The challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment

Similar documents
8. Risk Assessment Process

Joint Industry Programme on E&P Sound and Marine Life - Phase III

Collecting environmental baseline knowledge: the importance of partnerships and transparency

Section 4 Environmental Impact Assessment Framework

Known and potential impacts of deep sea mining and oil and gas exploration

Barossa Gas Export Pipeline Installation

6 Risk assessment methodology

Central Eyre Iron Project Infrastructure, Eyre Peninsula, SA (EPBC 2014/7285)

Oceans Act: Doing more than the EPBC Act?

6. COMMUNI TY AND S TAKEH OLD ER CON SU LTATI ON

Document ID: ABU Revision ID: 1.0 Revision Date: 10 October 2018 Next Revision Due: N/A Information Sensitivity: Public

Maintenance Dredging 2015 Environmental Monitoring Report

7 MONITORING PLAN 7.1 INTRODUCTION

14. ENVIRON MEN TA L I MPAC T ASSE S SMEN T - INTE GR ATIN G FACTOR - OF FSE TS

STRATEGIC DIRECTIONS

PART 2 Tabs EIS General Comments

Australian Network of Environmental Defender s Offices

Commonwealth Lands and Activities of the Commonwealth and Commonwealth Agencies

AMRUN Project Draft Maintenance Dredging Management Plan Port Independent Peer Review

4. Development Alternatives

U.S. ATLANTIC OCS GEOPHYSICAL SURVEYS: What are Seismic Surveys and How are They Done?

Garry Middle. Associate Professor, Department of Urban and Regional Planning, Curtin University of Technology, Perth WA

Australian EIA Practitioners views on addressing climate change

Compliance Assessment Report 2017: Ministerial Implementation Statement No. 873

Anthropogenic underwater noise pressures

Jemena Northern Gas Pipeline Pty Ltd

Section 20. Conclusions

Adani Appendix F1 Guidelines Cross Reference Table

Conserving Marine Environment towards the Sustainability of Marine Resources for Food Security

Protection of Ramsar Wetlands under the EPBC Act

Emerging long term effects:

ENVIRONMENTAL IMPACT ASSESSMENT (BASIC ASSESSMENT) PROCESS: PROPOSED REVERSE OSMOSIS PLANT, IRON ORE HANDLING FACILITY, PORT OF SALDANHA

Protection of World Heritage Properties under the EPBC Act

3 APPROACH TO EIA PROCESS AND PUBLIC PARTICIPATION

HOW OIL AND GAS COMPANIES WILL APPROACH THE ESIA PROCESS Mitigating potential impacts

Gorgon Gas Development and Jansz Feed Gas Pipeline

Bioacoustics Research. Dr Paul Lepper - Loughborough University

AT A GLANCE. Cairns Shipping Development Project. Revised Draft Environmental Impact Statement Fact Sheet July 2017.

Underwater Sound/Marine Environment Update

PART A INTRODUCTION TO THE AEIS 1. PURPOSE OF THE ADDITIONAL

Guidelines for Expressions of Interest and Applications

2. General Information

Section 3. Legislative Framework and Impact Assessment Process

About WCC LNG Project Ltd.

NSW MINING Health, Safety, Environment & Community

Submission on the draft terms of reference for Balaclava Island Coal Export Terminal project

Environmental and Social Impact Assessment (ESIA) for Oil & Gas Projects, a Myanmar Context

Ecosystem Based Fisheries Management from concept to practice: Australia, a case study. By Helen Webb BA

6 IMPACT ASSESSMENT METHOD

The key contact for this proposal is Belinda Bastow (AngloGold), Environmental Manager Exploration/ Tropicana:

Mauritania a model response planning process

With respect to the assessment of effects, we must question some key components of the amendment proposal.

