Operating Procedure PURPOSE... 1

Similar documents
Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1

Generation Desk Logging

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1

Procedure No. Operating Version No. Procedure Effective Date System Emergency Notice Templates Distribution Restriction: None 1.

SUPPORTING INFORMATION

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1

EAPP interconnection readiness workshop

Reference Document. Interconnected Operations Services

PJM Manual M36 System Restoration. A.1 Critical Black Start Criteria

Operating Procedure PURPOSE... 1

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Electricity Market Design and Structure ) Docket No.

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL

Revised Draft Final Proposal for Participation of Non-Generator Resources in California ISO Ancillary Services Markets

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Operating Procedure PURPOSE... 2

Table of Contents-Quick Reference

Standards for Imports of Regulation

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

Operating Procedure PURPOSE... 1

California Independent System Operator Corporation Fifth Replacement Tariff

Operating Procedure PURPOSE... 1

Operating Procedure PURPOSE... 1

Load Shed Philosophy

NERC-led Review Panel Decision on the Request by Orange Grove Energy, L.P.

Operating Procedure PURPOSE... 1

3. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

Table of Contents. Purpose. Inadvertent Interchange ATEC Payback OPERATING PROCEDURE

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION

Primary Frequency Response Stakeholder Education Part 2 of 2

CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION FERC ELECTRIC TARIFF Sheet No. 691 ORIGINAL VOLUME NO. III

Standard EOP System Restoration from Blackstart Resources

Policy 1 Generation Control and Performance Version 2

EOP-004-AB2-1 Disturbance Reporting

Procedure No. 2330C Version No. 5.4 Effective Date 11/22/2016. Reason Other Reason Instruction Description Text (EDF Code)

Generator Assessment & Roles During A Restoration

Consolidated Authoritative Document Glossary

Procedure: Station Power Portfolio Application

Comments Received and Peak Response. General Comments

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Business Practice Manual for Compliance Monitoring

California Independent System Operator Corporation

ELECTRICITY INDUSTRY ACT ELECTRICITY INDUSTRY (WHOLESALE ELECTRICITY MARKET) REGULATIONS 2004 WHOLESALE ELECTRICITY MARKET RULES

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D. POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009

Standard EOP System Restoration from Blackstart Resources

Eligible Intermittent Resource Dispatch Operating Target EIR DOT

Functional Entity Roles and Responsibilities

Comparison of IV.A.M2 and IV.A.M3 to EOP-005-1

Mapping Document. Project Phase 2 of System Protection Coordination. Revisions or Retirements to Already Approved Standards

Ancillary Services Matrix

Seminar on African Electrical Interconnection. Module 8 - Interconnected Systems Operating Conditions

DECLARATION OF AUTHORITY. This DECLARATION OF AUTHORITY ( Declaration ) is a declaration and certification made on by and between the following:

Educating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Facility Interconnection Requirements

RCR-35 Reliability Coordinator Reliability Plan for the SaskPower Subregion of the Midwest Reliability Organization

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Ancillary Service. the WEM System Management. June 2018

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff

Glossary of Terms Used in Reliability Standards. Preliminary Draft Version 0 Reliability Standards September 1, 2004

ReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability

A. Introduction. B. Requirements and Measures

Job Descriptions. Title & Job Functions: Transmission Function Employees

FACILITY CONNECTION REQUIREMENTS NERC TO-FAC 001-0

Transfer Capability Methodology. for the Near-Term. Transmission Planning Horizon

Standard EOP Load Shedding Plans

PacifiCorp Contract Review. Discussion Paper

NYISO Pilot Program Guide

The DAM consists of the following functions performed in sequence: the MPM-RRD, IFM, and RUC.

Reliability Coordinator Outage Coordination Methodology

Capacity Shortages RE Module. Interconnection Training Program PJM State & Member Training Dept.

EXELON UTILITIES TRANSMISSION FACILITY INTERCONNECTION REQUIREMENTS

Omaha Public Power District Facility Connection Guide

CIP Cyber Security - Supply Chain Risk Management. A. Introduction

Public Utility District Number 1 of Snohomish County

Public Utility District Number 1 of Snohomish County. Facility Connection Requirements February 9, 2018

NORMES DE FIABILITÉ DE LA NERC - IRO (VERSION ANGLAISE)

Connection Study Requirements

NEW STANDARDS NEEDED FOR SYSTEM BLACKSTART IN COMPETITIVE BULK-POWER MARKETS. Brendan Kirby and Eric Hirst * November 1998 INTRODUCTION

