CONSTRUCTION LOGISTICS OF BELGRADE WATERFRONT

Similar documents
Click on the following link for more information and to review the complete WSIB OPM.

CREFORM AGV OVERVIEW AGV AUTOMATED GUIDED VEHICLE. For KAIZEN. a continuous improvement process. Table of contents

Contents. Chapter 1 Introduction to Logistics and Supply Chain. 1. Introduction. Learning Objectives. Dr. Vin Pheakdey

INFRASTRUCTURE SOLUTIONS FOR INCREASED EFFICIENCY AND PRODUCTIVITY OF CONSTRUCTION MATERIAL TRANSPORTS IN CITIES

CROSS-DOCKING: SCHEDULING OF INCOMING AND OUTGOING SEMI TRAILERS

STATE OF INTERMODAL TRANSPORT IN CROATIA AND SERBIA

CONSTRUCTION TRAFFIC MANAGEMENT PLAN for LEICHHARDT PARK CHILDCARE CENTRE

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE

Geo24h. Buiding Service

Environmental Hot Spot Remediation

E3072 v2. GEF Large City Congestion and Carbon Reduction Project. Environment Management Plan. Public Disclosure Authorized

Construction Waste Minimization and Reuse Management

Contractor Experience with Precast Bridge Elements in Utah. Eric Wells. Granite Construction

ctbuh.org/papers Reform Measures of Korea s High-rise Buildings Construction Period Title: Ki-In Kim, Senior Manager, HanmiParsons Co., Ltd.

Trans Mountain Expansion Project Overview

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction

Assessing the costs and benefits of reducing waste in construction

SUGAR. Joint Planning Exercise SWOT Analysis Municipality of Palma

Review of Plans and Specs from a Constructability Perspective

Why Choose DIG IT Excavator Hire?

A study on construction and demolition wastes from buildings in Seberang Perai

INCOMAS JOINT-STOCK COMPANY STEEL PROCESSING

Part III MATERIAL HANDLING AND IDENTIFICATION TECHNOLOGIES

Vertical Transportation Planning Retail/Mixed-Use

The superior self-compacting concrete

Waste Management Solutions. Canberra

New Models Of Collective Housing Through The Application Of Steel And Steel Products

25.August Guideline for planning floor coverings in open spaces

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER

Construction of Transfer Plate - from various case studies. Presentation prepared by Raymond Wong

Drawings shown within this brochure is the Preston CarPark Innovation Concept and patents filed in August 2018.

Low Carbon Construction Implementation in a Public Housing Development and the Implication to the Life Cycle Decision Making Tool

Building Knowledge: Research Highlights

Automated Store Management For Drum Storage Facility

The construction technology of Chongqing Chaotianmen Bridge

Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay

Premier Matting Services

Progress in Concrete Technology

Exhibition sectors at BAU

inter.noise 2000 The 29th International Congress and Exhibition on Noise Control Engineering August 2000, Nice, FRANCE

The use restrictions in this Article provide primarily for heavy commercial and industrial development. Residential uses are not permitted by right.

Total fatal injuries (number) Total. Total Private industry Goods producing

AUTOCLAVED AERATED CONCRETE (AAC) BLOCKS PLANT

EUROMECC is situated in Catania - Italy - and the production unit extends on a m 2 area.

Lessons Learned Report D 4.4

The construction and demolition waste consist of inert material, most of which are recyclable. These constituents can be classified as:

6 Preliminary Assessment of Construction Method and Constructability Issues

Sana a Secretariat Yemen

MACHAVA INDUSTRIAL PROJECT

No. 1 SPINNINGFIELDS MANCHESTER

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok

Legal Summary SHE-037 Handbook of Business Operation in Thailand s Industrial Estate Version 2

FASTPATH. The ultimate one pass footpath surfacing solution AGGREGATES AND ASPHALT

The Role of Urban Goods in Sustainable Transportation Systems

New pallet circuit and modernization of the existing production plant at Skanska in Stängnäs, Sweden

Cambridgeshire County Council County Planning, Minerals and Waste

Crowlands Wind Farm. Project construction information and update

Types of Structures and Loads

Contents. Introduction 5. CantiDeck System 6. Fixed Flush CantiDeck 8. Super Roller CantiDeck 10. Specifications 12.