Pluto LNG Annual Compliance Report 2017

SUBMISSION GUIDE ECOLOGICALLY SUSTAINABLE DEVELOPMENT. May

2012 Code of Conduct for Minimising Acoustic Disturbance to Marine Mammals from Seismic Survey Operations

Environmental Impact Assessment (EIA) for Oil & Gas and Power Projects

International Symposium on Integrated Coastal Management for Marine Biodiversity in Asia, January 14-15, 2010, Kyoto, Japan

Gorgon Project Update

Contents. Non-Technical Summary. 1. Introduction. 2. Policy, Regulatory and Administrative Framework. 3. Impact Assessment Methodology

Hot Topics in Environmental Compliance

4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

Capacity building for biodiversity and Impact Assessment

3. LEGISLATIVE FRAMEWORK

Technical Officer, Coastal & Marine Conservation Project. Cambodia Programme. Application Pack. Innovative conservation since 1903

Conservation and Management of Marine Fauna. Responsibilities and Priorities. Kelly Waples Marine Science Program DEC

Strategic environmental assessment: What is it and what makes it effective?

Table 1. Introductory Courses Checklist (minimum of 3 credit hours from the following list)

7. Value Management Workshop

Scoping Document. for the. Strategic Environmental Assessment. for Exploration Activities. on the Southwestern Scotian Slope

Edithvale and Bonbeach Level Crossing removal project. Report of Dr Anthony Smith

RE: TGS-NOPEC s EIA for the NEG15 seismic survey

CHAPTER 7 STAKEHOLDER ENGAGEMENT

Experience from the UK: Monitoring, Modelling and Uncertainty

4 ADMINISTRATIVE FRAMEWORK 4.1 INTRODUCTION

Scoping Document for the Environmental Assessment. BP Exploration (Canada) Ltd. Tangier 3D Seismic Survey

A POSITIVE FUTURE FOR PORPOISES AND RENEWABLES. Assessing the benefits of noise reduction to harbour porpoises during offshore wind farm construction.

The overall objectives of the monitoring activities are to:

Urban Development Institute of Australia Western Australian Division Incorporated

Energy Development in the Outer Continental Shelf Environmental Consideration

COAL AND COAL SEAM GAS REGULATION

Statement of Canadian Practice with respect to the Mitigation of Seismic Sound in the Marine Environment

The Environmental Agency for the Mineral Resources Area (EAMRA) Jesper Bistrup Larsen. RE: TGS-NOPEC s EIA for the SEG15 seismic survey

Re: Significant New Information Requires a New Programmatic Environmental Impact Statement for Atlantic Geological and Geophysical Activities

Environmental Impact Assessment in Western Australia

RURAL ECONOMY AND CONNECTIVITY COMMITTEE SALMON FARMING IN SCOTLAND SUBMISSION FROM SCOTTISH NATURAL HERITAGE

4.1.1 Best Practices for Agency Coordination

GUIDELINES FOR MINIMISING ACOUSTIC DISTURBANCE TO MARINE MAMMALS FROM SEISMIC SURVEYS. April 2004

Conditions of Approval for the MDP for the brickworks at Perth Airport

INTERIOR S PLAN FOR A COORDINATED, SCIENCE-BASED RESPONSE TO CLIMATE CHANGE IMPACTS ON OUR LAND, WATER, and WILDLIFE RESOURCES

Scoping Document. for the. Strategic Environmental Assessment. for Exploration Activities. on the Southwestern Scotian Slope

Update on the implementation of EU nature, marine and fisheries policies relevant for ASCOBANS activities

MARINE FARMING PLANNING IN TASMANIA THE PERSPECTIVE OF THE PLANNING AUTHORITY

To improve the health of Indigenous people living in remote communities by improving access to a nutritious and affordable food supply.