PJM TO/TOP Matrix of Shared or Assigned Tasks

Project Revisions to TOP and IRO Reliability Standards Mapping Document Updated December 2014

Requirements for the Provision of Load Shedding Service for Import Version 4.0

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0

Transmission Reliability Margins. Table of Contents. Purpose. Operating Procedure

Straw Proposal. Post-Release 1 MRTU Functionality for Demand Response

Standard Development Timeline

Standard TOP Monitoring System Conditions

Energy Imbalance Market

California Independent System Operator Corporation Fifth Replacement Tariff

Transcription:

No. 5310 Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 1 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 2 3.1. Reporting Requirements/... 2 3.2. Communicating Operating Limits... 3 3.3. Voice Communication with Generating Unit Control Room Operator... 4 3.4. Normal Operations... 5 3.5. Emergency Operations Low Frequency... 6 3.6. Electric Grid Shutdown... 7 4. SUPPORTING INFORMATION... 7 Operationally Affected Parties... 8 References... 8 Definitions... 8 Version History... 9 5. PERIODIC REVIEW PROCEDURE... 9 Review Criteria & Incorporation of Changes... 9 Frequency... 9 APPENDIX... 10 Purpose Provides guidelines for Scheduling Coordinators (SC) and for generating stations that are owned and/or operated by Participating Generators (PG). 1. Responsibilities Scheduling Coordinator (SC) Generator Owner (GO) Will recognize and abide by the authority of the ISO as the Balancing Authority. Page 1 of 10

No. 5310 ISO Will recognize the responsibility of the PG to operate in such a manner as to avoid injury to personnel and/or damage to facilities. 2. Scope/Applicability 2.1. Background The ISO has jurisdiction of all Scheduled or Bid Energy and Ancillary Services relating to the ISO Balancing Area. Close coordination is required between Participating Generators (PGs), Participating Transmission Owners (PTOs), Utility Distribution Companies (UDCs), and the ISO to assure prudent and reliable operation of the ISO Balancing Area. If there is disagreement between the ISO and the PG relative to the action most appropriate for the reliable operation of the ISO Balancing Area or any sub-region thereof, and due to operating considerations there is insufficient time to reach concurrence, the ISO will be the final authority. Inconsistent or otherwise questionable direction by the ISO will be reviewed after the fact to improve coordination. During an emergency (as declared by the ISO), the ISO jurisdiction is expanded to include all operations of the PG, which impact or may impact the ISO Balancing Area and all Generating Units are subject to the instructions of the ISO as Balancing Authority. 2.2. Scope/ Applicability Includes expectations of the PG by the ISO, responsible PTOs, and UDCs. These operational expectations are especially useful during emergency operations, and during periods when communications are disrupted. 3. Detail 3.1. Reporting Requirements/ Take the following actions to coordinate the transfer of information: Description Page 2 of 10

No. 5310 It is essential that the ISO and Participating Generators promptly inform one another of any circumstance that may adversely affect the operation or reliability of the ISO Balancing Area, or the integrity or capability of the PG s facilities, including, but not limited to: Power System Stabilizer (PSS) status. Automatic Voltage Regulator (AVR) status. Change of status. Abnormal temperatures. Storms. Floods. Earthquakes. Equipment failures or malfunctions. Deviations from the Registered Data or operating characteristics. Participating Generator (PG), ISO 1. Inform the other as promptly as possible of any incident or situation (including, but not limited to, equipment outages affecting Generation, over-loads, over/under-voltages, or alarm indications) that, in the case of a PG, is reasonably likely to threaten any of the following: o The capability of the Generating Unit and facilities. o The reliability of the ISO Balancing Area. o Schedules. o Bids of Energy and/or Ancillary Services. 2. Notify the applicable PTO and the ISO as soon as practical, but no later than 30 minutes of a change to the status of automatic voltage regulators (AVRs) or power system stabilizers (PSSs). ISO 1. Communicate either through the SC or directly with the Generating Station Control Room, as described in Section 3.3 of this procedure. 2. When notified of the loss of an automatic Voltage Regulator Control (AVR), and the SC has not notified the PTO, notify the applicable PTO of the status of the device (the TO will direct the Generator Operator to maintain or change either its voltage Schedule or its Reactive Power Schedule as appropriate). 3.2. Communicating Operating Limits Page 3 of 10

