Natural Gas Pipeline Update

Similar documents
Alaska LNG Concept Information. Alaska LNG. Overview. October

Alaska South Central LNG (SCLNG) Project

THE ALASKA LNG OPPORTUNITY: DEVELOPING A WORLD-CLASS LNG EXPORT PROJECT APRIL 26, 2017 LIEZA WILCOX, VICE PRESIDENT OF COMMERCIAL.

ALASKA LNG. Alaska Municipal League November 16, 2017

State will answer most of FERC s questions by June; last items Aug. 1

Mileage-based tariff benefits Alaskans

OUTLINE PART I: Introduction to Alaska and its Enormous Resource Basin PART II: Progress on Gas Commercialization/LNG PART III: Why Alaska? Comparativ

Alaska LNG. Commercializing. Daniel S. Sullivan Commissioner, Alaska Department of Natural Resources

Chinese Investment Opportunities in Alaska

38th Annual Alaska Resources Conference

Alaska LNG Outlines Issues For Next Round of Resource Reports

Appendix A. Project Description

Meet Alaska Aligned Alaska = Strong Oil and Gas Industry & Stronger Alaska for another 40 Years

IS THE AK LNG PROJECT THE ONLY VIABLE OPTION FOR THE NORTH SLOPE? The Administration says yes but reality says NO - there are other options

ALASKA LNG AFL-CIO December 15, Keith Meyer, President

ALASKA NATURAL RESOURCES TO LIQUIDS (ANRTL) PLAN B A NORTH SLOPE GTL PROGRAM PLAN C ASAP + AN ANCHORAGE AREA GTL PROGRAM

Cook Inlet Natural Gas Supply Update

Point Thomson Project

APRIL Business Information Sessions

NATURAL GAS IN COOK INLET

S E T T L E M E N T O V E R V I E W

Alaska Highway Pipeline Project. Energy in Alaska Conference Anchorage, AK November 12, 2007

Cook Inlet Natural Gas Supply Update

Interior Energy Project: Pentex Purchase & Project Financing Agreements and Analysis. November 2017

Who is WesPac Midstream?

Liquefac on plant single largest cost for Alaska LNG project

Board Presentation North Slope LNG to Fairbanks Project

Alaska Gasline Development Corporation; BP Alaska LNG, LLC; Conoco Phillips. Alaska LNG Company; ExxonMobil Alaska LNG, LLC; TransCanada Alaska

Cook Inlet Gas Study Update

ALASKA PIPELINE PROJECT

Alaska and China Sign Historic Joint Development Agreement

Alaska s frigid climate could give state an edge in LNG

Freeport LNG Liquefaction Project

The Arctic Fox Pipeline

TAPS Highlights. December 8, Alyeska Pipeline Service Company

The Business of Oil & Gas in Alaska Joshua Kindred, Alaska Oil and Gas Association. November 12, 2015

ASX/MEDIA RELEASE 1 July 2014 KINDER MORGAN FILES FERC APPLICATION TO TRANSPORT GAS TO MAGNOLIA LNG PROJECT

4. RAILBELT LOAD FORECASTS

5.20 CUMULATIVE EFFECTS

What s next for Alaska gas

The Case for Investing in LNG Export Terminals in the US. Marine Money 2017 Meg Gentle, CEO

Glossary of Natural Gas Industry Terms and Natural Gas Conversion Tables

Beluga to Fairbanks. Natural Gas Pipeline System

DEPARTMENT of NATURAL RESOURCES

Natural Gas Opportunities

Yokogawa Corporation of America Receives Analyzer Systems and Shelters Order from Freeport LNG

US LNG Export Growth and the Benefits to Midstream

LNG buyers love everyone

Commonwealth North Gas Pipeline Infrastructure. September 13, 2013

Dominion Cove Point Export Project Platts 16 th Annual Liquefied Natural Gas February 9, 2017

ASX/MEDIA RELEASE 30 APRIL 2015 MAGNOLIA LNG PROJECT FERC NOTICE OF SCHEDULE FOR ENVIRONMENTAL REVIEW RECEIVED

Analysis of Oil and Gas Production in the Arctic National Wildlife Refuge

Docket No. PF Preliminary Resource Report No. 1 General Project Description Public Version

