Tack Coat: A Must Have in Pavement Placement. Robert Horan, PE Regional Engineer Asphalt Institute Mechanicsville VA

Similar documents
Tack Coat Best Practices. Greg Harder, PE Regional Engineer Asphalt Institute Tully, NY

Tack Coat Best Practices

Tack Coat Best Practices

Tack Coat Best Practices

Tack Coat Best Practices

FHWA Cooperative Agreement Subtask. Longitudinal Joints Intelligent Compaction

Oklahoma Workshop. Danny Gierhart AI Jason Dietz FHWA Resource Center

Enhanced Durability Through Increased In-Place Pavement Density. FHWA and Asphalt Institute Workshop

Focusing on What Matters Most- Increasing In-Place Density

NCHRP Synthesis Tack Coat Specifications, Materials, and Construction Practices

The Discussion. WV s Observations Literature Review. SEAUPG Annual Meeting Williamsburg, VA Thursday, November 19, 2015

Asphalt Pavement Construction: Best Practices

Talking Tack: A Synthesis of Practices Around the U.S.

Infrared Technology: Its Application and Benefit

Promoting Quality through the FHWA / AI Cooperative Agreement. Mark Buncher for ETG, Sept 2014

FHWA SHRP2 Overview & National Perspective. Steve Cooper SHRP2 Renewal Pavement Engineer

QUALITY ASSURANCE FOR SHRP2 R06C TECHNOLOGIES

Preserve Your Roadway Network

PAVEMENTS AND INNOVATION

Analysis of NBI Data for California Bridges

IDOT HMA Update. Christine M. Reed, P.E. Director Division of Highways Illinois Department of Transportation

Warm Mix Asphalt Scan Tour Technology 4/29/2011

Warm Mix Asphalt The Material of Today

Bonded HMA Overlays a matter of tack materials & method of application

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2015

EDC-4 Pavement Preservation (When, Where, and How) Update

Asphalt Issues Update Mixture & Binder Expert Task Groups. John Bukowski Asphalt Team Leader Office of Pavement Technology

ODOT Item 407 Tack Coat

Warm Mix Asphalt National Overview

The Every Day Counts Initiative

Future of the US Federal Highway Program

Warm Mix Asphalt Technologies

SPECIALTY CONCRETE MIXTURES AND THEIR USE

FHWA Pavement Surface Characteristics Program And Research Update

EPOXY INTEREST GROUP EPOXY-COATED REINFORCING STEEL IN PARKING GARAGES

FHWA UPDATE ON CONCRETE PAVEMENT ACTIVITIES GINA AHLSTROM, MIKE PRAUL, AHMAD ARDANI, RICHARD DUVAL

Construction Specification for Tack Coat

Tack Coat Materials and Methods for Optimizing for Thin HMA Applications

Surface Characteristics. MPPP November 13, 2013

EDC Summit Current State of the Technology

PUBLIC POWER = + + LOCAL CONTROL LOW RATES HIGH RELIABILITY

Longitudinal Joints. Two Goals

Bridge Management Questionnaire Report

Warm Mix Asphalt The Material of Today

Construction & Materials Outlook. March 9, 2009 Ken Simonson, Chief Economist AGC of America USA

North Dakota Asphalt Conference April 6-7, 2010

Post Installation Inspection - Value Assurance. Stew Waller, P.E., LEED AP

Indiana Energy Status

Non-Ambulatory Cattle and Calves

Flexible Pavement Preservation Treatment Construction Ultra-thin, Hot Mixed Asphalt, Bonded Wearing Course AT-TC3PP T1-JA01

Educating and Training Tomorrow s Workforce

Concrete Pavement Preservation Integrating Engineering, Economics and the Environment. John Roberts International Grooving & Grinding Association

VDOT S PREVENTIVE MAINTENANCE TECHNIQUES & EXPECTATIONS

NCHRP 20 68A U.S. Domestic Scan Program. Domestic Scan 13 03

Bonded Pavements m. Tack to the Max NCAUPG 2/3/2010. Andrew Fox VP-Innovation

Transportation Worker Identification Credential (TWIC) Program. American Association of Port Authorities 2013 Security Seminar July 17, 2013

MA Perspectives on Building Priorities for Climate and Energy Policy

Indiana Energy Landscape

Advanced Fuel Cycles?

