Excavation Equipment: Shovel

Similar documents
Hydraulic Excavators

Excavating and Lifting

SIMULATION OF CONSTRUCTION OPERATION WITH DIRECT INPUTS OF PHYSICAL FACTORS Simulation with first-order factors

SAN ANTONIO WATER SYSTEM P. O. BOX 2449 SAN ANTONIO, TEXAS TABULATION OF BIDS

CITY OF LETHBRIDGE SECTION Construction Specifications SIDEWALK CONSTRUCTION PAGE 1 of 5

B209 - EMBANKMENTS OVER SWAMPS AND COMPRESSIBLE SOILS - OPSS 209. Excavation method means to remove the swamp material mechanically.

CIVIL ENGINEERING CONSTRUCTION SBC2253

A FRAMEWORK FOR APPLICATION OF GENETIC ALGORITHM IN PRODUCTIVITY OPTIMIZATION OF HIGHWAY EQUIPMENTS USING EVOLVER SOFTWARE

PAVEMENT MATERIALS AND CONSTRUCTION

1 Exam Prep Walker's Guide to Estimating Questions and Answers

International Journal of Advance Engineering and Research Development ASSESSMENT OF FACTORS AFFECTING PRODUCTIVITY OF EXCAVATOR

LABOR AND MATERIAL PROPOSAL

Site Investigation. Economic Haul. Machine Selection. Machine Selection. Machine Selection. Case Scenario. C Existing I-70

IDENTIFICATION OF FAILURE SURFACES IN DRAGLINE DUMPS OF OPENCAST COAL MINES

Buckets. and Other Attachments

Excavation &Trenching

- Earthwork Operations & Equipments

Dredging and Dredged Material Disposal Overview

How to Estimate the Cost of a Rammed Aggregate Pier Foundation System. By: Robert Daniel Brosius, Jr. December 15, 2010

Load & Haul. Practical Cost Reduction Volvo Construction Equipment

Impact of Blast Fragmentation on Truck Shovel Fleet Performance

Chapter 10. Pipeline Installation

Lecture 1: Course Introduction

MANUFACTURERS OF HIGH QUALITY CRUSHING, SCREENING AND MATERIALS HANDLING SOLUTIONS FOR THE WORLD MINING, AGGREGATE AND RECYCLING INDUSTRIES

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

COST AND PRODUCTIVITY ANALYSIS OF EQUIPMENTS FOR FLEXIBLE PAVEMENT- A CASE STUDY

ROCK HAWG TECHNOLOGY. Hardcore Solutions for the Toughest Applications

Riprap must be placed uniformly and carefully to eliminate any weak area where erosion can get a start.

Considerations for Environmental Dredging of Contaminated Sediments. Michael R. Palermo, PhD, PE

Annex X Comprehensive Baseline Cost Estimate

J.F. Brennan Co., Inc. FULL SERVICE MARINE CONTRACTOR Lock and Dam Construction Hydraulic Dredging & Dewatering Specialty Construction and Diving

CONSTRUCTION SPECIFICATION FOR BORROW

Earthwork Basics and a Traditional Calculation Method

Appendix E8. Open Pit Loss and Dilution

Environmental Dredging Equipment and Processes. (Tab D)

Construction Technology L 4 (Engineering Fundamentals of Moving Earth)

SECTION ROCK REMOVAL

DEPARTMENT OF ENVIRONMENTAL QUALITY LAND QUALITY DIVISION

DETENTION, RETENTION AND RECHARGE STRUCTURES

Section 2: Mineral Exploration and Mining

100% Payment. 105% Payment #

Excavation. Stages. Surprises

Meuangvang Development Co.LTD Standard Working Procedure 046 Operation of a Excavator

Optimisation of Overburden Blasts at Glencore Ulan Surface Coal Operations

attachment guide Excavators Skid Steer Loaders Multi-Terrain Loaders

(Construction) Level 2 NVQ Diploma in Plant Operations (Cranes and Specialist Lifting) Level 2 NVQ Diploma in Plant Operations (Extracting)

BRUKS 805 STC NEW CONCEPT IN NORTH AMERICAN MOBILE CHIPPING

Brevard Contractors School

ERT 464 DESIGN OF MACHINE AND SYSTEM

The Mining Industry in Canada. By: Cameron Duhn, Jeremy Etmanski and Brandon Hallam

Optima Dipper Systems Product Overview

Contractor Experience with Precast Bridge Elements in Utah. Eric Wells. Granite Construction

1 HB By Representative Greer. 4 RFD: Transportation, Utilities and Infrastructure. 5 First Read: 03-MAR-15. Page 0

SUSTAINABLE FOUNDATION ENGINEERING MIXED-IN- PLACE TECHNIQUES FOR DURABLE CUT-OFF WALLS

ISO INTERNATIONAL STANDARD. Earth-moving machinery Cable excavators Terminology and commercial specifications

The headquarters of The General Auditing Bureau

Excavator Attachments. Product Range

State of Nevada Department of Transportation Materials Division

1.02 RELATED WORK: Refer to the following sections for related work: Section 4000-Concrete Materials and Methods

Lignite Mining and Reclamation Process. Kayla Torgerson The Coteau Properties Co.