Urban Development Institute of Australia Western Australian Division Incorporated

Activities. I. Introduction

Contents. ACKNOWLEDGEMENTS...i. TABLE OF CONTENTS...ii INTRODUCTION...1 METHODS...1 RESULTS...6 CONCLUSIONS REFERENCES... 10

Review into processes associated with aircraft noise management. December 2017

RESEARCH PRIORITIES FOR 2016

We invite you to find out more at careers.conocophillips.com

Biodiversity of the Kimberley

Transcription:

The challenges and complexities of impact assessment for a seismic survey in a remote coral reef environment J.G. Colman 1,2, C.C. Grebe 1 & R.L. Hearn 1 1 Woodside Energy Ltd (cameron.grebe@woodside.com.au, robert.hearn@woodside.com.au) 2 Current affiliation: Galaxia Marine Environmental Consulting Pty Ltd (galaxia@westnet.com.au) Abstract In 2007, Woodside Energy Ltd conducted a three-dimensional marine seismic survey (Maxima 3D MSS) at Scott Reef, approximately 425 kilometres north-west of Broome in Western Australia. This paper describes the challenges and complexities of impact assessment, management and mitigation as well as the regulatory approvals process for this survey. The identification and evaluation of potential impacts from the survey were primarily dealt with in an Environmental Protection Statement (EPS) under the Western Australian environmental approvals process. Engagement with a wide range of stakeholders as part of the approvals process highlighted some inherent uncertainties in the preliminary environmental impact assessment (EIA). These uncertainties were required to be addressed under Ministerial approval conditions. A plan for a field verification study, to validate impact predictions and modelling included in the impact assessment document, was developed. The field study presented major resourcing and management challenges, with the health and safety of personnel of paramount concern. At its peak, the activity involved 123 people and eight vessels operating in a remote offshore location. The challenge of maintaining safe operations, while balancing schedules and scientific and statistical rigour, was successfully met. Field results were incorporated into an adaptive management programme to ensure actual impacts during the execution of the survey did not exceed those predicted. Protection of the environment was demonstrated while enabling a business-critical activity to proceed as planned. Background In September 2007, Woodside Energy Ltd (Woodside) commenced a three-dimensional marine seismic survey (Maxima 3D MSS) to cover an area of approximately 362 square kilometres in both State and Commonwealth waters over Scott Reef, which is an emergent shelf atoll, situated in the Browse Basin approximately 425 kilometres north-west of Broome in Western Australia. Acquisition of this survey was the culmination of an extremely complex and resource-intensive process that spanned a period of over 12 months. It encompassed formal regulatory approvals at State and Commonwealth levels, extensive stakeholder engagement, and a suite of research and monitoring studies to address uncertainties arising from the environmental impact assessment (EIA). This paper does not set out to report on the results of the studies conducted in support of the Maxima 3D MSS, as these are still being collated and will be reported elsewhere. Rather, the intention is to outline the challenges and complexities faced during the impact assessment process, and to highlight some key conclusions and observations. Regulatory approvals The proposal to acquire the Maxima 3D MSS was referred to the Western Australian Environmental Protection Authority (EPA) by the Western Australian Department of Industry and Resources (DoIR) in August 2006. At this stage, it was unclear whether or not the proposal would have to be formally assessed under the Environmental Protection Act 1986 (WA) (EP Act). The EPA requested Woodside undertake a three-stage process to provide additional information concerning the potential impacts of airgun noise emissions on site-attached marine fauna, involving: 1. an analysis of the spatial distribution of received energy levels on the sea floor within and surrounding the seismic footprint as a result of the proposed operations. 2. an analysis of the relationship between the spatial distribution of received acoustic energy and the spatial distribution of benthic habitats. 1 'IAIA08 Conference Proceedings', The Art and Science of Impact Assessment 28th Annual Conference of the International Association for Impact Assessment, 4-10 May 2008, Perth Convention Exhibition Centre, Perth, Australia (www.iaia.org)

