SCREW PILE APPLICATION SHEETS

Similar documents
Modular System Advantages

Lightweight Recoverable Foundations on Suitable Ground

Halfen systems for the support and restraint of brickwork

Building Construction

Lesson 2 Substructure. Dr S.Sreenath BSc Engg, MSc Engg, MSc (ICM), MBA, PhD

Seven Wonders of the Ancient World

SCREW PILES INFORMATION SHEET

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Grade Separation Systems. Single-Span Rail Bridge Construction Procedure. An innovation from art engineering inc.

Lifting Sockets. Flat Lifting Sockets

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

SECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

Geotechnical Engineering Software GEO5

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding)

SECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT

Concrete Framing Systems - Walls and Columns

Concert Halls, Lyric Theatres and Performing Arts Venues

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

Matrix Helical Anchoring System

Topic: Site Formation

Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay

SECTION VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT

twenty four foundations and retaining walls Foundation Structural vs. Foundation Design Structural vs. Foundation Design

Miller Collective Safety at Height Solutions EPIC ULTRA Barrier System EPIC Post-N-Barrier System EPIC Basic Barrier System

Aveng Ground Engineering Profile

FrameFast Shoring System

SPECIFICATION FOR REINFORCED SOIL WALL

Jackson Crossing Located in Alexandria, VA. Technical Report 1 Michael Bologna

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

INNOVATION IN PROP DESIGN. For propping enquiries Australia wide call:

Sabah Shawkat Cabinet of Structural Engineering 2017

Smarter. Safer. Leaner.

Requirements for Measuring and Pricing of Structural Concrete

Installing DELTABEAM. Installation of DELTABEAM. Deliveries. Storage on-site

Statement of Special Inspections Michigan Building Code 2012 (MBC 2012)

HAMBRO COMPOSITE FLOOR SYSTEM

FEATURES APPLICATIONS. Technical data sheet SSW - STEEL STRONG-WALL FOR TIMBER FRAME RACKING RESISTANCE.

Masonry and Cold-Formed Steel Requirements

Elevated Slab Sequence

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2013

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

TABLE OF CONTENTS. 0 Structural calculations 0.1 General 0.2 Safety concept 0.3 Calculations for waterfront structures

Residential Deck Safety, Construction and Repair. Juneau Permit Center, 4 th Floor Marine View Center,(907) February 2016

WESTPRO PORTUS Use of RD Piles for Marine Construction

Steel Floor Framing Solutions

Statement of Special Inspections 2013 CBC

The construction technology of Chongqing Chaotianmen Bridge

Purna Fashions Ltd. RH Attire Ltd

Metal Web Floor System

TECHNICAL SPECIFICATION

Racking Solutions for Timber Framed Buildings T-RS-UK Edition. +44 (0)

THE CONCISE GUIDE TO MASONRY REPAIRS

TRITEC light Steel Panel Formwork

twenty seven concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

Innovative Construction Technology

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

PRECAST CONCRETE GIRDER ERECTION

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program

Building Department Informational Handout

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

Recommended Good Practice

Technical Notes 11B - Guide Specifications for Brick Masonry, Part 3 Rev [Feb. 1972] (Reissued Sept. 1988) INTRODUCTION

Steel Forming System BROCHURE. A durable, all-steel forming system that is ideal for pier caps and self-spanning applications.

Note on the assessment:

Project Address: Name of Person Completing Form:

Construction Details 5-37

GMS Composite Ltd. Shardagonj, Kashimpur,Gazipur,Bangladesh ( , ) 22 March 2014

CHAPTER III METHODS AND MATERIALS

Accelerated Bridge Construction in USA

TITEN HD Heavy Duty Screw Anchor for Concrete & Masonry

Student Services & Classroom Addition SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

fischer Test Report Fixing Tests for

A-BEAM W Erection Manual 2

BY DAYTON SUPERIOR. Max-A-Form FORMING SYSTEM

FOUNDATIONS. Foundations Copyright G G Schierle, 2006 Press Esc to end, for next, for previous slide 1

Design of Column Base Plates

Site Preparation... 2

Introduction. Structures may be classified on the basis of materials used for construction, as follows: Steel structures. Aluminium structures

TR ANSMISSION AND SUBSTATION FOUNDATIONS

SECTION ALUMINUM WALKWAY COVERS. A. The requirements of Division 1 specifications shall apply to work specified in the section.

fischer Test Report Fixing Tests for Bison Hollow Core Slabs

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

PERI PD 8 The cost-effective shoring for slab tables and high loads

Garage Beam System DAYTONSUPERIOR.COM FORMING. For Post-Tensioned Beam and Slab Parking Structures

Contents EN :2008+A1:2011 (E) Page

lindab we simplify construction LindabSandwichPanels Installation instructions Mineral Wool Panels

The Construction of the Langham Place in Mong Kok An Introduction

VOLUNTARY - EARTHQUAKE HAZARD REDUCTION IN EXISTING HILLSIDE BUILDINGS (Division 94 Added by Ord. No. 171,258, Eff. 8/30/96.)