MINING EQUIPMENT FOR MINES IN REK BITOLA

MICHIGAN TEST METHOD FOR STANDARD PRACTICE OF SAMPLING HMA PAVING MIXTURES

2.1.4 PROJECT CONSTRUCTION

The economics of extended pre-strip stripping

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Percent Passing by Weight. 105% Payment #200

USE OF TRENCH DRAINS TO IMPROVE CHRONIC EMBANKMENT STABILITY PROBLEMS. and SHANNON & WILSON, INC. ABSTRACT

How Phosphate is Mined and Processed

MINING IN A DAY OPERATIONAL EFFICIENCY AND IMPROVEMENTS. 20 TH April, 2017 Presented by: Sean T. Pellow

RIIMPO319A Conduct backhoe/loader operations Unit descriptor. Employability skills Application of the unit. Competency field

MUCKPILE SHAPING FOR DRAGLINES AND DOZERS AT SURFACE COAL MINES


CONSTRUCTION SPECIFICATION FOR BORROW

15th- 18th February 2012 Gujarat University Exhibition Centre Ahmedabad, India

Cohoe Radio Observatory, Alaska ~ Part 2, Guyed Tower Foundation Construction Whitham D. Reeve

On-site Assessment (OSA) Contents

29 CFR 1926 Construction Subpart P

AN ADVISORY SYSTEM FOR SCRAPER SELECTION. A Thesis JOHN CHARLES MAYFIELD

SCHEDULE OF RATES DAM AND ALLIED WORKS REFERENCE DATA NOTES ON BASIC RATES DATA FOR SCHEDULE OF RATES

SECTION 28 AGGREGATE BASE COURSE (FAA P-208) [For base course under runway and taxiway surfaces, use Section 29, FAA Item P-209.]

Timber Sale Appraisal Iron Mountain Sale WL W

Topic #4 Soil Compaction

Production, consumption and cost

Department of Administration State Construction Office SITE PREPARATION AND GRADING CRITERIA

Appropriate Storage Manure Handling Recycling or Disposing Protecting ti Water Quality

BID #KP10011 SERVICES TO INSTALL UNDERGROUND CONDUIT TERM CONTRACT

NZQA Expiring unit standard version 3 Page 1 of 6

DIVISION 4100 SITEWORK

Geotechnical Investigation Long Timber Brewing Building Highway 99 and Kelly Street Monroe, Oregon TABLE OF CONTENTS

Total Automatic Excavation System for TBMs Takayoshi Nakayama, Satoshi Inoue, Yasuhide Seno Kansai Branch, Okumura Corporation ABSTRACT

Section Excavation Tender No. [ ] Page 1

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Appendix D General Earthwork and Grading Specifications for Rough Grading

SECTION TRENCHING, BACKFILLING AND COMPACTION. B. Provide necessary sheeting, shoring and bracing.

Civil Geotechnical Surveying

Detailed Estimating-Introduction. Dr. Al-Hammad

Friction Reduction of Unlined Power Tunnels for Increased Power and Energy Production

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

Northwest Oil Drain Canal: Sediment Remediation Using Bypass and Excavation TEAL DREHER, ROB WEBB, PAUL FUGLEVAND DALTON, OLMSTED & FUGLEVAND, INC.

CHAPTER 3 LOGISTICAL CONSIDERATIONS

Transcription:

Arab Academy for Science, Technology & Maritime Transport College of Engineering & Technology Construction & Building Engineering CB 524 Methods and Equipment for Construction 2 Excavation Equipment: Shovel Spring, 2015 Instructor: Ahmed Elyamany Courtesy of Dr. Ahmed Alhady

EXCAVATORS TYPES There are two types of excavators: 1-Front Shovel (power shovel): To excavate usually in levels higher than the ground level. 2-Back Shovel (back Hoe): To excavate usually in levels lower than the ground level. Two types based on control method: Cable control. Hydraulic control. 2

EXCAVATORS TYPES 3

EXCAVATORS MOUNTING TYPES 4

EXCAVATORS MOUNTING TYPES 5

EXCAVATORS: FRONT SHOVEL 6

EXCAVATORS: FRONT SHOVEL 7

EXCAVATORS: FRONT SHOVEL 8

EXCAVATORS: FRONT SHOVEL USES Excavating (advantage: face excavation due to its strong hydraulic power, especially for hard materials). (disadvantage: under ground level excavation due to water table and soil conditions). Loading trucks. Operating in cut and fill. Wide area excavation. Forming heaps. Trench excavation. (Backhoe or trencher are better). Loading soils. (Dragline and clamshell are better). Excavate under ground level. (Backhoe is better). 9

