manila, Philippines September

Examples Page 43 of 45

Nuclear Energy Fundamentals

CHALLENGE: Post Operational Clean Out

SAMPLING AND RADIOLOGICAL ANALYSIS OF COMPONENTS OF THE TRIGA REACTOR AT THE MEDICAL UNIVERSITY OF HANNOVER

OUTLINE OF THE ROKKASHO MOX FUEL FABRICATION PLANT

ITER TOKAMAK VACUUM VESSEL THERMAL SHIELD ADDITIONAL NEUTRAL SHIELDING

RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1.

PRR-1 Decommissioning: Implementing Dismantling and Decontamination. R2D2 Project Meeting, Manila, Philippines September

Legislative Framework for the Regulation of Decommissioning at Egypt. Prof. Dr. Farouk M. A. Rahman

SPECIFICATIONS - DETAILED PROVISIONS Section Progressing Cavity Pump C O N T E N T S

Minimizing Activation, Size and Costs and yet Maximizing Efficiency

GENERAL CONTENTS SECTION I - NUCLEAR ISLAND COMPONENTS

The EnBW Strategyfor Decommissioningand DismantlingofNuclearPower Plants»

SHANDONG QISHUAI WEAR RESISTANT EQUIPEMNT CO.,LTD

Sampling of Reactor Pressure Vessel and Core Internals Ralf Oberhäuser

Tradition and Innovation. The ideal combination for success. Others promise the future We work on it BABCOCK NOELL

Generic Aspects for Dismantling Preparation of INPP Reactor Facilities. Aleksej Merežnikov, Ignalina NPP, July 2014

EUROPEAN STEEL SCRAP SPECIFICATION

SECURE LONG TERM STORAGE OF WASTE PRODUCTS AT THE KARLSRUHE RESEARCH CENTER

KÖNIG + CO. FORMING KNOW-HOW

COMPONENTS DISMANTLING AT NOVOVORONEZH UNITS 1, 2 SHUT DOWN FOR DECOMMISSIONING

Packaging for Transport of the ILW-LL of EDF First Generation Power Plant Dismantling 16517

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

Section 4. Annex to IAEA Request for Proposal STATEMENT OF WORK. Primary/Secondary cooling water Heat Exchangers

Replacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head

Best practices for preparing vessel internals segmentation projects

EQUIPMENT FOR REPAIR OF RBMK-1500 FUEL ASSEMBLIES OF IGNALINA NPP

VINCA Institute of Nuclear Sciences. Vinča Institute. Dragana Nikolić. Centre for Nuclear Technologies and Research 'NTI' Belgrade, Serbia

Steam Generating Heavy Water Reactor SGHWR The final chapter

Decommissioning and Dismantling of Prototype Reactors and Fuel Cycle Facilities at the German Karlsruhe Site Progress and new Challenges

Selection and evaluation of decontamination and dismantling techniques for the decommissioning of large NPPs components

THE DESIGN AND CONSTRUCTION OF A TEMPORARY STORE FOR RADIOACTIVE WASTE. J. Sims, M. Thomson MRP Systems Ltd. J. Voss Terra Verde Environmental, Inc

European Experience In Transport / Storage Cask for Vitrified Residues

MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications

All definitions are defined according to ANSI/AWWA C b. Flanged Joint: The flanged and bolted joint as described in ANSI/AWWA C110/A21.10.

Comparison of estimated and actual decommissioning cost of José Cabrera NPP

QUALIFICATION TESTING OF FIELD WELDERS

QUALITY ASSURANCE PROTOCOL (QAP)

SEMPELL. High Pressure Steam Bypass Valves - Type 115 ASME.

