Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track

Similar documents
Identification Selection Definition Execution. Schedule.

International Construction Consulting, LLC. Modularization Overview.

HSE Design Reviews and Action Close-out

Leading Indicators and Dashboarding for Advanced Work Packaging. Lloyd Rankin

ECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP

Engineering & Schematics

Doseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers

Advanced Work Packaging IMPLEMENTATION

Taking AWP to the Next Level

THE MISSING LINK - OBJECT ORIENTED ESTIMATING

Project and Program Management in ehealth

PROCESS & PRODUCTION ENGINEERING DIRECTORY

Path of Construction Enhancing the Best Practice for Engineering & Supply Chain to Support AWP Implementation

EST Accuracy of FEL 2 Estimates in Process Plants

Deliverables list for Projects in the fertilizer industry

Guten Tag. (good day)

Estimating and Scheduling

ENGINEERING MANAGEMENT

Oil & Gas Project demands on Engineering

Feasibility Consulting & Successful Study Completion

2.0 SCHEDULE DEVELOPMENT

The execution of a Complex Project A guided tour

Chapter 3 Managing the Information Systems Project

PMP Exam Preparation Course Project Time Management

Global Project Management, LLC

Chapter 4 Project Management

Importance of Adequate Interface Management and Systems Integration

GLOBAL ENERGY FORUM. Managing Large EPC Projects with Data at Your Fingertips. Maurice Tayeh. February 20 th, 2014 Houston, Texas

Effective Control of Instrumentation and Control (I&C) Modernization, Methods and Tools

FULLY INTEGRATED SCHEDULE FOR A REACTOR DECOMMISSIONING PROJECT. G. Cross, BNFL Inc.

CMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

Building an ERP Project Work Breakdown Structure - a few common scenarios

E2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: )

Project Management Consultancy Services. Ensuring safe and successful execution of your projects

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

Project Execution Plan For

TenStep Project Management Process Summary

REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017

Value improving practices for revamp and greenfield projects in fertilizer industry

Project Production Institute Challenges and Myths of Offsite Fabrication for Mega Projects

Software Global Customer Conference

SGM Engineering, Inc.

Information Technology Audit & Cyber Security

Managing Schedule Change

DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING

Statement of Work. 1.0 Executive Summary. InfraStruXure Site Coordination - 1 InfraStruXure - Site Coordination. Installation Services

Lecture- 10. Project Scheduling. Dronacharya College of Engineering

Fluid Catalytic Cracking (FCC) delivering Predictable Results

Project Management Consultancy Services. Ensuring safe and successful execution of your projects

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure

Project Management Auditing Guide

Why end users are selecting Foundation Fieldbus

A COMPLICATED PROJECT FOR POWER AND WATER CO- GENERATION: THE RAF SITE

Time has the least. amount of flexibility; Schedule issues are the main reason for

Current State of PSM

This guide is applicable to River Protection Project - Waste Treatment Plant (RPP-WTP) project suppliers and is intended for supplier use only.

Definition. Name of the tool or technique Project mission statement

Ageing Management and Development of a Programme for Long Term Operation of Nuclear Power Plants

Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects

Risk Mitigation in a Core Banking Conversion

Attachment J-4 Milestone Acceptance Criteria and Payment Schedule

Modern Systems Analysis and Design Seventh Edition

SMARTPLANT ENTERPRISE

ServiceNow Integration Services

QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector

A White Paper February System for piping global management

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:

Pilot Plant Cost Factors Guide

Canada. Iron and Steel Sector - PI Specifics

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

Emerson Digital Twin: A Key Technology for Digital Transformation

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?

7. Model based software architecture

Do not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

SmartSPEND. KBR SmartSPEND SM. The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns

Welcome to lecture 4 of Topic 2.9. In this lecture we focus on Phase 2 of the Project Management Lifecycle the planning phase

VI International Forum ATOMEXPO 2014

Project Time Management

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015

Project Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition

ENGINEERING SERVICES

Applying Dynamic Process Simulations Toward Flaring Reduction

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

Define and Initiate SubPhase

1. Project Definition

Engineering Management Manual

Project Management Professional (PMP) Exam Prep Course 4 - Project Integration Management

Design of Instrumentation and Control Systems for Nuclear Power Plants

In general, a model is used to understand a system. It is only a representation of a more complicated original system based on mutual

A DESIGN PROCESS MODELING APPROACH INCORPORATING NONLINEAR ELEMENTS

XXX Development. Facility Feasibility & Option Selection Plan

Well Delivery Process A Proven Method to Improve Value and Performance While Reducing Costs. IADC/SPE

