4D grouting pressure model of a bored tunnel in 3D Tunnel

Similar documents
4D grouting pressure model PLAXIS

SETTLEMENTS DUE TO TUNNEL CONSTRUCTION

The influence of tunnel boring on foundations and buildings in urban areas - A numerical study

Grout properties and their influence on back fill grouting

Modelling issues for numerical analysis of deep excavations

Ten years of bored tunnels in the Netherlands; Part I, geotechnical issues

Relationship between twin tunnels distance and surface subsidence in soft ground of Tabriz Metro - Iran

Modeling of TBM Tunnel Construction for the Greater Cairo Metro Line 3

PROCESSES AROUND A TBM

NUMERICAL ANALYSIS OF TUNNEL BORING MACHINE IN SOFT GROUND M. E. LEl-Kilany 1, T. A. EL-Sayed 2 *, R. A. Mohab 3

Modelling of ground deformation control induced by slurry shield tunnelling

3-D finite element modeling and construction aspects for vertical shafts in Metro C Rome

Design of deep excavations with FEM - Influence of constitutive model and comparison of EC7 design approaches

Underground works in urban environment

Monitoring pilot projects using bored tunnelling: the Second Heinenoord Tunnel and the Botlek Rail Tunnel

Structural design of linings for bored tunnels in soft ground

Dimensioning and design of the segmental lining

Back Analyses and Performance of Semi Top-Down Basement Excavation of 11m Deep in Sandy Alluvial Deposits overlying Kenny Hill Formation in Malaysia

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

RESULTS FROM NUMERICAL BENCHMARK EXERCISES IN GEOTECHNICS

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

Influence of slurry TBM parameters on ground deformation

COURSE ON COMPUTATIONAL GEOTECHNICS A Geotechnical Design Tool. Faculty of Civil Engineering UiTM, Malaysia

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

Challenges of quick clay excavation in urban area with sloping ground

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

TBM rescue projects using shafts and ground freezing

SEISMIC DESIGN OF THE STATIONS AND THE INTER-STATION TUNNELS OF A METRO-LINE IN SOFT GROUND: A CASE STUDY

CHAPTER 5 2D FINITE ELEMENT MODELLING OF BURIED PIPE TESTS

Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling

Challenges in Design and Construction of Deep Excavation With Case Studies - KVMRT in KL Limestone

Structural Analyses of Segmental Lining Coupled Beam and Spring Analyses Versus 3D-FEM Calculations with Shell Elements

Comparison of the results of load test done on stone columns and rammed aggregate piers using numerical modeling

Performance of the GHT Lining in the First Instrumented Plot

DAMAGE ON DEEP, MULTI-TIED-BACK EXCAVATION DUE TO DEFORMATION OF THE ANCHOR-SOIL BLOCK SYSTEM

Finite Element Analysis of Flexible Anchored Sheet Pile Walls: Effect of Mode of Construction and Dewatering Naveen Kumar 1, Arindam Dey 2*

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

3 Dimensional Structural Modelling of Segmental Tunnel Lining Using Finite Element Software

EFFECT OF DEEP EXCAVATION SUPPORTED BY CONCRETE SOLIDER PILE WITH STEEL SHEET PILE LAGGING WALL ON ADJACENT EXISTING BUILDINGS

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

Underground Construction Technology

Ten years of bored tunnels in the Netherlands

Case Histories in Geotechnical Engineering

Tunnels. Introduction in Shield tunnelling Pipe jacking & tunnelling Slurry & hydroshield Slurry versus EPB Principles of support pressure

FEATURES & BENEFITS OF ARMTEC TUNNEL LINER PLATE

Study on earth pressure acting upon shield tunnel lining in clayey and sandy grounds based on field monitoring

Settlement assessment of running tunnels a generic approach

Testing of ground anchorages for a deep excavation retaining system in Bucharest

From Colonia Jardín to Cuatro Vientos

Effect of Cavities on the Behaviour of Strip Footing Subjected to Inclined Load

ANALYSIS OF DIFFERENT LOADS AFFECTING THE URBAN RAILWAY TUNNEL SYSTEMS OF CAIRO METRO UNDERNEATH THE RIVER NILE

Modelling of a pile row in a 2D plane strain FE-analysis

IJMGE Int. J. Min. & Geo-Eng. Vol.48, No.2, December 2014, pp

Prof. Dipl.-Ing. H. Quick Ingenieure und Geologen GmbH provides geotechnical engineering services e. g. for high-rise buildings in Germany and abroad.