Decommissioning three main strategies: Immediate dismantling, Safe enclosure (Deferred dismantling), Entombment

All definitions are defined according to ANSI/AWWA C

Supplier Opportunities: Traveling Wave Reactor Program

Radioactive Waste Management at the NCSR Demokritos - Greece

DESIGN OF INNER HOOD OF BELL ANNEALING FURNACE FOR BETTER HEATING EFFICIENCY

Decommissioning in Germany: Greifswald NPPs. Bernd Rehs Federal Office for Radiation Protection (BfS)

CONDITIONING OF OPERATIONAL AND DECOMMISSIONING WASTES AT THE KARLSRUHE RESEARCH CENTER

DISMANTLING OF LARGE PLUTONIUM-CONTAMINATED GLOVE BOXES. H.-U. Arnold, DETEC (a NUKEM Company), Alzenau, Germany

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

ITEM 686 TRAFFIC SIGNAL POLE ASSEMBLIES (STEEL)

ADVANCED DECONTAMINATION AND DECOMMISSIONING SYSTEM

NEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS

MANDATORY APPENDIX 2 RULES FOR BOLTED FLANGE CONNECTIONS WITH RING TYPE GASKETS

Safety Considerations in the Transition from Operation to Decommissioning of Research Reactors

Flame and Plasma Cutting

SAUDI AIR CONTROL SYSTEM INDUSTRIAL REGISTRATION NO.353 FIRE DAMPERS

APPENDIX A WELDER (INDUSTRIAL) D.O.T. CODE O*NET CODE As Revised for MACNY, The Manufacturers Association

D ECO M M I S S I O N I N G O F KOZ LO D U Y NPP UNITS 1 4 P RO G R E S S & C H A L L E N G E S

B. Polyethylene samples shall be submitted for Owner approval of color and quality.

PROCESS GAS WASTE HEAT BOILERS WITH THIN FLEXIBLE TUBESHEET DESIGN

Radiation Protection during Decommissioning of Nuclear Facilities Experiences and Challenges

Progress Achieved in the Decommissioning of the Process Building of the Karlsruhe Reprocessing Plant

IN SAFE HANDS. Apparatus Construction Division EXPERTISE EXPERIENCE EXCELLENCE BORNE OF OFFERING YOU

Machine list + core competences Your contract manufacturer for mechanical engineering

TREPANING PROCEDURE APPLIED AT THE RPV OF THE FORMER GREIFSWALD NUCLEAR POWER PLANT

Latest Trends in Fabrication of High Thickness Reactors

EXPERIENCE AND DEVELOPMENTS FROM DECOMMISSIONING OF THE FORMER EUROCHEMIC REPROCESSING PLANT IN BELGIUM


Reactor Core Internals Replacement of Ikata Units 1 and 2

Handling of Reactor Internals at Forsmark Nuclear Power Plant

CANDU Fundamentals. 16 Reactor Fuel

05510: TAPERED STEEL TROLLEY POLES AND ACCESSORIES

CLASSIFICATION NOTES. Type Approval. Mechanical Joints. used in Piping

Decommissioning the Philippine Research Reactor (Under R2D2P): Updates and Challenges

1.2 REFERENCES.1 American National Standards Institute (ANSI)/American Society of Mechanical Engineers (ASME)

International Journal of Advance Engineering and Research Development

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

Transcription:

861 REMOTELY-OPERATED DISMANTLING OF THE REACTOR INTERNALS AT NIEDERAICHBACH POWER PLANT USING MANIPULATORS Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany ABSTRACT The joint venture NOELL/NIS received the order for the project and planning work and execution of the dismantling of the nuclear power plant Niederaichbach from the Kernforschungszentrum Karlsruhe. According to the present situation of the work progress a green meadow planted with green bushes shall be created in about 4 years instead of the present nuclear power plant. The dismantling and the disposal of radioactive internals in the reactor are hereby the technically most sophisticated and most difficult activities. Target is to prove by this work that it is possible according to the present level of engineering to perform the disposal of a nuclear reactor without danger. This can improve to successfully obtain the political acceptance for future nuclear engineering projects. 1. BACKGROUND INFORMATION ABOUT THE NIEDERAICHBACH POWER PLANT At times, when enrichment of uranium was still difficult, research activities were looking for a possibility to operate a nuclear reactor with natural uranium. After the completion of the NPP Niederaichbach there was sufficiant enriched uranium for acceptable prices on the world market - the concept of the NPP Niederaichbach had been superseded by the development. Difficulties during the commissioning of the reactor in the heat exchanger area caused the shut-down of the plant after only 18 days of operation at full load.