Assessing the costs and benefits of reducing waste in construction

In Service Replacement of Box Girder Bottom Slab

Moveco Systems Rollerkit system has the possibility of using several Moveco Systems

Success Story ENGINEERED TRANSFER CHUTES HELP TERMINAL MAINTAIN HIGH VOLUME COAL HANDLING

OSH5063EP(PRS3607) Workplace and Work Equipment Hazard. Session 9. Working at Height

INTERNATIONAL UNION OF OPERATING ENGINEERS. Local Union 14-14B Affiliated with the AFL-CIO WAGE SCALE

1 Transport. Introduction. 1.1 Lorries have empty or part loads

Construction Revolution. Eco Underpass Method. Solution for Traffic Congestion in Urban Area

IMPROVEMENT OF CONSTRUCTION AND DEMOLITION (C&D) WASTE MANAGEMENT ON CONSTRUCTION SITES

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

5. Event Resource Person Details :- Mr. Ravindra Mohane (Project Incharge)

Submission Cover Sheet Fishermans Bend Planning Review Panel

Introduction to Structural Analysis TYPES OF STRUCTURES LOADS AND

Discrete Event simulation

IN THE KYRGYZ REPUBLIC

DEVELOPMENT OF AUTOMATIC CONVEYOR SYSTEM AT CONSTRUCTION SITES

Construction Method Statement

Table of Contents. LASAN CLARTS OPF Abbreviated Feasibility Report November 17, Page 1 of 10

Optimizing the use of space occupied by urban goods transport

JOY AND SORROW OF POLISH OVERSIZE CARRIERS

SFLWS25 - SQA Code HD4K 04 SfL25 Receive goods

Container Terminal Modelling in Simul8 Environment

HOW DESIGN INFLUENCES COST

AGILE LOGISTICS IT FOR LARGE CONSTRUCTION SITES. Transparent and efficient delivery processes

Specification for Removal of Redundant Assets

Chapter 10. Transfer and Transport. Transfer & Transport

Enhanced Resource Planning

Challenges for Special Application cranes in constructing the next generation of infrastructure

Why Choose DIG IT Skid Steer Hire?

OPBW S.r.l. - Via Dell'Industria, Osimo (AN) - ITALY. Tel: (+39) Fax: (+39)

Ever wondered how bricks are made?

In Parallel and Integration with. AmmaN - Jordan 30 JULY 2 AUGUST 2018

Tilikum Crossing Transit Bridge. Portland, OR

SPOT THE SKILLS JOB DESCRIPTION CARDS

PRESS RELEASE. MATERIAL COSTS INDEX IN THE CONSTRUCTION OF NEW RESIDENTIAL BUILDINGS: September 2018, y-o-y increase 0.6%

EFFECTIVE DESIGN OF P&R SYSTEM IN METROPLOLITAN AREA

FOR EFFICIENT AND SAFE FLOW OF PEOPLE DURING CONSTRUCTION. Courtesy of the Gold Coast Bulletin. KONE JumpLift

Traffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

WAREHOUSING:- CONCEPT OF WAREHOUSING:-

About Viadukt. Our vision. Our mission

Transcription:

CONSTRUCTION LOGISTICS OF BELGRADE WATERFRONT Marko Stokić a*, Boško Radovanović a a University of Belgrade, Faculty of Transport and Traffic Engineering, Serbia Abstract: Belgrade Waterfront is the one of the most important projects of the city of Belgrade and currently the largest investment project in this part of Europe. The undisturbed project realization requires serious planning and management of the complex and intensive flows of goods, freight, material, people and information, as well as the flows of vehicles and mechanization, so it is the major challenge for the city logistics and construction logistics. This paper describes the construction logistics problems of Belgrade Waterfront and possible solutions. The location of temporary logistics centres, the problems of supplying the construction sites with materials, the supply chain management and the role of the reverse logistic during the project realization are considered. Keywords: construction logistics, delivery flows, reverse logistics, logistics consolidation centre 1. INTRODUCTION The construction logistics involves all technologies, rules, methods, knowledge and solutions related to the movement of material and other types of resources in construction flows (Duiyong et al., 2014). From the aspect of the project realization scheduling, it could be divided into three segments (Duiyong et al., 2014). The first segment is related to the logistics before starting the construction and involves supplying a construction site with necessary goods, labour force and mechanization to start the work. This construction logistics segment is very important and allows undisturbed construction starting. The basic project is following by the logistics during the construction, where the good communication among all construction site sectors is of particular importance for efficient logistics flows realization and undisturbed construction. The third construction logistics segment is related to the period after the completion of construction works and involves the activities related to the removal of various types of waste for their proper disposal at landfills, recycling and other renewal options. This paper presents the general project overview, construction logistics problems, possible solutions and the logistics concept of Belgrade Waterfront project. 2. BELGRADE WATERFRONT PROJECT According to the project, Belgrade Waterfront covers an area of 1.85 millions of squared meters and envisages the construction of about 200 facilities for various purposes and functions on the right riverside of Sava, between Railroad Bridge and Branko s Bridge, up to Karadjordjeva and Savska Street. The project implementation was conceived to be realized in four phases * markostokic12@yahoo.com 303

