PART A INTRODUCTION TO THE AEIS 1. PURPOSE OF THE ADDITIONAL

Similar documents
Major environmental impact assessment (EIA) processes in Queensland

Queensland Public Service Workforce Quarterly Profile

Section 3. Legislative Framework and Impact Assessment Process

ARROW BOWEN PIPELINE PROJECT

Certainty in uncertainty: navigating environmental impact assessment regulatory processes

Native Title Act 1993

GUIDELINE. environmental management of mining. GUIDELINE 11 - Terms of Reference and Preparation of an Environmental Impact. Statement.

Question on Notice. No Asked on 6 March 2014 MR BYRNE ASKED THE ATTORNEY-GENERAL AND MINISTER FOR JUSTICE (MR BLEIJIE)

7. Community Consultation

3. LEGISLATIVE FRAMEWORK

1. Introduction. 1.1 Revised Project Background. 1.2 Purpose of the AEIS. 1.3 Stakeholder Consultation and Public Notification

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017.

PART 2 Tabs EIS General Comments

Environmental Impact Statement Surat Gas Project

GLNG PROJECT ENVIRONMENTAL IMPACT STATEMENT

JOB INFORMATION PACKAGE LEGAL OFFICER (Corporate Entity)

INTERIM REPORT ON INNOVATE RECONCILIATION ACTION PLAN

March Protected area boundary adjustments fall within one of three categories:

Review of the Class Environmental Assessment for Waterpower Projects Ontario Waterpower Association

Chapter 1 - Table of Contents

Irrigation Price Review Submission Appendix B Governance arrangements and key legislative and regulatory obligations

COAG STATEMENT ON THE CLOSING THE GAP REFRESH. 12 December 2018

Public Relations Institute of Australia Golden Target Awards and State Awards for Excellence 2007 Gold Coast Desalination Project Climate Change =

Jemena Northern Gas Pipeline Pty Ltd

MAAS Governance Framework

NORTH STAR TO NSW/QLD BORDER PROJECT STUDY AREA SELECTION REPORT

Postal Address: PO Box Brisbane Adelaide Street QLD 4000

COAL AND COAL SEAM GAS REGULATION

STATE PARTY REPORT ON THE STATE OF CONSERVATION OF THE GREAT BARRIER REEF WORLD HERITAGE AREA (AUSTRALIA) PROPERTY ID N154

Facilitating Implementation of the Canada-Ontario Agreement on Environmental Assessment Cooperation

Submission on the draft terms of reference for Balaclava Island Coal Export Terminal project

Central Queensland Coal Project Appendix 14 Stakeholder Engagement Plan. Supplementary Environmental Impact Statement

6. COMMUNI TY AND S TAKEH OLD ER CON SU LTATI ON

Aboriginal and Torres Strait Islander secret/sacred and private material policy

2. Project Justification and Feasible Alternatives

STRATEGIC DIRECTIONS

1.0 INTRODUCTION 1.1 PROJECT PROPONENT

Secretariat National Aboriginal and Islander Child Care

The key contact for this proposal is Belinda Bastow (AngloGold), Environmental Manager Exploration/ Tropicana:

Office of the Latrobe Health Advocate

Jemena Northern Gas Pipeline Pty Ltd

QUEENSLAND ENVIRONMENTAL OFFSETS FRAMEWORK 20 August Nelson Wills

Key Environmental Constraints Affecting Queensland Agriculture

Reconciliation Action Plan 2012/15 Our vision for reconciliation Our work Our Reconciliation Action Plan

Page 1. Reconciliation Action Plan 2015/2016

Submission on Lake Eyre Basin Intergovernmental Agreement

Impact of the ASL Cap Survey Report

6. PUBLIC AND STAKEHOLDER CONSULTATION

Heritage Protection. Fact Sheet 13. Environmental Defender s Office of Western Australia (Inc.) An introduction to Heritage Protection