862 Data of Work: Start of construction work First criticality Reconstruction work/ Commissioning tests Shutdown Decision for decommissioning Approval for "safe enclosure" Contract for complete demolition given to NOELL/NIS "Safe enclosure" Start of dismantling Remotely handled dismantling "Green meadow" condition 1966 December 1972 1972-1974 July 1972-1974 December 1974 1975 1979 1981 1987 1990 1994 After shut down of this nuclear power plant the technical problems of disposal were to be studied. Because of its relatively low activity inventory the nuclear power plant of Niederaichbach provided a good example for this type of work. 2. LAYOUT OF THE REACTOR The construction of this heavy-water reactor type is very complicated and consequently makes great demands upon the remote-operated dismantling. The assembly is composed of a great number of welded and bolted connections with different wall thicknesses. Mainly stainless steel, ferritic steel and zirconium alloy were used as fabrication material. (see Figure 1) Technical Data: Gas-cooled pressure tube prototype reactor Moderator Heavy-water D20 Cooling agent Carbondioxide gas CO2 Thermic capacity 320,6 MW Electric net capacity 100,4 MW Moderator tank nominal diameter 6.140 mm height 5.240 mm

863 The masses of the reactor components to be dismantled by remote handling are composed of the following equipment: Component Weight (tons) Material Moderator tank 32 Austenite Pressure tubes 21 Special material Pressure tube shafts 35 Ferrite Seals and plugs 49 Austenite/ferrite Neutron shields 218 Austenite Thermic shield 137 Ferrite Total mass 492 3. PREPARATORY MEASURES FOR REMOTELY OPERATED DISMANTLING The following requirements were asked for the remote-operated dismantling: - No extension of the existing control area for work of dismantling, crushing and conditioning. Dismounting of the activated internals within the biological shield without water shielding, since filling of the reactor systems with water would have been connected with a considerable work and considerably additional secondary waste. Dismounting of contaminated and activated components and facilities as far as possible by mechanical separation processes. With the aid of the available drawings and descriptions of construction a strategy was developed as basis for the dismantling. The internals were investigated for possible techniques of crushing and subsequently the necessary toolings and machines were developed. An infrostructure conforming to the requirements had to be provided, such as access and departure systems, energy systems, control area (protection against radiation), lavatory and other facilities.

864 4. WORK STAGES AND THEIR SEQUENCE The strict compliance with the stipulated work stages is necessary by all means in order to achieve a safe dismantling. The work stages were stipulated according to the following criteria: - Safety of activity - Low load of radiation Optimal use of toolings The sequence of work stages was stipulated in such a manner that the separated work piece can be removed without difficulties and that the secondary waste does not cause disturbances for the following work stages. (see Figure 2) 5. REQUIREMENTS OF THE EQUIPMENT The toolings have to be taken by a remote-operated manipulator and the work stage has to be performed by this manipulator. A redundant securing has to be provided against possible false operations. The reactor internals have to be crushed to such a size that they can be deposited in an optimum manner into the standardized containers. Due to the high costs of ultimate storage a high packing density is emphasized, i.e. the number of required containers must be as small as possible. The equipment has to comply with the following criteria: - Low secondary waste Small quantity of cooling fluid, involved. small quantity of dust Sturdyness - Redundantly designed equipment performing work of other machines in case of their failure.