(Figure 1). The biggest part of the area, about 60%, is planned for the construction of residential units, 17% for commercial properties, 8% for hotels and a shopping mall, separately, 5% for shops and about 1% of planned areas for cultural and leisure activities. The buildings standing out are Belgrade Tower, 170 m tall, and the shopping centre which will cover more than 148,000 of square meters. When it comes to the street network, it was planned to keep the existing street matrix which will be linked by newly constructed boulevards. The project appreciates the cultural and historic heritage of the city of Belgrade, thus some buildings will not be razed during the works (http://www.rapp.gov.rs). Figure 2. Phases of Belgrade Waterfront project realization 3. CONSTRUCTION LOGISTICS The construction logistics involves planning, organization, coordination and costs of flows and logistics activities that are related to the construction project realization (Duiyong et al., 2014). The large construction project realization requires precise and clear organization of all operations at the construction site, implying developed supply chain. The supply chain includes all logistics activities, production operations and process coordination management and activities related to marketing, sale, product development, finance and information technologies, but their relationships too, as well as the coordination and collaboration among partners being in the same chain (Miljuš M., 2015). The supply chain may have a different impact on the construction site depending on the point of view (Vrijhoef R. & Koskela L., 2000). It is possible to consider the inherent relationship between the supply chain and construction site, the supply chain as an independent unit, activity shifting from the construction site to the supply chain and the construction sites (Vrijhoef R. & Koskela L., 2000). The experts in this field have attempted to define the main problems with construction work realization (Rogers P., 2005.): underused loading space of vehicles, waiting at the transshipment front, qualified staff engaged for unqualified tasks such as unloading, material are often transferred from one to another place within the construction site, poorly planned work time schedule for professional tasks, the large amount of material and waste and very poor training of logisticians for the work in the construction industry. Figure 2 shows the problems in the construction process. Poor logistics implementation may cause a series of consequences such as: unnecessary costs, poor image of the construction industry, poor construction quality, prolonged designing time, additional health and security risks etc. (Rogers P., 2005). On the other hand, by implementation of good logistics the many positive effects could be achieved, such as: reduction in movement volume, reduction in credit-linked capital, reduction in waste amount, rapid construction time, improved quality, lower health and security risk of the workers, more efficient use of labour force results in construction cost decreasing and, generally, in the improvement of industry s image (Rogers P., 2005). The good logistics can reduce the unnecessary material movements, shorten the production process and increase the productivity up to. It is possible to monitor system performances (both quantitative and qualitative) in two ways: 1) observation and monitoring of systems and its functioning; (2) comparison of implemented solutions, i.e. 304

monitoring how much the applied solutions are appropriate and to what degree they improve the system (Wegelius-Lehtonen T., 2001). Figure 3. Problems in the construction process (Vrijhoef R. & Koskela L., 2000) When designing, it is possible to use Last Planner method. The reasoning is to meet all prerequisites that are necessary for performing various construction tasks before these tasks are assigned to a working group. By this method, all the tasks related to the project could be classified into four categories (Ala-Risku T. & Karkkainen M., 2006): SHOULD tasks that need to be performed in the near future according to the overall project plan. CAN tasks that have all their prerequisites ready: e.g. previous project steps are completed, necessary materials are at hand, and work force is available. WILL the tasks that are commenced before the next planning round. DID the tasks that are completed. 4. CONSTRUCTION LOGISTICS OF BELGRADE WATERFRONT The construction of Belgrade Waterfront involves the processes of transport, storage, loading, unloading, packaging and stock management related to numerous of various types of materials and equipment. It is necessary to provide that all activities are taking place in a simple, quick, continual and controlled manner. In order to provide material availability in the moment of the request occurrence at the construction site, it is necessary to develop both long- and short-term plans for the material delivery which could be adjusted and upgraded during the project realization. During this period, each construction sector is obliged to submit a list of required materials for the next period (day, week and month) to the logistic centre. In order to make this system function, it is necessary to have a well-developed supply chain. 4.1 Supply chain The implementation of the supply chain into the project has many advantages: shorter time of the request realization, precise amount of material for the production, decreasing in stock and trapped capital level, quick realization of the logistics processes, electronic data processing and exchange, quality of service improvement, reduction in total costs etc. Considering that this is a 305