Comparison of geotechnic softwares - Geo FEM, Plaxis, Z-Soil

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro

Finite Element Analyses of Granular Pile Anchors as a Foundation Option for Reactive Soils

Mitigation of the effects induced by shallow tunneling in urban environment: The use of compensation grouting in the underground Line B1 works in Rome

Design of pipeline installation D-GEO PIPELINE

Concrete Pipe Jacking

Influence of unloading soil modulus on horizontal deformation of diaphragm wall

Performance review of a pipe jacking project in Hong Kong

Design of pipeline installation. D-Geo Pipeline

[Kouravand Bardpareh* et al., 5(6): July, 2016] ISSN: IC Value: 3.00 Impact Factor: 4.116

Combined cut and cover and new Austrian tunnelling methods for MRT station in Bangkok sub-soils

1st International Conference on Geomechanics and Geoenvironmental Engineering (icgmge 2017) 148

Inclusion Effect on Heterogeneity of Excess Pore Water Pressure Distribution in Composite Clay

Geotechnical Risk Management for Museum Our Lord in the Attic Amsterdam

Design Data 4M. Jacking Concrete Pipe

UNDERPINNING A CRANE FOUNDATION

Modelling of Piled Raft Foundation on Soft Clay

SOIL PRESSURE IN EMBANKMENT STABILIZATIONS

BEHAVIOUR OF GEOTEXTILE REINFORCED STONE COLUMNS MANITA DAS, A.K.DEY ABSTRACT

Behavior of Reinforced Embankment on Soft Ground with and without Jet Grouted Soil-Cement Piles

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

NUMERICAL ANALYSIS OF GEOSYNTHETIC REINFORCED SOIL ABOVE A TUNNEL

Verification of a multi-anchored wall

Performance of Soil Nail Stabilisation Works for a 14.5m Deep Excavation in Uncontrolled Fill Ground

8 Displacements near the Face of an Advancing Shaft

NUMERICAL STUDY OF INVESTMENT BEHAVIOR CONTAINMENT WALLS (CASE STUDY STRUCTURAL GUARDIAN SYSTEMS PROJECT OF HABIB HOTEL OF MASHHAD)

Compaction and Jet Grouting

Code No: RR Set No. 1

BOUNDARY CONDITIONS OF SHEAR WALLS IN MULTI-STOREY MASONRY STRUCTURES UNDER HORIZONTAL LOADINGS

Development of the effective segmental tunnel lining with flexible elements

EPS 2011 Lillestrøm, Norway, June 2011 LIGHTWEIGHT EMBANKMENTS WITH EPS BLOCKS ABOVE PRESS SEWERS OF A2 EINDHOVEN BY-PASS MOTORWAY

Pile foundations Introduction

Effects of Wall Embedded Length Ratio and Wall Thickness Ratio on Undrained Stability of Cantilever Piled Walls

P A (1.1) load or stress. elongation or strain

Risk Management of the Restoration of Shanghai Metro Line 4

Design Data 4. Jacking Concrete Pipe

Heading under the protection of jet grouting columns. 7.1 Road tunnel for the federal highway B 9 in Bonn-Bad Godesberg, Germany

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines

GEOTECHNICAL DESIGN AND CONSTRUCTION METHODOLOGY OF A DEEP BASEMENT CUT NEXT TO SENSITIVE BUILDINGS

Modeling and monitoring of an excavation support using CSM

STATIC ALTERNATING CYCLIC HORIZONTAL LOAD TESTS ON DRIVEN

Modulus of subgrade reaction for pipelines in a borehole installed by horizontal directional drilling

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Braced deep excavations in soft ground

PILE DESIGN METHOD FOR IMPROVED GROUND USING THE VACUUM CONSOLIDATION METHOD

Prof. Eng. Daniele PEILA & Prof. Eng. Sebastiano PELIZZA

Transcription:

4D grouting pressure model of a bored tunnel in 3D Tunnel F.J.M. Hoefsloot & A. Verweij, Fugro Ingenieursbureau B.V., The Netherlands INTRODUCTION For some ten years TBM-techniques have been used to construct tunnels in the Netherlands. Ground conditions vary from loose to dense granular soils, sometimes clays. In all cases groundwater is close to ground level. Front stability is maintained by bentonite slurry or earth pressure balance shields. Several research projects have been initiated by the Dutch Centre for Underground Construction (COB) in order to increase TBM applicability in urban areas. The COB has brought authorities, engineering consultants and contractors together in research committees. One COB research committee is investigating the interaction of soil and the tunnelling process using finite element method (FEM) analyses. The grouting pressure applied to fill up the tail void behind the TBM is believed to govern both deformations and internal lining forces. Several two- and three-dimensional FEM models that include tail void grouting are available. However, they do not describe time-dependent longitudinal lining deformations or bending moments. As part of this COB project Fugro Ingenieursbureau B.V. has developed a 4D FEM model. The model describes the progressive tunnel boring process using PLAXIS 3D Tunnel software. Figure 1: Face support pressure at the crown & surface settlement vs. ring number at the monitoring section. CASE STUDY The 4D grouting pressure model was derived from the twin tube Sophia Railway Tunnel constructed in the western Netherlands as part of the Betuweroute railway link between Rotterdam and Germany. Each tunnel is 4.2 km long and has an inside diameter of 8.65 m. Construction used a TBM with a bentonite slurry shield. Halfway along the tunnels a monitoring section was installed. This consisted of two lines measuring surface displacements laid out parallel and perpendicular to the tunnel axis. Also extensometers and inclinometers were installed. Grouting pressure transducers have been inserted in ring 2080 of the southern tunnel beneath the monitoring section. This instrumented ring was also monitored after installation. Along with TBM data this monitoring data has been used for achieving a history match with the FEM model. Figure 2: Grouting pressure & surface settlement vs. ring number (average uses 5 data points smoothing). ANALYSIS OF MEASUREMENT DATA In order to compare calculation results with measurements at the monitoring section an analysis of the boring process has been performed over some 200 m tunnel length. Major goals are to determine whether the tunnel boring process parameters and response at ground level at the monitoring section can be correlated and whether they are representative for a larger area. Data analysis for 140 rings (210 m) Surface settlement at ring number can be compared with front pressure at ring number x 5 in figure 1. The monitoring section is located at ring number 2080. Over the entire length there seems to be some correlation between vertical displacement and front pressure. In figure 2 the grouting pressure is given for a pressure transducer in the TBM tail. The grouting pressure in the boring phase varies by 100 kn/m² along this stretch. On this large scale there is no clear correlation between grouting pressure and final displacement other than that the average grouting pressure is constant at approximately 275 kpa and the average final settlement is 0 mm. In figure 3 the total number of strokes 7 Figure 3: Grout pump strokes & surface settlement vs. ring number. of the grouting pumps is given. The number of strokes varies considerably. Just like grouting pressure there is no clear correlation between the number of strokes and final displacement other than that the number of strokes is constant as well as the final settlement. On a smaller scale there is some correlation. For example between ring number 2070 and 2105 the final settlement is reduced by an increase in the number of strokes.