EXCAVATORS: FRONT SHOVEL OPERATION METHODS 10

EXCAVATORS: FRONT SHOVEL PRODUCTIVITY FACTORS: 11

EXCAVATORS: FRONT SHOVEL Productivity Factors 1. Front Shovel Bucket Capacity: There are two major capacities for the front shovel bucket: 1. Struck Capacity(SC). 2. Heaped Capacity(HC). HC=1.15SC. 12

EXCAVATORS: FRONT SHOVEL Productivity Factors 1. Front Shovel Bucket Capacity: Bucketfillfactor 13

EXCAVATORS: FRONT SHOVEL Productivity Factors 1. Front Shovel Bucket Capacity: EXAMPLE 1: A 2 cy hydraulic front shovel is excavating in common earth. What is the excavator practical capacity in m 3 ( Bank Measure)? Take the lower value for the bucket (dipper) fill factor. Solution: Based on Table 8.1, k = 1.0 Based on a given table (conversion factor), f = 0.8 (from loose to bank measure). Then, capacity = 2 cu yd*0.76(m3/cy)*0.8(f)*1.0(k) = 1.216 m 3 BM 14

EXCAVATORS: FRONT SHOVEL Productivity Factors 2.HEIGHTOFCUT Optimum height of cut is defined as the height that will result in a full dipper (bucket) in one pass. If the height of cut shallow, the bucket does notfillupinonepass.tosolvethisproblem: a) Apply more pressure. b) Make two passes. 15

EXCAVATORS: FRONT SHOVEL Productivity Factors 2.HEIGHTOFCUT If it is higher than the optimum, then, the bucket will be filled before pass completion. To solve this problem: a) Apply less pressure on the bucket. b) Dig upper part first, then, clean bottom part later. 16

EXCAVATORS: FRONT SHOVEL Productivity Factors 2.HEIGHTOFCUT Percent of optimum height(poh): POH = Optimum height = (30% - 50%) of max. digging height for the shovel. 17

EXCAVATORS: FRONT SHOVEL Productivity Factors 2.HEIGHTOFCUT The optimum height is 30% of max. digging height for material that is easy to excavate andload,suchasloam,sand,orgravel. The optimum height is 40% of the max. digging height for Common earth. The optimum height is 50% of the max. digging height for tough materials, such as stick clay or blasted rock. 18

EXCAVATORS: FRONT SHOVEL Productivity Factors 3.ANGLEOFSWING Angle of swing of a shovel is the horizontal angle, expressed in degrees, between the position of the bucket when it is excavating and the position where it discharges the load. The total cycle time includes digging, swing to the dumping position, dumping, and returning to the digging position. Increasing the swing angle will increase the cycle time and vice versa. 19

EXCAVATORS: FRONT SHOVEL Productivity Factors 20

EXCAVATORS: FRONT SHOVEL Productivity Factors OTHER FACTORS Size of hauling units should be 5-6 times as large as shovel bucket volume. Conditions of the shovel itself has a very big effect on productivity. Operator skills plays a good role in affecting shovel productivity. Similarly, job & management conditions affects greatly the shovel productivity. 21

EXCAVATORS: FRONT SHOVEL Selection The front shovel should be selected according to two major factors: 1. Excavated material cost per cubic yard: a)jobsize. b) Transportation expenses. c) Excavating and blasting cost. d) Fixed costs. e) Wages. 2. Job conditions in which the shovel will operate. 22

EXCAVATORS Front Shovel -Selection 23

EXCAVATORS: FRONT SHOVEL GENERAL OUPUT MODEL(GOM) Hourly output(cy/hr or m3/hr) = P = (3600 *Q * f * k* f 1 * f 2 * t)/ct Where;k=bucketfillfactor(Table8.1). P=productivityincy/hrorm 3 /hr. Q=bucketcapacityinloosecyorm 3. f = earth volume change conversion factor. f 1 =swing-depthfactor(table8.2). f 2 =jobandmanagementconditions. t = operating time factor. CT=cycletimeinseconds. 24

EXCAVATORS FRONT SHOVEL Example 2 A hydraulic excavator excavating bank clay has a heaped capacity of 1.5 cu yd. Its maximum digging height is given by the manufacturer as 7 m. The average angle of swing is 120. The average height of cut is 2.94 m. The operating time is expected to be 50 min per hr. Management and job conditions are assumed to be fair. What is the hourly rate of productioninm 3 bm/hr,iftheshovel'scycletimeis19 seconds? Take the shovel's optimum height of cut as equal to 30% of its maximum digging height. Take the smallest applicable value for the bucket fill factor. 25