No. 5310 Take the following actions to communicate promptly any changes in the Generating Unit Operating Limit (i.e. per unit) to the ISO: Scheduling Coordinator (SC) 1. Refer to ISO Operating 3210, Transmission Outages for guidance on reporting Outages and de-rates. 2. Include the full available Capacity as the Operating Limit of the Unit being scheduled, in all Schedules (This does not reflect the sum of all of the Energy and Ancillary Service Schedules). Example: A Unit capable of regulating up to 480 MW may have a current Energy Schedule of 250 MW and an upper regulating Ancillary Service Schedule of 100 MW, the Operating Limit to be included on these Schedules is to be 480 MW (i.e., not 350 MW, which is the sum of accepted Schedules). 3. If a Unit is equipped with digital input or other (e.g., thumb-wheel setters ) types of input devices used to transmit Operating Limits, set the values to indicate the full Automatic Generation Control (AGC) capability of the Unit within its operating range (High or Low), rather than the value of the existing Schedules. Note: Settlement payments for Ancillary Services may be affected by incorrect communication of Operating Limits, included within the Schedules submitted or by indication from setters. 4. If the Unit is restricted in its maximum output due to equipment out of service or other reasons, verify the communicated Operating Limit is reflective of this restriction. 3.3. Voice Communication with Generating Unit Control Room Operator Take the following actions, under one of the following reasons, should ISO not feasibly be able to communicate with the Scheduling Coordinator: ISO 1. If there is an emergency, or system integrity is threatened and there is insufficient time to communicate with a Generating Unit through the SC, or it is apparent that communications to an SC is not being conveyed to the Generating Unit in a timely manner, communicate directly with the Generating Unit Control Room Operator. 2. If communications between the ISO and a generating station is unavailable, relay communications through the appropriate PTO Control Center, as available. Page 4 of 10

No. 5310 Participating Generator (PG) 1. Ensure only qualified and authorized control room operations personnel are involved in direct communication with the ISO during emergency communications. 2. If the SC or PG is unable to contact the ISO Control Room within five minutes, contact the other ISO Control Room. 3. If the SC or PG is unable to contact either of the Control Rooms after ten minutes of continuous attempts, contact the responsible PTO Control Center and ask to be patched through to the ISO. If a patch is infeasible, remain in contact with the PTO Control Center for directions (either relayed from the ISO, or directly from the PTO if the ISO communication is not available). 4. Continue attempts to contact the ISO. 5. If direct communications between the ISO and the Generating Unit Control Room Operator has occurred, advise the SC of the content, nature, and time of the communications. ISO 1. Conduct periodic communication tests, as desired, with the generator control room operator to assure the viability of communication circuits and to maintain familiarity with direct ISO control room operator communications. 3.4. Normal Operations Take the following actions to maintain generating station requirements under normal operating conditions: Scheduling Coordinator (SC), Participating Generator (PG) 1. Maintain the capability for constant communication with the ISO. 2. Adhere to all Schedules. 3. Maintain normal frequency and voltage. 4. Maintain capability of providing immediate response to abnormal frequency. 5. Set governors to provide a five percent droop characteristic and to remain fully responsive to frequency excursions greater than 0.036 Hz. 6. Set load limit devices (i.e., Unit/governor blocks) at a point to enable a full available load (i.e., without substantial operator intervention) of each Unit to allow for maximum governor action upon the occurrence of low frequency. 7. Maintain Power System Stabilizers in service. 8. Obtain final approval from the ISO Generation Desk prior to taking a unit off line or placing a unit on line (applies to Generators >100 MW). Page 5 of 10

No. 5310 3.5. Emergency Operations Low Frequency Take the following actions for notification if the frequency drops below 60 Hz: Participating Generator (PG) 1. Set Generating Units low frequency alarms to 59.5 Hz. 2. If the system frequency should decay to 59.5 Hz as indicated by charts, frequency alarms, or Automatic Generation Control (AGC), maximize all Generation currently synchronized to the system. If the Generating Unit has quick-start capabilities, initiate a start on all idle and available quick-start Generation regardless if the Unit(s) has been bid into the market. Initiate the start of the Generating Unit prior to contact with the ISO regardless of the frequency at the time of the start initiation, contact the ISO Generation Desk to advise that the unit(s) is starting, when it will (or has) synchronize to the system, and to request a schedule for the Unit(s). If unable to contact the ISO Generation Desk, synchronize the Unit(s) to the system and Load to full available Load without exceeding 60.0 Hz. Continue attempts to contact the ISO. Note: Appropriate costs will be paid by the ISO to SCs for quickstart units that start in compliance with this procedure. 3. Inform the respective SC of any frequency excursion. Scheduling Coordinator (SC) 1. Contact the ISO Generation Desk to determine if a change in Schedules and/or services will be required. Participating Generator (PG) 1. If the Unit was on AGC prior to the frequency excursion, return to AGC. 2. If unable to reset AGC (due to low frequency or other problem), raise load until Unit AGC will reset or until Unit reaches full available load without exceeding 60.0 Hz. 3. If the frequency decays further to 57.0 Hz, with no immediate recovery, separate the Unit(s) from the system and, if feasible, attempt to carry auxiliary Load. 4. Prepare to restart the Unit(s) and/or prepare to resynchronize to the system. 5. Contact the ISO Generation Desk to provide start-up power requirements (if any) and for further instructions. 6. Refer to ISO Operating 4510, Load Management. Page 6 of 10