Earth Retaining System

Bonner Bridge Replacement Update:

Soldier Pile Walls Soil Nail Systems Secant Piling Soil Mix Walls Underpinning Slope Stabilization

INDEX FM Page

Plot Plan for Decks Date. Name Phone # Address Zip APN # _- _- _ (see property tax bill or call the assessor s office ) FRONT PROPERTY LINE

SEISMIC RESTRAINT SYSTEM

Typical Deck Details. Shenandoah County, Virginia. Based on the 2012 Virginia Residential Code

RapidBrace Installation Guide

elegrodeck Decking Installation Guide MATERIALS LIST Joist Spacing Installing the Decking Boards

Civil Engineering Construction I (CBE5031)

Transcription:

SCREW PILE APPLICATION SHEETS Advantages of screw piles Exceptionally fast installation rate up to 2... linear metres of pile installed per minute Load bearing capacities of over 300kN SWL Load bearing capacity is equal in tension.. and compression ideal for variable load...situations Requires only lightweight installation equipment can operate on soft terrain without the need for piling mats Ideal for restricted access sites and useable...where headroom is limited and even from...floating platforms Installs to laser level accuracy, within +/-...3mm tolerance necessary for modular...construction Minimal noise and vibration, with little...disturbance of the soil Environmentally friendly as no grouting required and can be reused or recycled perfect for temporary structures No removal of spoil, and no casing or dewatering required well suited for contaminated ground Resistant to desiccation or heave Sustains load immediately after installation enables rapid assembly of offsite construction Thick walled tube and galvanizing provides a truly permanent foundation

OAK FRAMED STRUCTURES Housing Garages Barn conversions Conservatories s At least 30 piles per day Tension & compression connection Totally dry installation Restricted access use Positive connection No curing time required Method (Concrete pile cap free system) Screw piles are installed to the required depth based on load requirements and geological conditions, using a torque motor attached to a 5 ton excavator. Once each screw pile reaches the correct level, the torque motor is removed from the pile and a circular termination cap is fitted. A reciprocal circular termination cap is fitted into a pre-cut slot in the end of the oak post and is fixed by inserting 3no. dowels. The post then sits directly on top of the screw pile termination cap where it is attached using 4no. M20 bolts.

TIMBER STRUCTURES Garden offices Holiday cabins Pavilions School buildings Visitor centres Completion within 1 week Loads up to 180kN SWL No piling mat required Totally dry installation No muck-away required Build off immediately Method (Machine profiled log structure for a school) The topsoil is stripped back and a vegetation barrier installed, if needed. Using a 5 ton excavator, a grid of screw piles is installed to approximately 100mm above ground. Termination caps and self-levelling shoes are then fitted to the grid of piles. A timber ground beam is then assembled on top of the self-levelling shoes. Finally, the timber connection plates are bolted and screwed to both the perimeter termination caps and the timber ground beam to provide additional lateral restraint. A timber cassette floor or similar can then be mounted straight onto the timber joists.

SCREW PILE FOUNDATIONS FOR CLOSED PANEL TIMBER FRAME BUILDINGS Working in partnership with: Garden offices Garages Extensions Self-build housing Holiday accommodation Lower embodied energy Completion within 1 week Loads up to 150kN SWL No piling mat required Totally dry installation No muck-away required Build off immediately Method (Gluelam( timber ground beam construction) The topsoil is stripped back and a vegetation barrier installed, if needed. Using a 5 ton excavator, a grid of screw piles is installed to approximately 100mm above ground. Termination caps are then fitted to the grid of piles. A timber ground beam is then assembled on top where timber connection plates are bolted and screwed to both the perimeter termination caps and the timber ground beam to provide additional lateral restraint. A timber cassette floor or similar can then be mounted straight onto the timber joists. Where isolated column loads exist (see above), piles have a cast in situ RC pile cap formed, ready to receive the column (timber, block-work or reinforced concrete).