Consumer, Carer and Community Participation and Engagement Policy

Protection of World Heritage Properties under the EPBC Act

COMMUNITY ACHIEVING. Stakeholder engagement POWERLINK ANNUAL REPORT 2011/12 COMMUNITY

Public Report Q-LNG01-15-MP Australia Pacific LNG Social Impact Management Plan Gas Fields and Pipeline

1 July Dear Sir/Madam,

Protection of Ramsar Wetlands under the EPBC Act

National Transport Commission Submission to Infrastructure Victoria

Australian Network of Environmental Defender s Offices

1. Introduction The Local Government Association of NSW and Shires Association of NSW (the Associations) are the peak bodies for NSW Local Government.

Three Year Review Social Union Framework Agreement (SUFA) Submission by Federal/Provincial/Territorial Ministerial Council on Social Policy Renewal

Group Executive Economic and Community Development

Parliamentary. Sustainable Ports Development Bill 2015

BACKGROUNDER Office of the Premier

Position Description: Chief Executive Officer

Appendix B6 Construction Heritage Management Plan

DR HELEN SWAN. Principal Consultant Governance & Policy. Personal Details Professional Qualifications

Submission to the Senate Legal and Constitutional Affairs Reference Committee

South Metropolitan Area Health Service Reconciliation Action Plan 2009 to 2014 Annual Progress Report for the Year 2010

Draft Submission on social impact assessment draft guidelines for State significant mining, petroleum production and extractive industry development

Review of the State NRM Plan: Our Place Our Future Phase 2: Draft Findings and Recommendations March 2017

Identified Aboriginal and Torres Strait Islander Position Guidelines April 2018

CEF. Cumulative Effects Framework. Interim Policy. for the Natural Resource Sector. October Cumulative Effects Framework

What We Heard. Developing a Resource Roads Regulation for Yukon

EDO NSW Key Issues Summary Biodiversity Certification: Upfront planning for conservation & future impacts 1 November 2017

Adani Appendix E11 Indigenous Social and Economic Impact Assessment

Commonwealth Lands and Activities of the Commonwealth and Commonwealth Agencies

Primary Health Networks

Monitoring compliance with Environment Protection and Biodiversity Conservation Act 1999 Conditions of Approval: Follow-on audit

Innovate Reconciliation Action Plan

Coal Seam Gas Water Management

SUPPLEMENTARY COMMUNITY CONSULTATION REPORT

Supplementary Report to the Surat Gas Project EIS Surat Gas Project

5. THE STEVE IRWIN AWARD FOR ECOTOURISM

Catchment management bodies in four Australian states: structures, legislation, and relationships to Government agencies

Review of Small Customer Gas Pricing and Competition in Queensland: Draft Report

Reflect Reconciliation Action Plan 2018

Section 3.19 Indigenous Cultural Heritage

The challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment

General Counsel Manager, Governance, Risk and Compliance

Policy Number: 019 Equity and Diversity November 2014

Caval Ridge Mine Change Request 8 Accommodation Village Condition Changes

Stakeholder Engagement Strategy

5. The Steve Irwin Award for Eco Tourism

Review of Functions and Responsibilities of Regional Development Commissions

LEPs and SEPPs. Planning, Development & Heritage. Local environmental plans (LEPs) Last updated: January 2013

Substantive Equality Framework Implementation Plan

National Standard for Environmental Risk Management of Industrial Chemicals

COMMUNITY OVERVIEW MARCH Overburden Management Project Environmental Impact Statement (EIS)

RECONCILIATION ACTION PLAN INNOVATE JUNE 2017 JUNE 2019

6. CULTURAL TOURISM. Total score for submission 100 points Site Inspection further 20 points IMPORTANT UPDATE. Important Notes:

australian network of environmental defender s offices

Transcription:

PART A INTRODUCTION TO THE AEIS 1. PURPOSE OF THE ADDITIONAL information to the environmental impact statement 1 1.1. Consultation process since release of the EIS 1 2. ANALYSIS OF SUBMISSIONS 4 2.1. Number and source of submissions 4 2.2. Methodology for response to submissions 6 PAGE i

