Note: Eastern Shore Natural Gas Company is referred to as ESNG thoughout this form. PART 1: CUSTOMER PROFILE PART 2: CUSTOMERS FACILITY DESCRIPTION

Similar documents
Financial Benefits of Mobile Natural Gas

Development of HK Electric Gas Receiving Facilities at

Ivins City Standard Specifications for Design and Construction Part 2 Engineering and Design Standards

INSTRUCTIONS FOR APPLICATION FORM (PUMP STATIONS, FORCE MAINS, AND GRAVITY SEWERS)

Module 8 Its Not Just About the Meter and Regulator

SEWER SYSTEM DESIGN GUIDELINES

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

Exhibit D Measurement & Regulation Facilities Records Required for DETI Operational Responsibilities

October 25, Via efiling. Ms. Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C.

Criteria Revision Request. Revise SPP Criteria Section 12.1 for EIA_411 reporting purposes. Normal Expedited Urgent Action

Attachment NEB U Mackenzie Gas Project Community Gas Pipelines

GUIDE TO WATER SERVICE APPLICATIONS

195LiquidsCatalog.

ALASKA PIPELINE PROJECT

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

CHAPTER 8 WATER SUPPLY SYSTEM

EQT MIDSTREAM COMPANIES DESIGN, CONSTRUCTION & COMMISSIONING REQUIREMENTS FOR INTERCONNECTS APPENDIX B Total Pages: 54

WESTERN ENGINEERING CONSULTANTS, Inc LLC

7. Electrical Facility Ratings

Application for Underground Pipeline Crossing or Longitudinal of Railroad Property and or Track

Observations from Several Condition Assessments of Prestressed Concrete Cylinder Pipe used at Energy Generation Facilities

PUB NLH 600 Island Interconnected System Supply Issues and Power Outages Page 1 of 5

C. heating turbine exhaust steam above its saturation temperature. D. cooling turbine exhaust steam below its saturation temperature.

Environment & Power Systems International. VOCGEN /CHP Feasibility Screening Data Form. Level 1 Feasibility Analysis

KUM & GO 300 SUBDIVISION THORNTON, COLORADO

DESIGN AND INSTALLATION OF A COMPLETE MEASUREMENT & CONTROL FACILITY Thomas G. Quine Northstar Industries

CHARLES COUNTY GOVERNMENT ITB NO MATTAWOMAN WATER RECLAMATION FACILITY (MWRF) PRIMARY CLARIFIER NO. 1 IMPROVEMENTS

Aeration Blower Requirements. Tom Jenkins 06/15/2016

PRELIMINARY STATEMENT

TransGas Customer Connections. Presented by: Tyler Danielson Manager, Pipeline Engineering

I - 15 CORRIDOR CAMPUS MASTER PLAN DRAFT EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT. Appendices

University System of New Hampshire, Durham UNH CHP Plant Application for New Hampshire State Certification as Class I Resource

ENBRIDGE GAS DISTRIBUTION METER BOX. Builder Installation Requirements February 2018

ENGINEERING REVIEW CHECKLIST City of Mount Clemens

USING DESIGN-BUILD TO MITIGATE RISK TO A MAJOR WATER DELIVERY SYSTEM ROCKY MOUNTAIN DBIA PRESENTATION MAY 20, 2016

Before the Public Utilities Commission of the State of South Dakota. In the Matter of the Application of Black Hills Power, Inc.

New Natural Gas Service Informational Packet

IMPACT ASSESSMENT. Bartow, FL (863) FORM

State Environmental Quality Review NEGATIVE DECLARATION Notice of Determination of Non-Significance

CITY OF PANAMA CITY BEACH Utilities Administration & Engineering Offices 116 South Arnold Road Panama City Beach, FL 32413

2014 Plan of Conservation and Development. Municipal Infrastructure

CHAPTER 5 WATER SYSTEM DESIGN STANDARDS

BAYFRONT CANAL AND ATHERTON CHANNEL PROJECT DESCRIPTION

Beaumont Lot Grading Guidelines

FLORIDA DEPARTMENT OF TRANSPORTATION

Permit for Construction of an Extension to a JEA Drinking Water Distribution System and/or JEA Wastewater Collection/Transmission System

DEFINITIONS. EXHIBIT to the GAS GATHERING AGREEMENT (Note Not all definitions are used in each Agreement.)