Inventory Management

Issued March 21, Permian Global Access Pipeline LLC. Notice of Non-Binding Open Season

Terasen Gas (Vancouver Island) Inc. Evidence In Response to VIEC CPCN Application for the VIGP

A message from the president

Issued February 21, Haynesville Global Access Pipeline LLC. Notice of Non-Binding Open Season

North American Gas Supply Outlook

[ P] SUMMARY: The Office of Fossil Energy (FE) of the Department of Energy (DOE) gives notice

Point Thomson: Key gas field that s challenging to produce

World s first LNG from Queensland, Australia A precursor to US LNG exports

IN-STATE PROPANE UTILIZATION STUDY FOR THE ALASKA GASLINE DEVELOPMENT CORPORATION JULY 1, AGDC. All Rights Reserved.

NATIONAL ENERGY BOARD

Alaska Pipeline Project Report Licensed under the Alaska Gasline Inducement Act (AGIA)

BUILDING A SUSTAINABLE GROWTH BUSINESS IN ALASKA

Opportunities and Challenges in the Energy Infrastructure Industry. Louisiana State University Energy Summit

PHILADELPHIA GAS WORKS

BlueCrest Energy Activity Update, J. Benjamin Johnson CIRCAC Board of Directors Meeting Kodiak, 9/12/2014

Socio-Economic Impact Analysis of Alaska LNG Project

NATIONAL ENERGY BOARD

LARGE STORAGE TANK PROJECT

Project Overview. November 2014

: The Yukon Pacific era

Scoping Study Highlights Chad Liquefied Natural Gas (LNG) Project

Exports of LNG from North America

Alaska s Propane Demand

Liquefied Natural Gas Limited

Alaska Department of SOUTHEAST CONFERENCE MARCH 9, 2011

LNG Facts A Primer. Presentation before US Department of Energy, Office of Fossil Energy, LNG Forums. March 10, Kristi A. R.

SYNOPSIS OF THE 2017 NATIONAL GAS POLICY

Management Review / KPI s

Gas pipeline efforts work on permits while waiting on the markets

Memorandum. Ports and Harbors Advisory Committee and Planning Commission. Brad Ryan, Director of Public Facilities, Haines Borough

Alaska Stand Alone Gas Pipeline

New Brunswick Building and Construction Trades Council 2014 Conference. Presenter. David Simon Construction and Turnaround Manager Irving Oil

LNG Exports: A Brief Introduction

ECONOMIC PROJECTIONS FOR ALASKA AND THE SOUTHERN RAILBELT

Memo. Matanuska Susitna Borough LRTP. Alaska Stand Alone Pipeline (ASAP) Project details still being researched

Ports and LNG as Maritime Fuel

Alaska Department of Labor and Workforce Development. Gas Pipeline Workforce Development Strategic Plan

ENERGY. Responding to the Upstream Boom

PROJECT DESCRIPTION AND STATUS

May 29, 2015 VIA ELECTRONIC FILING

2016 Statistics. About BP in Alaska. Employees 1,700 people. Operating budget $1.1 billion. Capital investment $600 million

2017 ANNUAL REPORT. V isit agdc.us

Comparison of Netbacks from Potential LNG Project with ALCAN Pipeline Project

Gorgon Project Update: Selected Images

PUBLIC PARTICIPATION PLAN

Natural Gas & LNG Fundamentals. Greg Kist Vice President, Marketing, Corporate & Government Relations

Transcription:

Natural Gas Pipeline Update FEDC: Energy for All Alaska Task Force Fairbanks, Alaska December 15, 2015

! State of Alaska s Objectives Secure a stable, affordable, long-term energy supply for Alaskans! Commercialize Alaska s enormous North Slope gas resource! Maximize the value of state s royalty and tax gas! Generate revenue, jobs and economic growth! Facilitate further oil and gas development! 2