865 6. DESIGN AND TESTING OF THE MANIPULATORS AND TOOLS FOR THE VARIOUS TASKS Three manipulators are provided for the remote-handled dismantling of the reactor internals. (See Figure 3) Rotary manipulator The rotary manipulator is a five- axis possibilities of movement: robot with the following 1. Circular rotation > 360 2. Horizontal moving 3.3 m 3. Vertical moving 15 m 4. Rotation of mast > 63 5. Opening and closing of the gripper The special design of the manipulator makes it possible to move across the cylindrical spaces underneath and above the point of support. The length of mast is adapted to the various stages of dismantling. The rotary manipulator is designed for the duty of separating all detachable and undetachable connections inside of the reactor and to transport these parts into the crushing station. Ring saw The ring saw is actually an abrasive and cutting-off machine which is only required for crushing of the thermic shield. Crane manipulator The reactor internals can be crushed to suitable size for container by means of the crane manipulator and be packed into the containers. Automated and remotely controlled tools for the rotary manipulator Tool Range of application Inside tube grinding unit Separating pressure tubes, shafts, bushings Circular cut milling unit Circular cut of neutron shield insulation layers around pressure tubes

866 Abrasive wheel cutter Linear cut of neutron shield insulation layers between pressure tubes Miniature abrasive wheel cutter Cutting-off piping and internals of thin walls Plasma torch separating unit Separating of internals with thick walls Nut runner unit Vacuum unit Screwing off bolts Sucking off steel shielding spheres & chips Combined ball/jaw gripper unit Picking and lifting spacers, plugs, shieldings from the fuel element arrangement & pressure tubes Vacuum gripper Picking & handling of flat and smooth parts Universal latch gripper Picking and handling large components inside the reactor and transporting to the crushing house Testing of tools The testing of tools - there are actually tooling machines - was performed in three stages: Cold run Functional test of equipment and proof of prespecified technical data - Performance test at the model The equipment is tested for its efficiency at special models. De- termination of the most favourable parameters for the use at the model. - Use of equipment with a manipulator, remotely operated at various reactor components.

867 For the testing of the total quantity of equipment a model of the lower neutral shield was fabricated, which was crushed and disposed of from the control room by remote operation. The equipment used in the nuclear power plant, which require maintenance, can be tested at the second control station prior to application in the reactor. Small reconstruction and repair work at the tools and their preparation for use in the reactor are performed in an intervention room. A repair room is existing for major repair work. 7. PERFORMANCE OF THE WORK The sequence of work had to be strictly performed according to the prespecified work stages, had however to be adapted to the respectively encountered circumstances and conditions due to the different actual constructional designs compared to the ones on the drawings. During the current dismantling it has shown that some initially involved work could be manually performed, because the existing radiation was lower as originally assumed. The reactor internals were separated with at the detachable and undetachable connections by means of the available tools, transported into the crushing station by means of grabbing and transporting equipment, there crushed to suitable sizes for container and packed into the containers put at disposal. The net weight and the activity inventory is to be considered when packing into the various container types. The internals did not always match with the existing drawings, a fact that resulted in minor modifications of the tooling sets. For example the following deviations were determined: The shielding spheres were found in raw pressed condition and not ground as assumed; - the bolt head shape of some bolted connections was designed as a kind of hammer-head bolt instead of a hexagon; - tack welds and welded connections were larger than assumed. These differences unavoidably resulted in a minor delay of work. Important in this connection is however the fact that the existing tools can also be used for such deviations. The work is performed in three shifts by approximately 70 men, with 20 men being engaged in protection against radiation, in order to keep the specified time schedule.

868 8. SURVEY OF FUTURE PROJECTS The constuctional design of the nuclear power plant Niederaichbach is certainly one of the technically most sophisticated plants and consequently also a very difficult one for dismantling. As far as the radiation is concerned, this nuclear power plant is not problematic for dismantling. The radiation of a pressure-water reactor is much more critical for the disposal work, i.e. a longer period of decay has to be considered prior to starting the actual dismantling. For reasons of protection against radiation the crushing of the internals would have to be performed under water. Experiences gained from the dismantling of the nuclear power plant Niederaichbach will be helpful for further dismantling projects, however the competent Authorities will wait for the completion of the entire disposal of the nuclear power plant Niederaichbach before granting approval for further dismantling projects. In the future the later disposal of a nuclear power plant should already be considered within the scope of construction and design, as already done for cars and other consumer goods.

00 a) CD

870 Fig-2 Detail of neutron shield Fig.3 Manipulators