3. a summary of the current state of knowledge, including the identification of knowledge gaps, with respect to the relationship between the magnitude of acoustic emissions and likely impacts on tropical marine fauna. This process, which covered the period September to December 2006, required a comprehensive risk assessment, comprising detailed modelling of noise propagation and received sound levels, an evaluation of the use of benthic habitats as a surrogate for fish diversity, a GIS-based spatial analysis of the risk of sound exposure to different habitats, and an assessment of the significance of the potential impacts identified. Overall, the conclusion of the risk assessment was that the proposed survey was not expected to have any long-term, biologically significant impacts on the fish populations at Scott Reef (Woodside, 2007a). It also required an extensive literature review of the effects of seismic airguns and other sources of pulsed sound on marine fishes, and the commencement of stakeholder engagement that included the establishment of a technical round-table committee. In January 2007, following assessment of the additional information provided by Woodside, the EPA determined that the proposal was to be formally assessed under the EP Act, and that the level of assessment required was an Environmental Protection Statement (EPS). Following release of the EPS document (Woodside, 2007a) and the statutory public review and comment period, the EPA delivered its report to the Western Australian Minister for the Environment in April 2007 (EPA, 2007). The Ministerial Statement providing approval for the survey to commence, and detailing conditions, was released at the end of August 2007 (Government of Western Australia, 2007). The proposal for the Maxima 3D MSS was also referred to the Commonwealth Department of Environment and Water Resources (now the Department of Environment, Water, Heritage and the Arts) in July 2006 under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act). A similar parallel process to the State approvals followed, with final Commonwealth approval received on 11 September 2007 (DEWR, 2007). Final State environmental clearances came through on 14 September The pre-survey field verification study (see below) started on schedule one day later. Stakeholder engagement Woodside maintains a proactive approach to engaging stakeholders in key activities, which was aligned with the requirements of the regulatory approvals process through two levels of stakeholder engagement: The establishment of a technical roundtable committee to assist in the risk assessment process. This committee was composed of representatives from the WA Department of Environment and Conservation (DEC), DoIR, DEWR, WA Department of Fisheries, WA Museum, Curtin University Centre for Marine Science and Technology (CMST), Australian Institute of Marine Science (AIMS), URS Australia and WWF. Engagement of additional relevant stakeholders as part of the EPS process. This involved discussions with a number of individuals and non-governmental organisations (NGO), including RecFishWest, Kimberley Marine Tourism Association, Kimberley Professional Fishermen s Association, Environs Kimberley, and the Conservation Council (WA). A number of organisations provided formal submissions on the draft EPS, and 127 issues raised by stakeholders were addressed in the final EPS document. Early engagement of relevant stakeholders through the technical round-table committee provided significant benefits. It ensured Woodside s assessment was fully informed by stakeholder concerns and was a key factor in demonstrating to the EPA that an EPS level of assessment was appropriate for this proposal - typically this level of assessment is applied to proposals where a formal public review period may be unnecessary because the proponent has adequately consulted with stakeholders. It also meant that a number of the key government, scientific and NGO stakeholders were already well-versed in the highly complex technical aspects of the project, in advance of the release of the final EPS. 2