Sarah Doll, Safer States BizNGO December 2014

Special Provision for Hot-Mix Asphalt Prime Coat

A Comparison of In-Service Statistical Test Programs

2005 AWPA Annual Meeting New Orleans, LA May Nelson G. Bingel III. Chair - ANSI O5 Principal - NESC

Welcome to the 7 th Annual Safeguard Properties Vendor Conference. Cleveland, OH August 22-25

Topics. Look Ma, No Mess. Demonstration. Demonstration. Demonstration. Pavement. Pavement Behavior. Pavement. New Approaches to Tack Application

Potential Damage from Asian Longhorned Beetle

Bank of the Sierra stays in the black with the help of Eaton UPS and service plan

Goal Setting: Nutrient Pollution Standards and Technology. October 29, Ephraim King OST

State of the Network. EN2014 February 25, 2014

Concrete Pavement Preservation. Integrating Engineering, Applications and the Environment

1825 W. Adams, Phoenix, AZ Phone (602) / Fax (602)

Watershed Plan Implementation in Oklahoma: What We Do and What We ve Learned

OF PIPEDREAMS AND PIPELINES

Pennsylvania s Experience with Thin Asphalt Overlays

The Component Model of Infrastructure (CMI): An Infrastructure Model for Evaluating Tobacco Control Programs

NAPA INITIATIVES. RICHARD WILLIS, PhD PENNSYLVANIA ASPHALT PAVEMENT ASSOCIATION JANUARY 16, 2018

Building Energy Codes Update NGA Energy Working Group

October 27, 2008 Bob Orthmeyer

Special Provision No. 308F01 May 2010

Mary. E. Torrence DVM, Ph.D., DACVPM National Program Leader, Food Safety

2011 State Average Electricity Prices (cents/kwh)

Flexible Pavement Preservation Treatment Construction Thin Functional and Maintenance Overlay Projects AT-TC3PP T1-JA01

EPA Carbon Regulations Stakeholder Meeting

Thin Hot Mix Asphalt Overlays

ISO s Data Management Roadmap. October 13, 2015

Developing a Framework for Integrated Energy Network Planning

Destination for Education? Your Facility. Bring Us to You!

Update on Energy Efficiency Opportunities in the Commonwealth

U.S. Wind Industry Fourth Quarter 2014 U.S. Wind Industry First Quarter 2016 Market Report Market Report

Risk Mitigation Benefits of Energy Efficiency

The Changing Landscape and Business Case for Water Loss Control

Farm Computer Usage and Ownership

NCHRP 20-68A US Domestic Scan Program

U.S. National Overview Cold-In Place- Recycling. Laramie, Wyoming 18 th July 2013

SEAUPG 2004 Conference - Baton Rouge Presented By Dr. Louay Mohammad, LSU

Laws are like. better not to see. made.

Construction & Materials Outlook September 4, 2009

Milk Production, Disposition, and Income

Election Day Command Centers: The Vortex 2016 STATE CERTIFICATION TESTING OF VOTING SYSTEMS NATIONAL CONFERENCE MIT JUNE 20, 2016

Maximizing the Value From Commercial Roof Systems. An Industry Report

Transcription:

Tack Coat: A Must Have in Pavement Placement Robert Horan, PE Regional Engineer Asphalt Institute Mechanicsville VA

Our Visit Today Purpose of Tack Coats Terminology Consequences of Poor Bond Relative Cost for Tack Coat Tack Coat Field Operations Manuals of Practice Best Practices Surface Preparation Truck Setup Research on Bond Strength Testing

Tack Coat Best Practices Outline Materials Traditional New Materials Selection Tack Coat Challenges Contractor Agency Spray Pavers Review and Summary Common Tack Coat Questions Areas of Known Agreement

Purpose of Tack Coats To promote the bond between pavement layers. Prevent slippage/ shoving failures Full bond is vital for structural performance of the pavement. When bonded, all layers working together. Critical that tack materials are applied uniformly at appropriate application rate Apply tack coat on all surfaces including vertical surfaces. 4

Far Too Frequent Poor Practices

Key Factors for Tack Coat Success Condition of Existing Pavement Tack Coat Application Rate Residual Binder Content Proper Distributor Operation Emulsion Break and Set Times 6

Terminology Tack Coat sprayed application of liquid asphalt upon an existing asphalt or Portland cement concrete pavement which may or may not have been milled before an overlay, or between layers of fresh asphalt concrete. Original Emulsion (emulsified asphalt) an undiluted emulsion which consists of a mixture of paving grade binder, water, and an emulsifying agent. Diluted Emulsion an emulsion that has been diluted with additional water. Critical to control 1:1 typical (original emulsion: added water)

Terminology Residual Asphalt the remaining asphalt after an emulsion has set typically 57-70 percent. Tack Coat Break the moment when water separates enough from the asphalt showing a color change from brown to black. Tack Coat Set (cure) when all the water has evaporated, leaving only the residual asphalt. Some refer to this as completely broken.

