Lessons Learned Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International

Similar documents
Lessons Learned Schedule Updating and Maintenance using Primavera P6

How to Develop, Manage and Communicate Effective Schedules Using Primavera P6 Professional

P6 Instructors Sample Presentation

3-Day Oracle Primavera P6 Professional Fundamentals - Training Outline -

P6 Instructors Sample Presentation

(Really) Understanding Microsoft Project

PROMASTAR Instructor led Professional Training Services Primavera Accredited/Certified Class Courses

2-Day Oracle Primavera P6 Professional Advanced Scheduling - Training Outline -

Primavera P6 R8.3 Professional Fundamentals Training Course Outline

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 7 and Earlier Versions 3 day training course

Project Planning and Control Using Oracle Primavera P6 : P8.3, 8.4, 15.2

User Guidance Manual. Last updated in December 2011 for use with ADePT Design Manager version Adept Management Ltd. All rights reserved

Schedule Management User Guide

P6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show

IPECC C ONSULTANTS Course Title: Primavera Enterprise 6.0. Primavera Enterprise. Project Management, Training & Contract Workforce

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.1 & 8.2 Professional and Optional Client 3 day training course SAMPLE SLIDE SHOW

P6 Instructors Sample Presentation

Administration. Welcome to the Eastwood Harris Pty Ltd MICROSOFT PROJECT AND PMBOK GUIDE FOURTH EDITION training course presented by.

Project Forecast Survey Results Good Scheduling Practices June 2016

by Ron Winter Consulting LLC January 6, 2015

1Z

Contents Getting Started... 9 Sample Dashboards... 17

Welcome to the Eastwood Harris Pty Ltd Primavera P6 Versions 8.2 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management

EXHIBIT 2-2-C SCHEDULES

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

Welcome to the Eastwood Harris Pty Ltd PRINCE2 TM Revised 2009 and Microsoft Project 2010 training course

Massport Capital Programs Enterprise Schedule Management. Document 11 A. Primavera Schedule Toolkit Vertical Projects. July 2017 Version 1.

2017 Construction CPM Conference Ron Winter, PSP, FAACE Schedule Analyzer Software CPM ACTIVITY STATUS

P3 to P6 Professional Migration Guide

LONG INTERNATIONAL. Andrew Avalon, P.E., PSP and Curtis W. Foster

Primavera Training - P6 Basic Course (102)

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Project Management Courses

RiskyProject Lite 7. Getting Started Guide. Intaver Institute Inc. Project Risk Management Software.

Borderlink Resources Limited.

6 PROJECT TIME MANAGEMENT

A Xymphonic Systems White Paper Anyplan Product Overview

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

Design & Development of a Schedule Management Plan. Session #PRJ10

Primavera P6 Exercise Worksheet

Mastering Microsoft Project 2010

1Z Oracle 1Z0-567 Primavera P6 Enterprise Project Portfolio Management 8 Essentials Version: 4.9

Analytics Cloud Service Administration Guide

Sample Slide Show THIS SLIDE REQUIRES NEW PICTURE. Administration. Course Objectives. Course Agenda. Course Agenda

Team Member Application

RiskyProject Professional 7

What s new in PrimaveraReader

2-Day Oracle Primavera P6 Professional Advanced Resource & Cost Management - Training Outline -

Exposition Metro Line Construction Authority CRITICAL PATH METHOD SCHEDULE AND COST/SCHEDULE INTEGRATION SYSTEM

Microsoft Office Project 2007, Managing Projects

Microsoft Project 2013 Core Essentials

Contents Getting Started... 7 Sample Dashboards... 12

Project Time Management

RiskyProject Lite 7. User s Guide. Intaver Institute Inc. Project Risk Management Software.

Andrew Avalon, P.E., PSP

P6 Analytics Reference Manual

Planning and Scheduling Training Program Course Brochure and Competency Matrix

Software Application Lab 2018 PROJECT PLANNING & SCHEDULING USING PRIMAVERA. CIT, Gubbi, Dept. Of Civil Engg. Page 1

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

The Survey Says! Source: The Project Manager, Pinnell-Bush, Inc. Owner s say 31% of contractors do not submit monthly updates. 41% don t submit recove

Useful P6 EPPM Terms Security Configuration Process in P6 EPPM Defining Global Security Profiles in P6 EPPM... 19

Scheduling Challenges in the Industrial Construction Sector

1 - Introduction to Microsoft Project Describe how Project relates to the discipline of Project management.