Data analysis near monitoring section Other monitoring results near ring 2080 have been analysed in detail. Surface settlement versus time can be plotted as settlement versus TBM position. For a uniform tunnel boring sequence these plots should show the influence of front pressure, TBM volume loss and tail void grouting. Such plots have been given for ground level at the location of three rings in figure 4. Surface settlement has not been constant in relation to TBM position. Figure 6: Vertical displacement extensometer E 7113 at ground level (GL), GL 6 m and GL 12.5 m as a function of time. Also plotted is the TBM s position. The question can be raised whether these deformations can be directly related to TBM drilling data. They are plotted versus time in figures 7, 8 and 9. Figure 4: Surface settlement ring numbers 2070, 2080 & 2090 vs. position. In order to find the source of these differences, settlement at ground level and displacement of extensometer points are given as a function of time in figures 5 and 6. Extensometer E7113 is located at the tunnel centreline near ring 2080. In these figures the TBM progress has also been plotted; boring for ring number n given on the right hand scale starts at the moment given on the time scale. During boring the centre of this ring is inside the TBM with a decreasing distance of approximately 5.2 to 3.7 m from the tail end. From figure 8 it appears that there is a positive correlation between grouting pressure and vertical displacement: a decreasing grouting pressure in the morning of June 27 results in settlement just as the relatively low grouting pressure in the morning of June 28 (see figure 6); the latter a result of TBM stops. An increase of grouting pressure around mid-night June 29 results in heave at all locations. The correlation of displacement with the number of strokes in figure 9 is less obvious as has been concluded from figure 3. From the above mentioned it is evident that tunnel boring from rings 2070 to 2090 has not been constant: TBM stops and variation in grouting pressure have resulted in different longitudinal settlement troughs versus TBM position. At all locations settlement occurs at the same time and in most cases due to TBM stops. The largest settlements are found at ring 2090 during TBM stops after boring for ring number 2087, 2088 and 2089. Heave is mainly found during boring for ring numbers 2090 through 2094. In addition the extensometer point at ground level 12.5 m shows heave during boring for ring 2080. At that moment ring 2080 was located within the TBM at a distance decreasing from approximately 5.2 to 3.7 m from the tail end. Thus the measured heave did not originate directly from entering the grouting zone. This heave is limited to the zone directly above the tunnel and does not extend to ground level. Interesting is the response of the extensometer at 12.5 depth to every boring phase at least up to ring number 2094 which is located at 21m distance. Figure 7. Face pressure measured at the crown of the TBM as a function of time. Figure 5: Vertical displacement at ground surface above rings 2070, 2080 and 2090 as a function of time. Also plotted is the TBM position. 8 Figure 8: Grouting pressure measured in the grout injection zone transducer G02 as a function of time.

Layer level γsat ϕ c E ref 50 E ref oed E ref UR NAP */** kn/m³ kn/m² MN/m² MN/m² MN/m² Sand -1.5 19 35 1 25 25 85 Peat -1.9 11 25 10 2 1 15 Clay -8.0 13 28 4 4 2 20 Sand *** -13.2 20 38 1 40 40 150 Kedichem Clay -24.6 20 32 1 9 6 60 Bottom -36.0 * NAP = Dutch reference level ** Top of the layer *** Pleistocene Figure 9: Grouting pump strokes as a function of time. Table 1: Hardening Soil parameters FEM-MODELLING Geometry and soil parameters The model has been built using PLAXIS 3D Tunnel (Brinkgreve & Broere 2004). The model was extended modularly, i.e. first starting with only a tunnel and face support, then adding a new component in order to investigate the model s response. Subsequently adding the TBM weight, a grouting pressure zone, jack forces and finally TBM contraction and backup train weight. Half a tunnel is modelled with standard boundary conditions for soil and lining. The length of one tunnel ring is 1.5 m. In longitudinal direction 70 slices of 1.5 m have been used to model the phased construction. This number of stages is required in order to create a constant bending moment at some distance from both TBM and model boundaries. The total length and width of the model is 165 m and 75 m respectively. The model base has been chosen at the base of the Kedichem formation (stiff sandy clay). The underlying sand formation is even more stiff regarding unloading (E UR ref = 150 MN/m²). The major part of the tunnel was bored through Pleistocene sand; only a small part protrudes in the Kedichem clay. Part of the model is sketched in figure 10. The soil has been modelled using the Hardening Soil model (Brinkgreve & Broere 2004). This model implements soil behaviour under the unloading-reloading conditions governing tunnel construction. Soil parameters were derived from in situ and laboratory tests. Table 1 lists important soil parameters. Tunnel Boring Machine (TBM) The TBM is modelled by plate elements. The diameter, stiffness and unit weight vary along the length of the TBM. Contraction of the TBM results in volume loss as tunnelling progresses. TBM face pressure is modelled by a pressure at the crown and a pressure gradient of 14 kn/m²/m (measured values). The jack forces measured during tunnelling have been applied on the tunnel lining using point forces. Like the face support they are modelled as external forces not linked to the TBM. The horizontal balance forces of the face support and jack forces have not been modelled. This is because the resulting horizontal force is relatively small, as is confirmed by additional calculations. The backup train is modelled by point loads behind the TBM. Figure 11 displays the different process parameters implemented in the 4D grouting pressure FEM model. Figure 10: Schematic FEM model geometry 9

