Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized CAMLICA ELEKTRIK URETIM A.S. CAMLICA III RESERVOIR AND HYDROELECTRIC POWER PLANT (HEPP) ENVIRONMENTAL MANAGEMENT PLAN (EMP) Kayseri Province, Yahyali District
ENVIRONMENTAL MANAGEMENT PLAN-MITIGATION PART Phase Issue Mitigating Measure Responsibility* Sitting - Construction camps will not be established near the forested areas I. Sitting of construction camps and municipal services for worker camps -Construction camps will be sited at least: (a) (b) (c) 1 km from any protected areas 50 meters from any surface water bodies, and 1 km from any villages or sites of cultural significance Services (a) Water for the camps will be purchased from the Yahyalı Municipality. (b) Compact waste water treatment unit will be established at Çamlıca III main camp. Treated water will reach at least to minimum allowable water discharge criteria and than it will be discharged to zamantı River. (c) Recycleable solid waste will be collected at suiatable storage area and then will be given to recycling firms. (d) Garbage from the camps will be put in garbage drums and it will be collected periodically by Yahyalı Municipality. - Construction camp restored to compatible use after work is completed. Construction II. Construction solid waste management (soil, rock, packaging materials etc.) - Rock shall be used as fill to the greatest extent possible, excess to be disposed of at site approved by authorities - Topsoil will be stored and covered to prevent erosion. After construction completion, soil will be restored to original location and revegetated. - Packaging wastes from electrical equipment will be recycled wherever possible. otherwise it will be collected by Yahyalı Municipality. - Burning is to be limited to prevent forest fires. - Verify construction equipment has valid operating permits III. Construction engine equipment exhausts - Minimize engine idling by turning off equipment not in use for more than 5 minutes
IV. Construction equipment storage - Avoid tree cutting to create storage area - Place equipment on impervious surface to prevent oil leaks from contaminating soil - Locate storage area at least 50 meters away from any surface water bodies, avoid villages and any population centers Elektrik Üretim Construction V. Noise - Construction would take place only during daytime (from 7.00AM to 7.00PM) - The noise level will be kept under the stated limit in "Environmental Noise Assessement and Management Regulation". If noise level exceeds the limit (except during blasting), measures such as installing protection walls will be taken. - Workers who exposed to high level of noise will use necessary equipments such as headset or earplug. - If construction during evening is required, the local affected people will first be consulted at least one week in advance. - Sub-contractor VI. Dust - Water spraying in dry and windy conditions on local roads where trucks pass and at any construction sites - Dusty materials will be covered with canvas cloth during transportation VII. Worker safety - Contractor will be required to develop a health and safety plan two weeks before starting construction work, and then subproject sponsor will review and approve it; workers will be subjected to health screening and health and safety training sessions will be provided; public health education will be part of the construction program - Necessary safety tools such as helmets, working shoes, ear protection, dust filter and others will be provided and be required to be used by workers. VIII. Soil erosion and silt runoff - Any transmission towers or other structures will be located to avoid high slope (>30 ) areas - In case selection of such slope areas cannot be avoided, structures will be designed to minimize excavation on slopes - Construction will proceed during dry conditions - Bunds, sedimentation ponds, or other silt trapping devices constructed to avoid siltation into surface waters IX. Existing roads - Minimize additional traffic movements on existing roads - Repair any roads as soon as damage becomes evident - Keep roads free from mud, debris and other obstacles Elektrik Üretim X. Access road siting and construction - Use existing access roads wherever possible - Avoid tree cutting or economically productive lands wherever possible