Absolute Energy Raters Commissioning Plan Outline Template

Project Management. Risk Management

Organization and Responsibilities of Internal/External TSO

Project Engineering Support for the Site Construction Preparation and Coordination Activities. Technical Specification

CONSIDERATIONS AND MILESTONES INFRASTRUCTURE FOR A RESEARCH REACTOR PROJECT

Transcription:

progetti Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track By Armando Bianco, Engineering Manager, Eniprogetti Global Conference on EPC Contract & Project Management 9th-10th November 2017 Lisbon, Portugal

Index Eni Design Basis, Key Deliverables & Battery Limits: how to approach a Front End Engineering Design Balance between engineering freezing and early procurement: Long Lead Items strategy Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project goals Conclusions 2

Eni 3

Design Basis, Key Deliverables & Battery Limits: how to approach a Front End Engineering Design 4

Oil and Gas Project Development Phases Pre-feasibily 1-3 MM (typical ref.) Feasibility 2-4 MM (typical ref.) Basic - FEED 3-9 MM (typical ref.) G1 G2 G3 Detail Design & Procurement 9-18 MM (typical ref.) Construction Commissioning 12+ MM (typical ref.) Execution: detailed development and physical realizatio of the scope of the project s ork Definition: finalization of the development concept Selection: choice of optimal development configuration Appraisal / Evaluation: assess e t of the opportu it s eco o ic alue Project expenditure Capital Risk Difficulty to implement changes Personnel involved Stakeholders e pectatio s Time 5

Project Development Phases Key Activities -> Key Deliverables (es. for process and piping and layout engineering) Pre-feasibily 1-3 MM (typical ref.) Feasibility 2-4 MM (typical ref.) Basic - FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) Construction Commissioning 12+ MM (typical ref.) Support to Construction and commissioning Feasibility Red-marked and as-built Finalization of all processes, utilities and transportation systems. Design of all engineering systems Constructability reviews finalization 3D model Detail Engineering Design Procurement and Construction P&ID (with vendor information) Equipment DS (for all items) Details MTO (2 nd and 3 rd ) Isometrics Construction drawings Stress Reports Finalization of Heat & Material balance, P&ID & Equipment and packages DS Plot Plan, Equipment layouts, Underground layouts Finalization of Technical Specifications (Stress analysis Criteria) Single lines for steel structures Preli i ar MTO s Pipi g ( st MTO) 6 Identification and analysis of the main process and utilities for each generated concept alternative Preparation of process specifications, design criteria, for all processes, utilities and transportation systems. Preliminary engineering, safety and constructability. Technology selection report Preliminary Heat & Material balance Block Flow Diagram Preliminary Site Plan Process Flow Diagrams Battery Limits Table Preliminary P&I Ds Equipment Data Sheets Design Criteria Preliminary Plot Plan

How Design Basis, Key Delivery and B.L. can affect a Project What if Desig Bases are not finalized Example: the pressure of the Sea Water Make-up (rely upon information) was significantly different from the reality. Technical resolution: lower the pumps with an additional basin (groundwater level very high). Impact: additional costs and delay in schedule Key Deliverables are not ready as needed Example: the supply of a critical reactor was assigned to a vendor in the Far East and a shipping to North Africa was fixed in advance. Due to the delay in the 3D model, the nozzle orientation was not ready as per original plan agreed with the vendor resulting in late finalization of the vendor engineering and eventually of the supply. Recovery plan: an acceleration plan was agreed with the vendor to meet shipping window. Impact: additional costs 7 Battery Li its are not aligned (process-wise) Example: two different mechanical contractors were assigned to install the cooling water circuits in the relevant area and a battery limits was established. During the commissioning phase after the battery limits were connected it was noticed that one contractor inverted the connection from a process point of view. Technical resolution: the connections were modified during commissioning and with acceleration in procurement for the unforeseen additional material during commissioning Impact: delay during commissioning phase Note: Lesson Learnt not related with ENI projects

Why Basic-FEED is the most important part of a Project? Pre-feas. Feasibility 1-3 MM 3-6 MM (typical ref.) Basic - FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) Construction 12 32 MM (typical ref.) Construction Commissioning 12+ MM (typical ref.) $ value BOQ & Construction strategy Material Selection & Take-off Peak Construction Cost Project Cost Curvet Peak Material Cost Availability of Information time 8 During Basic FEED project costs can be properly evaluated by finalization of material selectio a d MTOs, owi g to that this phase is the ost i porta t for the go/ o go final assessment

