OFF-THE-SHELF MID-SMALL-MINI-SCALE LNG PLANT CASE STUDYFOR APPLICATION

Similar documents
LNG as a marine fuel in BC. West Coast Marine LNG Workshop 26 th June 2012

Mid to Large Scale Floating LNG Plant -Technology Development and JGC Contribution

Dry and Liquefied Gas to European Markets

LNG Experience. Owner & Investor Project Management

Beyond the Horizon (FY ) New Medium-Term Business Plan. - 1st Stage of Growth Strategy Toward Attaining the Corporate Vision - Masayuki Sato

Developing efficient and reliable LNG infrastructure to support Indonesia s fast-growing energy demand

Status of first generation of FLNG and trend and perspective for the next generation

IPTC MS The Outlook for LNG Supply to Asia. Stuart Traver, Lalitha Seelam and Nick Fulford Baker Hughes Inc. and Gaffney, Cline & Associates

Role of LNG in Growing Asian Gas Market

GLADSTONE TO JAPAN: EXPORT LNG PROJECT. December 2007

Alaska South Central LNG (SCLNG) Project

ENGINEERING SERVICES

COMPETITIVE ANALYSIS OF CANADIAN LNG. CERI Breakfast Overview Allan Fogwill, President & CEO Sept 19, 2018

Domestic seaborne distribution systems in Asia

ENVIRONMENT AND ENERGY BULLETIN

KOGAS s Technical Capability and Plan on Off-shore Plant Business

SOUTH-EAST EUROPE: A STRATEGIC ROLE IN EURO-ATLANTIC ENERGY SECURITY

Natural Gas & LNG Fundamentals. Greg Kist Vice President, Marketing, Corporate & Government Relations

Floating Liquefaction Project Overview February 2016

SMALL-SCALE LNG BUNKERING

Growth through Innovation and Integration

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

Lecture 12. LNG Markets

LNG Import Facility Infrastructure Options

Sakhalin II Project Update

Shale Gas Global. New Zealand LPG

LNG QUALITY AND THE UK GAS MARKET

Growth Leadership: Vopak s LNG growth strategy

Floating Regasification The Aegean LNG terminal

Noriyuki Kokubun a, Kiyohiko Ko b and Masahiko Ozaki c *

Alaska LNG Concept Information. Alaska LNG. Overview. October

GIE ANNUAL CONFERENCE. EUROPEAN GAS MARKET IN A GLOBAL CONTEXT SUPPLY/PRICE OUTLOOK May 2013 Andrew Morris

The International Propeller Club Port of Genoa

Introduction. FLNG: Costs and Cost Drivers. What is FLNG (and what isn t) FLNG Project Costs

Smart storage solutions for the LNG market

Doseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers

LNG a generational opportunity for British Columbia. Madeline Whitaker President BG Canada ITA Youth Conference 26 November 2014

Natural Gas and Japanese Energy Market. Hiroshi Ozaki

Offshore Tanzania. Equinor in Tanzania

ESSENTIAL NEED FOR NEW LNG PROJECTS Satisfaction of gas demand by region Bcf/d 100 North America +1.1% CAGR Europe Asia* +1.3% CAGR +4.4% CAGR

LNG Logistics A complete LNG supply solution along waterways

An Economic Solution to Small Mid Scale Liquefaction. Paul Emmitt New Technology Manager Brian Songhurst Director of LNG

3. Potentiality of Russian Far East 4. New LNG Projects in Russian Far East

LNG as a Bunker Fuel - LNGF (3 Days)

2019 LNG as a Bunker Fuel - LNGF (3 Days)

Feasibility study of CO2 free hydrogen chain utilizing Australian brown coal linked with CCS

INVESTMENT POTENTIAL INVEST IN PORT TERMINALS AT THE PORT OF WALVIS BAY NORTH PORT PROGRAM DATE: 29 AUGUST 2016 REVISION: 1

The outlook and opportunities for petrochemicals based on China s development of shale gas

LNG TERMINAL IN ŚWINOUJŚCIE AS A LNG GATE TO THE BALTIC SEA

Transforming into a Global Gas Company

member of the TSAKOS GROUP of companies

Natural gas. Natural Gas Embedded in Seas Close to Japan Natural gas reserves are abundant

Basic Hydrogen Strategy (key points)

Queensland LNG: Past, Present and Future

ENERGY POLICY & LNG SUPPLY AND DEMAND in TAIWAN

Infrastructure, transport and system aspects on CCS. Maurice Hanegraaf TNO

Port infrastructure for alternative fuels and maritime transport: the Livorno case

IMO future plans for regulation

Onshore terminal plants

Democratizing LNG Lowering the cost of small and mid-scale LNG solutions. Rainer Kersting: October 13 th 2016