SECTION CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION

CHARLES COUNTY GOVERNMENT ITB NO WHITE PLAINS FAILING SEPTIC SYSTEM IMPROVEMENTS

Commercial Remodel Permit

STANDARD GRADING AND SOIL EROSION & SEDIMENT CONTROL PLAN FOR SINGLE LOT SINGLE FAMILY RESIDENTIAL CONSTRUCTION AND MINOR EARTH DISTURBANCES

CITY OF MERIDIAN LAND DEVELOPMENT SERVICES SUBDIVISION PLAN REVIEW CHECK LIST

Application for Underground Pipeline Crossing or Longitudinal of Railroad Property and or Track

Liquefied Natural Gas Conversion Systems for Plant Startup and Shutdown and Natural Gas Curtailment at CT Stations

CITY OF PUNTA GORDA, FLORIDA

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

ADELPHIA GATEWAY PROJECT

For more information, visit our web site at: h2o.enr.state.nc.us/ndpu/

Western Region RFP Supplemental Information Required by Bidders in Connection with Proposal Submission Updated March 4, 2012

APPLICATION FOR PIPE OR WIRE OCCUPANCY

Proposed Boykins Substation Microwave Tower May 31, 2017

EXHIBIT B. Notice of Non-Compliance

Appendix A Technical Specifications Engineering Services for the Nocatee 230/26kV Substation

SECTION 813 SEWER FLOW CONTROL

ATTACHMENT A: FINDINGS

Propane Tests at Chesapeake Building

GAS. Gas Distribution Systems Safety and Loss Management System Guidelines. Prepared by: Brad Wyatt, Provincial Safety Manager - Gas

Operating Procedure PURPOSE... 1

Director TGP Facility Planning and Gas Control June 3, Prepared for the Harvard Electricity Policy Group

This is a digital document from the collections of the Wyoming Water Resources Data System (WRDS) Library.

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

DESIGN GRADING AND EROSION CONTROL A. Slope Criteria

APPENDIX B STANDARD CONSTRUCTION DRAWING NOTES

MONTEREY COUNTY HEALTH DEPARTMENT ENVIRONMENTAL HEALTH BUREAU DRINKING WATER PROTECTION SERVICES APPLICATION FOR A NEW OR AMENDED WATER SYSTEM PERMIT

Zoning Permit Application

STANDARD SPECIFICATIONS FOR CONSTRUCTING UTILITY FACILITIES DIVISION II - DESIGN CRITERIA

COMPARATIVE STUDY ON ORIFICE VERSUS TURBINE METERS FOR GAS FLOW MEASUREMENT

NOVA Gas Transmission Ltd. Facilities Design Methodology Document (FDMD) FDMD 5/2018

APPENDIX A 2018 INDEX TO SCHEDULES

BGE Smart Energy Savers Program Combined Heat and Power Program Manual

Turbine Meter. P e

THE SASKATCHEWAN CODES OF PRACTICE GAS INSTALLATION SUPPLEMENT CSA-B PROPANE STORAGE AND HANDLING CODE

COLLIER COUNTY Growth Management Department

Model 5100 Model 5400 Insertion Turbine Flowmeters for Liquid and Gas

Description [in natural gas volume] Emissions estimated from size of breach / pressure / duration calculation

Accessory Building/Detached Building Permit

Expanding Existing Pipeline Capacity to Meet New England s Energy Needs. Mike Dirrane Director, Marketing

Dynamic Pricing. June 2, 2016 Harvard s Electricity Policy Group

VLM10 In-line Vortex Mass Flow Meter

2004 NBIC Interpretations

Digester Gas Utilization at SWRP Where Should the Biogas Go?

CUSTOMER INSTALLATION STANDARDS FOR GAS SERVICE

Engineering Standard. Saudi Aramco DeskTop Standards

Thermal Mass Flow Meters Help Reduce Energy Costs and Enhance Emissions Monitoring Systems

Request for New Point of Receipt

ENBRIDGE GAS DISTRIBUTION METER BOX. Builders Installation Guidelines September 2011

Proposed Southampton Substation Microwave Tower May 31, 2017

FEE SCHEDULE 7 Water Development and Connection Fees Aurora Water (Platted Before January 1, 2017)

AREA STRUCTURE PLAN SW W4M CAMROSE COUNTY BYLAW ## JULY 2017(REVISED) PREPARED BY: AUSTROM CONSULTING &VICINIA PLANNING & ENGAGEMENT INC.