EXCAVATORS FRONT SHOVEL Example 2 Parameters in the GOB model: Capacity:Q=1.50x0.76=1.14m3loosemeasure Earth volume change conversion factor from loose tobm(fromtableinhandouts):f=0.79 CycletimeCT=19sec Optimumheightofcut=7.00x0.30=2.10m Percentofoptimumheight:=2.94x100/2.10=140% Depth-swing factor(from table 8.2): f 1 =0.81 26

EXCAVATORS FRONT SHOVEL Example 2 Job and management efficiency factor (from table in the handouts): f2= 0.65 Bucketfillfactor(fromtable8.1):k=1.00 Operatingtimefactor:t=50/60=0.83 RateofoutputwithGOMmodel: P=(3600*Q*f*K*f1*f2*t)/CT= =(3,600*1.14*0.79*1.00*0.65*0.81*0.83)/19 = =74.57m3bm/hr. 27

EXCAVATORS FRONT SHOVEL Example 3 2,300 m 3 of bulk pit excavation is composed of common earth. The excavation period given in the contract is 3 days. The contractor has to account for 20% bad weather andworkingtimeof8hrs/day.theaveragedepthofcutis 3.00 m whereas the average angle of swing will be 60. Job and management conditions are expected to be good. The operating time is 50 min/hr. Excavator bucket capacity Maximum digging heights Estimated cycle times for this Job Hourly costs of owning and operating 1.75 cy 10.0 m 24 sec $35/hr 2.00 cy 13.0 m 25 sec $40/hr 2.50 cy 14.5 m 26 sec $45/hr 3.00 cy 15.5 m 27 sec $50/hr 28

EXCAVATORS FRONT SHOVEL Example 3 Questions: 1. Select the right size of power. The optimum height of cut in this operation that involves relatively soft material is to be taken as 30% of the maximum digging height of the excavator. Take the smallest applicable bucket fill factor(k). 2.Whatistheunitcostofexcavation? 29

EXCAVATORS FRONT SHOVEL Example 3 (3.1)Totalworkingtime=3days@8hrs/day=24hours Net working time (excluding bad weather) = 24 hrs x 0.80 = 19.20 Hours RequiredhourIyoutput=2,300m 3 /19.20hrs= 119.79m 3 bm/hr Using the GOM model: Try1.75cuydfrontshovel: Capacity:Q=1.75(cy)x0.76(m3/cy)=1.33m 3 loose Earth volume change conversion factor from loose to bm (from handouts):f=0.80 Bucketfillfactor(fromtable8.1):K=1.00 Optimumheightofcut=10.00x0.30=3.00m Percentofoptimumheight=3.00x100/3.00=100% 30

EXCAVATORS FRONT SHOVEL Example 3 Depth-swingfactor(fromtable8.2):f1=1.16 Jobandmanagementefficiencyfactor(fromhandouts):f 2 =0.75 Operatingtimefactor:t=50/60=0.83 RateofoutputwithGOMmodel: P=3,600*Q*f*K*f 1 *f 2 *t/ct= P=3,600x1.33x0.80x1.00x1.16x0.75x0.83/24=115.25m 3 bm/hr. Since the rate of output (115.25 m 3 bm/hr) does not satisfy the required rate of output (119.79 m 3 bm/hr), the 1 3/4 cu yd front shovel is not appropriate. 31

EXCAVATORS FRONT SHOVEL Example 3 Try2.0cuydfrontshovel: Capacity:Q=2.00x0.76=1.52m 3 loose Earth volume change conversion factor from loose to bm (from handouts): f = 0.80 Bucketfillfactor(fromtable8.1):K=1.00 Optimumheightofcut=13.00x0.30=3.90m Percentofoptimumheight=3.00x100/3.90=77% Depth-swingfactor(fromtable8.2):f 1 =1.11 Job and management efficiency factor (from handouts): f 2 =0.75 32

EXCAVATORS FRONT SHOVEL Example 3 Operatingtimefactor:t=50/60=0.83 RateofoutputwithGOMmodel: P=3,600*Q*f*K*f 1 *f 2 *t/ct= P=3,600x1.52x0.80x1.00x1.11x0.75x0.83/25=120.99m 3 bm/hr. Since the rate of output (120.99 m 3 bm/hr) does satisfy the required rate of output (119.79 m 3 bm/hr), the 2.00 cu yd front shovel is appropriate. (3.2) Unit cost of operation = 40 $/hr / 120.99 m 3 bm/hr = $0.33 per m 3 bm 33

Thank You 34