1. PURPOSE OF THE ADDITIONAL INFORMATION TO THE ENVIRONMENTAL IMPACT STATEMENT This Additional Information to the Environmental Impact Statement (AEIS) to the Nathan Dam and Pipelines Environmental Impact Statement (EIS) has been prepared in response to submissions received by the Coordinator-General following the public review period of the EIS. The EIS was prepared in accordance with the Terms of Reference (ToR) prepared by the Coordinator-General under the State Development and Public Works Organisation Act 1971 and in accordance with the Bilateral Agreement between the State of Queensland and the Australian Government made under the Environment Protection and Biodiversity Conservation Act 1999 (Cth) EPBC Act. Accordingly, by letter dated 26 July 2012 the Coordinator-General requested SunWater to prepare additional information to the EIS to address the issues raised in submissions received. Figure 1-8 of the EIS is reproduced below (Figure 1-1) to show the position of the AEIS in the steps of EIS preparation. The purpose of the AEIS is not to duplicate the original EIS, but to provide further clarification of specific issues raised in submissions. The AEIS will be provided to the Coordinator-General for consideration in preparing the Coordinator-General s report. Since release of the EIS, the Project has further developed and the AEIS provides an opportunity to make these developments known to the Coordinator-General. The developments generally represent refinement of elements of the Project and they have in part been undertaken in order to address the submissions received. The main areas of refinement are the pipeline route and length, and the land acquisition requirements. These are described in Part C of the AEIS. 1.1. Consultation process since release of the EIS The consultation process for the EIS was described in the EIS. The process was broad ranging and thorough. The EIS was publicly released for comment on 23 April 2012. The comment period closed on 5 June 2012. Immediately prior to release a public notice was placed in newspapers circulated in the local area, the State and nationally and stated: where copies of the EIS are available for inspection; how it can be purchased (or obtained free of charge); that submissions may be made to the Coordinator-General about the EIS; the date by which submissions must be made; and the address for submissions. During the display period SunWater undertook a range of consultation activities as summarised below: placed hardcopies of the EIS at 4 regional locations for viewing (and Brisbane); distributed numerous electronic copies on CD ROM; PAGE 1

placed 2 advertisements in three regional newspapers (in addition to CG required advertising in State and national newspapers) describing the EIS and submission process; distributed Newsletter 3 to approximately 250 stakeholders and placed it at 3 locations; held public information days at Dalby, Chinchilla, Taroom and Theodore; held a Community Liaison Group meeting in Taroom; held agency briefings in Brisbane and Rockhampton; and maintained the Project web site and 1800 number. A consultation report for this period is included as Appendix A1-B. PAGE 2

SunWater prepares initial Advice Statement (Project has been declared significant by Coordinator-General (CG) under SDPWOA) EPBC referral submitted to Commonwealth government (Project has been declared controlled action under EPBC Act) EIS required project to be assessed under bilateral agreement between the Commonwealth and Queensland governments CG prepares and releases draft ToR for public and agency review and invites written comments CG considers comments SunWater prepares EIS to address ToR (this includes consultation with local community) ToR issued to SunWater CG releases EIS for public and agency review and invites written submissions SunWater submits draft EIS to CG (to ensure ToR has been adequately addressed) CG prepares assessment report on EIS, AEIS and other relevant materials CG considers properly made submissions Federal Minister reviews CG report and other material under bilateral agreement and makes decision on Project SunWater prepares AEIS QE0999.930 Environmental Impact Assessment Process.vsd Figure 1-1 Key Steps in EIS preparation PAGE 3

2. ANALYSIS OF SUBMISSIONS 2.1. Number and source of submissions Fifty-eight submissions on the EIS were received by the Coordinator-General. These comprised twenty-eight from individuals, nine from organisations, two from local government, seventeen from State government departments or Government-owned corporations and two from Commonwealth agencies. The source of submissions is summarised in Table 2-1. The Coordinator-General accepted submissions received after the formal closure of the submission period and these have been included. It is noted that for privacy, the identity of private submitters is not provided. Some State government departments have changed names since the submission was made. PAGE 4