TGP Outages May, June and July

Transcription:

Note: Eastern Shore Natural Gas Company is referred to as thoughout this form. Return completed form by mail, fax or e-mail to: Eastern Shore Natural Gas Company 1110 Forrest Avenue Dover, DE 19904 Attn: Senior Manager, Commercial Business & Marketing E-Mail: jmayan@esng.com Fax: (302) 734-6745 PART 1: CUSTOMER PROFILE Full Name of Customer: Customer Contact Name: Address: Fax: Cell: Engineering/Technical Contact: Address: Fax: Cell: Email: Email: Phone: Phone: The deliveries will be for (check all that apply): LDC City Gate Commercial End User Industrial End User Electric Power Generation Specify whether delivery will be: Existing Firm Transportation (FT) Interruptible Transportation (IT) New Firm Transportation Released Capacity PART 2: CUSTOMERS FACILITY DESCRIPTION This request is for: (A) a new interconnect or If (B), what is the name of the ex. Interconnect? If (B), what is the max. amount of time the station can be out of service? What time period is best for the outage? Brief description of Customer s existing System, Proposed facilities and use: Yes No

Part 3: Proposed meter station location Unless otherwise agreed upon by, the meter station will be located at a site determined by. City, County & State: County road, state or US highway fronting or nearest site: Approximate dimensions of site and acreage (if known): Brief description of topography, existing condition and use: Length of access road to be constructed: Distance to Nearest Utilities: Part 4: Flow and Pressure Requirements Abbreviations and conversion factors: Mscfh = 1,000 scfh (@14.73 psia pressure base, 60 F temp. base); MMcfd = 1,000,000 scf per day 1,000 BTU/scf, i.e. 1.0 MMBTU/hr = 1.0 dt/hr = 1 Mscfh where MMBTU = 1,000,000 BTU and dt = dekatherm Specify TBD for To Be Determined, for Not Applicable, NR for Not Required To ensure that measurement facilities are appropriately designed for the full range of anticipated flow, please provide hourly flow RATES. Where minimum hourly flow rate is requested below, Minimum Flow is the lowest sustained hourly flow rate other than no flow or 0, for power generation facilities, it occurs while there is no power generation, yet minimal gas is delivered for plant utilities and for any heaters prior to operating the combustion turbines. GENERAL Deliveries will generally be: Constant year-round Summer peaking Winter peaking Standby/alternate delivery point for city gate/ldc Other (specify) Table 1 - Flow and Pressure information for commercial end users Maximum Hourly Flow (Mscfh): Average Daily Flow (Mscfd): Average Daily Winter Flow (Mscfd): TABLE 2 - FLOW RATE PROFILE FOR LDC / CITY GATE Peak Season 1. In-service Date (m/d/yy) 2. What percentage of incremental flow rates will serve power generation 4. Peak Days - No. days per year Electric: Distance from s pipeline to Customer s pipeline, plant or facility: 3. Annual Peaking occurs from (m/d - m/d) 5. No. of hours peaking during each peak day 6. Peak Hourly Flow Qpeak on Peak Day (Mscfh) 7. Convert Qpeak to Daily Rate (24 x Mscfh/1000 = MMscfd) 8. Minimum (Nighttime) Hourly flow (>0) QPeakMin on Peak Day 9. Convert QPeakMin to Daily Rate (24 x Mscfh/1000 = MMscfd) Off-Peak Season (Period other than above Peak Season) 10. Annual Off-Peak Season occurs from (m/d - m/d) 11. Maximum Hourly Flow Qmax on Non Peak Day (Mscfh) 12. Convert Qmax to Daily Rate (24 x Mscfh/1000 = MMscfd) 13. Minimum Hourly Flow (>0) Qmin on Non-Peak Day (Mscfh) 14. Convert Qmin to Daily Rate (24 x Mscfh/1000 =MMscfd) Telephone: Minimum Hourly Flow (>0) (Mscfh): Average Daily Summer Flow (Mscfd): MAOP of Customer s System (psig): Exist./Initial Phase 1 - Phase 2 Total