Design approach Key points The Basic - FEED engineering shall be tailor fit to allow the correct definition of the i vest e t cost a d to support the go / o go decisio gate 3 (key deliverables fit for purpose to the activities and not vice-versa); In Basic FEED phase, the key deliverables allow to fix the material selection and estimate material take-offs which are the input for the procurement and construction strategy based on the project drivers; 9

Balance between engineering freezing and early procurement: Long Lead Items strategy 10

Long Lead Items definitions Those components of a system or piece of equipment for which the times to design and fabricate are the longest and for which an early commitment of funds may be desirable or necessary in order to meet the earliest possible date of system completion. 11

Critical Path The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration [PMBOK 6.6.2.2 Critical Path Method] Appling Critical Path method for all the systems of a project, even material with a rather short delivery can result to be critical, owing to that we can split LLI in two categories: Typical LLI such as: High pressure equipment High temperature equipment Special Material equipment 12 Not Typical LLI such as: Tie-ins: integration with existing Facilities Bulk material for early commissioning system

Tie-ins: integration with existing Facilities REFERENCE GREEN-FIELD PROJECT SCHEDULE Pre-feas. 1-3 MM (typ.ref.) Feasibility 3-6 MM (typ.ref.) FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) PROCUREMENT PROCUREMENT FOR TRADITIONAL FOR LLI LLI Construction 12 32 MM (typical ref.) Commissioning 3-12 MM (typical ref.) EARLY ENGINEERING EARLY CONSTRUCTION EARLY PROCUREMENT TIE-INS PRODUCTION PLAN of EXISTING FACILITIES EARLY COMMISSIONING UNIT 10 UNIT 20 UNIT 30 Plant to be disinvested Shutdown Shutdown Production Dismantelling Dismantling Production Shutdown OVERALL SCHEDULE INTEGRATED WITH PRODUCTION PLAN Feasibility Study TIE-INS FEED TIE-INS INSTAL. Shutdown Detail Design & Procurement TIE-INS INSTAL. Dismantling Construction Commissioning 13 Tie-ins shall be planed in an early stage of the project, with a dedicated engineering, construction and commissioning team. The project schedule incorporates the production plan in terms of turn-around or critical milestones.

Bulk Material for Early Commissioning System Engineering design for bulk material is aimed to produce MTOs with increased levels of definition Procurement generally follows the MTO by engineering based on master agreements or project agreements Construction strategy is divided into: 1 st phase by area 2 nd phase by system 14 During the engineering phase it is important to verify that the delivery of bulk material fits the Mechanical Completion dates (additional specific MTOs can be envisaged).

Long Lead Items strategy Key points The critical path developed for all the project systems allows us to recognize critical delivery items which do not have the longest delivery such as tie-ins or bulk material for early commissioning system, which shall be focused since the start of the project with a dedicated integrated team (engineering, construction and commissioning); For a revamping project, the integration of the production plan in the project baseline allows to execute tie-ins during turn-around, minimizing the number of shut-downs and avoiding unnecessary loss of production; 15

Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project goals If you're not confused, you're not paying attention. Tom Peters 16

Project objectives and Fast-Track Projects Pre-feas. 1-3 MM (typ.ref.) Feasibility 3-6 MM (typ.ref.) Basic - FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) Construction 12 32 MM (typical ref.) Commissioning 3-12 MM (typical ref.) Opt.1) Compress the activity lengths Pre-F. Feasibil. FEED Detail Design & Procurement Opt.2) Fast-Track by parallelization of phases Feasibility Study FEED Detail Design & Procurement 17

Possible outcomes when implementing a Fast-Track in a project Relying upon preliminary information Overdesign material Design based on assumptions Increased interface management Not linear approach in decision making Higher Cost More Engineering Man-hours More Reworks More difficult engagement of personnel Increased possibility of inconsistencies Higher Risk Which it the greatest objective? 18

How to mitigate risks in fast-track projects Feasibility Study FEED Re-cycling Design inputs/outputs Detail Design & Procurement ENGINEERING Preliminary information evaluated from Basic (used for detail design) are always re-checked when more information are available ENGINEERING Final alignment mitigates risk of further phases for critical aspects D MATERIAL Material check/re-rated is re-consolidated both in Basic and Detail Design to avoid reworks during construction and commissioning MATERIAL When procurement cycle is long, procurement can be start with preliminary data, updating more consolidated information during the vendor alignment before PO Final alignment TEAM If the approach is aligned since the beginning with a common goal, all the team is aimed to support unavoidable project changes and reworks activities 19

Case Study Feasibility Study FEED Detail Design & Procurement D Project Organization Engineering Approach: Re-cycling Design 1. Process and Layout for critical circuit 2. 3D Model Review 30% and 60% 3. Material Selection 4. Vendor design 5. Design Philosophy Operating manual 20