The future of LNG Carriers

STRIKE ENERGY Limited Energy Users Association of Australia - 4 June 2014

of Tokyo Gas 24 Review of operations Core Business: Gas Sales

The City of Yokohama PRESS RELEASE

Hydrogen Energy Supply Chain from Overseas

LNG Opportunities. An Oil Search Perspective. PNG Chamber of Mines and Petroleum 28 November Oil Search Limited ARBN

A Global Outlook on Natural Gas

World s first LNG from Queensland, Australia A precursor to US LNG exports

LNG conversions for marine installations

Basic Hydrogen Strategy (key points)

CASE STUDY LNG SKIKDA S PROJECT

Hydrogen Energy Supply Chain utilizing brown coal

Floating LNG Business A breakthrough in offshore gas monetization

Liquefied Natural Gas Limited. ASX RELEASE COMPANY UPDATE 20 May 2013

Gas Commercialisation Update - May 2007

New energy for Italy

Energy Prospectus Group

Coal and Natural Gas The Evolving Nature of Supply and Demand

LNG Supply Chain Infrastructure Configuration

Coal Policy and Supply/Demand in Japan

EUROPEAN ENERGY FORUM 2013

Companies Behind LNG Canada Formalize Joint Venture; Milestone for Proposed Project

Appendix A: Project Characteristics

Ample supplies of LNG have created a low

Japan s LNG Policies and Japan-Argentina Cooperation. December 2014

Shale gas operation & water resource preservation. PECC, November 2013

GIBRALTAR STRAIGHT GATEWAY / EXIT TO THE MED. Directly above Gibraltar Airport at 375kts sse dn

New Medium-Term Business Plan (FY ) Beyond the Horizon. - 1st Stage of Growth Strategy for Realization of Corporate Vision

LNG R E F E R E N C E P R O J E C T S. Phone: +49(0) GOC Engineering GmbH Bachovenstr. 8; Sinzig, Germany

The Outlook for Energy: A View to 2040

ADI Analytics is a consulting firm serving oil and gas, energy, and chemical companies with passion, expertise, and rigor

CryoInnoNet- Network Biogas as a driving force for change. Pawel Warszycki

Learn more at

Upstream & Downstream

World and U.S. Fossil Fuel Supplies

On Board Regasification for LNG Ships. 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry

Gas Infrastructure Development in CEE: building basis for a major shift in energy-mix

Natural Gas- Green, Homegrown Energy for Virginia. Greg Kozera. President, Virginia Oil and Gas Association

Power & Politics Navigating the Changing Vision of Our Energy Future. Rayola Dougher, API Senior Economic Advisor,

COMPLETING THE LNG VALUE CHAIN

Transcription:

OFF-THE-SHELF MID-SMALL-MINI-SCALE LNG PLANT CASE STUDYFOR APPLICATION Yoshihisa Wakamatsu Deputy Manager, LNG Project Department International Project Division Shin Matsui Executive Officer, LNG Project Department International Project Division Yoshio Yatsuhashi Technical Advisor, LNG & Offshore Department Global Marketing Division JGC Corporation 2-3-1, Minato Mirai, Nishi-ku Yokohama 220-6001, Japan http://www.jgc.co.jp/ wakamatsu.yoshihisa@jgc.co.jp ABSTRACT Standard design engineering packages for Mid-small-mini Scale LNG Plant, having 0.1 1.5 million tons per year production capacity, were developed focusing on compact, pre-assembled and short LNG plant delivery for the development of mid-small gas fields less than 5 TCF. LNG demand is increasing and timely LNG supply is required, especially for power generation in Japan after the earthquake in 2011. It takes relatively long time to make the final investment decision (FID) for base-load LNG projects due to the huge total investment and stepwise approach: Feasibility Study, Pre-FEED, FEED, Bid, FID, and EPC. The off-the-shelf LNG design packages can contribute to achieve earlier LNG delivery. In addition to the conventional usage for power generation and utilities, there is a new trend in LNG usage as transportation fuel for trucks, trains, and ships, instead of diesel oil. Further, natural gas resources have become more diversified with the shale gas and coal seam gas. The off-the-shelf Mid-small-mini Scale LNG Plant can provide various optimum solutions with value-added ideas for realization of LNG projects based on JGC standard design engineering packages. The plant design concept is Reliable operation, Cost competitiveness and Fast track. This paper gives three conceptual case studies of Mid-small-mini Scale LNG Plant application: (1) Phased Development, (2) LNG Carrier Direct Loading and (3) Mini LNG for Transportation Fuel. 1. INTRODUCTION LNG demand is increasing and timely LNG supply is required, especially for power generation in Japan after the earthquake in 2011. Standard design engineering packages for Mid-small-mini Scale LNG Plant, having 0.1 1.5 million tons per year production capacity, were developed focusing on compact, pre-assembled, and short delivery LNG plants for the development of mid-small gas fields less than 5 TCF. The plant design concept is Reliable operation, Cost competitiveness and Fast track adopting proven/marketable processes and equipment based on optimized modular design. This paper gives three conceptual case 1