TABLE 3 - FLOW RATE PROFILE FOR INDUSTRIAL END USERS AND POWER GENERATION PLANTS Proposed or Preliminary Name of Facility: Make/Model-Combustion Turbine (CT)/Combined Cycle (CC): Note: Power generation units (CTs, CCs, etc.) referred to as units in the table below. Combustion Turbines for Power Generation Exist./Initial Phase 1 Phase 2 Phase 3 Total 1. No. Units Installed 2. In-service Date - Equipment testing (mm/dd/yy) 3. In-service Date - Plant (mm/dd/yy) 4. Annual Peaking occurs from (mm/dd - mm/dd) 5. Peak Days - Number of days per year 6. Number of hours peaking during each Peak Day 7. MW Rating of each unit (MW) 8. What is the fewest number of units which could be operating for a sustained period of several hours? Fuel Rate During Peak Unit Operation 9. Hourly Fuel Rate per Unit @ Min. Ambient Temperature and 100% load (dt/hr = MMBTU/hr) 10. Peak Fuel Rate Qpeak - all units @ 100% Load (Mscfh) Fuel Rate During Off-Peak or Baseload CT Operation 11. No. of units on-line during off-peak or baseload period 12. Hourly Fuel Rate per unit @ % load (dt/hr) 13. Total Off-Peak Fuel Rate Qoffpeak - All Heaters (Mscfh) Fuel Rate during Start-up of the First Unit 14. Duration of start-up of first unit to 100% load (minutes) 15. Initial rate during firing up of unit (the instant when fuel is first introduced into the unit duing start up) Qstart (Mscfh) Heaters for Heating Fuel Gas for the Power Generation Units 16. Will gas fired heaters be used to heat the fuel gas for the units? Yes No (If YES, complete below) Heater Fuel Rate during Peak Unit Operation 17. Number of Heaters Installed 18. Maximum Fuel Rate Required per Heater (MMBTU/hr) 19. Total Heater Fuel Qhtrpeak - All Heaters (Mscfh) Heater Fuel Rate during Off-Peak/Baseload CT Operation 20. During non-peaking hours, will heaters operate at less than 100% ( standby ) load? Yes No 21. If yes, how many heaters? 22. Heater Fuel Rate during Standby per Heater (MMBTU/hr) 23. Total Heater Fuel Rate Qhtroffpeak during Stanby (Mscfh)

Utility and Other Fuel Gas Consumption (i.e. space heating for building, water heater, etc.) 24. Are there utility gas requirements other that the units and Heaters? Yes No (If YES, complete below) 25. Utility gas will be required: Year round, 24 hr/d Year round, daytime only During Peaking Season (#4 specified above), daytime only Other (specify): 26. Minimum Utility Fuel rate Qminutl (Mscfh) Exist./Initial Phase 1 Phase 2 Phase 3 Total 27. Maximum Utility Fuel Rate Qmaxutl (Mscfh) TOTAL GAS FLOW RATE SUMMARY 28. Total Peak Hourly Rate Qtotpeak = Qpeak + Qhtrpeak + Qhtroffpeak + Qminutl (Mscfh) 29. Convert Qtotpeak to Daily Rate (MMscfd) 30. Total Non-Peak Hourly Rate Qtotoffpeak = Qoffpeak + Qhtroffpeak + Qminutl (Mscfh) 31. Convert Qtotoffpeak to Daily Rate (MMscfd) 32. Total Hourly Rate During Start-up, Including utilities Qtotstart = Qstart + Qhtroffpeak + Qmaxutl (Mscfh) 33. Convert Qtotstart to Daily Rate (MMscfd) 34. Total Hourly Rate during Unit Shutdown - Utility Only Qtotshutdown = Qminutl (Mscfh) 35. Convert Qtotshutdown to Daily Rate (MMscfd) PaRt 5: DESIGNATION OF RESPONSIBILITIES As a general rule, recommends that each party design and construct those facilities which it proposes to own, operate and maintain, as indicated in the table below. In all instances, shall design, construct, own, operate and maintain the tap valve(s) to their pipeline(s). In addition, shall design, construct, own, and operate all custody transfer measurement equipment as indicated below. If otherwise, please designate a C for Customer responsibility or for responsibility, NR for Not Required or NA for Not Applicable. Customer-owned and operated facilities installed in yard may be subject to limited review by for (1) compliance with federal codes and industry standard, (2) compliance with s own design and operation requirements (3) compatibility with s equipment and system operation and (4) adequate work space and safety for field operation personnel. Such review does not constitute that has verified and approved Customer s design calculations for MSOP, wall thickness and yield of materials, pressure drop, gas velocity, sizing of control valves, relief valve sizing, suitability of materials and coating, pipe stress and supports, compliance with all jurisdictional agency directives, regulations and limitations, and the like. Description Design, Procure, Materials, Permits Construct Own Operate and Maintain Acquire land for the meter station facility Obtain clearances for cultural resource, threatened and endangered species, wetlands delineation, etc. for Prior Notice Obtain state and local approvals, variances and building permits for zoning, subdivision, conditional use and site plan Survey, topography, boundaries/easements, geotechnical Site development, clearing, grading, access road, parking, fencing, gravel, landscaping, soil erosion control Pipeline from s custody transfer point to Customer s plant site Tap valve(s) and manifold Water bath gas heater, if applicable (see Part 7)