AGDC Overview Independent public corporation! Initially created as a public response to concerns over declining Cook Inlet gas supplies! Corporation has primary responsibility for developing a North Slope natural gas pipeline project on the State s behalf! May enter into contracts to treat, transport, liquefy or market gas! Shall assist DNR & DOR to maximize the value of the state s gas resources! 3

North Slope Gas Projects AGDC is owner of two Project alternatives! State s priority project! $45-$65 billion LNG export project! Partnership with Exxon, BP, Conoco! State s back-up project! $10 billion in-state gas pipeline! Currently 100% state owned! Either project is capable of delivering gas to Alaskans but they vary significantly in size, scope and cost! AGDC is also responsible for planning and developing the plans for gas off-take within Alaska regardless of project built! 4

Special Session Results Legislature just concluded special session appropriating $157.6 mill:! $68.4 mill Acquire TransCanada s mid-stream interests in the Alaska LNG project! $75.6 mill Fund state s full 25% share of remaining Alaska LNG pre-feed! $13.0 mill - Fund state agency participation through the end of FY16 (June 2016)! AGDC will now assumes state s full 25% equity in the project and will oversee as the owner! 5

Governance Issues Resolved Equity Alignment: State s share of gas in the project (25%) was not equal to its equity in the integrated project:! o State, through AGDC, held 25% in the downstream (LNG plant)! o TC held 25% in the midstream (pipeline & GTP)! o State s resulting equity in the integrated project was ~ 12.5%! Voting Rights: State didn t have full voting participation in all project decisions:! o State, through AGDC, voted on downstream issues! o TC voted on mid-stream issues! o AGDC will now have full voting rights on project components and in all integrated project decisions! 6

Project Participation Resource Owners Project Interest State s Interest 75% 25% Gas Treatment Plant (GTP) Pipeline LNG Facility TransCanada previously held State s mid-stream interest: Pipeline & GTP AGDC board authorized conveyance on Nov 21 st ; DNR closed purchase & sale agreement Nov 24 th AGDC will now hold State s interest in the entire integrated project 7

Completing 2 nd year of Pre-FEED! Project Update $690+ million commitment by all parties - following a stage gate approach to development! 135 full-time personnel on Project Management Team! FERC environmental permitting (NEPA) process initiated! DOE export approval granted for both Free Trade and Non-Free Trade countries! AOGCC recently approved gas off-take levels! 2016 Work Program & Budget Approved - $230 mill! Pre-FEED is expected to be concluded by 1Q 2017! 8

Project Timeline Key Milestones Date Pre-FEED Ini,ated July 2014 Conclude Pre-FEED 2016-2017 FEED Decision 2017 Conclude FEED (2-3 years) 2019 Final Investment Decision (FID) 2019-2020 Construc,on (5-6 years) 2020-2025 Project Complete/First Gas 2025-26 Pre-FEED: Preliminary Front-End Engineering and Design! FEED: Front-End Engineering and Design! 9

Meeting In-State Gas Demand AGDC s is responsible for developing pipelines and other mechanisms for delivering natural gas in-state! Completed a forecast of in-state natural gas demand! Completed preliminary cost estimates for gas off-take facilities! Developed a framework to assist policy makers in evaluating in-state off-take infrastructure! AGDC Board has authorized the formation of a subsidiary capable of aggregating in-state gas demand. Potential activity:! o o o Pool small quantities of in-state demand! Serve as an intermediary between resource owners (including DNR) and small instate buyers! Assist small communities in developing local distribution entities! 10

In-State Gas Demand Project volumes more than adequate to meet in-state demand growth Base Case 2040 demand 333 MMscfd (122 Bcf per year) High Case 2040 demand 422 MMscfd (154 Bcf per year) Demand will be par,ally supplied from Cook Inlet during the forecast period Demand by Segment 2014 Actual 2030 2040 ExisVng Demand Enstar, railbelt electrical u,li,es, and industrial users (excluding export) 214 227 243 PotenVal Demand Interior hea,ng and power u,li,es 2.5 51 56 Industrial opera,ons (primarily mining) 0 31 31 Small communi,es within 50 miles of alignment 0 3.2 3.4 Total Base Case Demand: 217 312 333 In-State Natural Gas Demand: Base Case Es,mates (MMscfd) 11