studies of Mid-small-mini Scale LNG Plant application: (1) Phased Development, (2) LNG Carrier Direct Loading, and (3) Mini LNG for Transportation Fuel. 2. BACKGROUND OF DEVELOPMENT 2-1. Project Schedule It takes relatively long time to make the final investment decision (FID) for base-load LNG projects due to the huge total investment and stepwise approach: Feasibility Study, Pre-FEED, FEED, Cost Estimate (including Bid), FID, and EPC. Figure-1 shows the typical schedule for base-load LNG projects. Especially, the duration of Pre-FEED and FEED sometimes takes a few years. As EPC bid starts after FEED completion ( A Project ), the timing of Final Investment Decision (FID) is assumed to be in Year 4 at the earliest. Dual FEED including the EPC cost estimate ( B Project ) gives slightly shorter project duration to FID. Figure-1: Typical Schedule for Base Load LNG Projects The off-the-shelf LNG design packages contribute to achieving earlier FID and LNG delivery as shown in Figure-2 by greatly reducing the pre-epc project phases. As the standard design engineering package includes a complete set of engineering deliverables, such as Process and Instrument Diagrams (P&IDs), once the site selection is done by Owner, it takes 9 months from the planning start to submission of the cost estimate for FID. The actual LNG production is calculated based on the standardized design using the actual feed gas composition and site data to be given by Owner. 2

Figure-2: Expected Schedule for Off-the-shelf Mid-small-mini Scale LNG Plant 2-2. New Trend in LNG Usage In addition to the conventional usage for power generation and utilities, there is a new trend in LNG usage as transportation fuel for trucks, trains, and ships, instead of diesel and heavy oil as shown in Figure-3. Figure-3: New Trend of LNG Usage From the environmental view point, carbon dioxide emissions of transportation are more than 20% of total emissions, and Sox/NOx emission regulations are being reinforced in Emission Control Areas (ECA) as shown in Figure-4. These facts are promoting the LNG usage for transportation fuel as substitution for the conventional oils. 3

Figure-4: Environmental Aspect for LNG Usage as Transportation Fuel The off-the-shelf Mini LNG plants having 0.1 0.3 million tons per year production capacity can be applied to supply of LNG fuel network. 2-3. Diversification of Gas Resources Natural gas resources have become more diversified with the addition of huge reserves of unconventional natural gas, such as shale gas, coal seam gas, and tight-sand gas. Figure-5: Possible Reserves Increase Figure-5 shows the possible reserves increase considering conventional natural gas and shale gas. For the purpose of this paper, the off-the-shelf LNG design packages take the lean gas characteristics of shale gas or coal seam gas into consideration. 4

3. CONCEPTUAL CASE STUDY FOR APPLICATION In order to demonstrate the advantage of the off-the-shelf LNG production models, this paper gives three conceptual case studies of Mid-small-mini Scale LNG Plant application: (1) Phased Development, (2) LNG Carrier Direct Loading and (3) Mini LNG for Transportation Fuel as shown in Figure-6. Figure-6: Conceptual Study Cases for Application 3-1. Phased Development Case-1 Mid-small LNG plant concept can be applied to the development of mid-small size gas fields. Study basis for Phased Development (Case-1) is shown in Table-1. As the natural gas reserves are assumed to be approximately 4 TCF, LNG production capacity may be set within a range of 3 to 3.5 million tons per year (MTPA). The overall concept for the project development is shown in Figure-7. One approach is to conduct the specific development work as Pre-FEED and FEED to optimize the plant capacity to meet the subject gas field size. Another approach is Phased Development adopting the off-the-shelf LNG plant, for example 3 trains of 1.0 MTPA as fast truck project execution. As 1.0 MTPA is the name plate capacity, the actual LNG production is calculated based on the standard design engineering package using the actual feed gas composition and site conditions like the meteorological data. 5

Table-1: Case-1 Study Basis for Phased Development Figure-7: Overall Concept for Project Development Figure-8 shows 1.0 MTPA LNG plant model consisting of equipment modules of process units and main piperack modules. The design concept of the optimum modularization was studied and developed. 6

Figure-8: 1.0 MTPA LNG Plant Model Figure-9: Project Schedule for Phased Development As shown in Figure-9, the first LNG production commences within Year 4 after the planning starts as fast track. The phased development is flexible (intervals between trains) and it depends on Owner s investment plan. As an example, Figure-9 shows 6 month interval between trains. For comparison and reference, a typical project schedule of conventional development like 3.0 MTPA is indicated in Figure-9. It may take approximately 7 years to commence LNG production at the earliest. The 3 rd train may be optional and the timing of construction is flexible depending on Owner s plan. 7

The proposed phased development should be one of the practical solution and the big advantage is fast track project realization with the earliest and timely LNG production. 3-2. LNG Carrier Direct Loading Case-2 Study basis for LNG Carrier Direct Loading (Case-2) is shown in Table-2. Due to availability of feed gas for this study, LNG production nominal capacity is selected to be 0.5 MTPA. In Mid-small LNG plant, the cost of the LNG storage tank, is one of the biggest portion of the total investment compared with a normal size base-load LNG plant, for example 5.0 MTPA LNG production capacity. Therefore, to minimize the cost of the off-site facilities, a drastically new approach was studied, i.e. eliminating the LNG storage tank and directly loading LNG from the rundown line into the LNG carrier. The plant location is assumed to be west coast of Canada. The LNG production calculated based on the lean feed gas from the existing pipeline is 0.56 MTPA, corresponding JGC s 0.5 MTPA LNG model. Table-2: Case-2 Study Basis for LNG Carrier Direct Loading Figure-10 shows the overall plot plan for LNG carrier direct loading. The sea shore of the site is steep enough to construct an LNG jetty with the minimum length of the trestle. Figure-11 shows 0.5 MTPA LNG plant model of the process train on a basis of module fabrication design. 8

Figure-10: Overall Plot Plan LNG Carrier Direct Loading Figure-11: Plot Plan LNG Train 9

It is assumed that two used BGT LNG carriers of 125,000 m3 are owned by Owner instead of the investment of new LNG storage tank construction so that the demurrage cost may not be considered. Two shuttle carriers are utilized for direct loading and transportation to final destination, for example Asian region. The carriers when loading will also function as storage. LNG loading method is shown in Figure-12. To replace the loaded carrier with the next shuttle carrier, 3 days interval is considered using LNG buffer tank having 5,000 m3 storage volume. The LNG loading duration of each shuttle carrier is estimated to be 33 days including berth/departure time for LNG loading weight of 55,000 tons. The loading duration corresponds to the average sailing period, for example 29 days between Canada and Japan. It should be the optimum for this application. Figure-12: LNG Loading Method The approach of the LNG carrier direct loading should have an advantage of the first investment cost reduction based on the overall CAPEX/OPEX evaluation. 3-3. Mini LNG for Transportation Fuel As mentioned before, there is a new trend in the LNG usage as transportation fuel for trucks, trains, and ships. Study basis for Mini LNG for Transportation Fuel (Case-3) is shown in Table-3. The multi Mini LNG plants are built for distribution to LNG stations in inland area of the subject country. It is assumed that the feed gas is supplied from the existing pipeline and the locations of Mini LNG plants are close to end users. The concept of Mini LNG for transportation fuel is shown in Figure-13. One Mini LNG plant having 0.25 MTPA production capacity covers certain area to deliver LNG to LNG stations by tank lorry. This LNG production corresponds to 200 tank lorries per day to the LNG stations and LNG supply to 5,000 trucks per day at the stations. 10

Table-3: Case-3 Study Basis for Mini LNG for Transportation Fuel Figure-13: Mini LNG Concept for Transportation Fuel Figure-14: Mini LNG Conceptual Layout 11

Figure-14 shows the Mini LNG conceptual layout of 0.25 MTPA model for truck LNG loading. The Mini LNG plant is designed on a modular basis to optimize the module sizes taking the module transportation on road into consideration depending on the locations of site and fabrication. Figure-15: Mini LNG Conceptual Layout (0.5 MTPA) For reference, Figure-15 shows the layout of 0.5 MTPA model for ship LNG loading being applied to alternative fuel of ships. The key of Mini LNG concept is design one, build many. 4. SUMMARY AND CONCLUSION Recently, plans of LNG projects are increasing in number due to the increased demand of LNG in the world. It takes relatively long time to make the final investment decision (FID) for base-load LNG projects due to the huge total investment and stepwise approach. For the materialization of the project, speedy approach to develop the plant concept and estimate the investment cost. On the other hand, there is a new trend in LNG usage as transportation fuel for trucks, trains, and ships from the environmental view point. Natural gas resources have become more diversified with the addition of huge reserves of unconventional natural gas, such as shale gas, coal seam gas, and tight-sand gas. The off-the-shelf Mid-small-mini Scale LNG Plant can provide various optimum solutions with value-added ideas for realization of LNG projects based on its standard design engineering packages. JGC believes that its plant design concept of Reliable operation, Cost competitiveness and Fast track will greatly contribute to the realization of Mid-small-mini Scale LNG Plant projects for the development of mid-small gas fields less than 5 TCF and the unconventional natural gas. 12