Table 2-1 Source of submissions Number of submissions Submitter category 2 Australian Government: Department of Sustainability, Environment, Water, Population and Communities (now Department of the Environment) Great Barrier Reef Marine Park Authority 17 State Government Departments and Government-owned corporations: Department of Aboriginal and Torres Strait Islander and Multicultural Affairs (now Department of Aboriginal and Torres Strait Islander Partnerships) Department of Agriculture, Forestry and Fisheries (now Department of Agriculture, and Fisheries) Department of Communities, Child Safety and Disability Department of Education, Training and Employment Services (now Department of Education and Training) Department of Energy and Water Supply Department of Environment and Heritage Protection Department of Housing and Public Works Department of Justice and Attorney General Department of Local Government and Planning (now Department of Infrastructure, Local Government and Planning) Department of Natural Resources and Mines Department of State Development, Infrastructure and Planning (now Department of State Development) Department of Tourism, Major Events, Small Business and the Commonwealth Games Department of Transport and Main Roads Queensland Health Queensland Police Service Queensland Treasury Stanwell Corporation Ltd 2 Local Government: Banana Shire Council Western Downs Regional Council 9 Non-government organisations: AgForce Taroom Capricorn Conservation Council Cotton Australia Fitzroy Basin Association Gladstone Area Water Board Queensland Conservation Council Queensland Murray-Darling Committee Taroom Community Liaison Group Wildlife Preservation Society 28 Private PAGE 5

2.2. Methodology for response to submissions Each submission was reviewed by staff of the Department of State Development, Infrastructure and Planning (now Department of State Development, DSD) to identify the issues raised. The issues were recorded in an issues database. Each issue was allocated an individual identification number comprised of the submission number and the issue number within that submission. For example, 13.9 is the ninth issue identified in Submission 13. A comprehensive list of the issues raised in each submission is provided in Appendix A2-A. Part B of this AEIS responds to the issues raised and is structured to align with EIS chapter headings. Within each chapter the specific comments raised are pooled into broader issues so that related issues can be addressed in a coordinated manner. The table in Appendix A2-A cross references each specific issue to the section of the AEIS in which the response can be found. The AEIS provides technical responses to the issues raised in submissions and provides conclusions with regards to those issues. As previously discussed, the purpose of the AEIS is not to duplicate the original EIS, SunWater having already prepared an EIS in accordance with the ToR, but to provide further clarification of specific issues raised in submissions. Furthermore, the EIS as released is a public document and cannot be altered. Where submissions noted typographical errors, incorrect cross-references or suggested changes to wording, these amendments are addressed in Appendix A2-B as the EIS cannot be reissued with these changes. DSD officers determined that some of the issues raised did not require a response. For example some points raised in submissions represented information provided for the proponent s benefit. All submitters who provided such information are thanked and the information will be used at the appropriate time should the Project proceed. Some submissions represent the respondents views on broad issues, such as disagreeing with dams per se, or contained general statements that the EIS was inadequate. If the submitter did not specifically identify in what way the EIS was inadequate, such as by offering an alternative assessment methodology, identifying an overlooked relevant report or finding a technical error in a calculation, then a response is not possible other than restating what is already in the EIS. There were also a number of points which suggested various plans or outputs should be completed within the EIS phase. In most cases those plans represent the outcome of standard mandatory processes that will occur at the appropriate time with respect to Project approvals and the design process. Bringing them forward makes no material difference to the ability of agencies or the public to assess the prudence or feasibility of the Project and as they are a requirement of standard planning processes, their development is assured. In the time since the EIS was produced a number of pieces of relevant legislation and policy have changed. These are identified in Section 1.5 of Part B of the AEIS then used in the relevant chapters. PAGE 6

This page has been intentionally left blank