CONTAINERISED BUILDINGS Medical structures Hotel accommodation Temporary buildings Construction site offices Up to 30 piles per day Up to 180kN SWL Speed of installation No ground beams required Readily removable Potentially reusable Method Using a standard 5 ton excavator, screw piles are installed to precise levels at predetermined locations. Pre-cast or cast-in-situ pile caps are then constructed. Lateral restraint is not required as the structural design of the containers provides for this, saving the additional expense in the formation of ground beams. The buildings are then delivered to site and craned into position with the skids from the containers sitting directly on the pile caps (which can be formed partially above ground especially on sloping sites). The system is ideal for temporary structures as the piles can be unscrewed after use and are potentially reusable for the next project.

FOUNDATION REINFORCEMENT Subsidence Foundation repair Storey extensions Loft extensions Up to 20 piles per day Cantilevered needles Up to 180kN SWL No internal works Laser level accuracy Restricted access use Works can be carried out. with occupancy Method 1.75m trenches are dug at 2m intervals, including localised excavation of the existing footing in preparation for the needle formation. Two screw piles are installed in each trench, offset by 500mm and 1500mm from the centre line of the wall being supported. A termination cap is then bolted to each pile ready for the formation of a reinforced concrete needle in the trench. The piles take compressive and tensile loads so that all works can be carried out externally, allowing continued occupancy of the building. Once the needles have cured, the brickwork immediately above is removed between each needle to allow installation of a pre-cast lintel or steel beam to span the loads. Alternatively, a masonry beam can be formed within two beds of chopped out mortar, 4 to 6 courses of brickwork apart, using grouted-in helical steel reinforcing rods.

MARINE CONSTRUCTION Jetties Boardwalks Pontoon Guides Moorings Up to 3m spacing 3 to 5 ton excavator Square termination cap Timber or GRP frame Minimal access required No floating working...platforms required Laser level accuracy No muck-away required Build off immediately Method (Jetties) Using a standard 3 to 5 ton excavator, the first four screw piles are installed from the side of the marina until the appropriate torque and level is reached, after which a frame is constructed over the top from the edge of the marina. The excavator then moves out onto the newly-created frame and installs the next set of piles, whereupon another frame is added and the process repeated until the full length of the jetty is created. The machine is then removed and the final surface of the jetty is installed (normally a GRP-wood composite offering increased longevity).

SCREW ANCHORING Lateral loads on foundations Excavated wall tie-backs Soil nailing Embankment stabilization Retaining walls Method (Tie-backs) 38.1mm SSS screw pile 5 to 7 ton tracked rig Up to 30 anchors per day Dry installation Up to 165kN SWL Initial excavation of the ground takes place reducing the level by up to 1.5m. At regular intervals, tension piles are installed at an inclination into the side of the newly-formed bank, using a standard tracked rig with a torque motor attached to a rotating mast. Universal steel columns are then installed vertically at each anchor location, with slots to receive the end of the tension pile, and pattress plates are then fitted to provide the tensional restraint of the column. Finally, sleepers are installed into the columns to complete the lateral restraint of the excavated earth wall. The process is repeated for each further reduction in level. Each time sleepers will be inserted into the columns from the top, pushing the existing ones into the latest set of columns at the base of the wall. No grouting required Minimal noise/vibration High load capability No reliance on skin friction Restrains immediately

MAST CONSTRUCTION Telecommunications Wind turbines Rail infrastructure Signal posts Matrix columns Installed in one day Up to 180kN SWL Restrains variable loads Laser level accuracy Restricted access use Totally dry installation No curing time required Method (Telecommunication) Using a standard 5 ton excavator, screw piles are installed to precise levels at predetermined locations. A steel grillage is then attached using bolting arrangements which enable it to withstand the variable compressive and tensile loads and the overturning moments associated with mast construction. In the example shown above, piles are installed at a raked angle to increase performance. The mast can be lifted into position immediately after the grillage has been attached, allowing a very swift installation, without the need for curing time and a further visit to site.

MEZZANINE FLOOR CONSTRUCTION Retail stores Car decks Office extensions Commercial buildings 3 ton excavator Live working environment Inside existing buildings Up to 150kN SWL No spoil created Laser level accuracy Restricted access use Totally dry installation Method (Retail store) Using a standard 3 ton excavator working in a live store at night, screw piles are installed into a pre-excavated holes through the existing floor without creating any spoil, vibration or requiring the use of grout. Reinforced concrete pile caps are then formed and a temporary steel plate is placed on top to protect the plate whist the pile cap cures. The steel frame can then be erected after 7 days curing. Screw piles are best suited to mezzanine floor construction as CFA creates spoil which has to be removed from within an existing store and steel cased driven through vibration may cause damage to existing foundation and the building itself, both piling systems also require grouting adding further cost to the remediation of the site once piling has taken place.