Construction XI. Transmission line routing and construction XII. Historical, archeological and cultural artifacts, and areas/structures of local/international cultural value - Use existing ROWs wherever possible - Avoid migratory or local bird routes, particularly protected areas (e.g. Ramsar sites) - In case any historical, cultural or archeological asset in encountered during excavation/construction, the excavation/construction work shall be stopped and the Provincial/Municipal Directors of Culture and Museum Directorate shall be immediately informed thereof. No persons are permitted to remove articles or disturb the area: such action are grounds for dismissal or contract cancellation. The construction work will be resumed after inspection and written approval by the authorities. - In case any transmission line or access road or structure passes through or is to be sited on village cemeteries, the alignment or site would normally be changed. If it is unavoidable, a special consultation with the affected communities would be held to determine culturally appropriate means of relocating the gravesites in accordance to local customs/beliefs/traditions. No tower pads are to be placed in cemeteries. C lt t -Museum Directorate -Provincial Directorate of Culture and Nature XIII. Raw material supply All materials supplied to the subproject, e.g. stone, concrete, sand, etc. must be provided by contractors with valid operating permits XIII. Management of hazardous materials (fuels, lubricants, explosives etc.) XIV. Fish passage XV. Loss of forest - All hazardous materials are to be stored on impervious surfaces, in well ventilated buildings that are locked and fenced when not in use and to which public access is denied and at least 50 meters from any surface waters. - Maintanance and lubrication of all trucks and construction equipment will be done at authorized service centers at neighbouring towns. In emergency case, it may be done at construction site but in this case, waste lubricants will be collected in drums and send to service centers. - Population centers and forested areas are to be avoided - In order to maintain natural life of every kind of fishes, a fish passege will be constructed. The project for fish passage will be prepared together with a hydrobiologist, in order to make sure that all type of fishes easily move forward through zamantı River. - Avoid siting project in forested areas, to the extent possible. Any forest removed must be restored after construction or replaced at some other location Consultant Consultant Consultant Noise (from power house) - Equipment should be housed in sound insulated buildings, and/or trees shrubs planted around noisy equipment to further absorb sound. - Workers who exposed to high level of noise will use necessary equipments such as headset or earplug. Elektrik Üretim Consultant ion - Workers will be subjected to health screening and health and safety training sessions will be provided retim onsultant
Operation Operati Worker safety - Necessary safety tools such as helmets, working shoes, ear protection, dust filter and others will be provided and be required to be used by workers. - All operational activities will be in compliance with the relevant Turkish Occupational Health and Safety Regulation Domestic sewage (operations staff) - Domestic sewage will be stored temporarily in a isolated underground septic tank and will be periodically collected by Sambeyli Municipality. Domestic solid waste (operations staff) - Recycleable solid waste will be collected at suiatable storage area and then will be given to recycling firms. - Domestic garbage will be put in garbage drums and it will be collected periodically by Yahyalı Municipality. - Accumulated clay and sandy soils in sedimentation pool will be collected periodically. Sınce this soil is very useful for agricultural activities, it will be given to neighbouring farmers. Elektrik Ür Co - Environmental Consultant
ENVIRONMENTAL MANAGEMENT PLAN-MONITORING PART Phase/Issue What parameter is to be monitored? Where How When is the parameter to be monitored? is the parameter to be monitored/ type of monitoring equipment? is the parameter to be monitoredfrequency of measurement or continuous? Construction - Camp location - Camp site - Quarterly, greater frequency (e.g. weekly) if improper practices are noted Responsibility I. Siting of construction camps and municipal services for worker camps - Arrangements for water - Water supply site, sewage and supply, sewage, and garbage disposal sites municipal solid waste - Campsite properly restored? - Quarterly, greater frequency (e.g. weekly) if improper practices are noted - Campsite - Completion of construction work - Packaging waste recycling and disposal practices - Package waste storage and/or disposal site II. Construction solid waste management (soil, rock, packaging materials etc.) III. Construction engine equipment exhausts - Rock and soil reuse or disposal practices - Adequacy of topsoil temporary storage site (covered and erosion protection measures in place), restored area properly revegetated - Rock and soil storage and or disposal site - Topsoil temporary storage site and revegetation site when completed - Turkish registration - At project site entrance - Once, when equipment enters construction site - Unused equipment idling times Quarterly, greater frequency (e.g. weekly) if improper practices are noted - At construction site - Monthly, greater frequency (e.g. weekly) if improper practices are noted - Tree cutting involved in preparing storage site?