In-State Gas Off-Take PBU + PTU GTP Main Pipeline LNG Facility Export Non-Project Costs Customers Off-Take Facility Lateral to AK Community Local U,lity Meters Meters Meters Project Costs - project is responsible for providing a minimum of 5 interconnec,on points along the line where gas can be accessed for in-state use Non-Project Costs - facili,es required to remove gas from the project and process it for in-state use are the responsibility of third par,es SOA, local governments, public u,li,es, end users or a combina,on of these groups Off-take Facili,es Lateral/Spur Lines Local Distribu,on Systems Fuel system conversion costs AKLNG Project Costs 12

In-State Gas Off-Take Progress to date: Approximately 20 potential interconnection points identified along pipeline corridor! Some communities would be best served from a common access point, off-take facility and lateral! AGDC has developed conceptual cost estimates for offtake facilities, excluding local distribution and appliance conversion costs! Preliminary analysis highlights significant economic challenges with bringing small communities online! 13

Challenges By every standard, this is a world class construction project: $45 to $65 billion, three mega-projects! Regulatory and construction risks are higher in Alaska! Difficult to estimate long-term LNG demand, pricing, and world-wide competition! Competing against other LNG projects looking to sell to same buyers! Final Investment Decision (FID) will be economically driven! Low oil price environment makes large capital investments more difficult for producer partners! Balancing the risk/rewards of state equity participation in a challenging fiscal environment! 14

Questions Miles Baker!! VP, External Affairs! & Government Relations!!!! Alaska Gasline Development Corporation (AGDC)! 3201 C Street, Suite 200! Anchorage, Alaska 99503! (907) 330-6300! www.agdc.us! 15

Backup Slides 16

North Slope Gas Projects Project Sponsors State of Alaska, ExxonMobil, BP & ConocoPhillips State of Alaska Design Objective Facilities Gas Treatment Pipeline LNG Plant Liquefied Natural Gas (LNG) principally for export markets GTP at Prudhoe Bay (~200+ acres) 8 Compressor Sta,ons (30kHP) 800 mile, 42 mainline In-state off-takes LNG plant, storage tanks and tanker berths at Nikiski (~600 acres) U,lity grade lean gas principally for in-state markets GCF at Prudhoe Bay (~70 acres) Compression at Prudhoe Bay 733 mile, 36 mainline 30 mile, 12 lateral to Fairbanks In-state off-takes N/A Terminus Nikiski (Kenai Peninsula) Currently Near Big Lake (ENSTAR s Beluga line) Design Capacity ~ 3.3 billion cubic feet/day at GTP ~ 2.2 billion cubic feet/day at LNG plant Currently 500 million cubic feet/day Cost ~ $45 - $65 bill ~ $10 bill (+/- 20%) Workforce Peak: 9,000-15,000 Opera,ons: ~1,000 Peak: 8,000 Opera,ons: ~150 Construction 5-6 years (after FID in 2019) 3.5 years (after FID in 2019) Completion 2025-2026 2024 17

Project Overview Integrated LNG export project! Prudhoe Bay & Point Thompson gas fields! 98% of known NS gas resource! Gas Treatment Plant (GTP)! 3.3 bcfd peak! Three process trains w/compression! CO2 removal and reinjection! Gas Pipeline! 800-mile; 42 diameter; 8 compressors! ~1.2 million tons of steel! Liquefaction Facilities at Nikiski! Three trains; 20 million tons/year! Storage & Marine Terminals! Two jetties; 15-20 tankers per month! 18

In-State Gas Off-Take Off-Take Facility Cost EsVmates Size Volume (MMscfd) Off-Take Facility Capital Expense ($Mill)* Macro 80.00 330.00 $38 CharacterisVc Community North/South Cook Inlet Mini 20.00 75.00 $28 Fairbanks Size Micro 0.40 2.00 $15 Medium Density Nano 0.04 0.25 $14 Very Small *Cost of laterals, spurs, local distribu,on and appliance conversions not included in figures above 19