Case Study Organization Chart OWNER FEASIBILI TY PRE- FEAS. LICENSOR FEASIBIL. CNT DETAILED ENG. BASIC - FEED FAST-TRACK BASIC FEED VENDOR VENDOR DETAIL ENG. VENDOR CONSTRUCTION SUB. CONSTRUCTION SUB. SUB. CONSTRUCTION SUB. Interface Management

#1: Process and Layout for critical circuit 2) PROCESS SCENARIOS (DESIGN CASES AND TRANSIENTS) 1) PRELIMINARY SIZE CALCULATION & PLOT PLAN PUMP FV s Valves Flow PSVs Valves Flow DISCHARGE File by FVA FVB FVC PSVA PSVB PSVC A B C IN OUT IN OUT IN OUT IN OUT IN OUT IN OUT Case EST9 4 SA 1 351 351 351 351 351 351 351 351 351 351 351 351 351 351 351 EST9 4 SA 2 380 380 380 380 380 380 380 380 380 380 380 380 380 380 380 EST9 4 SA 3 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 EST9 4 SA 4 351 351 250 351 351 351 351 250 250 351 351 351 351 250 250 EST9 4 SA 5 250 351 351 250 250 351 351 351 351 250 250 351 351 351 351 EST9 4 SA 6 351 250 351 351 351 250 250 351 351 351 351 250 250 351 351 EST9 4 SA 7 351 351 351 351 351 351 351 351 351 250 250 250 250 250 250 x x x x x x x x x x x x x x x CEER 4 CEER 1 351 351 250 351 351 351 351 250 250 250 250 250 250 250 250 CEER 4 CEER 2 351 250 351 351 351 250 250 351 351 250 250 250 250 250 250 CEER 4 CEER 3 250 351 351 250 250 351 351 351 351 250 250 250 250 250 250 CEER 4 CEER 4 351 351 250 351 351 351 351 250 250 351 351 351 351 250 250 CEER 4 CEER 5 351 250 351 351 351 250 250 351 351 351 351 250 250 351 351 CEER 4 CEER 6 250 351 351 250 250 351 351 351 351 250 250 351 351 351 351 CEER 4 CEER 7 351 351 351 351 351 351 351 351 351 351 351 351 351 351 351 CEER 4 CEER 8 380 380 380 380 380 380 380 380 380 380 380 380 380 380 380 CEER 4 CEER 9 351 351 351 250 250 250 250 250 250 250 250 250 250 250 250 In Process: Pump Nozzle Alignment for installation case, Pumps ABC at ambient CEER 4 CEER temperature, piping not anchored to the pumps. CEER 4 CEER In Process: Pump Nozzle Alignment for maintenaince case, Pump A, B or C as spare. CEER 4 CEER In Process: Tracing Failure Scenario analysis 3) STRESS CRITERIA WITH PRELIMINARY CRITICAL VERIFICATION AND TYPICAL DETAILS 4) 3D LAYOUT 6) UPDATING PROCESS LINE CALCULATION & PLOT PLAN 5) STRESS CALCULATION BASIC-FEED DETAIL ENGINEERING 22

#2: 3D Model Review 30% AND 60% DETAIL ENGINEERING BASIC-FEED BASIC-FEED DETAIL ENGINEERING 23

#3: Material Selection (Piping) Fluid list Piping Classes Process Fluid List Material Requirements Vendor Follow-up Material requisition & Purchase Order BASIC-FEED DETAIL ENGINEERING 24

#4: Vendor design Process DataSheet Material Requisition Mechanical and Material Check Vendor Follow-up BASIC-FEED DETAIL ENGINEERING 25

#5: Design Philosophy Operating manual Updated Control Philosophy Updating Process Design Design Scenarios Operating Scenarios Process Philosophy Operating Manual BASIC-FEED DETAIL ENGINEERING 26

Fast Track Key points The Fast Track with parallelization of phases which traditionally are developed sequentially is a possible strategy to meet Project Objectives when the schedule is challenging; To mitigate the risk associated to fast track (more interfaces, reworks, designing by conservative assumptions rather that consolidated data etc.) project team needs to be integrated with an interface management plan and dedicated engineering methods such as re-cycling and final alignment need to be set-up in the engineering execution plan. 27

Conclusions - Key Factors for Basic-FEED Projects Tailor fit Design by Project Objectives Advanced monitor of costs with correct Basic-FEED data System-wise approach since the beginning of the project For revamping, integration of project schedule with production plan Interface management, re-cycling and final alignment for fast-track project 28