IV. Construction equipment storage - Site avoids population centers and surface water bodies? Proposed construction equipment storage site Once, before site is prepared - Equipment situated on an impervious surface? - Construction hours - Site observation - Monthly - Sound barriers needed and installed? (if necessary) - - Monthly - Headset or earplug V. Noise provided to and being used by workers who exposed to high level of noise? Construction site - - Monthly - Local population informed of any off-hour construction at least one week in advance - Consult with local affected groups - One week before off-hour construction starts - Water spraying performed properly? - Construction site and access roads - During hot, dry, or windy weather VI. Dust - Covering of dusty materials - Construction site and access during transportation or at roads storage areas performed properly? - Monthly - Acceptable health and safety plan prepared? - (with a copy of the - Before any physical worker activities are health and safety plan for initiated verification) VII. Worker safety - Safety equipment provided to and being used by workers? In areas where workers are performing their assignments - - Weekly. More frequently (at random) if violations are observed - Construction proceeding in dry season? Structure site Prior to start of construction VIII. Soil erosion and silt runoff Slope of structure site <30 0?
Appropriate silt trapping Areas of major runoff systems included? During or immediately after rainstorm Existing roads Condition, cleanliness within 1km of site Site visit/visual Weekly during construction More frequently (at random) if violations are observed Access road siting and construction Route selection offers Access road route review of plans, site visit Before construction minimal intrusion with new construction, tree cutting, use of productive land etc. Route selection offers minimal intrusion with new construction, tree cutting, Transmission line use of productive land etc. routing and construction Transmission line route review of plans, site visit Before construction Migratory bird paths, Ramsar sites etc. avoided? Accidental find of articles of At any excavation site Determine of authorities cultural value notified and proper procedures followed? Chance find of cultural artifacts, and areas/structures of local cultural value Location of any cemeteries Along planned alignment or structures (natural or man-routemade) of local value towers, or newly planned of any transmission access road Determine if proper consultations conducted by speaking with local affected groups During construction - Environmental Consultant Raw material supply Validity of the suppliers operating license At the entrance of the project site or at the suppliers office inspection of license Before signing an agreement for material supply Management of hazardous materials (fuels, lubricants, explosives etc.) Storage facilities locked, fenced, well ventilated, on impervious ground? Hazardous materials storage site inspection of building and site Before start of construction and quarterly thereafter.. Increase frequency if improper practices observed. - Environmental Consultant
Location far from population centers? Fish passage Adequacy of fish passage At construction site review of plans, site visit Before start of construction and twice in a year thereafter.. Increase frequency if - Hydrobiologist improper practices observed. Loss of forest Removal of trees, forest clearing Project site as well as off-sites (storage facilities, access roads, transmission line routes, etc.) Prior to any land clearing activities Noise (from power house) Operation Noise levels At or near power house db meter Sound absorbing measures Nearest population centers installed (housing, tree (particularly if there are planting, sound barriers etc.) complaints) Quarterly, or immediately after any complaint is lodged by local population Acceptable health screening and safety training made? (with a copy of the health and safety reports for verification) Worker safety Safety equipment provided to and being used by workers? In areas where workers are performing their assignments Quarterly, or immediately after any complaint is lodged by workers Complience with Turkish Occupational Health and Safety Regulation Has a septic tank of proper design been installed and is it operating properly. (system design and construction) Before start of operations Domestic sewage (operations staff) Domestic sewage in the septic tank collected by Yahyalı Municipality on a regular basis? Immediate area surrounding septic tank and groundwater underneath septic tank Quarterly, or immediately after any complaint is lodged by workers
Waste collected by Yahyalı Municipality on a regular (at least weekly) basis? Domestic solid waste (operations staff) Recycleable solid waste and accumulated clay and sandy soil given to suitable firms/person General area where staff are working or housed and temporary waste disposal site Every two weeks more frequently (weekly or daily) if observations reveal poor operation Temporary storage facilities properly protected?