long-term project, it is necessary to make contracts among all participants in Belgrade Waterfront construction process and define their rights and obligations in order to secure the undisturbed supply chain functioning. To make supply chain function, it is primarily necessary to make a special IT platform in order to provide a high-level communication and data exchange and processing. The material and information flows have different movement directions within a system. To consolidate smaller deliveries and provide the timely material delivery to different locations within a construction site, it is proposed to implement the construction material consolidation centre. Its implementation is temporary and it is determined by project duration. 4.2 The location of temporary logistics centre After detailed analysis of the project and schedule of Belgrade Waterfront realization, the authors identified some possible location of the logistics consolidation centre. Based on the estimation by several criteria (the available surface area, time distance from all construction phases, transport infrastructure development, connection to main roads etc.), the location of future Belgrade Park is proposed. However, the location of the centre may vary in different phases of the project construction if it is economically justified. The chosen location covers 40,000 m 2 of space, occupies the central position on the project map, being situated near the riverside and connected to other construction phases by main roads. Within the centre, there will be the entry/exit check point, administration building and warehouse for construction material, parking facility for freight and construction vehicles, fuel tanks, maintenance system, the space for waste and unused material disposal. The planned area for the logistics centre installation is also convenient from the aspect of the arrangement after the completion of work. Nevertheless, the choice of a logistics centre location requires quantitative and qualitative analysis of potential locations from the aspect of a larger number of criteria and the application of operational research methods. 4.3 Types and amounts of material With the aim of flow volume estimation and for the purpose of this paper, only basic material categories are considered in the facility construction process. Besides the steel poles, which presents the frame and gives shape to the facility, this paper involves steel floor coverings, through which the concrete is poured for the purpose of the fire protection, armature, bricks for room separation, sheet material (marble, ceramic tiles, parquet) and windows that provide a futuristic look to the buildings. The material amounts are estimated by phases (Table 1), based on the scope of work, i.e. the planned area in m 2. Table 1. Estimated material amounts for Belgrade Waterfront construction Type of material Phase 1 555.000 m 2 Estimated scope Phase 2 Phase 3 Phase 4 Total 832.000 m 2 278.000 m 2 185.000 m 2 1.85 mil.m 2 With 5% of reserve Steel poles (t) 120.000 39.000 14.500 21.000 194.500 204.225 Floor coverings (t) 30.000 3.500 1.300 2.300 37.100 38.955 Concrete (m 3 ) 2.175.000 330.000 66.000 135.000 2.706.000 2.841.300 Armature (t) 110.000 16.500 3.500 6.700 136.700 143.535 Brick (t) 640.000 80.000 30.000 53.000 803.000 843.150 Sheet material (m 2 ) 2.100.000 245.000 91.000 164.000 2.600.000 2.730.000 Windows (m 2 ) 95.000 24.000 8.900 16.000 143.900 151.095 306