Project Management User Guide. Release

Strategic Management Guide

Exam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.

Microsoft Project Tips & Tricks. Project Solutions Group, Inc.

Your easy, colorful, SEE-HOW guide! Plain&Simple. Microsoft Project Ben Howard

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) UNIT PRICE CONTRACTS

SCH202: Manage Schedules

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

Understanding Import & Export with NetPoint 4.2

KeyedIn Projects Project Manager User Guide

Payroll Process Guide

SECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10

Sample book with two chapters

SAMPLE. SCHEDULE LOGS TCM Framework: 10.1 Project Performance Assessment. AACE International Recommended Practice No. 93R-17

Risk Management User Guide

Q&As. Managing Projects with Microsoft Project Pass Microsoft Exam with 100% Guarantee

MSP How to guide session 3 (Updating)

P6 Team Member Implementation Stories

Week 5 Project Work Plan

Ultimate Study Guide: Foundations Microsoft Project Dale A. Howard Gary L. Chefetz

Workshop: Advanced Cost Management Techniques Using Cobra

Sample book with one chapter

PREVIEWING NETPOINT 5 AND USER-REQUESTED FEATURES SERGIO PONCE DE LEON SEVE PONCE DE LEON

PROJECT TITLE PROJECT NO: CONTRACT TITLE UNIVERSITY OF CALIFORNIA, DAVIS CITY, CALIFORNIA

The Force is Strong With This One Darth Vader, Star Wars Episode IV, Quick Start Page 1 of 14 Workamajig

Managing Projects with MS Project 2010

Views and Layouts for Program Management

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

Information Technology Project Management, Seventh Edition

SECTION CONSTRUCTION SCHEDULES (COMPUTERIZED CPM FORMAT) [LUMP SUM CONTRACTS]

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

IBM TRIRIGA Application Platform Version Introduction to the Gantt Scheduler

PrimaveraReader. Product Overview

What's New New Features in Primavera P6 EPPM 18

MnDOT Project Management Office Presents: Impact Schedules. Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc.

Planer ET 2011 professional. Programming time-location Economic planning

Transcription:

Schedule Updating and Maintenance using Primavera P6 Hannah Schumacher, PSP, PMI-SP, LEED AP Hill International Charlie Jackson, PSP, Primavera Certified Trainer Hill International Construction CPM Conference - 2015

Charlie Jackson, PSP Degree: BA Journalism University: Baylor University, Waco, TX Years of Experience: 17 Professional Field: Construction, primary focus on scheduling and project controls, implementation of scheduling systems and document control systems Something you do not know about me: 2 Started my construction career working as a scheduling assistant during college using Primavera DOS version Currently Vice President of Primavera Services for Hill International

Hannah Schumacher, PSP, PMI-SP, LEED AP Degree: BS Construction Management BS Building Construction Technology University: Wentworth Institute of Technology, Boston, MA Years of Experience: 20+ Professional Field: Construction, primary focus on scheduling and project controls Something you do not know about me: Started my construction career working as a General Laborer during college Worked as an Estimator, Planner / Scheduler, Project Controls Engineer, Project Engineer, Scheduling Engineer, Scheduling Director Currently Managing Consultant for Hill International 3

Many specifications are requiring the use of the latest Primavera software (P6). Our presentation focuses on the use of Primavera P6 to update and maintain schedules. The Schedule Update Process consists of 4 main steps: 1. PLAN 2. UPDATE 3. REVIEW / ANALYZE 4. COMMUNICATE 4

PLAN Understand Contract and Specification Requirements Determine Update Frequency Establish Baseline / Contract Schedule Assign Responsibility to each activity Provide Training Gather Data Visit Job site, hold update meeting, and validate data Understand P6 settings that affect updates 5

Understand Contract and Specification Requirements Frequency of updates Procedures for updates versus revisions Earned Value requirements Cost and/or resource status requirements Change management procedures Software requirements 6