No. 5310 3.6. Electric Grid Shutdown Take the following actions if a total or partial electric grid shutdown occurs, as evidenced by zero voltage on the facilities Interconnecting with the ISO Balancing Area: Participating Generator (PG) 1. Advise the respective SC of this zero voltage condition. Scheduling Coordinator (SC) 1. If the Generator has reported experiencing zero voltage at its Interconnection, advise the Generating Unit to make contact as previously detailed in Section 3.3. Participating Generator (PG) 1. If communication cannot be established with the respective SC, contact the ISO Generation Dispatcher directly. 2. If unable to contact the ISO, proceed as previously detailed in Section 3.3. 3. Prepare for Start-Up, and initiate a Start-Up as soon as auxiliary power requirements can be met. Blackstart Resource Owner, Participating Generator (PG) 1. Start all Blackstart capable Generating Units and supply auxiliary power to the other Generating Units at the same Generating site. ISO 1. Refer to ISO Operating 4610, System Restoration (not available for public distribution). 2. Direct (as necessary) Generating Units with Blackstart capability to be started to supply Start-Up power at other stations, or for nuclear Generating Unit reactor safety (see ISO Operating 3350, Offsite Power Requirements and Restoration for Nuclear Power Plants). 4. Supporting Information Page 7 of 10

No. 5310 Operationally Affected Parties Shared with Peak RC and Public. References Resources studied in the development of this procedure and that may have an effect upon some steps taken herein include but are not limited to: CAISO Tariff ISO Operating NERC Requirements WECC Criterion Other References 3350 Nuclear Plant Interface Coordination 4510 Load Management Programs and Underfrequency Load Shedding 3210 Transmission Outages VAR-002: R2, R3 (Regulatory References - New) ISO Technical Standard - Monitoring and Requirements for Generating Units Providing Only Energy and Supplemental Energy. Participating Generator Agreement PGAE Dispatching Instructions SDG&E Standard Operating s SCE System Standard Operating s Definitions Unless the context otherwise indicates, any word or expression defined in the Master Definitions Supplement to the CAISO Tariff shall have that meaning when capitalized in this Operating. The following additional terms are capitalized in this Operating when used as defined below: Automatic Generation Control (AGC) Blackstart Generating Unit PG Quick-Start Generating Unit An SC that allows the ISO to remotely control their Generating Stations within a specified range of operation. Generating Unit that is capable of self-starting without a source of off-site electricity. Participating Generator, has an approved PGA (agreement). Generating Unit that (taking into account personnel and fuel availability, etc.) can be started (locally or remotely), Page 8 of 10

No. 5310 Version History Reactive Power synchronized to the system and available for loading in ten minutes or less. Generation or other equipment needed to maintain acceptable voltage levels on the ISO Controlled Grid and to meet reactive Capacity requirements at points of interconnection on the ISO Controlled Grid. Version Change Date 2.7 Annual Review 6/9/2009 3.0 Re-inserted comment to start peakers at 59.5 Hz 8/30/2010 4.0 Reformatted for new prototype 5/1/2011 4.1 Policy section split up into Background and Responsibilities sections, and some content from Purpose has been moved to Scope/Applicability. 6/13/2011 4.2 Updated the role names used in this procedure to their new role names. 3/24/2017 Minor grammar and format changes. Updated ISO facility references. Changed all references of CAISO to ISO. Replaced term directive with instruction pursuant to IRO-001-04. Replaced CAISO with ISO except when in reference to the tariff. Removed references to Folsom or Alhambra. 5. Periodic Review Review Criteria & Incorporation of Changes There are no specific criteria for reviewing or changing this document, follow instructions in s 5510 and 5520. Frequency Every 3 Years. Page 9 of 10

No. 5310 Appendix 5310A Generator Control Room Phone Numbers. Page 10 of 10