Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy

Similar documents
Re: PW Appendix 3 - Part 8

Public Private Partnerships: Lessons from Florida

How Public Private Partnerships Can Create Real Value in Water Projects

Pattullo Bridge Replacement Project. Cost Report

Gardiner East EA & Integrated Urban Design Study

Pattullo Bridge Replacement Project. Procurement Options Report

DEPARTMENT OF MUNICIPAL AFFAIRS AND ENVIRONMENT MUNICIPAL INFRASTRUCTURE PROJECT GUIDELINES

Summary of Findings. Bridge Inspection and Monitoring. Introduction. Findings

Design-Build and Design-Bid-Build

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON APRIL 24, 2017

Conceptual Design Report

Steeles Avenue Widening (Tapscott Road to Ninth Line) Principles of a Cost-Sharing and Implementation Agreement

2016 STRUCTURE INSPECTION APPRAISAL REPORT. Prepared For: THE CORPORATION OF THE TOWNSHIP OF AMARANTH COUNTY OF DUFFERIN

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

MINISTRY OF TRANSPORTATION ONTARIO MANAGING OUR ASSETS

Review of Construction Costs and Time Schedules for Virginia Highway Projects

Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017

Joint Legislative Transportation Oversight Committee January 6, 2016 Maintenance Operations Performance Analysis Report (MOPAR) Kristin Barnes

BID COMMITTEE DECISION DOCUMENT MEETING 99

Engineering & Capital Improvements. Shore Acres Civic Association August 21 st, 2017

DTX Project Delivery Methodology and Options. January 9, 2014

SCHEDULE 5 ADDITIONAL PAVEMENT MARKING SERVICES

SEPARATED PROJECT DELIVERY SYSTEMS

CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON OCTOBER 24, 2017

Design-Build: the National Perspective

13/05/2013. Kees Cusveller, VP Business Development, Graham. David Clinckett, Assistant Director Construction, Calgary Catholic School District

PPPs Canada s experience Water sector

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Public Private Partnerships (P3) Management Framework

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Models for Management and Delivery of Capital Projects

TxDOT Public-Private Partnerships Lessons Learned. OMW: Market, Communication, and Policy Trends in Tolling

Queensville Holland Landing Sharon Sanitary Servicing. York Region Project Update

Sunrise Project South I-205 Corridor Improvement Project

Special Provision No. 199S53 February 2005

TABLE OF CONTENTS. Manual Section. Introduction 1. Using This Manual 2-3. Administrative Actions 4-6. Road and Bridge Project Types 7

ATTACHMENT F EXAMPLE SIMPLE CONCEPTUAL CTD (CONTRACT TIME DETERMINATION) FOR 25% DESIGN STAGE

City of Portage la Prairie Wastewater Treatment Plant Upgrade Summary P3 Business Case. August 2016

Surrey-Newton-Guildford LRT Project. Procurement Options Identification Report

Highway Construction Program

BA Blacktop Ltd. An ISO 9001:2008 registered

STRUCTURE AND BRIDGE DIVISION

Nova Scotia s Primary and Secondary Highway Systems: 10-Year Needs

January25, **Revised** P3 enables Anthony Henday Drive S.E. to open in 2007

SCHEDULE THREE TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS

Report No. 3 of the Environmental Services Committee Regional Council Meeting of April 18, 2013

Open house Sept. 29, 2016

Performance Based Contracts in Non- Revenue Water Reduction Programs March 2017

PUBLIC-PRIVATE PARTNERSHIPS TRANSPARENCY AND ACCOUNTABILITY BILL. No. 605

Preserve Your Roadway Network

PUBLIC NOTICE. From: Corporate Services Date: March 26, 2012 Re: Federal Gas Tax Reporting

Exhibit A Mn/DOT Contract No

Deploying Integrated Systems in a DBM or DBOM Environment

Maine Turnpike Authority FINAL 4-year Capital Investment Plan ( )

Report for Action. Relief Line South Tunnel Design. Summary. Recommendations. Financial Summary