Description Design, Procure, Materials, Permits Construct Own Operate and Maintain Meter(s), isolation valves, custody transfer flow computer/rtu, transmitters, etc. Meter Station headers, yard piping, builiding and foundation Phone line, radio or other data communications Furnish electric power to site, if required Pressure regulation and overpressure monitoring (see part 7) Odorization system (not currently applicable as all gas odorized) Other: PART 6: CONTINUITY OF SERVICE AND POINT OF OWNERSHIP CHANGE Does Customer want the meter station and tap designed for: (A) initial flow rate only (i.e. piping and equipment not sized to facilitate future incremental capacity expansion nor space provided for future meter tubes), i.e. not expandable (B) initial flow rate for the meters only; ultimate flow rate for yard piping, taps & headers (phased expansion) (C) ultimate flow rate for all facilities designed and installed during initial phase. The tie-in and point of ownership change between and Customer facilities shall be located downstream of s meter station at the isolating flange set or joint installed by. What is Customer s proposed line size, wall thickness and yield strength at the tie-in? Yes No Occasionally, will temporarily remove a section of the pipeline from service for maintenance, repairs, smart pigging, upgrade and modification, or emergencies. If has more than one pipeline available, does Customer want a secont tap on the second line to minimize service interruptions? Does customer desire to have block and bypass valves installed in the meter station yard piping (i.e. station bypass) to continue service if the meter station is temporarily shut in? (This can also facilitate future expansion of the meter station while gas flows through the bypass.) PART 7: PRESSURE REGULATION, OVERPRESSURE PROTECTION AND GAS HEATING Customer may be responsible for designing, constructing, owning and operating pressure reduction and overpressure protection facilities capable of receiving gas at s prevailing pressure, up to the MAOP. prefers that Customer operate, monitor and control their own system pressure, using their own design criteria and material specifications. Will Customer: (A) Design its pipeline downstream of the meter station at or above 's pipeline pressure OR (B) Install, operate, and maintain (or request that provide) pressure regulation immediately downstream of (and adjacent to) the meter station and before their pipeline? If (B), what will the reduced or outlet pressure be? psig. Design pressure: psig. With regard to gas heating, will Customer: (A) Waive requirement for a gas heater (typical when no pressure control is required) OR (B) Request to install provisions for a future heater connection (facilitates future heater installation when necessary) OR (C) Install, operate, and maintain (or request that provide) gas heating equipment at the meter station?

PART 8: ELECTRONIC FLOW MEASUREMENT Will Customer want to: (A) connect transducers directly onto meter(s)/piping and feed the inputs to their own flow computer (B) install their own check meter, instruments and flow computer downstream of s meter station in the same yard (C) receive an instantaneous 4-20mA flow rate signal (corrected for temperature and pressure only, but not for BTU or specific gravity) directly from s flow computer (D) other - please specify / describe below: PART 9: OTHER REMARKS OR SPECIAL REQUIREMENTS Prepared By: Date: