EXTERNAL REPORT. Smart Metering Entity (SME) MDM/R Report 4 th Quarter October to December. Issue January 29, 2014

Similar documents
Accessibility of Big (Smart) Data

Best practices for smart meter data management. Gary Michor President and CEO The SPi Group Inc.

MDM/R Status Update and Plans

Electricity Power System Planning

Distributed Generation in the Ontario Regulatory Context

Market Analysis & Costing Model for Electricity Consumption Data. January 31, 2018

Green Energy and Green Economy Act. Changes to Ontario s Electricity Sector

Ontario s Submission to the National Energy Board Modernization Expert Panel

SUMMARY OF TRANSMISSION BUSINESS

CONSERVATION FRAMEWORK MID-TERM REVIEW

Improving the RFP and Contracts Process With COBIT 5

Toronto Hydro-Electric System Limited EB Exhibit F1 Tab 6 Schedule 2 ORIGINAL Page 1 of 5 CUSTOMER SERVICES

Setting the Stage for Renewable Energy in Ontario: the Renewable Energy Standard Offer Program (RESOP) and other OPA Initiatives For Sustainable

Ontario Energy Board Business Plan

BULLETIN. DATE ISSUED: October 18, 2018

A. General Information

Request for Proposals Facilitating Utility Smart Energy Education (FUSED)

Major Event Response Reporting April 15, 2018

MASTER COMPETITIVE SERVICE AGREEMENT MANAGEMENT OFFICE SUMMARY REPORT May 2008

SHARED SERVICES - ASSET MANAGEMENT

Internal Audit Implementation Status Report

A. General Information

PAULA ZARNETT. She has performed assignments for clients in North America, China, Ghana, and Barbados.

Hydro One Experience with Renewable Distributed Generation & Advanced Distribution System Initiative

Ontario s Electricity Pricing and Rate Design

Ontario Open Government

Putting Ontario s Long-Term Energy Plan Into Action

MASTER COMPETITIVE SERVICE AGREEMENT TRANSPARENCY REPORT May 2009

Exhibit A - Scope of Services AMI Implementation Project Management Services

Moving Ahead: Smart Meters and TOU Pricing in Ontario, Canada

Non-Operational Reporting and Analytics (NORA) Harnessing the potential of information at Ontario s Community Health Centres

Procedure for Community Selection

The City of Guelph s Community Energy Initiative

Smart Meter Implementation Plan Ontario Energy Board

ITIL Intermediate Capability Stream:

Mid-Term Review: Conservation Framework. 1 st Mid-term Review Public Webinar April 18, 2017

Draft Working Document Version 0.6. Prepared by: The SMI Data Standards Working Group September 27, 2005

REGIONAL PLANNING PROCESS

BUSINESS SECTOR STRATEGY:

Gas-Electric Coordination Enhancements. Webinar - May 7, 2015

Analysis of the final version of Cameroon s R-PP

RAI Compliance Activities Overview

Barrie Hydro Distribution Inc.

INVESTMENT PLAN DEVELOPMENT

Overview of the IESO- Administered Markets. IESO Training

Table of Contents. Executive Summary...3. Overview of Division...5. Summary of Accomplishments...6

SMART METERING PROJECT PHASE 1 INFORMATION PAPER CER/09/024

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

CLIMATE DATA AND SERVICES FOR ADAPTATION PLANNING

Item 1 Appendix 1. Quarterly Performance Report

Agenda Member Representatives Committee Pre-Meeting Informational Session Conference Call and Webinar July 18, :00 a.m. 12:00 p.m.

Follow-Up on VFM Section 3.06, 2015 Annual Report RECOMMENDATION STATUS OVERVIEW

Be Smart About Meter Data Management

Trilliant Incorporated: Bill Vogel, CEO

Oracle Taleo Business Edition Implementation Fixed Scope Offerings

Ontario s Local Food Strategy

Oakville Hydro Inc. Conservation and Demand Management Annual Report. Submitted to: Ontario Energy Board EB

Enterprise Technology Projects Fiscal Year 2012/2013 Fourth Quarter Report

March Workplace Safety and Insurance Board Workwell Program 2011 Value for Money Audit

Greater Ottawa Region Local Advisory Committee Meeting #5. June 21, 2016

21,363 MW 22,774 MW ONTARIO ENERGY REPORT Q JULY SEPT 2014 ELECTRICITY. Electricity Highlights Third Quarter Ontario s Power Grid

STRATEGIC BLUEPRINT: Keeping Pace With an Evolving Energy Sector

Incident Management Process

Customer Information System (CIS) Replacement Project

E-vote SSA-V Appendix 2 Contractor Solution Specification Project: E-vote 2011

Total Market Demand Wed Aug 08 Thu Aug 09 Fri Aug 10 Sat Aug 11 Sun Aug 12 Mon Aug 13 Tue Aug 14

Version 4.6. CMS Online Quarterly Release Notes. October Copyright 2017 International Human Resources Development Corporation

UCPath Program. Academic Business Officers Group April 14, ucpath.universityofcalifornia.edu/

THE ROLE OF GOVERNMENT BACKGROUND PAPER

SGF Agenda Item # 5: Demand Response Theme Discussion. Ontario Smart Grid Forum Tuesday, June 8, 2010

Meter Data Management System (MDMS) Sharing. Ricky Ip CLP Project Manager

Scorecard - Hydro One Networks Inc. 9/24/2017

Economic Viability of Residential Microgrids in Ontario

ServiceNow Custom Training and Adoption

ATTACHMENT FINAL IESO RESULTS REPORT POWERSTREAM RZ

EXHIBIT A SCOPE OF SERVICES CONSULTANT SERVICES DISTRICTWIDE TRAFFIC SIGNAL RETIMING FINANCIAL PROJECT ID:

Workplace Safety and Insurance Board Workwell Program 2011 Value for Money Audit. Executive Summary March 2012

CDM Forecasting Initiative

EDA s Vision : Local Distribution Utilities Future Role in Building the Sustainable Communities of Tomorrow

A Progress Report on Contracted Electricity Supply

MARKET PRICES FOR SOLAR ELECTRICITY IN ONTARIO

Guidance on Application of. Provincial Air Quality Objectives for NO 2. B.C. Ministry of Environment

The Value of Electricity to Ontario

Electricity Distribution Rate Design for Commercial & Industrial Customers

EVALUATION OF THE IMPACT OF SUB METERING ON MULTI RESIDENTIAL ELECTRICITY CONSUMPTION AND THE POTENTIAL ECONOMIC AND ENVIRONMENTAL IMPACT ON ONTARIO

Acquisition of MDUS/ODS Software

Fertilizer Canada: Delivering Exceptional Member Value Through 2020

CHANGING THE DSO TO REAP THE FULL BENEFITS OF SMART GRIDS

Supplementary Submission on the OPA CDM Strategy Design Process

Taking Greater Control of Your Energy Use: A Municipal Energy Profile

Ontario-US Comparator: Standard-Making and Enforcement Functions

Audit Committees and Regional Internal Audits

Authors: Steven Jewell Assistant Director IT and e-government Tel: ; Paul Fleming Systems Architect

2017 Project Prioritization & Budgeting Process

Cost Management in the AWS Cloud. March 2018

SSL ClearView Reporter Data Sheet

Introduction to SEND Assurance Tool

Accessibility compliance and enforcement report 2017

Helpful hints for utilities providing energy or water consumption data to building owners

Follow the Sun SAP Application Management Support (AMS) Services

Transcription:

REPORT EXTERNAL, Smart Metering Entity (SME) MDM/R Report 4 th Quarter 2013 October to December Issue 2.0 - January 29, 2014

Table of Contents 1. Introduction... 2 1.1 Purpose... 2 1.2 How to Use this Document... 2 2. MDM/R Operation and Processing Performance... 3 2.1 Performance... 3 2.2 Training... 3 2.3 Other Activities... 3 3. MDM/R Service Levels... 4 4. Initiatives and Software Testing... 5 5. Additional Risks and Issues... 6 Issue 2.0 01/29/2014 Page 1 of 6