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY

Contract Administration Section

STATUS REPORT Congestion-Relief Program. Steve Gillen Illinois Asphalt Pavement Association March 12, 2007

Special Provision No. 599S22 March 2001

SPECIAL REPORT. MTO s Kevin Bentley

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

City of Regina Wastewater Treatment Plant Upgrade Design, Build, Finance, Operate, & Maintain Project

2018 OPERATING BUDGET BRIEFING NOTE Costs Incurred for Engineering Services

CUY-480-Valley View Bridge. Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street

JOB BB0903 HWY. 71B INTCHNG. IMPVTS. (S) JULY 25, 2018

Pattullo Bridge Replacement Project Development

South Fraser Perimeter Road Project Request For Qualifications

Developing an Asset Management Plan for Highway DBFO Projects

Fall 2018 Engineer Trainee Recruitment Preference Sheet

Attachment A. TransformTO Short-term Strategies Business Cases

DRAFT SCOPE 1.0 General Requirements

Wednesday, October 17, Texas A&M University College Station, Texas

BACKGROUND

TERMS OF REFERENCE PROJECT EDINBURGH ROAD FROM SPEEDVALE AVENUE TO LONDON ROAD

RESILIENT INFRASTRUCTURE June 1 4, 2016

3.14 Maintenance of the Provincial Highway System

Gordie Howe International Bridge Public Information Meeting. Detroit, Michigan July 19, 2017

Understanding NC House Bill 857 Design Build and Public-Private Partnerships

Eastern Region, Ministry of Transportation, Ontario. Island Park Drive Rapid Bridge Replacement

National overview of the bridge condition and management: Japan

SUSTAINABLE PAVEMENT DESIGN: DOING MORE WITH LESS

Audit of the Initiation Phase of the New Bridge for the St. Lawrence Corridor (NBSLC) Project

Overview of the Project Development Process. Brian Blanchard, PE Assistant Secretary for Engineering and Operations

PUBLIC WORKS COMMISSION 2018 STREET EXCAVATION PERMIT PROCEDURE

Construction Management at Risk (CMAR) INFORMATIONAL MEETING July 18, 2013

CONSTRUCTION MANAGEMENT REQUEST FOR PROPOSAL EAST RUTHERFORD PUBLIC SCHOOLS

Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495

Millennium Line Broadway Extension Project. Cost Report

Planning Analytics for Asset Lifecycle Management (PALM)

1 TRANSPORTATION IMPROVEMENTS DONALD COUSENS PARKWAY TO MORNINGSIDE AVENUE LINK AMENDMENT TO THE ENVIRONMENTAL ASSESSMENT PROJECT UPDATE

395 Express Lanes Project Design-Build Procurement Industry Outreach. March 23, 2016

Report to: General Committee Date Report: February 20, Award of Tender 213-T-14 West Thornhill Phase 1B Storm Sewer and Watermain Replacement

Design-Build Terminology

Request for Proposal Design-Build Reconstruction of Bridge No. 15 and Bridge No. 17

Humber Bridge Trail Bowstring Arch Bridge Class Environmental Assessment

Peterborough County Road Safety Audit Guideline Pilot

Transcription:

Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy Presentation to Executive Committee September 21, 2015 1

Overview Project Background Procurement Options Analysis of Alternative Financing & Procurement Approach Procurement of External Advisors Project Governance Structure and Timelines Recommendations Summary 2

Background F.G. Gardiner Expressway At-grade section: Hwy. 427 to Dufferin Street (1955 to 1958) Elevated section: Dufferin Street to Logan Avenue (1959 to 1966) Strategic Rehabilitation Plan Study area: Highway 427 to Logan Avenue (Don Valley Parkway) Recent condition assessments and prioritization of works based on public safety and needs Consideration given to recently completed interchange EA studies Identify: immediate, short term and longer term rehabilitation needs 3

Expressway Cross Section of Span F.G. Gardiner Expressway 10" Lake Shore Boulevard 4