EIA uncertainties In spite of the comprehensive risk assessment undertaken, uncertainties still remained concerning actual versus predicted impacts from airgun noise emissions on tropical marine fish and corals. As a result, the conditions of Ministerial approval required the completion of a preliminary field verification study at Scott Reef (Phase I), to verify predictions of impacts on fish and coral communities, as well as to verify the minimum airgun array size consistent with successful seismic data acquisition. Following the completion of Phase I, the data acquisition phase (Phase II) could be undertaken. This requirement was addressed via the development and implementation of a Draft Adaptive Management Programme (with approval prior to Phase I), and a Final Adaptive Management Programme (completion required prior to Phase II) (Woodside, 2007b). Details of the adaptive management approach are provided in another paper at the IAIA 2008 conference (Grebe et al., in press). The Ministerial Statement also required the development and implementation of the following: Cetacean Monitoring Plan (Woodside, 2007c); Non-Indigenous Marine Species Management Plan (Woodside, 2007d); Fish Monitoring Programme (Woodside, 2007e); Oil Spill Contingency Plan; and Coral spawning monitoring. Woodside prepared an Environment Plan, in accordance with regulatory requirements, that incorporated all of the environmental management elements listed above. Additional commitments to limit the potential for environmental impacts included: no seismic acquisition during coralspawning periods and inside of buffer zones during peak turtle nesting times; the presence of continuous daylight marine mammal/fauna observations on the seismic vessel and support vessel during the Phase I and Phase II surveys; and the exclusion of seismic data acquisition in buffer zones of 400 metres distance from 3 the outer reef edge and 800 metres from the reef inside the lagoon of south Scott Reef. Field verification study The field verification study comprised a suite of monitoring activities the EPA required to be conducted in situ in the southern lagoonal waters of Scott Reef. The study included the exposure of faunal communities to airgun noise emissions using the survey vessel and seismic array proposed for the full Phase II part of the Maxima 3D MSS. Over 20 scientific specialists, with expertise in underwater sound, coral reef ecology and reef fish biology, designed and executed unique scientific investigations relating to the impact of seismic surveys on a coral reef environment. The monitoring work consisted of: shallow water fish diversity and abundance (underwater visual census); coral monitoring (drop-camera transects); deep-water fish diversity and abundance analysis using baited and unbaited remote underwater video (BRUVs and RUVs); collection of fish samples for: o pathology studies (e.g. gross damage to non-auditory tissues) o physiological studies otolith analysis (hair cell damage), and fish hearing threshold analysis (auditory brainstem response - ABR) subsurface equipment: o sound loggers (validation of sound propagation and noise exposure modelling) o fish exposure cages o RUVs (behavioural responses) fish school location (sonar transects). The field verification study presented major resourcing and management challenges, with the safety of personnel being of paramount concern. At its peak, the study involved 123 people, from a variety of organisations, including: Woodside; SKM-ERM environmental consultancy; CMST; AIMS; Blue Planet Marine; Pearl Sea Coastal Cruises; the Australian National University; Pennsylvania State University; the Northern Territory Department of Fisheries; and eight vessels operating in a

remote offshore location. The challenge of maintaining safe operations, whilst balancing schedules and scientific and statistical rigour, was successfully met. Key outcomes from the field verification study were: successful, world-first execution of fish ABR measurements conducted onboard a vessel at sea; the identification of a new hearing specialist fish species (verified with anatomical studies); no hearing impacts (temporary or permanent threshold shift) found in fish after exposure to airgun emissions; no evidence of coral damage or fish mortality caused by airgun emissions; the observed impacts were less than initially modeled and predicted in the EIA; the DEC was able to provide approval for Woodside to continue with the Phase II survey, with no additional monitoring or mitigation requirements; and excellent health and safety performance for such a large operation - no injuries/incidents. In February 2008, Woodside released a compliance report that summarised the information collected during the Phase I and Phase II surveys, and demonstrated compliance with the conditions and commitments made during the approval process (Woodside, 2008). Ongoing monitoring The Ministerial conditions required a level of ongoing monitoring after the end of the Phase II (seismic data acquisition) survey, to further the scientific understanding of any potential longer term effects of noise exposure on fish communities following a seismic survey. This ongoing monitoring includes additional postseismic survey studies of reef fish diversity and abundance (with a first post-survey study at Scott Reef conducted by AIMS in January 2008), plus an investigation into the time-related sequence of damage to, and repair of, auditory hair-cells of fish exposed to noise emissions during the Phase II survey (undertaken by CMST). These hair cell experiments continued for a period of three months following the initial exposure to airgun emissions. 4 Conclusions Key conclusions and observations resulting from this impact assessment process are: Uncertainties in the actual versus predicted impacts in the EIA led to considerable delays to regulatory approvals for the Maxima 3D MSS the original proposed timing for the survey was November 2006; this then slipped to January-March 2007, and then to May-June 2007; actual acquisition of the survey commenced in September 2007, more than 12 months after the proposal had originally been referred to the EPA. It is estimated that the total cost to Woodside and its joint venture participants in the Browse LNG Development Project resulting from the impact assessment process, field studies and compliance with the conditions of the Ministerial Statement exceeds A$8 million, which is a significant proportion of the overall cost of the seismic programme. This probably represents the most comprehensive and complex field investigation of the environmental impacts of seismic airgun noise on an offshore, tropical reef environment conducted anywhere in the world to date. This is the first time that a monitoring programme has incorporated all of the key aspects in relation to the potential impacts of seismic airgun emissions on fish and coral communities i.e. simultaneous/combined use of sound loggers, visual transects (diver and drop-camera), behavioural observations using baited and unbaited remote underwater video, physiological studies examining hair cell damage and auditory brainstem response, pathological examination of non-auditory tissues, and fish school location using sonar. It is expected that the results of the monitoring will make a significant contribution to reducing the uncertainty around the potential impacts of airgun emissions on fish. This process clearly illustrates the benefits of early stakeholder engagement in building relationships, and in ensuring open and transparent communication and a