Emulsion Breaking & Setting Emulsions are asphalt droplets suspended in water Breaking Contact with surface changes ph; reducing charge Setting Evaporation leads to coalescence Original asphalt characteristics return

Consequences of Poor Bonding Poor pavement performance Slippage cracks Shoving Early fatigue cracking Bottom up Top down Costly pavement repairs Repair of isolated area relatively inexpensive Removal and replacement of a portion or the entire pavement structure is very expensive Shorter than expected pavement life can be devastating for agency budgets

Consequences of Poor Bonding Layer independence Reduced fatigue life Increased rutting Slippage Shoving Compaction difficulty Direction of traffic?

Pavement Behavior Load Distributed by Tire Shear Transfer? Compression Stress Distribution Tension Aggregate Base Soil Subgrade Courtesy of Rich May

Bonding Demonstration ½ Deflection, 60# Load ¼ Deflection, 160# Load Unbonded Fully Bonded

Bonding Demonstration Highlights 5 unbonded layers deflected 4x more than 5 bonded with the same loading. 2 bonded layers had less deflection than 5 unbonded with the same loading. 5 bonded layers with over 2½x the load deflected half as much as 5 unbonded. 14

Loss of Fatigue Life Research May and King: 10% bond loss = 50% less fatigue life Roffe and Chaignon No bond = 60% loss of life Brown and Brunton No Bond = 75% loss of life 30% bond loss = 70% loss of life

8 10 years (est.) Interstate Pavement Courtesy of MODOT

Cores Showing Debonding Bonding Failures Courtesy of MODOT

What Does It Cost? Cost of Tack Coat New or Reconstruction About 0.1-0.2% of Project Total About 1.0-1.5% of Pavement Total Cost Mill and Overlay About 1.0-2.0% of Project Total About 1.0-2.5% of Pavement Total Cost

Estimated Cost of Bond Failure in Only the Top Lift Assume no inflation for materials Estimated traffic control Used project plans for thicknesses Used bid tabs for: Milling Material costs Replaced pavement markings 30-100% of Original Pavement Costs

Common Tack Coat Materials Emulsified Asphalt Most common option SS-1, SS-1H CSS-1, CSS-1H RS-1, RS-1H, RS-2 CRS-1, CRS-2 PMAE PG Graded Binders Neat Binders PG 58-28 PG 64-22 PG 67-22 Polymer Modified Reduced or Non-tracking Emulsions

States - Reduced Tracking Tack Mat ls CA AZ CO NM TX OK AR LA MO KY AL GA FL VA OH MI VT AK MT NV ME WA OR UT KS ID WY ND SD MN NE WI IA IL IN MS TN SC NC WV PA NY CT NJ DE MD DC MA NH RI HI PR 21

Handling of Emulsions Dilution Verify if it is allowed. If allowed, where? Supplier only? Contractor? Control amount of water added. 1:1 typical (Original Emulsion: Added Water) Use acceptable/approved water. Terminal added or field diluted. Always add water to emulsion. 22

Tack Coat Field Operations

Manuals of Practice Asphalt Institute MS-4 The Asphalt Manual, 7 th Edition (2007) MS-16 Asphalt Pavement Preservation and Maintenance, 4 th Edition (2009) MS-19 Basic Asphalt Emulsion Manual, 4 th Edition (2008) MS-22 Construction of Hot Mix Asphalt Pavements, 2 nd Edition Comments AI has a long history of promoting the proper use of tack coats.

Manuals of Practice QIP-128,Tack Coat Best Practices, NAPA (2013) Hot-Mix Asphalt Paving, US Army Corp of Engineers (2000) Airfield Asphalt Pavement Construction Best Practice Manual, NCAT (2008) Tack Coat Guidelines, Caltrans (2009) Tack Coats: How and what to apply! Colorado Asphalt Pavement Association (CAPA) (2011) Guide for Using Prime and Tack Coats, CFLHD (2005) Best Practices for Applying Undiluted Emulsified Asphalt Tack Coats, CAPA (2013)

Tack Coat Application

Tack Coat Challenges Contractor Variable application rates Consistency of application Tack coat pick-up or tracking by construction vehicles Breaking/setting time prior to paving Agency Acceptance (method or performance) Bond quality testing Dilution? Visual inspection Application rate measurement

Example of Tack Pick-Up Photo courtesy of Road Science

Best Practices Surfaces need to be clean and dry. Uniform application. All surfaces are tacked. Tack should not be tracked off the road.

Best Practices Match application to conditions. Materials Residual rate Verify application rate. Resist tacking too far ahead of paver.