Condition Assessment Key Findings Elevated Section: Concrete Deck and Barrier Walls are in poor condition and nearing the end of their service life Some of the Bents require extensive concrete repair work Drainage modifications are necessary Concrete T-beams and Box Girders are in good to moderate condition Steel girders are good condition and will be in need of recoating within the next 25 years At Grade Section: Overpass and Underpass Concrete Repairs Pavement reconstruction and resurfacing Roadside safety improvements 5

Strategic Rehabilitation Accelerated Bridge Construction Approach 6

Accelerated Bridge Construction Approach Typical duration for 2 lane reconstruction (8 metres X 400 metres) = 2 months (6 months for entire section) Prefabrication Facility 7

Strategic Rehabilitation Conventional vs. Accelerated Bridge Construction NPV Total Project Cost ($ Billions) 9 8 7 6 5 4 3 2 1 0 Traffic Impact: > 20 years $7.4 B $4.5 B $1.21 B $1.31 B Conventional Traffic Impact: 12 years Accelerated Capital Costs User Impact Costs 8

Council Decision (April, 2014) Strategic Rehabilitation Plan Approved Accelerated Construction Approach Report back through Transportation Services 2015 Capital Budget and 2016 to 2024 Capital Plan submission on: Procurement approach & project delivery schedule Multi-year cash flow requirements & financing strategy Update the Strategic Rehabilitation Plan to account for the Gardiner East EA preferred option Proceed with the conventional construction approach for the West Deck (Exhibition Place to west of Bathurst Street: 800 metres) because: Two at-grade construction projects also planned for 2014 Estimated 3 year lead time to begin accelerated construction approach 9

Background Gardiner East EA 10

Gardiner East EA Hybrid Option 3 Hybrid Design Alternatives are being evaluated (PWIC September 22, 2015) 11

Strategic Rehabilitation Plan Revisions Revised Strategic Rehabilitation Plan: incorporates the Hybrid Option for elevated section of the Expressway east of Jarvis Street For purpose of procurement analysis "base case" hybrid option presented to Council in June, 2015, was used The Hybrid Option Design Alternatives may incur higher capital costs over the "base case" The recommended procurement option is not expected to be affected by the choice of Hybrid Option Design Alternative, but project costs will be affected 12

Procurement Options Traditional Design-Bid-Build Most common approach used in City municipal works construction: Procure engineering design and construction separately, and sequentially 12-year implementation schedule for the Strategic Rehabilitation Plan using the Accelerated Bridge Construction approach is based on Design-Bid-Build Design-Build Bundle the design and construction of a project Use one competitive procurement to hire a private sector firm at a fixed fee Applying the Design-Build model to the Revised Strategic Rehabilitation Plan could lead to further compression of the schedule 13

Alternative Financing & Procurement (AFP) AFP is a project procurement and delivery model Expressway remains in City ownership City continues to control all aspects of Expressway AFP approach is typically used for large, complex projects Used across Canada and United States Process is designed to transfer risks to the contractor, where project schedule and construction challenges are taken into account in their bid 2 AFP approaches considered Design-Build-Finance Design-Build-Finance-Operate-Maintain 14

AFP Procurement Options Design-Build-Finance Places responsibility for project financing, as well as the engineering design and construction, with the contractor Design-Build-Finance-Operate-Maintain (DBFOM) Adds a long-term operations and life cycle maintenance concession contract to the design and construction contract Contractor is also responsible for short and long term financing of all project costs City only pays a portion of project cost at substantial completion of construction 15

Procurement Options Contractor Roles & Responsibilities Procurement Option DBB DB DBF DBFOM Preliminary design Detail design Design and construction co-ordination Construction Maintenance Lifecycle (major capital refurbishment) Operations Short-term financing during construction Long-term financing 16

Qualitative Analysis Design-Build-Finance-Operate-Maintain Potential further acceleration of construction (from 12 to 6 years) Improved schedule certainty Stronger incentives for on-time completion Procurement supports innovation in design and delivery Can add significant value Long-term effective warranty as a result of 30-year concession contract Private sector (financier) oversight assures contractor compliance particularly schedule DBFOM is a requirement for P3 Canada Funding 17

