SAFETY» Total Man Hours Worked This Week: 19935» Total Man Hours on Project: 689727» Crafts On Project This Week: 24» OSHA Recordable Rate: 0 November 13, 2016 Page 1
CURRENT CONSTRUCTION ACTIVITIES East Zone» Continued Overhead Rough-In @ Buildings E & F.» Continued MEP Rough-In @ Building E.» Continued FCU Ductwork @ Buildings E & F.» Continued MEP Trim-out @ Building G.» Gas Water Heaters Start-up @ Buildings E & F.» Continued Setting Showers @ Building E.» Continued Hanging Drywall @ Buildings E & F.» Continued Finishing Drywall @ Building G.» Continued Priming Walls @ Building G.» Continued Tile Flooring @ Building G.» Continued Forming East Monumental Stairs.» Poured Sidewalk North of Building F.» Began Grading @ East Spine. Bldg. E Overhead Rough-In Bldg. F Exterior Soffit Framing Bldg. G Fire Rated Frames & Glass SITE, HUB, & WEST ZONE» Began Interior Framing @ Building B.» Continued Brick Masonry @ HUB & Building B.» Continued MEP Rough-In @ HUB.» Continued Roofing @ HUB & Building B.» Continued Glass Installation @ HUB & Building B.» Poured Topping Slab @ Building C.» Continued Interior Framing & Drywall @ Building A.» Continued DEFS @ Building A.» Continued MEP Rough-In @ Building A.» Began Precast @ Building D.» Installed Water Line from HUB to Cooling Towers.» Continued Coil Piping to AHU @ HUB.» Began Priming HUB Canopy Steel. East Monumental Stair Forms Pedestrian Sidewalk North of Building F November 13, 2016 Page 2
NEXT WEEK S ACTIVITIES East Zone» Elevator Inspection @ Building E.» Continue Overhead Rough-In @ Buildings E & F.» Continue MEP Rough-In @ Building E.» Continue FCU Ductwork @ Buildings E & F.» Continue MEP Trim-out @ Building G.» Continue Fire Protection Upfit @ Building E.» Continue Setting Showers @ Building E.» Continue Hanging Drywall @ Buildings E & F.» Continue Finishing Drywall @ Building G.» Continue Priming Walls @ Building G.» Continue Tile Flooring @ Building G.» Pour Steps @ East Monumental Stair. Bldg. A Overhead MEP Rough-In Bldg. B Interior Framing Bldg. D Precast SITE, HUB, & WEST ZONE» Continue Curtain Wall Framing @ HUB.» Continue Brick Masonry @ HUB & Building B.» Continue MEP Rough-In @ HUB.» Continue Roofing @ Building B.» Continue Glass Installation @ HUB & Building B.» Continue Interior Framing & Drywall @ Building A.» Continue Interior Framing @ Building B.» Continue MEP Rough-In @ Building A.» Continue Interior Framing @ Building B.» Complete HUB Roofing.» Pour SOG @ Building D. HUB Curtain Wall HUB Canopy Steel - Prime Coat November 13, 2016 Page 3
MANPOWER TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Holder Construction Company General Contractor 39 1950 88615 American Deep Foundation Auger Cast Piles 0 0 6166 Baker Roofing Sheathing and Shingles 0 0 7194 Brightview Landscape Development Hardscape & Landscape 5 200 2300 Carolina Fire Protection Sprinklers 16 800 14825 C&C Fence Site Fence 0 0 854 Cowart Tree Mulch Tree Removal 0 0 710 Davis Crane Erectors Pre-Cast Erection 12 600 22950 D.H. Griffin Tank Foundation Removal 0 0 90 Elite Flooring Tile 3 150 300 Feltman Brothers West - Masonry 25 1250 8250 Gainesville Mechanical Ductwork 33 1815 48634 Gill Plumbing Plumbing 30 1500 14800 Graham Hodge Glass 5 250 1350 Gregory Electric Aboveground Electric 13 650 10550 Hutch-N-Son Early Site Work 0 0 1337 1st Choice Glass Glass 8 360 8062 Johnson Controls Building Controls 3 150 3375 JBR Construction Early Site Work 0 0 2049 Johnsons Modern Electric Aboveground Electrical 28 1540 28112 King Asphalt Asphalt 0 0 4189 Kone Elevators 2 100 2103 Labor Finders Labor Force 16 640 35438 Metro Power Underground Electrical 6 240 19967 Nations Roofing Roofing 7 420 3435 Old North State Masonry East - Masonry 3 165 27794 Osteen Chill Water pipe 0 0 2122 Precision Concrete 6 240 82500 Pyramid Masonry Hub Masonry 13 390 4710 R.E. Mclean Tank Tank Demo 0 0 660 November 13, 2016 Page 4
MANPOWER CONTINED TRADE CONTRACTORS ON SITE Subcontractor Trade Employees Man Hours Total Man Hrs. Reeves Young Site Grading & Utilities 12 600 55463 Rival Construction Inc. Concrete 17 850 34126 RJ Coogan Deck Installers 0 0 560 Ruppert Landscaping Landscape/ Hardscape 0 0 380 Sears Contract Drywall/Metal Trusses 96 4800 70412 Silt Fence Installation Site Erosion Control 0 0 1031 Southern Mechanical Inc. Electrical/Plumbing 25 1000 39190 Specialty Finishes Painting 7 350 600 Steel Toe Labor Force 7 280 8685 Tree South Arborist 0 0 2041 Upstate Curb Curb and Gutter 0 0 684 Valley Farm Construction Tree removal/grading 0 0 395 Waterproofing Specialties Waterproofing 4 160 2784 Total 412 19935 689727 November 13, 2016 Page 5
WEATHER CURRENT WEEK Rain Days This Week = 0 Rain Days To Date = 53 SAFETY REVIEW LOG Douthit Hills Monthly OSHA Statistics Man-hours worked RCR/DART 830000 730000 630000 530000 430000 330000 230000 130000 10 9 8 7 6 5 4 3 2 1 30000 Cumulative Man- Hours Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec- Jan- Feb- Mar- Apr- May- Jun- Jul- Aug- Sep- Oct- Nov- 15 16 16 16 16 16 16 16 16 16 16 16 93142 111684 135019 166748 201384 268272 307534 395795 475812 563897 627462 689727 RCR 0 0 0 0 0 0 0 0 0 0 0 0 DART R 0 0 0 0 0 0 0 0 0 0 0 0 0 November 13, 2016 Page 6
MANPOWER CHART Douthit Hills Workforce 120 100 80 60 40 20 0 1 4 7 10 13 16 19 22 25 28 31 34 37 40 43 46 49 52 55 58 61 64 67 70 73 76 79 82 85 88 91 94 Reeves Grading Metro Power American Deep Foundations Davis Crane Erectors Old North State Masonry Pyramid Masonry Sears Contract Gainesville Mechanical 1st Choice Glass Precision Concrete Southern Mechanical Rival Construction Feltman Brothers JME Graham Hodge Elite Flooring Speacialty Finishes Baker Roofing Holder November 13, 2016 Page 7