Distributor Truck Setup

Distributor Truck Setup Liquid temperature Monitor and match to material Calibrate distributor truck Spray bar height Spray bar pressure Nozzle selection Nozzle angle Thermometers Volumeter Application rate

Direct Measurement using ASTM D2995 Method A Weighing Pads Pre-weigh pads Secure pads to surface Apply tack coat Reweigh pads Calculate application rate

Direct Measurement using ASTM D2995 Field Measurement of Application Rate Longitudinally Transversely Units of Gallons/Yard 2 (Liters/Meter 2 ) Photos courtesy of Dr. Louay Mohamad

Photo courtesy of Ergon Asphalt

Nozzle Selection

Nozzle Selection Consult with distributor truck manufacturer to match the material to the nozzle. ONE SIZE DOES NOT FIT ALL 38

Effect of Nozzle Orientation Proper nozzle angle of 15-30% assures proper overlap between nozzles without interference of tack streams.

Spray Bar/Nozzles

Nozzles are clogged, but triple overlap covering the gap. Note: not a tack coat, but principle applies.

Cleaning Distributor Tank Critical when changing from one product to another Significant safety hazard can occur Product quality can be affected Best Practice is to empty the tank and clean if necessary. 42

Key Items for Inspectors Check truck setup. Spray bar height (~12 ) Appropriate nozzles Nozzle orientation (15-30 ) Check application rate gauge in truck Check application temperature Collect samples. Know the desired application and residual rates. Visually inspect application Verify application. Volume Mass ASTM D2995 43

44

Testing Methods Materials Emulsion Paving grade asphalt Field/Laboratory Bond Testing Shear Testing Torsion Testing Pull-Off Testing (tension)nsion) Cyclic

Comments on Testing Options Shear Testing Lab test Quick Repeatable Most widely promoted Uses common lab equipment Cleanly ranks materials Torsional Testing Lab or field test Quick Poorer repeatability (manually ran) Tension Testing Lab or field test Quick Repeatable Cleanly ranks materials Used in Texas and Kansas Cyclic Testing Lab test More time consuming Repeatable Cleanly ranks materials

Common Tack Coat Questions What Type of Bond Testing? Shear Torsion Pull off Cyclic All have advantages and disadvantages Further research and acceptance will likely lead to a generally preferred method.

Review and Summary

Common Tack Coat Questions Experts commonly disagree Do I still need to tack Milled Surface Fresh Pavement Late season/cooler days Asphalt Institute recommends tacking all surfaces

Common Tack Coat Questions When can I pave on the emulsion? Has emulsion broken? Does it need to be set? Asphalt Institute recommends paving begin after the emulsion has broken. How can I prevent tack pull-up/tracking? Make sure tack coat is broken Use emulsions with hard base asphalt (CSS-1h) Use a proprietary reduced-tracking emulsion Use a spray paver

Spray Pavers Spray pavers are an engineered system that consists of a paver with built-in emulsion application systems that applies tack just prior to asphalt laydown. Emulsions used in spray pavers are designed to perform without break/set. No tack coat tracking or pull-up

Roadtec SP 200 Spray Paver Courtesy of Roadtec

Vögele: Spray Jet Courtesy of Road Science

Purported Spray Paver Benefits No tracking of the tack Better bonding of overlays Increased Overlay life Reduce Rutting Reduce Cracking Improved bond = easier compaction

Common Tack Coat Questions What is the optimal aplication rate? Surface type Surface condition Asphalt Institute recommended ranges Surface Type Residual Application Rate (gsy) New Asphalt 0.020 0.045 Existing Asphalt 0.040-0.070 Milled Surface 0.040 0.080 Portland Cement Concrete 0.030 0.050

Common Tack Coat Questions When to Re-Tack? Tracking Contamination Re-Tack when in doubt. Is Dilution okay? Follow state specs Verify dilution amount Can not be used to stretch tack as residual value is key. Limit dilution to supplier.

Areas of Known Agreement Layer Bonding is Vital Surface Preparation Clean Dry Millings Improves Field Performance Shear Cleaning

Areas of Known Agreement Application Quality Vital Proper Rate Consistency Distributor Truck Setup Calibration/Verification Maintenance Tacking of Longitudinal Joints Bonding Confinement Excessive Tack is Bad

Areas of Known Agreement Tack Coat Rate Depends on Surface Condition Fresh Weathered Raveled Milled Treat Tack as Separate Pay Item vs. Incidental Item Need for Research Field Performance Field Testing Bond strength Application amount

Successful Tack Coat The Ultimate Goal: Uniform tack coat coverage

Thank You! Free 4-hour workshop requested through FHWA divisional offices Free webinar: http://www.asphaltinstitute.org/public/asphalt_academy/ webinars/tack-coat-best-practices-webinar-recording.dot