Value for Money Analysis Present Value Cost Comparison of Traditional Procurement vs AFP (DBFOM) Positive Value for Money after adjustment for retained risks of at least 16% or $500 million (NPV) over: 6-year construction period; and 30 year concession period (for O&M and lifecycle maintenance) 18

Provincial Auditor General Review of IO- AFP Projects December 2014 AG review of 74 Infrastructure Ontario AFP projects: Indicated project cost estimates $8 billion higher than traditional estimates, before consideration of estimated $15 billion avoided/transferred costs/risks Acknowledged that AFP projects were for the most part on time and at contracted cost Identified concerns about IO estimates of value of transferred/avoided risks (inadequate empirical data, formula inconsistencies, cost estimates overly conservative) Led to improvements to IO value for money assessment 19

DBFOM Approach Estimated Construction Capital Costs Preliminary Estimated Project Construction Capital Costs $ Millions (As spent) Construction Cost $2,460 Professional Services $110 Total Capital Project $2,570 Preliminary Estimated 1/3 Federal Contribution ($820) Net Capital Cost to City $1,750 20

DBFOM Approach Estimated 10-year Capital Costs: 2016-2025 Preliminary Estimated 10 year Capital Outlay 2016-2025 $ Millions nominal / as spent Professional Services $110 Net City Substantial Completion Payment (85%) $1,265 Amortized Construction Payments 2024-25 $58 Total City Estimate 2016 2025 $1,433 Assumptions 100% debt financed 15% capital cost financed over concession period 30-year debt Excludes O&M, Lifecycle maintenance costs 21

DBFOM Approach Total Estimated Contract Value (with 30 year concession period O&M) $ millions as spent Construction Cost (2018-2023) $2,460 Concession Charges: O&M, Lifecycle Maintenance, Capital Financing (2024 2053) $1,390 Total Estimated DBFOM Contract Value $3,850 Less Estimated Federal Capital Funding ($820) Estimated Net Contract Value $3,030 22

Infrastructure Ontario (IO) Proposed Continued Support IO brings extensive experience procuring and managing large-scale, complex infrastructure projects using an AFP approach Proposed support: Develop Project Specific Output Specifications (PSOS) Documents Identify, procure, manage necessary technical advisors Manage the Request for Qualifications and Request for Proposal processes Assist with negotiations with the Preferred Proponent to reach Commercial and Financial Close Fee estimate for continuing assistance from IO is approximately $12 million inclusive of non-recoverable HST 23

Additional External Advisors Additional external advisors: Fairness Monitor Financial Advisor Insurance Consultant Legal Advisor Quality Advisor Scheduling Consultant Technical Advisor Traffic Consultant All additional external advisors will be retained as required through competitive processes Some of the advisors could be procured by IO, with the City retaining all final decision making authority on the advisors retained The fees for External Advisors are estimated to be $40M 24

Public Consultation Top issue identified through the polling: Ensuring that the rehabilitation of the Expressway is completed on time and on budget Project delivery by the private or public sector was not considered relevant Survey results identified the following top 5 priorities: 1. Ensure that the construction work that is undertaken is of high quality 2. Minimize traffic congestion caused by construction 3. Minimize construction duration 4. Deliver the construction work on budget 5. Keep the costs to the City as low as possible 25

Project Procurement Governance Structure 26

Project Timelines PROJECT PHASE Timeline Preparation of Procurement Documentation 2015 Procurement of the Preferred Proponent to deliver the Revised Strategic Rehabilitation Plan 2016 Recommend AFP Contract Award to Council 2017 Commencement of Construction 2018 Completion of Construction 2023 Commencement of Operations and Maintenance 2024 27

Recommendations Overview Implement the Strategic Rehabilitation Plan using a Design-Build- Finance-Operate-Maintain procurement approach Submit business cases to P3 Canada and Infrastructure Canada for 1/3 of the eligible capital construction costs Request 1/3 matching funding from the Province of Ontario Enter into an agreement with Infrastructure Ontario for assistance with the DBFOM procurement Submit proposed cash flows and funding sources as part of the 2016 Budget process Report back to Executive Committee and Council on the results of the procurement process and to seek authority to award a contract 28