cooperative approach between the proponent, government, the scientific community and NGOs. The impact assessment and field studies can be successfully used to ensure that seismic airgun emissions of the magnitude used during the acquisition survey can meet environmental protection requirements and will not result in unacceptable impacts on sensitive shallow water marine ecosystems such as Scott Reef. References DEWR (2007) Maxima 3D Marine Seismic Survey, Scott Reef. EPBC Act Referral No. 2006/2945. Referral Decision. Australian Government, Department of Environment, Water, Heritage and the Arts. September http://www.environment.gov.au/cgibin/epbc/epbc_ap.pl?name=current_referral_det ail&proposal_id=2945 EPA (2007) Maxima 3D Marine Seismic Survey Scott Reef. Report and Recommendations of the Environmental Protection Authority. Western Australian EPA Bulletin 1255. April http://www.epa.wa.gov.au/docs/2490_bull_1255 _Maxima_0407_final.pdf Government of Western Australia (2007) Maxima 3-Dimensional Marine Seismic Survey Scott Reef. Ministerial Statement No. 746. Western Australian Minister for the Environment & Climate Change. August http://portal.environment.wa.gov.au/pls/portal/d ocs/page/doe_admin/environment_conditi ONS_REPOSITORY/000746.PDF Grebe CC, Colman JG & Reid CA (in press) Practical application of an adaptive management approach for a marine seismic survey. International Association for Impact Assessment 28 th Annual Conference (IAIA 08). The Art and Science of Impact Assessment. Conference presentations and documents. 4-10 May, Perth, Western Australia. Woodside (2007a) Environmental Protection Statement. Maxima 3D Marine Seismic Survey, Scott Reef. Woodside Energy Ltd., April ima+3d+marine+seismic+survey/environmental+ Protection+Statement.htm Woodside (2007b) Final Adaptive Management Program. Maxima 3D Marine Seismic Survey, Scott Reef. Woodside Energy Ltd., September ans+and+monitoring+programs/adaptive+manag ement+program.htm Woodside (2007c) Cetacean Monitoring Program. Maxima 3D Marine Seismic Survey, Scott Reef. Woodside Energy Ltd., August ans+and+monitoring+programs/cetacean+monit oring+program.htm Woodside (2007d) Non-Indigenous Marine Species Management Plan. Maxima 3D Marine Seismic Survey, Scott Reef. Woodside Energy Ltd., August ans+and+monitoring+programs/non- Indigenous+Marine+Species+Management+Plan.h tm Woodside (2007e) Fish Monitoring Program. Maxima 3D Marine Seismic Survey, Scott Reef. Woodside Energy Ltd., August ans+and+monitoring+programs/fish+monitoring+ Program.htm Woodside (2008) Maxima 3D Marine Seismic Survey, Scott Reef Environmental Compliance Report. Woodside Energy Ltd., February 2008. ima+3d+marine+seismic+survey/monitoring+rep orts+and+results.htm 5