1. Introduction 1.1 Purpose The purpose of this report is to provide a quarterly update to the Ontario Energy Board on the ongoing operations of the Meter Data Management and Repository (MDM/R). This report includes the following updates: MDM/R Operation and Processing Performance; MDM/R Service Levels for both Critical and Non-Critical Services as set out in Appendix A of the MDM/R Terms of Service ; Initiatives and Software Testing; Additional Risks and Issues; and, Roles and Responsibilities of the SME as set out in Article 2.2 of the Smart Metering Agreement for Distributors 1.2 How to Use this Document This report presents information and status updates on MDM/R operation and processing performance (in Section 2), MDM/R Service Levels (in Section 3), and Initiatives and Software Testing (in Section 4). The report focuses on quarterly updates for the MDM/R including updates on the Roles and Responsibilities of the SME through the end of the indicated month. More information about the provincial Smart Metering Initiative and the MDM/R is available on the websites of the Ministry of Energy (http://www.mei.gov.on.ca/), the Ontario Energy Board (http://www.oeb.gov.on.ca/oeb/industry) and the IESO/SME website (http://www.smi-ieso.ca/). Each section provides updates as required by the Ontario Energy Board in connection with MDM/R operations and performance, service level attainment, initiatives and software testing, as well as risks and issues. Issue 2.0 01/29/2014 Page 2 of 6

2. MDM/R Operation and Processing Performance 2.1 Performance The MDM/R production environment remains stable and reliable, processing reads from over 4 million meters for 71 LDCs on a daily basis. The SME continues to respond to and address LDC support, service requests, and issues in a timely manner. For the reporting period October 1 to December 31, 2013, the MDM/R operated well, meeting and exceeding service levels for 98.47% of meter reads, 99.62% of billing quantity requests, and 100% for master data updates. Where there were processing delays, service was restored in a timely manner, or the delay was related to poor quality or timing of data submissions by one or more LDCs. During the past quarter, the SME published LDC-specific performance metrics reports for the months of September, October and November. These reports provide each LDC with valuable data related to their organization s meter read, synchronization, and billing performance. Feedback from LDCs has been very positive on this initiative. As part of the SME s outreach plan, and as a result of the positive feedback received from LDCs, the SME plans to continue scheduling and conducting more on-site visits with LDCs for 2014. Although the SME continues to observe improvements in LDC performance related to the MDM/R, the SME continues to work with LDCs and their metering providers to manage the quality and timing of meter read data submissions in order to improve the performance of meter read and billing processing. As part of the scheduled SME Steering Committee meetings, a conference call was held in November for the benefit of all LDCs. All LDCs were invited to participate during this call. 2.2 Training During the fourth quarter, the SME delivered one Advanced Graphical User Interface training session and one basic session. The advanced course provides LDCs with a variety of scenarios for investigation and troubleshooting of meter read data submissions, synchronizations, and billing exceptions. For the complete training schedule, please visit the SME website. 2.3 Other Activities On November 15, 2013 the IESO received an unqualified opinion in the completed annual audit. The Meter Data Management and Repository s (MDM/R) operations, processes, and procedures are in accordance with the Canadian Standard on Assurance Engagements for Reporting Controls at a Service Organization, set out in the CICA Handbook Assurance ( CSAE3416 ). The CSAE 3416 report covered the period from April 1, 2013 to September 30, 2013 and the results of this audit were made available to Distributors upon request. In December, the SME deployed enhanced functionality in the MDM/R Service Desk tool enabling LDCs to better manage their contact information and users. The SME continues to make improvements to this tool and processes based on feedback from Distributors and agents. Issue 2.0 01/29/2014 Page 3 of 6

3. MDM/R Service Levels The Service Level Performance Chart splits Service Level summaries into two parts: Critical Service Level Summary, and; Non-Critical Service Level Summary The Critical Service Level Summary section includes processing metrics for Meter Read Data, Billing Quantity Response, MDM/R Master Directory, and the Graphical User Interface (GUI). The Non- Critical Service Level Summary section includes processing metrics for Service Desk Response Times. The table includes a Service Level breakdown for each month along with a quarterly summary. Critical Service Level Summary Meter Read Data Processing Billing Quantity Response Processing MDM/R Master Directory (MMD) Processing MDM/R Graphical User Interface Service Desk Response Time Oct-2013 Nov-2013 Dec-2013 4 th Quarter # of Intervals Processed 3,206,387,570 3,058,223,015 3,119,569,125 9,384,179,710 # of Intervals Processed within Service 3,089,086,178 3,034,888,847 3,116,949,741 9,240,924,766 Level Time % Intervals Processed within Service 96.34% 99.24% 99.92% 98.47% Level Time # of Incidents with Single Delay > 45 mins 2 6 0 8 and/ or # of Incidents resulting in Accumulated Delay > 240 mins # of BQ Requests Processed 3,041,811 3,751,092 3,474,013 10266916 # of BQ Requests Processed within 3,002,562 3,751,092 3,474,013 10227667 Service Level Time % Requests Processed within Service 98.71% 100.00% 100.00% 99.62% Level Time # of Incidents with Single Delay > 45 mins 1 0 0 1 and/or # of Incidents resulting in Accumulated Delay > 240 mins # of Data Elements Processed 3,581,200 2,030,207 1,818,637 7430044 # of Data Elements Processed within 3,581,200 2,030,207 1,818,637 7430044 Service Level Time % Data Elements Processed within 100.00% 100.00% 100.00% 100.00% Service Level Time # of Incidents resulting in Data Elements 0 0 0 0 Processed outside Service Level Time User Interface Availability 99.64% 100.00% 100.00% 99.88% # of Incidents resulting in non-availability of Service < 99.80% 1 0 0 1 Non-Critical Service Level Summary Response Time (90% of Sev 1 and Sev 2 incidents response time within 15 minutes) # of Incidents (Sev 1 and Sev 2) OSP responded after 15 mins 100.00% 100.00% 100.00% 100.00% 0 0 0 0 Issue 2.0 01/29/2014 Page 4 of 6