Determine Update Frequency Factors to consider: Contract Requirements Internal company policy Project budgeting Considerations Benefits to frequent updates: Greater accuracy of as-built documentation Promotes early identification of issues Promotes timely issue resolution / mitigation Enhances user s skill in application & management of schedule Provides starting point to which user can return if errors are made in updating process 7

Establish Baseline / Contract Schedule Baseline is the accepted as-planned schedule (Contract Schedule) In Primavera Baseline is a snapshot of project plan (similar to Target in P3) Number of baselines (maximum number is set by Administrator) User can assign up to 3 baselines to current schedule for data comparisons Can copy baselines when copying project 8

Assign Responsibility to each activity Use Activity Code Global vs. Project Specific Group and Sort by Activity Code 9

Assign Responsibility to each activity Assign Resource / Role CAUTION: Resources and Roles are Global (use unique identifier) Group by resources in Assignments window 10

Provide training How to update the schedule How to review the schedule How to add fragnets for change management Content of update reports What information is needed from each individual 11

Gather Data Use Update Layout or Report Visit the jobsite, hold an update meeting, and validate data 12

Understand P6 settings that affect updates Security access settings Based on Organizational Breakdown Structure (OBS) Read / Write access can be defined down to the Work Breakdown Structure (WBS). Set by the Administrator (Admin, Security Profiles) 13

Understand P6 settings that affect updates Percent Complete Types Duration Percent Complete (default) Physical Percent Complete Units Percent Complete 14 Default type defined at the Project Level (Projects Details, Defaults tab) and can be changed at the Activity Level (Activity Details, General Tab) Project Level defaults only apply to new activities.

Understand P6 settings that affect updates Duration Types Fixed Duration and Units (default) Fixed Duration and Units/Time Fixed Units Fixed Units/Time 15

Understand P6 settings that affect updates Activity types Milestones Task Dependent and Resource Dependent Level of Effort and WBS Summary Default Activity type is set at Project Level (Project Details, Defaults tab) Change type at Activity Level (Activity Details, General tab) 16

Understand P6 settings that affect updates Calculation settings (General) Relationships to and from other Projects Open ends Schedule Calculation options Retained Logic Progress Override Actual Dates Critical activity definition Calculate SS lag Float definition Calendar for scheduling relationship lag 17

Understand P6 settings that affect updates Resource settings Resource Details for Labor, Nonlabor, Material Auto Compute Actuals Calculate costs from units Activity Details Override Resource Details settings 18

Understand P6 settings that affect updates Resource settings at Project Level (Project Details, Calculations tab) Link Actual and Actual This Period Units and Costs (when using Financial Periods) Resources Drive activity dates by default (Project Details, Resources tab) 19

Understand P6 settings that affect updates Financial Periods Defined at Admin Level (Admin menu, Financial Periods) CAUTION: Financial Periods are GLOBAL 20

UPDATE Opening the file (Exclusive / Shared / Read Only) Importing and Configuring Outside Information Maintain Baseline Rename File Assign and Compare Baselines Enter Status (dates, percent complete, resources, costs) Enter Revisions / Forecast (activities, durations, logic) 21

Opening the file 22 Exclusive only one user can change / modify the schedule Recommended to use when updating / statusing Shared multiple users can change / modify the schedule AT THE SAME TIME CAUTION: this is the default when selecting project from Project Window, right-click, select Open Read Only view only mode can not change / modify the schedule

Importing and Configuring Outside Information Import Configuration utility how to handle duplicate data. Do Not Import Insert New Keep Existing Update Existing Delete 23

Maintain Baseline (Activity window, Project, Maintain Baseline) Rename File to new version (i.e. EX00 EX01) (Project Window) P6 allows user to copy current schedule as a Reflection, make changes and merge back into current schedule CAUTION: The following data items when deleted in a Reflection copy WILL NOT be deleted in current schedule during the merge: Activities, Relationships, Resource Assignments, WBS elements, Work Products and Documents, Project Expenses, Project Issues and Project Risks. These would need to be manually deleted. (Oracle 24 Knowledgebase ID 908732.1)

Assign and Compare Baselines Project: Standard baseline for comparison for all users (typically the Contract Baseline Schedule) User Baseline (Primary, Secondary, Tertiary) Primary Baseline allows for dates, resource, etc. comparisons Secondary and Tertiary compare date information only Check earned value settings (Admin, Earned Value, Earned Value Calculation) 25 These settings determine which baseline dates will be used for comparison.