Tunnel lining The tunnel lining is modelled by plate elements. The bending stiffness in both ring and longitudinal directions have been assessed by FEM analyses accounting for reduced stiffness caused by joints between ring segments. It is possible to select a plate thickness and Young s modulus such that both ring and longitudinal bending stiffness can be modelled correctly. Three slices of lining have been applied in the tail end of the TBM corresponding to the actual situation. These additional tunnel rings inside the TBM result in a downward force on the lining next to the grouting zone. Calculation process The tunnel boring process has been modelled by a staged construction calculation with PLAXIS 3D Tunnel V2, where in approximately 60 stages one ring per stage is bored. This version includes a copy option whereby the features (e.g. loads, structures, state of soil elements, water pressures etc.) of one stage can be easily copied to the next. This results in an efficient modelling procedure and a minimisation of input errors. RESULTS 4D FEM ANALYSIS Introduction After performing the modular construction of the model and assessing the governing process parameters the final model was constructed using best estimate values for every possible input parameter. This calculation is called the standard run. The standard run is equipped with: measured (applied) face pressures real bending stiffness for TBM values of contraction of the TBM fully supplied measured (applied) jack forces real bending stiffness lining in both ring and longitudinal direction measured grouting pressures Figure 11: Tunnel boring process parameters featured in the 4D grouting pressure FEM model Figure 12: Close up of the tunnel, showing the location of the point loads representing the backup train GROUT During boring of the second tunnel the grouting pres-sure has been measured at 14 locations along the circumference of one instrumented ring. Both the measured pressure and pressure gradient vary with distance. They also differ during periods of excavation (high pressure (gradient)) and standstill (lower pressure (gradient)). The grouting pressure has been modelled for a length of six rings behind the TBM. The modelled pressure and pressure gradient are given in figure 13. Behind the grouting pressure zone, the grout is assumed to behave like a soil and is therefore modelled by volume elements as an elastic material with a Young s modulus assumed equal to the surrounding soil. Figure 14: Standard run: calculated and measured transverse settlement troughs. Where possible, the results of the standard run have been compared with measured soil deformations. In addition a series of calculations have been conducted in order to determine the model s sensitivity to certain parameter variations. Results of the standard run: surface settlement The results show that the maximum of the calculated final surface settlement is about 10 mm (figure 14 and 15 depict the transverse and longitudinal troughs). The final Figure 13: Modelling the grouting pressure 10 Figure 15: Standard run: calculated longitudinal settlement trough