4. Initiatives and Software Testing MDM/R Release 7.6 Upgrade This project will upgrade the MDM/R software to a more current version to keep it maintainable and supportable, and also deliver the Measurement Canada 2012 Phase 2 solution functionality. We are targeting to complete this project by Q3 2014. This project is well underway, and the SME will continue to provide updates to LDCs as the project progresses. Measurement Canada 2012 Phase 2 The software for the Measurement Canada (MC) 2012 Phase 2 solution is expected to be made available for LDC testing at the same time as the upgrade of the MDM/R (above) in mid 2014. The MC 2012 Phase 2 solution provides additional quality indicators for estimated and calculated register reads and the ability to designate externally submitted register reads as estimated. It also allows LDCs to use the MDM/R for billing based on hourly and periodic consumption in order to further support Measurement Canada requirements. Phase 2 of the Measurement Canada 2012 solution includes the following components: Calculative reads equality adjustment (periodic and hourly) and related measurement profiles; Additional quality indicators for externally estimated and calculated register reads using estimated intervals; and Extension of the Trilliant meter readings interface for estimated register reads. To reduce the SME s and LDCs efforts and costs of testing and deploying both the Measurement Canada 2012 Phase 2 solution and the MDM/R Release 7.6 upgrade in two separate releases, the SME is combining the testing and deployment into one software release. The SME Steering Committee expressed unanimous support of this approach. MDM/R Infrastructure Refresh The project to update the computing infrastructure of the MDM/R is currently underway in order to deliver further improvements to the performance and operation of the MDM/R. Testing of the updating computing infrastructure is progressing well. At this time, the SME is targeting to have the MDM/R transitioned to the new computing infrastructure in March 2014 pending successful completion of testing. MDM/R Data Access The SME is involved in three Ministry initiatives to improve access to electricity data stored in the MDM/R and derive additional value from that data: To help consumers conserve energy and save on electricity costs the Ministry launched the Green Button Initiative on November 21, 2012 with the objective to provide electricity consumers with greater access to information about their energy consumption, and encourage the creation of new innovative tools for consumers.. Issue 2.0 01/29/2014 Page 5 of 6

In March 2013 the Ministry launched the MDM/R Road Map initiative to identify opportunities to derive additional value from the investments already made in the Province s smart metering infrastructure and the MDM/R. In accordance with a Ministry Directive, on February 11, 2013, the OEB s Supplemental Report on Smart Grid stated that The Smart Metering Entity (SME) must investigate opportunities for providing access to depersonalized, generic data to third parties for planning, research, and customer benchmarking purposes (e.g., allowing customers to compare their consumption with that of their neighbours). The SME has conducted initial research of technologies that could be used to support broader data access and analysis of data stored in the MDM/R. The IESO has provided multiple updates to the Ontario Energy Board, the Ministry, OPA, and LDCs on the progress of this project over the past few months. Feedback from the Ministry, OEB, OPA and LDCs has been very supportive and encouraging. Further work is required with the Ministry of Energy, the Ontario Energy Board and stakeholders of the MDM/R to assess the future level of demand for and value of data access and analytics, in order to determine next steps. In December, the SME received a letter from the Ministry indicating that the Ministry would be working with the IESO to develop a business case over the coming months for a data access platform. 5. Additional Risks and Issues There are no additional risks and issues to report. Issue 2.0 01/29/2014 Page 6 of 6