Prior to statusing, make sure time is shown to alleviate nonstandard start/finish times (Edit, User Preferences) 26

Enter Status Actual Start dates Actual Finish dates Percent complete Remaining duration Resources and/or Costs Enter Manually Apply Actuals (Tools menu, Apply Actuals) Update Progress (Tools menu, Update Progress) CAUTION: Apply Actuals and Update Progress use PLANNED Dates versus Scheduled Dates or Early Dates which may be different Calculate the schedule (Tools, Schedule) with new Data Date Recommendation: To improve speed and efficiency of the program, turn off option to Schedule automatically when a change affects dates Review data entered Maintain Baseline (with Status only in title) 27

Enter Revisions / Forecast New Activities Delete Activities (Do not reuse Activity IDs) Revise Logic Revise Durations Calculate the schedule (Tools, Schedule) with new Data Date CAUTION To improve speed and efficiency of the program, turn off option to Schedule automatically when a change affects dates Review data entered Maintain Baseline (with Revision added to title) Review compared to status only update as well as previous update and Baseline schedule 28

REVIEW & ANALYZE Review and Verify data input (Scheduler self-check) Compare to previous update and Contract schedule Review Logic reports / Layouts and Changes made Finalize and Maintain Baseline (of this finalized update) 29

Review and Verify data input (Scheduler self-check) Open Ends (activities with no Predecessors and / or Successors) Dangling Relationship ties (Start to Start and/or Finish to Finish ties without a Predecessor and/or Successor) Incorrect and non-overlapping lag ties that result in gaps in sequencing Start to Start lag that exceeds the activity duration Finish to Finish lag that exceeds the successor duration Finish to Start lag Out of Sequence progress Actual dates in the future Incorrect times Calendars Activities on the data date (verify predecessor logic) Excessive float values Negative float New activities, durations, logic and impact to plan Critical Path and Near Critical Path Constructability issues Stacking of trades 31

Compare to previous update and Contract schedule Create comparison layouts Assign appropriate baseline (Project menu, Assign Baseline) Select baseline bars (View, Bars) and baseline data columns Note: varying baseline types (Project vs. User Baselines Primary, Secondary, Tertiary) allow for different levels of data for comparison. Check earned value settings (Admin Preferences, Earned Value) Determines what dates will be used for comparison Planned or Start/Finish Recommendation: use Budgeted values with current dates CAUTION: Setting is global, not project specific, affects all projects in the database 32

Lessons Learned Comparison layout: 33

Review Logic reports / Layouts and Changes made Schedule Log Claim Digger Tabular Reports Schedule Analyzer for the Enterprise (SAe) 34

Once the entire team has reviewed and approved the draft update, finalize and Maintain Baseline Maintain Baseline (Project, Maintain Baseline, Save Copy) Export Backup to safe location(s) 35

COMMUNICATE Layouts Reports 36

Layouts Global (available to all projects in the database) User (available to only the user) Project (specific only to the project) Bar charts Look ahead schedules Critical Path Near Critical Path Responsibility sorts 37

Time Scale Logic (available in P6 v7 Service Pack 3) (Tools, Time Scale Logic Diagram) 38

Standard Reports Schedule Resource Cost Customized Reports using Report Editor or Report Wizard 39

CONCLUSION Understand contract and specification requirements Understand the P6 settings that affect updates Provide training to those responsible for providing and reviewing the update data Visit the jobsite and walk the job Hold an update meeting and verify data Update Frequently Review and Analyze the schedule Maintain Baselines for comparison Compare to previous updates and Baseline Schedule Communicate the schedule using Reports and Layouts 40

We hope that you can use schedule updating and maintenance lessons learned outlined in this presentation to update your schedules quickly and efficiently using Primavera P6 Questions? Hannah Schumacher Managing Consultant Hill International HannahSchumacher@hillintl.com Charlie Jackson Vice President of Primavera Services Hill International charliejackson@hillintl.com (602) 390-1048 (702) 540-9767 41