deformations at surface level measured at the monitoring section varied between approximately 15 mm heave and 10 mm settlement. Hence the 4D model with best estimate parameters calculates the maximum of the measured settlements. The calculated transverse trough is symmetric, while the measured one is not. This asymmetry is probably caused by variations in grouting pressure at the monitoring section and / or the presence of a safety shaft constructed before the tunnels. The calculated longitudinal trough is one of three possible troughs found during the passage of the TBM underneath the monitoring section (see also figure 4). Results of the standard run: tunnel displacement When performing a staged construction calculation with PLAXIS 3D Tunnel, every new ring is added in a stressless situation. In obeying this condition the new ring is placed with an offset onto the tunnel. This repeated process causes a displacement of the tunnel as displayed in figure 16, where uplift is plotted against distance from the front of the model. After having modelled 60 rings this displacement is about 60 mm. This phenomenon is believed to stem from the stressless procedure in PLAXIS, excluding real life construction effects. This means that in reality newly added rings are probably built in warped (intentionally or unintentionally) and / or a downward force is exerted on the tunnel by the TBM (see figure 18). Figure 18: Warped position of newly placed tunnel rings (left) or downward force exerted by TBM on tunnel (right) Results of the parameter variation study In order to assess the sensitivity of the 4D FEM model to parameter variations, additional calculations were performed. The most important variations were carried out for: tunnel bending stiffness reduced by a factor 0.5 soil stiffness E UR ref reduced by a factor 0.7 modelling TBM without contraction The results of the variations study are presented in tables 2a and 2b, where the focus is on the maximum final surface settlement and the calculated net uplift of the tunnel construction respectively. The results can be compared with the results of the standard run, given in the top row. standard run 10 mm settlement tunnel bending stiffness x 0.5 no effect soil stiffness x 0.7 8 mm settlement front pressure +10 kn/m² * no effect grouting pressure +20 kn/m² ** 8 mm settlement grouting pressure +50 kn/m² *** 2 mm settlement grouting pressure +100 kn/m² **** 30 mm heave no contraction TBM 2 mm settlement * +10 kn/m² equals +5% ** +20 kn/m² equals +6 to +10% *** +50 kn/m² equals +14 to +25% **** +100 kn/m² equals +28 to +50% ***** N/I = not investigated Figure 16: Calculated displacement of the tunnel over 60 rings The calculated net uplift of a tunnel segment caused by grouting pressures after installation is displayed in figure 17. Also shown are the measured displacements of ring 2080, the only ring monitored after installation. The measured uplift is about 20 mm and occurs over a distance of approximately 12 m after installation. The calculated uplift is only 4 mm and occurs over a length of 9 12 m. The difference is significant. Figure 17 indicates that further uplift is suppressed by backup train loads Table 2a: Maximum value calculated surface settlement standard run 4 mm tunnel bending stiffness x 0.5 7 mm soil stiffness x 0.7 4 mm front pressure +10 kn/m² 4 mm grouting pressure +20 kn/m² 5 mm grouting pressure +50 kn/m² 6 mm grouting pressure +100 kn/m² N/I ***** no contraction TBM N/I ***** Table 2b: Maximum value calculated net uplift tunnel Finally the measured and calculated horizontal displacements are plotted in figure 19. The shapes match well. When omitting TBM contraction the calculated curve shifts toward the measured one. On raising the grouting pressure uniformly by 50 kn/m² the calculated curve closely matches those measured. Correlating the calculated surface settlements and the results from figure 19 indicate that either the applied contraction is too high or the grouting pressures are too low in the standard run. Possibly a combination of these two should be implemented to match the measured ground deformations.` Figure 17: Displacements of 1 tunnel ring after installation. Small triangles represent backup train wheel loads. 11

Bending moments and normal forces in the tunnel lining Apart from displacements, also the forces and moments in the tunnel lining can be derived from the calculation. In figure 20 the bending moments in various cross sections are given for various distances to the TBM. In cross section 1 the moments are given in the lining, just before the lining exits the TBM tail. In section 2 the lining is loaded by the grout pressure and the point load from the wheels of a backup train. The influence of this wheel load can be clearly seen. The other sections are taken further back and show a diminishing influence of the wheel loads. Figure 21 shows the distribution of these moments over the entire lining. CONCLUSIONS & RECOMMENDATIONS Figure 19: Inclinometer results showing measured values and calculated values for three calculations (s.r. means standard run; c = 0 means zero contraction; +50 kn/m² indicates the raised grouting pressure ). The results presented in this paper show that state of the art FEM software and computer technology combined with the practical experience currently available it is feasible to model tunnel boring with a 4D approach. Process parameters can be modelled without difficulty and their individual influence on model response can be evaluated with certain parameters can be varied easily (soil / tunnel properties) and the PLAXIS copy Figure 20: Bending moments at various cross sections in the 3D Tunnel model option now available limits repetitive data entry and minimises input errors. However, changing contraction or grouting pressure distribution demands means defining and running a new calculation. This is more time consuming. Both monitoring and TBM data show that the boring process has not been constant at the section used for the history match with the FEM model. However, the case study and parameter variations show that recalculation of a tunnel boring process in terms of soil displacements is feasible. Grouting pressures and TBM contraction govern soil displacements. Hence, these parameters should be carefully assessed. Measured grouting pressures provided the input for this 4D FEM model. In future predictions grouting pressure distribution can be determined using the recently developed grout consolidation model as presented by Bezuijen & Talmon (2003). It is questionable whether TBM contraction should be fully applied. In practice contraction might be limited by either face or grouting pressures. Figure 21: bending moments M11 in the tunnel linng 12 REFERENCES Bezuijen, A. & Talmon, A. 2003. F220-E-03-109 Groutdruk-metingen Sophiaspoortunnel Metingen en analyse beide buizen. Gouda: COB (The Netherlands) Brinkgreve, R.B.J. & Broere, W. (eds.) 2004. PLAXIS 3D Tunnel version 2 - user manual.