Among estimated amounts, the dominant material is the concrete, which will be used for the purpose of building stability, paneling of steel poles, forming of floor concrete slabs and public roads too. The large amounts of concrete and armature will be used in the construction of central support pillar of Belgrade Tower, on which the steel frame will be relied. Besides timely material delivery, the successful project realization requires the delivery of the construction mechanization such as: earthmoving machines (bulldozers, excavators, loaders, levelers, vibratory rammers, rollers and pavers), lifting (cranes and elevators) and transport machines (trucks, tippers, dumpers) and mixers (towing mixer and truck mixer). 4.4 Problems, possible solutions, directions and methods of material delivery It is well-known that the city of Belgrade has difficulties with traffic jams on the bridges and the street matrices in the old part of the city are mainly narrow and unidirectional, with the prohibition of large transport means movements. Night delivery is not feasible for all flows, so the construction site supply will be a large traffic problem. Since Belgrade Waterfront is spatially relied on right riverside of Sava, one of the possible solutions to the problem is the use of the river transport. By choosing this delivery method, it is possible to enable the unloading of street networks, without vehicle accumulation and congestion occurrence, as well as the timely delivery of large amounts of the material by reduced number of transport means (one push barge-barge system replaces dozens of road vehicles). In addition, the transport cost will decrease and the environmental pollution will be significantly reduced. The use of river transport was also justified by analysing the potential directions of material delivery: Smederevo Ironworks (steel materials), factories from Pančevo producing concrete and glass, brick production plant from Novi Sad and sheet material manufacturer from Šabac. For the delivery of the concrete, it is also possible to use river transport by choosing the vessels for transport of the whole road vehicles (mixers and truck mixers). It is possible to establish the connection between the riverside and consolidation centre by installation of an adequate type of belt conveyor. For the heavy-weight and irregular-shape materials, it is possible to use cranes for reloading into road transport means for bulky loads. Nevertheless, the choice and use of transport and transshipment systems, as well as the opportunities for vessel docking, require a detail analysis. 4.5 Reverse logistics The reverse logistics has a very important role in the construction project realization. Large construction sites generate a large amount of waste which could cause many problems (Nunes et al., 2009). The waste material could be classified into three main groups: the inert construction waste, which is disposed at landfills, the recycling waste (glass, steel, iron etc.) and the waste which is the overage in some facility construction, but it could be temporary reused in some other facility construction (marble slabs, windows, parquet, rod materials etc.). Waste collection from the active construction sites could be realized periodically, by special vehicles. The waste would be disposed at temporary landfill near the consolidation centre. With the aim of the vehicle movement optimization when delivering material from the consolidation centre and collecting the waste, it is possible to apply the travelling salesman method in order to minimize the distance and, consequently, the collection time and transport costs, and to maximize the capacity utilization of vehicles. After collecting a priori determined amount of waste, it is performed its ad-hoc removal, i.e. dial a removal. This method of waste removal from the logistics centre is good because the transport capacity of vehicles used for delivery is maximally exploited. Since there are various groups of material at the construction site, it is necessary to sort them, in terms of separating inert and recycling materials. It is probably better to sort materials at the construction site by placing containers for different types of waste, in order to reduce time interval until the later further sorting. The material which could be used for the 307

construction of other facility is stored in the consolidation centre until the moment of requesting its re-delivery to the embedding site. Besides the reverse logistics of the materials, the return logistics of the construction mechanization must not be forgotten after the completion of work. 5. CONCLUSIONS The construction logistics faces numerous technical and organizational problems, as well as environmental problems, which influence the costs and construction time and quality. In larger construction projects, such as Belgrade Waterfront, which includes a broad scope of work, numerous contractors and extensive and complex material flows, an inadequate logistics concept and a lack of coordination result in serious disturbances. The logistics centralization and supply chain introduction implies the reduction in total costs of project, quality improvement and shorter time for completion of the construction. Numerous studies have showed that the most of the problems in the supply chain occur in the previous phases of the chain. The information exchange among the participants is often very poor, resulting in poor synchronization of construction project s processes and activities. The solution to these problems lies in cooperation among all participants in the construction project and in coordination of all activities and processes in its realization. One of the main strategies would be the integration of basic logistics function in the supply chain with marketing, production and finance. ACKNOWLEDGMENT This paper was written on the basis of the seminar work for the subject City logistics. We would like to thank Prof. Slobodan Zečević and Asst. Prof. Snežana Tadić, lecturers, for their support during the entire paper development, for sharing their professional experiences and for assistance in solving problems that have arisen during the paper development, thus enabling the realization of the project. REFERENCES [1] Ala-Risku, T., Karkkainen, M. (2006). Material delivery problems in construction projects: A possible solution. Int. J. Production Economics, 104, 19-29 [2] Duiyong, C., Shidong, J., Mingshan, S. (2014). Engineering construction project site logistics management. Journal of Chemical and Pharmaceutical Research, 6(7), 353-360 [3] Miljuš, M. (2015). Lanci snabdevanja, Faculty of Transport and Traffic Engineering, University of Belgrade, Belgrade. [4] Nunes, K.R.A., Mahler, C.F., Valle, R.A. (2009). Reverse logistics in the Brazilian construction industry. Journal of Environmental Management 90, 3717-3720 [5] Republic Agency for Spatial Planning. http://www.rapp.gov.rs/ (Accessed: 20.02.2015.). [6] Rogers, P. (2005). Improving Construction Logistics. Report of the Strategic Forum for Construction Logistics Group. Great Britain. [7] Vrijhoef, R., Koskela, L. (2000). The four roles of supply chain management in construction. European Journal of Purchasing & Supply Management, 6, 169-178 [8] Wegelius-Lehtonen, T. (2001). Performance measurement in construction logistics. Int. J. Production Economics, 69, 107-116 308