Biogas Cogeneration of Heat & PowerEnergy Reduction at the McAlpine Creek Wastewater Management Facility www.tinyurl.com/combinedheatandpower Jon Lapsley, PE CDM Smith Will Rice CLT Water November 14, 2016 Raleigh, NC
Outline Charlotte Water and McAlpine Creek WWMF Background Implementation History Biogas Study Findings and Recommendations Summary of Improvements Current Status and Lessons Learned Questions
Charlotte Water and McAlpine Creek WWMF
Background Charlotte and Mecklenburg County Over 775,000 Customers 5 Treatment Facilities
McAlpine Creek WWMF Largest Facility at 64 mgd Receives Primary Sludge and WAS from Sugar Creek WWTP Also has capability to receive flow from Sugar/ Irwin
Energy In Wastewater WERF- ENER1C12 A GUIDE TO NET-ZERO ENERGY SOLUTIONS FOR WATER RESOURCE RECOVERY FACILITIES)
McAlpine Creek WWMF You ever thought of taking that methane and making power? The General Public 2+ flares, 24/7/365
Implementation History
Implementation History North Carolina Solar Center Biogas Study CDM Smith Biogas Utilization report The Intern Started The Intern Study (i.e. lots of phone calls to ORCs/ Chiefs) (Fall) Attempted DBOF/ESCO: Limited Interest Considered Alternatives and Cost Paybacks (Winter) RFP CLT Water Purchased Cogeneration Engine (Summer) NCDEQ CWSRF Loan Funding Approved Final Design and Bidding Construction Begins
2009/2010 Biogas Study and Findings
CLT Water Commissioned Several Studies North Carolina Solar Center Evaluated Multiple Methods Internal Combustion Engine most efficient and least life cycle cost 9-14 year Payback
CLT Water Commissioned Several Studies Biogas Utilization Study Updated Anaerobic Digester Gas Projections Future Co-digestion considerations Preliminary Siting and Layouts
Anaerobic Digester Gas Projections >2 MW
Anaerobic Digester Gas Analysis (2010-2014) Average Carbon Dioxide: 32.1% Average Methane: 64.3% Average Nitrogen: 1.2% Average Oxygen: 0.3% Average Total Siloxanes: 0.606 ppmv Average Hydrogen Sulfide: 8.5 ppmv Average HHV: 637 BTU/cubic foot Average LHV: 573 BTU/cubic foot (GOOD) (VERY LOW)
Implementation History North Carolina Solar Center Biogas Study CDM Smith Biogas Utilization report The Intern Started The Intern Study (i.e. lots of phone calls to ORCs/ Chiefs) (Fall) Attempted DBOF/ESCO: Limited Interest Considered Alternatives and Cost Paybacks (Winter) RFP CLT Water Purchased Cogeneration Engine (Summer) NCDEQ CWSRF Loan Funding Approved Final Design and Bidding Construction Begins
2011-2013 The Intern and the ESCOs
The Intern(al) Study on CHP and RFP Lots of Phone Calls How well and how often do your engines run? How did you procure yours? Who does your maintenance? Who built it? What were your lessons learned? Conclusion: CLTW didn t want financial or operational risk Attempted to do Design/ Build/ Operate/ Finance/Own Failed: ESCOs didn t want to Own/ Finance
Implementation History North Carolina Solar Center Biogas Study CDM Smith Biogas Utilization report The Intern Started The Intern Study (i.e. lots of phone calls to ORCs/ Chiefs) (Fall) Attempted DBOF/ESCO: Limited Interest Considered Alternatives and Cost Paybacks (Winter) RFP CLT Water Purchased Cogeneration Engine (Summer) NCDEQ CWSRF Loan Funding Approved Final Design and Bidding Construction Begins
2013/2014 The Planets Align: State Revolving Fund and A Cancelled Order
Winter 2013 RFP CLT Water Purchased Cogeneration Engine Order for 4x GE Jenbacher J320 Containerized Engines Cancelled Nixon Energy contacted CLTW RFP was released for 1 MW CHP Engines GE was lowest responsive bidder, engine was purchased at significant discount
Engine Arrival 64,000 lbs Telescoping Trailer Multiple Ports 2 trucks
2014 CWSRF Funding First Application was not accepted Second Time Application was accepted Borrowing $3.2 million at 0% Green Project Reducing Power Use by 20% OR Generating Power
Implementation History North Carolina Solar Center Biogas Study CDM Smith Biogas Utilization report The Intern Started The Intern Study (i.e. lots of phone calls to ORCs/ Chiefs) (Fall) Attempted DBOF/ESCO: Limited Interest Considered Alternatives and Cost Paybacks (Winter) RFP CLT Water Purchased Cogeneration Engine (Summer) NCDEQ CWSRF Loan Funding Approved Final Design and Bidding Construction Begins
Summary of Improvements
Main Project Components Anaerobic Digester Gas Piping System Gas Conditioning System Cogeneration Engine Hot water system Electrical improvements with Duke Energy
Anaerobic Digester Gas Piping Getting from A to B Above ground vs. buried piping Connection downstream of existing H2S Scrubbers
Gas Conditioning System Downstream of existing Hydrogen Sulfide scrubbers Packaged Treatment System Gas compression and drying Siloxane scrubbing system/activated carbon filters
Cogeneration Engine CLT Water Purchased Cogeneration Engine Jenbacher 1,059 kw/hr, 2,430 MBTU/hr Engine Table Cooler Engine Exhaust Decoupling Heat Exchanger Engine Container Exhaust Gas Recovery Electrical Transformer
Hot Water System Balance heating needs vs. biogas use (now 3 biogas avenues) Biogas fired boiler system for digester hot water heating Combined Heat and Power Engine Flare System Connect at existing HW to HW Heat Exchanger
Hot Water System Heat Recovery from engine block/jacket and exhaust gas Closed loop system with recirculation pump Balancing valves and recirculation pumps on VFDs
Electrical Improvements Driven by Power Purchase Agreement (PPA) 1 MW Restriction by Duke Energy Sell All PPA Major Components 480 V to 24 kv step up transformer Underground system to existing 24 kv system New poles and metering by Duke Energy
Current Status and Lessons Learned
Current Status Construction is underway Startup Scheduled for Early 2017
Construction Photographs
Construction Photographs
Construction Photographs
Combating fears: Enough gas, cost prohibitive, does not impact permit compliance Engine acquisition: In the bid vs. pre-purchase Power cost vs. payback: delivery method Gas conditioning: Upfront capital vs. O&M costs Site visits critical: Operations and Management Funding sources: Energy reduction is big Power Purchase Agreements: Negotiating varies Operations: Consider 3 rd party O&M Contracts Container 3 rd Party Listing US vs. International Standards
www.tinyurl.com/combinedheatandpower www.tinyurl.com/combinedheatandpower Questions? Will Rice: wrice@charlottenc.gov Jon Lapsley: lapsleyjs@cdmsmith.com www.tinyurl.com/combinedheatandpower